This document contains the project specifications for a federal contract opportunity to modify the breakwater and wave attenuator system for the water intake barge located at Echo Bay in the Lake Mead National Recreation Area. The purpose is to install a new floating wave attenuator system around the existing water intake barge to protect it from wind, waves, and lowering water levels in Lake Mead.
The key details include:
- The existing breakwater system has failed and needs to be replaced.
- The new wave attenuator system must be able to withstand wind speeds up to 60 mph and waves up to 4.5 feet high, and reduce the transmitted wave height to a maximum of 1.5 feet.
- The system must be adjustable to accommodate fluctuations in the lake water level between 1015 feet and 1090 feet.
- The contractor will be responsible for designing, fabricating, and installing the new wave attenuator system, including anchors, cables, lighting, and a separate winch platform barge.
- The contract performance period is 60 calendar days after the Notice to Proceed.
- The solicitation number is 140P8124B0011 and is being issued by the Department of the Interior National Park Service Pacific West Region.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P8124B0011_Amd_0005.pdf | ||
| Sol_140P8124B0011_Amd_0004.pdf | ||
| Sol_140P8124B0011_Amd_0003.pdf | ||
| Sol_140P8124B0011_Amd_0002.pdf | ||
| Sol_140P8124B0011_Amd_0001.pdf | ||
| B08_-_Atch_3_-_Limitation_on_Subcontracting_Report.xlsx | XLSX spreadsheet | |
| Sol_140P8124B0011.pdf | ||
| B08_-_Atch_2_-_Wage_Determination_NV20240024.pdf | ||
| B08_-_Atch_4_-_Construction_Contraction_Administration.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LAKE MEAD NATIONAL RECREATION AREA
BOULDER CITY, NEVADA
ECHO BAY WATER INTAKE BARGE BREAKWATER MODIFICATION
LAKE – 254113
PROJECT SPECIFICATIONS
NATIONAL PARK SERVICE
July 30, 2024
LAKE 254113 Page 2 of 59
DIVISION 1 GENERAL REQUIREMENTS
SECTION 01110 SUMMARY OF WORK
1.1 EXISTING CONDITIONS
The Project location is the Lake Mead National Recreation Area. The site is located near the Echo Bay Cove developed area.
The Echo Bay water intake barge provides drinking water to the water treatment. The intake barge was recently relocated to place the barge in deeper water as the water elevation of Lake Mead continues to decrease. A single string of wave attenuators was placed around the current water intake barge location.
The purpose and need for this project is to modify the breakwater and wave attenuator system to the water intake barge located at Echo Bay. Due to the lowering water levels in Lake Mead, the water intake barge has been relocated into deeper water of the lake. The current location of the barge out in deeper water puts the barge further out into the main body of the lake. The intake barge is now exposed to more of the weather including wind and waves. The barge has equipment including pumps and controls that will have a longer service life where a more stable platform is provided.
There are remnants of an existing breakwater at the location. The breakwater is secured by cables and anchors. The current breakwater has failed and is not useable.
This project will install a breakwater/wave attenuators or approved equal around the existing floating water intake barge.
1.2 GENERAL PROJECT STATEMENT
A. The work of this section consists, in general, of furnishing all labor, materials, equipment, tools, transportation, and incidentals required to design, fabricate, and install a floating wave attenuator. All floating wave attenuators shall be fabricated from structural steel and concrete. All material shall be compatible and intended for the freshwater (marine) environment. The approved floating wave attenuator shall be furnished and installed complete, including anchoring system (winches, cables, and anchor blocks), solar mounted lights, connecting hardware, and appurtenances.
B. A site visit will be scheduled for a pre-bid visit with the interested respondents. The site visit will be to an overlook where the barge site can be viewed.
C. Contractor shall provide their own equipment and transportation to and from the construction site including their use of boats and work barges.
D. On November 8, 2023, a site visit was conducted. The boat’s depth gauge at the intake barge read 110 feet. The Bureau of Reclamation recorded the Lake Mead surface elevation as 1065.07’.
LAKE 254113 Page 3 of 59
1.3 SCOPE OF WORK
The scope of work for this contract consists of:
A. See ECHO BAY WATER INTAKE BARGE BREAKWATER maps Figure 3 and 4.
B. See pictures at the end of these specifications for existing site conditions and visual site conditions.
C. All breakwater products shall be new and undamaged. Products and equipment shall be properly handled and stored on site.
D. Laydown and storage areas shall be coordinated with the COR on site.
E. Contractor shall use existing launch ramps. Blockage of the launch ramps shall not occur.
The ramps shall remain open to the public. Extended use of the launch ramps shall be coordinated with the COR.
F. Submittals of product to be installed shall be submitted to the COR for review and approval.
G. System required qualities:
1. There shall be no direct exposed Styrofoam components.
2. Cable lengths and anchor weights installed per manufacturers recommendation.
3. The proposed system shall enclose 3 sides of the water intake barge. Boat access to both sides of the breakwater and to the water intake barge will be required.
4. The product shall be specifically designed as a wave suppression device. The device shall suppress waves generated by boats, waves and winds.
5. The units shall be able to be adjusted in weight and height to allow adjustment to a level that allows for maximum wave suppression.
6. Stainless steel cable shall be used to string the units together and provide anchor cable support. The cable shall be commercial grade with a minimum of 18,000-pound breaking strength.
