B01 Attachment J02 - Final Construction Specifications.pdf
PDF 15 MB Posted
- Solicitation number
- 75H70122R00044
About this file
This document outlines a solicitation for construction services to remodel the Inpatient and Outpatient Pharmacies at Pine Ridge Hospital in Pine Ridge, South Dakota. The Indian Health Service is seeking a contractor to demolish and replace the existing pharmacy spaces. The estimated value of the contract is between $1 million and $5 million. The period of performance is 365 calendar days from the notice to proceed. This procurement is set aside for small businesses with a preference for Indian Economic Enterprises. The selected contractor will be awarded a firm fixed-price contract determined by lowest price technically acceptable criteria. The solicitation includes plans, specifications and wage determinations for offerors to prepare proposals. The site visit details and registration requirements are also provided. Proposals are due by the date specified in the solicitation, which is available on SAM.gov along with any amendments.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
HFG Architecture, LLC © 2022
Pine Ridge Comprehensive Healthcare Facility
Design USP 795, 797, 800 Pharmacy Renovation
Pine Ridge, SD | Task Order No:75H70121F30008 | Contract No.: HHSI10220180005I
PROJECT MANUAL | SPECIFICATIONS
FINAL CONSTRUCTION DOCUMENTS | 05-26-2022
http://www.hfgarchitecture.com/
PINE RIDGE USP 795,797,800 PHARMACY RENOVATION
HFG Architecture © 2022
PROJECT DIRECTORY
00 01 03 - 1
SECTION 00 01 03
PROJECT DIRECTORY
PART 1 GENERAL
SECTION INCLUDES
Identification of project team members and their contact information.
OWNER:
Name: Indian Health Service.
Address: 607 Indian Health Road.
City: Pine Ridge.
State: South Dakota.
Zip Code: 57770.
Telephone: 605-867-5131.
Primary Contact: All correspondence from the Contractor to the Architect will be through this party, unless alternate arrangements are mutually agreed upon at preconstruction meeting.
Title: COR.
Name: Corey Sawatzky.
Email: corey.sawatzky@ihs.gov.
CONSULTANTS:
Architect: Design Professional of Record. All correspondence from the Contractor regarding construction documents authored by Architect's consultants will be direct, with copies to this party, unless alternate arrangements are mutually agreed upon at preconstruction meeting.
Company Name: HFG Architecture.
Address: 330 N Mead, Suite 100.
City: Wichita.
State: Kansas.
Zip Code: 67202.
Telephone: 316-262-2500.
Primary Contact: .
Title: Project Manager.
Name: Wayne Bongartz.
Email: wayneb@hfgarchitecture.com.
Interior Design Consultant:
Company Name: HFG Architecture.
Address: 330 N Mead, Suite 100.
City: Wichita.
State: Kansas.
Zip Code: 67202.
Telephone: 316-262-2500.
Primary Contact: .
Title: Seniior Interior Designer.
Name: Susan Sanders.
Email: susans@hfgarchitecture.com.
Mechanical/Electrical/Plumbing Engineering Consultant Company Name: HP Engineering.
Address: 16 S. Lewis Ave.
City: Tulsa.
State: Oklahoma.
Zip Code: 74104.
Telephone: 918-895-6510.
Primary Contact: .
PROJECT DIRECTORY
00 01 03 - 2
Title: Project Manager.
Name: Jamison Miranda.
Email: jmiranda@hpengineering.com.
