This document is an amendment to a solicitation for the "LAKE - ECHO BAY BARGE BREAKWATER PROJECT" contract. The key details are:

The purpose of this amendment is to answer contractor questions regarding the project timeline, use of the existing launch ramp, onsite concrete casting, quality control requirements, and need for engineering stamps. The bid due date remains September 12, 2024 at 11:00am PDT, and all other terms and conditions remain the same. The solicitation is being issued by the Department of the Interior National Park Service Pacific West Region for the design, production, and installation of a floating wave attenuator system. The agency clarified that a production and installation timeline will be considered, complete launch ramp shutdown is not acceptable, onsite concrete casting is not allowed, ISO 9001 certification and engineering stamps are not required qualifications.

View the file

Other files for this federal contract opportunity

Other files attached to LAKE - ECHO BAY BARGE BREAKWATER PROJECT, newest first.
File Type Posted
Sol_140P8124B0011_Amd_0005.pdf PDF
Sol_140P8124B0011_Amd_0004.pdf PDF
Sol_140P8124B0011_Amd_0002.pdf PDF
Sol_140P8124B0011_Amd_0001.pdf PDF
B08_-_Atch_1_-_EB_Barge_Breakwater__PMIS_254113_Specs_-_Update_07302024.pdf PDF
B08_-_Atch_3_-_Limitation_on_Subcontracting_Report.xlsx XLSX spreadsheet
Sol_140P8124B0011.pdf PDF
B08_-_Atch_2_-_Wage_Determination_NV20240024.pdf PDF
B08_-_Atch_4_-_Construction_Contraction_Administration.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

140P8124B0011 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

PPL

Boulder City NV 89005-2426 601 Nevada Way

NPS, PWR - LAKE MABO

08/30/20240003

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

08/13/2024

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

See Continuation Page

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Caroline Bachelier

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

140P8124B0011 Amendment 0003

The purpose of this amendment is to:

A. Answer Contractor Questions:

Question 1: Based on our extensive experience in design/building multiple wave attenuator systems, the allotted time is not sufficient. Typically, a job of this size would be 3 months for design (plus NPS response), 5-6 months for material procurement/manufacturing and 2-months for installation. Will the National Parks Service extend the completion time period, in order to have adequate time for a successful project?

Answer 1: Production and installation of the product timeline will be considered.

Question 2: Will the national park service allow partial shutdown of the existing launch ramp in order to launch the new floating wave attenuator modules. This will be necessary in order to launch the new modules in the water with equipment.

Answer 2: The EB Launch ramp currently only has 1 lane of in-water use. Complete shutdown of the launch ramp for an extended period would not be acceptable. We have to share the workspace with the public for access.

Question 3: Will the National Park Service allow the casting of new concrete anchor blocks to be casted onsite at the designated lay down are

Answer 3: No. The potential for washing concrete waste and wash water into the lake is present.

Question 4: Does the floating wave attenuator manufacture have to be ISO 9001 certified?

Having a verified quality control program helps ensure the floating wave attenuator system is built with quality and helps ensure client satisfaction in the publicly funded system.

Answer 4: No.

Question 5: Does the floating wave attenuator system need to be stamped by a licensed engineer?

Having a fully stamped engineered system will help ensure the floating wave attenuator is properly designed to handle the required design criteria in the RFP. Should the license engineer carry errors and omissions Insurance at a minimum of $5million dollars? This would help keep the designer liable with any problems with the design.

Answer 5: No. A PE stamp or a lack of a PE stamp on the design will not be a qualifier or used as a disqualifier. Engineer carrying insurance will not be used as a qualifier or disqualifier.

Question 6: Does the National Park Service have a current bathymetric survey showing the surrounding area with a radius of 500-1,000ft? Depth information is required in order to have to do an anchor layout design. Anchors will be further away from the water intake barge where the current depth measurement is noted.

Answer 6: This is what we currently have for a survey of the area.

B. The bid due date remains the same, September 12, 2024, at 1100 PDT.

C. All other terms and conditions remain the same.