7. Cable sizes, connections and cable diameter shall be per manufactures recommendations.
8. Any cable or structure being strung through the wave attenuator units shall have an additional wearing surface around the item. The item should not directly bear on the wave attenuator without an additional wearing surface. This shall be a continuous bearing surface and not split up per individual wave attenuator.
9. All fasteners, thru rods and associated hardware shall be hot dipped galvanized after fabrication in accordance with ASTM A123. All weldments shall be hot dip galvanized after fabrication.
LAKE 254113 Page 4 of 59
10. Concrete used in the attenuator structure shall have a compressive strength of 5000 psi.
11. Proposed design and components shall be submitted to the CO/COR for review and
H. The existing breakwater system that is remaining shall be removed by the contractor. The surface floats shall be removed. Anchor blocks do not need to be removed.
I. Proposed System: Contractor shall be responsible for the installation of any needed cable and anchor blocks for the final triple string installation.
1. Anchor weights, locations and direction shall be determined by the contractor.
a. Anchor weight shall be per manufacturers recommendations.
b. The lake experiences high winds and wave heights. Anchoring system shall accommodate the anticipated weather at the project site.
2. The breakwater shall be able to stand up to the conditions encountered on the lake.
a. Winds in excess of 60 miles per hour are encountered on the lake.
b. Significant wave heights of 3 feet in height are encountered on the lake.
c. Maximum wave heights of 4.5 feet in height.
d. Wave period of 3.3 seconds.
e. Wavelength of 36 feet.
f. Breakwater shall reduce transmitted wave height to a maximum of 1.5 feet on the inside towards the water intake barge.
g. Design and calculations to illustrate the method that the installed product shall attenuate the wave shall be provided to the CO/COR for review and approval.
h. Rapid fluctuations of the lake level may be encountered. Method of adjustment of the anchor cables shall be incorporated into the product.
i. Before fabricating the wave attenuator components, submit designs and calculations. The calculations shall demonstrate that the floating wave attenuator, using the criteria specified herein as minimum requirements, is designed to withstand the specified loads without damage throughout the design service life of the system.
j. Before fabricating the wave attenuator components, submit wave attenuator stability and wave transmission analysis. The calculations shall demonstrate the floating wave attenuator is designed to meet the criteria.
3. The anchors, chains and attachment points shall be installed in a configuration surrounding the intake barge or approved equal.
LAKE 254113 Page 5 of 59
4. New cables and anchors blocks shall meet manufacturers recommendations.
5. New installed cable lengths shall allow the wave attenuator system to vary in lake water elevation from 1015’ to 1090’.
6. Estimated current water depth is 110 feet (11/2023) at the intake barge site. Cable lengths shall be set at the water elevation at time of installation.
7. The wave attenuators shall be placed a minimum of 50 feet away from the water intake barge per manufacturers recommendation to allow boat access to and from the water intake barge. Anchors and cables shall be placed accordingly to allow boat access to the intake barge.
8. The proposed wave attenuator system shall consist of the system being installed on 3 sides of the water intake barge with the 4th side open for boat access. The 4th side should face the shoreline per manufacturers recommendations.
9. Field verify all items and components.
10. Contractor shall submit at the end of the installation as-built drawings, sketches and details of the installation.
a. Details shall indicate the items installed, items revised, direction of the anchor cables, lengths of the anchor cables, weight/size of the anchor blocks and the depth of the water at installation.
b. Drawings, sketches and details shall be a PDF format.
c. Photo files shall be transmitted to the CO/COR at the end of construction as a part of the close out procedures.
11. Wave attenuators shall have winch platforms and winches to adjust anchorage during lake water elevation changes. All winch platforms shall have adequate cleats, mooring lines & anchors, and solar navigation lights per USCG standard for operation and maintenance.
12. Provide a safe means of tie-up capability and access to each winch for maintenance staff.
13. Wave Attenuator Barge Winch Platform:
a. The lake level fluctuates seasonally on Lake Mead. A separate barge winch platform or attach winches to proposed wave attenuators is proposed to facilitate easy adjustment of the anchor cables that hold the wave attenuator system in place both vertically and horizontally. Submit proposed design for review and
b. A galvanized steel winch platform is proposed. Platform to be approximately 10 feet by 12 feet in size. Submit design for review and approval.
LAKE 254113 Page 6 of 59
c. A rigid deck system shall be used to support the weight and access of staff to stand on the deck to adjust the winch.
d. Solid or Encased flotation devices shall be used. Exposed Styrofoam shall not be used.
e. Galvanized “Heavy” cleats shall be installed. A minimum of 2 cleats shall be firmly attached to the deck of the winch barge. Minimum of 15” cleats shall be used.
f. Hand or wheel crank marine winches shall be used. The winch drum capacity shall accommodate the manufactures recommended cable diameter for a water surface elevation between 1090’ and 1015’. The 11/20223 water surface elevation is currently at 1065’. The installed cable length for this project shall allow the barge to fluctuate between 1090’ and 1015’ without adding or removing additional cable.
g. Use manufacturers recommendation of stainless steel winch cable. Provide submittal for review and approval per manufactures recommendations.
h. The winch shall be placed on a galvanized winch riser. This will allow the operator room and easy access to the winch. The winch shall be securely secured to the riser which shall be securely attached to the platform.
i. The wave attenuator system shall be securely attached to the winch platform per manufactures recommendation of attachment points and sizes.
j. The anticipated number of winches and locations shall be designed and recommended per manufactures recommendations.
k. Contractor shall provide details and concept to the CO/COR as a submittal for review and approval.
l. Roller fairleads shall be used areas where the anchor cable may rest on another steel component or a redirection of the cable direction allowing easy adjustment of the cable length to reduce the friction of the cable against a fixed object.