END OF SECTION
TABLE OF CONTENTS
00 01 10 - 1
SECTION 00 01 10
TABLE OF CONTENTS
PROCUREMENT AND CONTRACTING REQUIREMENTS
DIVISION 00 -- PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 03 - Project Directory 00 01 10 - Table of Contents 00 01 15 - List of Drawing Sheets - See Title Sheet on the Drawings
SPECIFICATIONS
DIVISION 01 -- GENERAL REQUIREMENTS
01 10 00 - Summary 01 25 00 - Substitution Procedures 01 30 00 - Administrative Requirements 01 32 16 - Construction Progress Schedule 01 35 53 - Security Procedures 01 40 00 - Quality Requirements 01 42 16 - Definitions 01 50 00 - Temporary Facilities and Controls 01 51 00 - Temporary Utilities 01 52 13 - Field Offices and Sheds 01 55 00 - Vehicular Access and Parking 01 57 19 - Temporary Environmental Controls 01 58 13 - Temporary Project Signage 01 60 00 - Product Requirements 01 61 16 - Volatile Organic Compound (VOC) Content Restrictions 01 70 00 - Execution and Closeout Requirements 01 74 19 - Construction Waste Management and Disposal 01 78 00 - Closeout Submittals 01 79 00 - Demonstration and Training 01 91 00 - General Commissioning Requirements
DIVISION 02 -- EXISTING CONDITIONS
02 41 00 - Demolition
DIVISION 05 -- METALS
05 50 00 - Metal Fabrications 05 70 10 - Expanded Metal
DIVISION 06 -- WOOD, PLASTICS, AND COMPOSITES
06 10 00 - Rough Carpentry 06 41 16 - Plastic Laminate Casework - Custom
DIVISION 07 -- THERMAL AND MOISTURE PROTECTION
07 21 00 - Thermal Insulation 07 54 23 - Thermoplastic Polyolefin (TPO) Membrane Roofing 07 84 00 - Firestopping
TABLE OF CONTENTS
00 01 10 - 2
07 92 00 - Joint Sealants
DIVISION 08 -- OPENINGS
08 11 13 - Hollow Metal Doors and Frames 08 14 16 - Flush Wood Doors 08 31 00 - Access Doors and Panels 08 33 13 - Coiling Counter Doors 08 71 00 - Door Hardware 08 80 00 - Glazing
DIVISION 09 -- FINISHES
09 05 61 - Common Work Results for Flooring Preparation 09 21 16 - Gypsum Board Assemblies 09 22 16 - Non-Structural Metal Framing 09 51 00 - Acoustical Ceilings 09 65 00 - Resilient Flooring 09 90 00 - Painting and Coating - Healthcare Facility Guide Spec 09 93 00 - Staining and Transparent Finishing
DIVISION 10 -- SPECIALTIES
10 14 00 - Signage 10 22 13 - Wire Mesh Partitions 10 26 00 - Wall and Door Protection 10 28 13 - Toilet Accessories 10 44 00 - Fire Protection Specialties 10 51 13 - Metal Lockers 10 56 13 - Metal Storage Shelving 10 56 26 - High Density Mobile Storage Shelving
DIVISION 11 -- EQUIPMENT
11 53 13 - Laboratory Fume Hoods
DIVISION 12 -- FURNISHINGS
12 31 00 - Manufactured Metal Casework-Mid-Mark
A. 12 34 53 - Modular Systems Furniture 12 35 53.13 - Metal Laboratory Casework-Herman Miller Co/Struc 12 36 00 - Countertops 12 50 00 - Modular Systems Furniture-Herman Miller Action Office 2
B. 12 51 16 - Plastic Laminate Modular Casework- Herman Miller Mora and Nevi Ht Adj Desks
DIVISION 13 -- SPECIAL CONSTRUCTION (NOT USED)
DIVISION 21 -- FIRE SUPPRESSION
21 05 13 - Common Motor Requirements for Fire Suppression Equipment 21 05 17 - Sleeves and Sleeve Seals for Fire Suppression Piping 21 05 18 - Escutcheons for Fire-Suppression Piping 21 05 23 - General-Duty Valves for Water-Based Fire-Suppression Piping 21 05 48 - Vibration and Seismic Controls for Fire Suppression Piping and Equipment
TABLE OF CONTENTS
00 01 10 - 3
21 05 53 - Identification for Fire Suppression Piping and Equipment 21 07 00 - Fire-Suppression Systems Insulation 21 08 00 – Commissioning of Fire Suppression Systems 21 13 13 - Wet Pipe Sprinkler System
DIVISION 22 -- PLUMBING