J. A steady white light Solar Lighting system shall be installed. A light shall be installed at each individual section of breakwater between the anchor sections. Mounting the light on the winch barge is acceptable. The light shall be installed in a sturdy method. The light shall be resistant to the wave and wind action experienced on the lake. If the light becomes damaged, blown over or vandalized, the resulting lighting mount shall not cause damage to the wave attenuators themselves and not cause any of the attenuators to float away, sink or lose their ability as attenuators.
a. Navigation lights shall be solar-powered models with white light emitting diode and a visible range of 2 nautical miles.
b. Navigation lights shall be mounted on fence posts at the locations shown in the plans.
c. Navigation lights shall be set for a 4-second flash period with a flash length of 0.4 second.
LAKE 254113 Page 7 of 59
K. Materials and Equipment: The Contractor shall provide all materials, equipment, and labor required to perform the work described in this specification. All materials and equipment shall be NEW and Contractor furnished from outside the park. A schematic, equipment plans and equipment specifications shall be submitted to the NPS for approval before construction and installation. Follow the included approval submittal process.
Construction shall follow those approved submittals. Submit to the COR for review and approvals.
L. Floats, connections and materials used shall be industry standard.
M. The contractor shall provide their own access to the job site. Access includes the use of their own boat, vessel and work barge. Shuttle/transportation of the COR to the project site shall be done by the contractor if requested from the COR for site visits and inspections.
N. Scuba diving operations may be used. Any dive operator shall submit a dive operation and safety plan to the CO/COR for approval.
O. The water intake barge has a 6” HDPE water pipe and a power cable attached to it. Both lines shall be maintained and undisturbed. The anchor cables and anchor weights shall be placed not to disturb these utilities. The existing cables and anchor blocks from the water intake barge shall be preserved and undamaged. Breakwater anchor cables shall be placed with separation to not allow rubbing of the cables in existing conditions or future lowered lake levels. Use of the intake barge anchors for the breakwater anchors shall not be allowed.
P. A final inspection and operational testing shall be performed at the site with the COR and a representative of the Lake Mead Utility Systems Branch present.
Q. All excess material that has been removed/demolished or was unused shall be disposed of outside of the park boundaries.
R. A daily log shall be prepared by the contractor representing the work that was performed that day.
1. The log shall describe the tasks performed that day and the contractor staff working.
2. 2 or more representative photos of the tasks being performed that day shall be included in each daily log.
3. The submitted daily logs shall be in a PDF format. Emailing to the CO/COR is acceptable.
4. The daily logs shall be sent to the CO/COR once a week. For every week worked in the field, the daily log shall be sent to the CO/COR.
S. The Contractor shall manage a weekly progress meeting, conference call or Teams meeting between the contractor and the COR or NPS representatives. The need for the meeting shall be determined by the CO/COR and the contractor.
LAKE 254113 Page 8 of 59
1. A weekly schedule update shall be presented at the meeting. Schedule shall show the previous weeks accomplishments and tasks. The schedule shall show the proposed work schedule for the future two (2) weeks of work. Three (3) weeks of work shall be shown. It should be updated weekly and sent to the COR in a PDF format.
2. Photographs of the work progress shall be taken. Regular submittal of a PDF file showing representative progress photos, or a log of the previous weeks work shall be done weekly.
T. Other Items related to the Installation:
1. Items shown on the plans may vary in quantity and location. Field verify all items and underground/underwater components.
2. Notify the COR of construction phasing. Close coordination between the NPS and contractor is required in order to coordinate in down time of the existing water intake barge is needed. A 3-day notification to the NPS and COR is needed for any shutdown of the existing water intake barge for work. Any shutdown should occur during the mid-week. Tuesday, Wednesday or Thursday.
3. Photos of all connections are to be taken and provided, documenting the progress of the construction and the suitability of each connection. This is especially important of any connection, cable connector or piping that will be buried or placed underwater.
a. Photos shall be JPG format.
b. No labels or text shall be placed on the photographs.
c. High resolution photos are preferred.
d. Name or number the photos to represent the task shown in the photo.
e. Photo files shall be transmitted to the CO/COR at the end of construction as a part of the close out procedures.
4. Lake Mead contains the invasive Quagga Mussel.
a. The contactor will need to clean their equipment and vessels to safely transport their equipment once leaving Lake Mead NRA. Many state and regional inspection stations require inspections showing the cleaning of equipment that have been exposed to aquatic invasive species.
b. Lake Mead has decontamination stations located throughout the park.
c. Decontamination Stations are open 7 days from Oct 1st-April 30th 8:00a- 4:30p and from May 1st-Sept 30th 9:30a-8:00p, if you would like a decon you can call 702-757-5757 and we can schedule an appointment.
d. Nevada Department of Wildlife manages the operation of these cleaning stations.
LAKE 254113 Page 9 of 59
1.4 ESTIMATED SCOPE OF QUANTITIES
This quantity list may not be complete and accurate. Contractor shall field verify items and adjust their quantities accordingly. This list is included but not limited to:
1. Mobilize to Site
2. Porta-potty rental and associated site safety items
3. 500’ (Verify length) of Wave Attenuator equipment – purchase and install
4. Install a wave attenuator system
5. Cables and Anchors – purchase and install
6. Winch assemblies and/or barge – purchase and install
7. Motor Vessel use
8. Clean up and dispose of extra materials
9. Superintendent and project management
10. Bonds and Insurance
1.5 LOCATION
A. Project Location: Lake Mead near the Echo Bay developed area, Clark County, Nevada;
within Lake Mead National Recreation Area (LAKE NRA).
1.6 PERFORMANCE PERIOD: The project schedule is based on calendar days from the "Notice to Proceed" (NTP) date.
A soft NTP will be issued upon receipt of Division 1 submittals to allow purchase of materials.
A second NTP will be issued for On Site Construction work. Work to be started within 30 days of this NTP. The On-Site Construction Period of performance for this task is 60 calendar days.
1.7 FIELD VERIFICATION
A. The Contractor shall field verify all new and existing dimensions affecting the work in this contract before ordering any materials, equipment, or parts.
1.8 CONTRACTOR'S USE OF PREMISES
A. The site is located in public areas. Security of the equipment shall be maintained during construction.
B. Contractor shall at all times conduct his operations to ensure the least inconvenience to the recreation area visitors and employees.
C. The contractor shall at all times make the job site, laydown area and storage area safe to the public.
1. Traffic control devices shall be used around the active job site.
2. Markings, tape, or barriers shall be used to separate the work area on land from the public.
3. Signs and barriers shall be used when extended use of a launch ramp is used.
LAKE 254113 Page 10 of 59
D. Preservation of Natural Features: Confine all operations to work limits of the project.
Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
E. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for interruption of existing utility service, if appropriate.
1. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair the utility at no additional expense to the Government.
2. The NPS can assist to locate utilities but the NPS does not know where all of the utilities are located.
F. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent.
G. Work Limits: The Contractor shall be confined to conduct his work to job site area and work limits as shown on drawings or approved by the Contracting Officer. Contractor shall be responsible to pay for rehabilitation work for any resource damage outside authorized work limits.
H. Care shall be taken to ensure that fuel, oil and other spills do not occur. If spills occur, cleanup will be completed at no additional expense to the Government.
1.9 HOURS OF OPERATION
A. Hours of operation shall be Monday through Friday between the hours of 7:00 AM and 5:00 PM unless alternate hours are approved by the Contracting Officer and the Contracting Officers Representative (COR). Requests for changes shall be submitted to the COR.
B. Due to the location of the construction site and vicinity of the public, these hours should be adhered to including idling of equipment, starting of equipment, backup alarms of equipment and delivery of equipment in hours outside of the approved times.
1.10 SPECIAL PROVISIONS
A. Time Constraints:
1. Quiet Hours in the park are from 10:00 PM until 6:00 AM. The Contractor shall not operate equipment or make loud noise between these hours.
2. No work will be performed on weekends or on federal holidays without the advanced, written authorization of the CO.
3. Any request to work outside of normal working days and hours shall be submitted to the CO and COR at least 3 business days before the requested event for authorization.
B. Park Entry:
LAKE 254113 Page 11 of 59
1. The contractor shall furnish a list of personnel with phone contact information.
Vehicles associated with the contractor shall be waived entrance fee upon entering in a marked company vehicle or by providing the names of employees entering in personal vehicles. The entrance fee is waived only for the purpose of reporting directly to a specific work location. Any deviation for recreational purposes is subject to payment of required entrance fees.
C. Park Regulations:
1. Ensure all personnel (contractors, subcontractors, and vendors) entering or working in the park are familiar with and obey all park regulations. Law enforcement rangers will intervene if they perceive any unsafe or unlawful activity.
D. Emergency Medical and Accident Reporting:
1. All accidents and incidents shall be reported to the CO and COR.
a. The Contractor or subcontractor shall contact Park Dispatch for any medical emergency or traffic accident occurring within the Park.
Emergency number: Dial 911 as needed.
Park Dispatch: 702-293-8932 EMERGENCY
Park Dispatch is called so that the entrance station will be prepared should any emergency vehicles (e.g. ambulance) need to enter the Park and so that any available Emergency Medical Services personnel in the Park might respond until such time as the ambulance arrives.
b. The Contractor or subcontractor is required to report ANY personal injury and / or property damage incident occurring within the park. This report must be made to a Law Enforcement Ranger at the first available opportunity before leaving the park:
Park Dispatch: 702-293-8998 NON-EMERGENCY
E. Logistics:
1. The public access in the public areas shall always be maintained. NPS Employee access should be maintained to all facilities during construction.
2. The Contractor shall be responsible for the security of all materials staged/stored on LAKE NRA property.
3. The launch ramps may be used. They are open to the public. Public access to the launch ramp areas shall be maintained.
F. Environmental Compliance Requirements:
1. The Contractor and all employees working on the Project will be required to take “Desert Tortoise Awareness Training” which will be provided by the Government at no cost to the Contractor. This training will take approximately 30 minutes or less.