22 05 00 - Common Work Results for Plumbing 22 05 13 - Common Motor Requirements for Plumbing Equipment 22 05 16 - Expansion Fittings and Loops for Plumbing Piping 22 05 19 - Meters and Gauges for Plumbing Piping 22 05 23 - General-Duty Valves for Plumbing Piping 22 05 29 - Hangers and Supports for Plumbing Piping and Equipment 22 05 48 - Vibration and Seismic Controls for Plumbing Piping and Equipment 22 05 53 - Identification for Plumbing Piping and Equipment 22 07 00 - Plumbing Insulation 22 11 16 - Domestic Water Piping 22 13 16 - Sanitary Waste and Vent Piping 22 13 19 - Sanitary Waste Piping Specialties 22 31 00 - Domestic Water Softeners 22 40 00 - Plumbing Fixtures 22 43 00 - Healthcare Plumbing Fixtures 22 45 00 - Emergency Plumbing Fixtures 22 47 00 - Drinking Fountains and Water Coolers
DIVISION 23 -- HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC)
23 01 30.51 - HVAC Air-Distribution System Cleaning 23 05 00 - Common Work Results for HVAC 23 05 13 - Common Motor Requirements for HVAC Equipment 23 05 16 - Expansion Fittings and Loops for HVAC Piping 23 05 19 - Meters and Gauges for HVAC Piping 23 05 23 - General-Duty Valves for HVAC Piping 23 05 29 - Hangers and Supports for HVAC Piping and Equipment 23 05 48 - Vibration and Seismic Controls for HVAC 23 05 53 - Identification for HVAC Piping and Equipment 23 05 93 - Testing, Adjusting, and Balancing for HVAC 23 07 00 - HVAC Insulation 23 08 00 - Commissioning of HVAC 23 09 00 - Instrumentation And Control for HVAC 23 09 15 - Variable Speed Drives 23 21 10 - Condensate Piping 23 21 13 - Hydronic Pipoing 23 21 23 - Hydronic Pumps 23 23 00 - Refrigerant Piping
TABLE OF CONTENTS
00 01 10 - 4
23 25 00 - HVAC Water Treatment 23 31 13 - Metal Ducts 23 33 00 - Air Duct Accessories 23 34 16 - Centrifugal HVAC Fans 23 34 23 - HVAC Power Ventilators 23 36 00 - Air Terminal Units 23 37 13 - Diffusers, Registers, and Grilles 23 38 16 - Fume Hoods for Laboratory Use 23 41 00 - Particulate Air Filtration
DIVISION 25 -- INTEGRATED AUTOMATION (NOT USED)
DIVISION 26 -- ELECTRICAL
26 00 00 - General Electrical Reequirements 26 05 19 - Low-Voltage Electrical Power Conductors and Cables 26 05 23 - Control-Voltage Electrical Power Cables 26 05 26 - Grounding and Bonding for Electrical Systems 26 05 29 - Hangers and Supports for Electrical Systems 26 05 33 - Raceway And Boxes for Electrical Systems 26 05 44 - Sleeves And Sleeve Seals for Electrical Raceways and Cabling 26 05 48.16 - Seismic Controls for Electrical Systems 26 05 53 - Identification for Electrical Systems 26 05 73.13 - Short-Circuit Studies 26 05 73.16 - Coordination Studies 26 05 73.19 - Arc-Flash Hazard Analysis 26 08 00 - Commissioning of Electrical Systems 26 09 23 - Lighting Control Devices 26 22 00 - Low-voltage Transformers 26 24 16 - Panelboards 26 27 26 - Wiring Devices 26 28 16 - Enclosed Switches and Circuit Breakers 26 36 00 - Transfer Switches 26 29 23 - Variable-Frequency Motor Controllers 26 51 00 - Interior Lighting 26 52 13 - Emergency and Exit Lighting
DIVISION 28 -- ELECTRONIC SAFETY AND SECURITY
28 08 00 - Commissioning of Safety and Security Systems 28 31 11 - Digital, Addressable Fire-Alarm System
DIVISION 40 -- PROCESS INTEGRATION
SUMMARY
01 10 00 - 1
SECTION 01 10 00
SUMMARY
PART 1 GENERAL
1.01 PROJECT
A. Project Name: Pine Ridge Pharmacy Renovation B. Architect's Name: HFG Architecture.
C. The Project consists of the construction of Pharmacy Expansion and Renovation.
1.02 CONTRACT DESCRIPTION
A. Contract Type: General, Structural, Mechanical and Electrical work,
1.03 DESCRIPTION OF ALTERATIONS WORK
A. Scope of demolition and removal work is indicated on drawings and specified in Section 02 41
00.