2. The Contractor’s employees shall never handle a desert tortoise.
LAKE 254113 Page 12 of 59
3. The Contractor and employees shall immediately report the presence of any desert tortoise to the COR.
4. Herbicides shall not be used in or around the Project site.
5. The environmental compliance contacts for this project are Clayton Merrill, Kelly Wallace, and Matthew D’ambrosi. For questions or additional information, contact the following people via email:
a. Kelly Wallace, Biologist: kelly_wallace@nps.gov
b. Matthew D’ambrosi, Biological Science Technician: matthew_dambrosi@nps.gov
G. Equipment Washing:
1. Equipment washing is required to preclude the introduction and spread of non-native species into the Park. Therefore, all equipment shall be cleaned outside of the Park before entering the Park. Equipment leaving the park for any reason must be re-washed before returning to the job site. Equipment that is moved from the job site, but remains within the original developed area, need not be re-washed prior to returning to the job site. It is also known that there are areas inside the Park that have non-native plants and weed species infestation. Therefore, before equipment can be moved from one developed area to another, it must be washed at the location identified on the Site Plan (see attached site plan and mileage table) to ensure weeds are not spread from one developed area to another.
2. The Contractor shall clean all equipment prior to the equipment entering Lake Mead National Recreation Area. It is recommended that cleaning be accomplished by hot water, pressure washing, using water only. All equipment surfaces shall be cleaned, with special emphasis given to the undercarriage. This includes, but is not limited to:
wheel wells, bumpers, radiator grills, springs, shock absorbers, wire harnesses, skid plates, oil pans, axles, frame ledges, buckets, tracks, belly pans, etc. Cleaning shall also include all dirt and debris inside the cab, or operator area. A Shop-Vac or commercial car wash vacuum system may be used for operator compartments, provided the method used effectively removes all visible debris. Equipment cleaning is for the purpose of removing any seed and soil accumulations to prevent the potential spread of non-native plant and weed species from outside the park to locations inside the park. Cleaning shall be performed in a manner that will reasonably remove all visible soil, plant and other foreign material. All equipment that requires washing shall be inspected by government personnel, or contractors/partners assigned to this duty, to ensure compliance.
3. Equipment that requires washing is generally defined as track or rubber-tired machinery intended for use primarily off-road. Examples include backhoes, loaders, earthmovers, graders, rollers, bulldozers, water trucks, etc; or four wheel drive or passenger vehicles that are driven in off road areas. Equipment may also be stationary, such as a material screening plant, conex storage containers, or a mobile office (mobile offices may be cleaned in the same manner as operator compartments
LAKE 254113 Page 13 of 59 as outlined in paragraph 2). The equipment is generally under the direct control of the contractor or sub-contractors, is likely to remain on the construction site for an extended period of time, and may contain adhered soil and seed from other project sites.
4. Equipment/Vehicles that do not require washing are defined as those normally used for highway driving only, and travel primarily on paved surfaces and well maintained service roads and parking areas (this includes approved staging areas). Examples include semi-tractor trailers, dump trucks, concrete trucks, pickup trucks, fuel trucks, service trucks, etc. These delivery and passenger vehicles are generally not under the direct control of the contractor, have no earth-moving function, and do not remain on the project site. These vehicles have a low probability of carrying adhered soil and seed from other projects. However, every vehicle and piece of equipment is subject to rejection from entering the park if there are obvious signs (covered in mud, plant material adhered to it, etc.) that it could be transporting non-native species into the Park.
H. Post Equipment Washing Inspections:
1. All equipment subject to inspection will be inspected by government, or other authorized personnel prior to leaving the paved surface or designated washing area identified on the Site Plan. Equipment determined to be free of soil or mud based on visual examination by government personnel will be cleared to enter the project area, or proceed to other areas of the park as appropriate. The Contractor shall arrange for needed inspections by contacting the NPS inspection office no less than 5 working days prior to the inspection. Such contact shall provide sufficient time to accommodate scheduling and travel to the site. Equipment not passing initial inspection must be rewashed outside the park at no additional expense to the government.
2. A list of government Inspectors for this project will be provided by the list below.
Please contact via email all members and coordinate designated representative for inspection:
a. Kelly Wallace, Biologist: kelly_wallace@nps.gov
b. Matthew D’ambrosi, Biological Science Technician: matthew_dambrosi@nps.gov
1.11 DESIGNATED OFFICIALS
A. The NPS Project Manager (PM) and Contracting Officer's Representative (COR) will be:
Carl Bush PE, Lake Mead NRA Telephone: 702-859-0194 (cell) E-mail: carl_bush@nps.gov
LAKE 254113 Page 14 of 59
B. The Contracting Officer (CO) will be:
TBD
END OF SECTION 01010
LAKE 254113 Page 15 of 59
LAKE MEAD NATIONAL RECREATION AREA
FIGURE 1
Project Site
Lake Mead Maintenance Building
LAKE 254113 Page 16 of 59
LAKE MEAD NRA DISTANCE CHART
FIGURE 2
LAKE 254113 Page 17 of 59
ECHO BAY SITE MAP
FIGURE 3
LAKE 254113 Page 18 of 59
ECHO BAY SITE MAP
FIGURE 4
LAKE 254113 Page 19 of 59
SECTION 01270 DEFINITION OF BID ITEMS
1.1 DESCRIPTION
A. The intent of this section is to explain, in general, what is and what is not included in a bid item, and the limits or cut-off points where one bid item ends, and another begins.
B. If no bid item exists for a portion of the work, include the costs in a related bid item.
1.2 LIST OF ANTICIPATED BID ITEMS
A. BID ITEM No. 01 – Install Additional Break Water System Components, as specified.
1. UNIT – lump sum
2. DEFINITION – Unit price includes all necessary labor, materials, and equipment to install the additional components to the existing breakwater. Work also includes but is not limited to: transportation vessel to the project site, equipment leasing, cables, anchors, lift equipment and mobilization/demobilization. All removed/demolished equipment and materials shall be transported and legally disposed of off-site.
END OF SECTION 01270
LAKE 254113 Page 20 of 59
SECTION 01310 PROJECT MANAGEMENT AND COORDINATION
1.1 SUMMARY
A. This Section includes administrative provisions for coordinating construction operations on this project including, but not limited to the following:
1. Supervisory and administrative personnel.
2. Project meetings.
3. Coordination procedures.
1.2 SUPERVISORY AND ADMINISTRATIVE PERSONNEL
A. General: In addition to the project superintendent, the Contractor shall provide other supervisory and administrative personnel as required for proper work performance. This may include special personnel required for coordination of operations with subcontractors and material suppliers.
B. Staff roster:
1. Within 14 days after the NTP, the Contractor shall submit a list of staff assignments, including subcontractor personnel (if applicable), working at the job site. Identify each individual and their duties and responsibilities.
1.3 PROJECT MEETINGS
A. Submittals required prior to the Preconstruction Conference.
1. Letter designating the Project Superintendent.
2. Proposed construction schedule.
3. Schedule of values.
4. Accident prevention plan.
5. Site health & safety plan.
6. A list of Subcontractors for this project.
7. Written statements from subcontractors certifying compliance with applicable labor standard clauses.
8. Satisfactory evidence of liability insurance coverage and workman’s compensation for the Contactor and all subcontractors.
9. Waste and recycling plan.
B. Preconstruction Conference: Once the contract is awarded, an initial orientation meeting will be scheduled for a time and date that is agreeable to the Government and Contractor
LAKE 254113 Page 21 of 59 and will be conducted in the Lake Mead Maintenance Building. Lake Mead personnel will be present to go over park specific requirements of the project with the Contractor and the Contractor’s supervisory and administrative team. The Notice to Proceed date will also be established at the Preconstruction Conference.
1. Agenda: Items to be discussed will include but not be limited to:
1. Park Rules and Regulations.
2. General correspondence procedures.
3. Labor standards provisions.
4. Payroll reports.
5. Payments to the Contractor.
6. Acceptance/rejection of work.
7. Progress Meetings.
8. Subcontractors.
9. Documents required under contract.
10. Local emergency phone number.
11. Specifications and drawings.
2. Once the Notice to Proceed date has been established, the Contractor shall submit the proposed work schedule to the Government for approval.
1.4 COORDINATION PROCEDURES
A. Coordination: Coordinate the construction operations identified in the various Sections of this Specification to ensure the efficient installation of all materials and equipment.
1. Schedule construction operations in the proper sequence required to obtain the best results where installation of one part of the Work depends on installation of other components before or after its own installation.
2. Coordinate installation of different components with subcontractors and Government personnel to ensure maximum accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
LAKE 254113 Page 22 of 59
1.5 INSTALLATION SCHEDULE REQUIREMENT
A. Installation Baseline Schedule: Prepare Installation Baseline Schedule using computerized scheduling software.
1. Installation Baseline Schedule shall show submittal review, installation start date, work activities / staff resources, activity durations, major milestones, inspection dates, closeout activities, and project end date.
2. Establish procedures for updating Installation Baseline Schedule and for reporting progress. Coordinate procedures with progress meeting and payment request dates.
3. Contracting Officer may request an updated Installation Schedule at any time to confirm progress of the work.
1.6 SCHEDULE OF VALUES
A. Submit a schedule of dollar values based on the Contract Bid Schedule. Include bond costs, mobilization, general condition costs, overhead, and profit in the total dollar value of unit price items and in the component parts of Work for each lump-sum item as described below. Do not include mobilization, general condition costs, overhead, or profit as separate items; however, payment for bond premiums can be made based upon evidence of payment to the surety. Bond premiums may be shown as a separate item.
B. Break down each lump sum Bid Item into component parts of Work for which progress payments may be requested. The total costs for the component parts of work shall equal the bid amount for the lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values.
C. The total cost of all items shall equal the contract total, or 100%. The Schedule of Values will form the basis for progress payments. Each progress payment request shall include the overall percentage complete to that date.
END OF SECTION 01310
LAKE 254113 Page 23 of 59
SECTION 01330 SUBMITTALS
A. The intent of this section is to explain submittal requirements before and during construction.
B. This section also includes the requirements for properly handling "Substitutions" and
"Comparable Products" the Contractor submits as being "equal" to the product that has been specified.
1.2 SUBMITTAL AND APPROVAL PROCEEDURES
A. All submittals shall be transmitted to the COR, as original and three (3) copies, using National Park Service form CM-16, dated 4/00.
1. A copy of the form is included at the end of this Section.
2. No action will be taken on a submittal unless it is accompanied by a transmittal form.
3. All submittals shall be carefully reviewed by the Contractor prior to submission to the
Government to eliminate errors.
B. Content of the RFI or Submittal: Include a detailed, legible description of item needing information or interpretation and the following:
1. RFI/Submittal number, numbered sequentially.
2. Date.
3. RFI subject.
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, as appropriate.
6. Contractor's suggested resolution. If Contractor's suggested resolution impacts the
Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
7. Contractor’s signature.
8. Requested date for response.
9. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, and details of affected materials, assemblies, and attachments on attached sketches.
C. Manufactures' Catalog Sheets: Submit only pertinent pages and mark each copy of standard printed data to identify products proposed for use. Submittal forms with attached Manufactures' Catalog Sheets that are not marked to identify products proposed for use will be disapproved by the COR and shall be resubmitted by the Contractor.
D. Manufactures' Installation Instructions: Provide one (1) complete set of instructions to the
COR and keep another complete set of instructions at the job site until substantial completion.
E. The Contractor shall forward submittals to the COR in accordance with the milestones.
LAKE 254113 Page 24 of 59
F. Lake Mead personnel will review and approve or disapprove and provide comment to submittals in as short a timeframe as possible, but not to exceed 7 calendar days.
G. Contracting Officer will not respond to RFIs submitted by other entities controlled by
Contractor.
H. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
1.3 REQUIREMENTS FOR APPROVED EQUALS
A. For each "Substitution" or "Comparable Product" the Contractor submits as being "equal" to the product that has been specified, the Contractor shall submit supporting documentation that includes:
1. Statement indicating why specified material or product cannot be provided.
2. Detailed comparison of the characteristics of the proposed item with that specified.
3. Changes required in other elements of the work because of the substitution.
4. Name, address, and telephone number of vendors.
5. Product data, including drawings, descriptions, fabrication, and samples as appropriate.
6. Manufacturer's literature regarding installation, operation and maintenance, schematics for electrical systems, and parts lists.
a. Describe availability of maintenance service and state a source of replacement parts and materials.
B. A request for approval constitutes a representation that the Contractor:
1. Has investigated the proposed item and determined that it is equal to or superior in all respects to that specified.
2. Shall provide the same warranties for the proposed item as for the item specified.
3. Has determined the proposed item is compatible with interfacing items.
4. Shall coordinate the installation of the alternate item and make all changes required in other elements of the work because of the substitution.
5. Wavier all claims for additional expenses the may be incurred as a result of the substitution.
C. If all of the requirements listed above are not met by the Contractor, the COR will disapprove the "Substitution" or "Comparable Product" request.
END OF SECTION 01330
LAKE 254113 Page 25 of 59
TRANSMITTAL - NATIONAL PARK SERVICE
LAKE 254113 Page 26 of 59
TRANSMITTAL CONTINUATION - NATIONAL PARK SERVICE
LAKE 254113 Page 27 of 59
SECTION 01360 ACCIDENT PREVENTION
A. After contract award and before the Pre-Construction conference, submit for review an
Accident Prevention Plan. The Contracting Officer will review the proposed Plan. If the plan requires any revisions or corrections, the Contractor shall resubmit the Plan within ten
(10) days. No progress payments will be made until the Plan is accepted.
1.2 SUBMITTALS
A. Accident Prevention Plan - The Plan shall be written to comply with OSHA and project requirements including but not limited to the following information/topics:
1. The name of the responsible supervisor who shall carry out the program.
2. Documentation of the personnel training program; both initial and continuing.
3. Weekly and monthly safety meetings.
4. First aid procedures.
5. Outline the work, associated hazards, protective measures, and the methods proposed to ensure property protection, safety of the public, National Park Service personnel, and Contractor's employees.
6. Planning and checklists for possible emergency situations.
7. A fire protection plan.
8. And a fall protection plan.
B. Daily Submittals: Submit Daily Quality Control Report showing all inspections and tests on the first workday following the date covered by the report.
C. Tests: Submit triplicate copies of complete test results not later than three calendar days after the test was performed. Submit failing test results and proposed remedial actions within four hours of noted deficiency.
D. Off Site Inspection Reports: Submit prior to shipment.
E. Progress Payments: If the CQC plan and Daily Quality Control Reports are not submitted in a timely manner, the Contracting Officer may retain an appropriate amount of the applicable progress payment.
1.3 QUALIFICATION OF EMPLOYEES
A. Ensure that employees are physically qualified to perform assigned duties in a safe manner.
LAKE 254113 Page 28 of 59
B. Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.
C. Operators of vehicles, mobile equipment, hoisting equipment, and hazardous plant equipment shall be able to understand signs, signals, and operating instructions, and be capable of operating such equipment. Provide operating instructions for all equipment.
1.4 ACCIDENT REPORTING
A. Reportable Accidents: A reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, fires, and property damage by accident in excess of $100. Notify Contracting Officer immediately in the event of a reportable accident. Within 7 days of a reportable accident, fill out and forward to Contracting Officer an Accident/Property Damage Report (Form CM-22). Form may be obtained from the Contracting Officer.
B. All Other Accidents: The Contractor shall report all other accidents to the Contracting Officer as soon as possible and assist the Contracting Officer and other officials as required in the investigation of the accident.
1.5 PERSONNEL PROTECTIVE EQUIPMENT
A. Meet requirements of National Institute for Occupational Safety and Health (NIOSH) and
OSHA.
B. Inspect personal protective equipment daily and maintain in a serviceable condition.
Clean, sanitize, and repair, as appropriate, personal items before issuing them to another individual.
C. Inspect and maintain other protective equipment and devices before use and on a periodic basis to ensure safe operation.
D. It is the Contractor's responsibility to require all those working on or visiting the site to wear necessary protective equipment at all times.
1.6 EMERGENCY INSTRUCTIONS
A. Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.
1.7 FIRST AID FACILITIES
A. Provide adequate facilities for the number of employees and the hazards associated with the types of ongoing construction work at the site.
1.7 SAFETY MEETINGS
A. As a minimum, conduct weekly 15-minute "toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite.
LAKE 254113 Page 29 of 59
B. Conduct monthly safety meetings for all levels of supervision. Notify the COR of meeting dates and times. These meetings shall be used to review the effectiveness of the Contractor's safety effort, to resolve current health and safety problems, to provide a forum for planning safe construction activities, and for updating the accident prevention program.
END OF SECTION 01360
LAKE 254113 Page 30 of 59
SECTION 01400 QUALITY REQUIREMENTS
A. The intent of this section is to explain the requirements for preparing and executing a Quality Control Program.
A. Quality Control Plan: At the time of the Pre-Construction Conference the Contractor shall submit for approval a written Contractor Quality Control (CQC) plan to the Government. If the plan requires any revisions or corrections, the Contractor shall resubmit the plan within 10 days. The Government reserves the right to require changes to the plan during the contract period as necessary to obtain the quality specified. No change in the approved plan may be made without written concurrence by the Contracting Officer. The plan shall include:
1. A list of personnel responsible for quality control. Include each person's qualifications.
2. A copy of a letter of direction to the Contractor's quality control supervisor outlining assigned duties.
3. Names and descriptions of laboratories to perform sampling and testing, and samples of proposed report forms.
4. Methods of monitoring and controlling environmental pollution and contamination as required by regulations and laws.
5. Methods of performing, documenting, and enforcing quality control of all work.
B. Daily Submittals: Submit Daily Quality Control Report showing all inspections and tests on the first workday following the date covered by the report.
C. Tests: Submit triplicate copies of complete test results not later than three calendar days after the test was performed. Submit failing test results and proposed remedial actions within four hours of noted deficiency.
D. Off Site Inspection Reports: Submit prior to shipment.
E. Progress Payments: If the CQC plan and Daily Quality Control Reports are not submitted in a timely manner, the Contracting Officer may retain an appropriate amount of the applicable progress payment.
1.3 QUALITY ASSURANCE
A. General: Except for tests or other items of work specified to be performed by the Government, the quality of all work shall be the responsibility of the Contractor. Inspect and test all work often enough to ensure that the quality of materials, workmanship, construction, finish, and functional performance is in compliance with applicable specifications and drawings.
LAKE 254113 Page 31 of 59
B. Quality Control Staff: The Contractor's job supervisory staff may be used for quality control, supplemented as necessary by additional technicians. The Contractor's designated Quality Control Supervisor shall be employed full time at the project site whenever contract work is in progress.
C. Testing Laboratory and Equipment: Employ certified independent laboratory to perform sampling and testing.
1. All measuring devices, laboratory equipment, and instruments shall be calibrated at established intervals against certified standards in accordance with NBS/NIST requirements. Upon request, measuring and testing devices shall be made available for use by the Government for verification tests.
2. The testing laboratory organization shall be experienced in the type of testing work to be done.
1.4 OFF-SITE CONTROL
A. Items that are fabricated or assembled off-site shall be inspected for quality control at the place of fabrication.
1.5 ON-SITE CONTROL
A. Notify the COR at least 24 hours in advance of the initial and follow-up phases.
B. Preparatory: Perform before beginning each feature of work.
1. Review control submittal requirements with personnel directly responsible for the quality control work.
2. Ensure that provisions have been made for field control testing.
3. Examine the work area to ensure that all preliminary work has been completed.
4. Verify all field dimensions and advise the COR of discrepancies.
5. Ensure that necessary equipment and materials are at the project site and that they comply with approved shop drawings and submittals.
C. Initial: As soon as work begins, inspect and test a representative portion of a particular feature of work for quality of workmanship. Review control testing procedures to ensure compliance with contract requirements.
D. Follow-Up: Inspect and test as work progresses to ensure compliance with contract requirements until completion of work.
1.6 DOCUMENTATION
A. Maintain Daily Quality Control Reports of quality control activities and tests. Daily Quality Control Reports may not be substituted for other written reports required under the General Provisions, such as Disputes, Differing Site Conditions, or Changes.
LAKE 254113 Page 32 of 59
1.7 ENFORCEMENT
A. The Contractor shall stop work on any item or feature pending satisfactory correction of any deficiency noted by the quality control staff or the COR. Construction shall not proceed on any feature of work containing uncorrected work.
END OF SECTION 01400
LAKE 254113 Page 33 of 59
SECTION 01510 TEMPORARY SERVICES
A. The work of this section consists of providing temporary services required for Contractor's performance of the work of this contract.
1.2 GENERAL REQUIREMENTS
A. Temporary materials may be new or used but must be adequate in capacity for the required usage, must not create unsafe conditions, and must not violate requirements of applicable codes and standards.
1.3 SANITARY FACILITES
A. Provide and maintain temporary toilet facilities in accordance with State Health Department and National Park Service requirements.
B. Sufficiently lighted and ventilated toilet facilities in weatherproof, sight-proof, handicap accessible, sturdy enclosures with privacy locks.
1.4 FIRE PROTECTION EQUIPMENT
A. Extinguisher shall have a minimum UL rating of 2-A: 10-B:C.
1.5 ELECTRICITY AND LIGHTING
A. Make arrangements with utility company for metered connection to existing utility and pay…