B. Scope of alterations work is indicated on drawings.
C. Renovate the following areas, complete including operational mechanical and electrical work and finishes:
D. Plumbing: Alter existing system and add new construction, keeping existing in operation.
E. HVAC: Alter existing system and add new construction, keeping existing in operation.
F. Electrical Power and Lighting: Alter existing system and add new construction, keeping existing in operation.
G. Fire Suppression Sprinklers: Alter existing system and add new construction, keeping existing in operation.
H. Fire Alarm: Alter existing system and add new construction, keeping existing in operation.
I. Telephone: Alter existing system and add new construction, keeping existing in operation.
J. Security System: Alter existing system and add new construction, keeping existing in operation.
1.04 WORK BY OWNER
A. Items noted NIC (Not in Contract) will be supplied and installed by Owner before Substantial
Completion. Some items include:
1. Movable cabinets.
2. Furnishings.
3. Pharmacy equipment.
B. Owner will supply and install items as indicated on teh Equipment Plans C. Owner will supply equipment for installation by Contractor as indicated on the Equipment Plans
1.05 OWNER OCCUPANCY
A. Owner intends to continue to occupy adjacent portions of the existing building during the entire construction period.
B. Owner intends to occupy the Project upon Substantial Completion.
C. Cooperate with Owner to minimize conflict and to facilitate Owner's operations.
D. Schedule the Work to accommodate Owner occupancy.
1.06 CONTRACTOR USE OF SITE AND PREMISES
A. Construction Operations: Limited to areas noted on Drawings.
1. Locate and conduct construction activities in ways that will limit disturbance to site.
B. Arrange use of site and premises to allow:
1. Owner occupancy.
2. Work by Others.
SUMMARY
01 10 00 - 2
3. Work by Owner.
4. Use of site and premises by the public.
C. Provide access to and from site as required by law and by Owner:
1. Emergency Building Exits During Construction: Keep all exits required by code open during construction period; provide temporary exit signs if exit routes are temporarily altered.
2. Do not obstruct roadways, sidewalks, or other public ways without permit.
D. Existing building spaces may not be used for storage.
E. Utility Outages and Shutdown:
1. Limit disruption of utility services to hours the building is unoccupied.
2. Do not disrupt or shut down life safety systems, including but not limited to fire sprinklers and fire alarm system, without 7 days notice to Owner and authorities having jurisdiction.
3. Prevent accidental disruption of utility services to other facilities.
1.07 WORK SEQUENCE
A. Construct Work in phases during the construction period. Phases are noted on the Drawings
1.08 SPECIFICATION SECTIONS APPLICABLE TO CONTRACT
A. Unless otherwise noted, all provisions of the sections listed below apply to all. Specific items of work listed undercontract descriptions constitute exceptions.
B. Section 01 30 00 - Administrative Requirements.
C. Section 01 32 16 - Construction Progress Schedule.
D. Section 01 70 00 - Execution and Closeout Requirements.
E. Section 01 78 00 - Closeout Submittals.
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION - NOT USED
SUBSTITUTION PROCEDURES
01 25 00 - 1
SECTION 01 25 00
SUBSTITUTION PROCEDURES
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Procedural requirements for proposed substitutions.
1.02 RELATED REQUIREMENTS
1.03 DEFINITIONS
A. Substitutions: Changes from Contract Documents requirements proposed by Contractor to materials, products, assemblies, and equipment.
B. Substitutions: See General Conditions for definition.
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION
3.01 GENERAL REQUIREMENTS
A. A Substitution Request for products, assemblies, materials, and equipment constitutes a representation that the submitter:
1. Has investigated proposed product and determined that it meets or exceeds the quality level of the specified product, equipment, assembly, or system.
2. Agrees to provide the same warranty for the substitution as for the specified product.
3. Agrees to coordinate installation and make changes to other work that may be required for the work to be complete, with no additional cost to Owner.
4. Waives claims for additional costs or time extension that may subsequently become apparent.
B. Document each request with complete data substantiating compliance of proposed substitution with Contract Documents. Burden of proof is on proposer.
C. Content: Include information necessary for tracking the status of each Substitution Request, and information necessary to provide an actionable response.
D. Limit each request to a single proposed substitution item.
3.02 RESOLUTION
3.03 ACCEPTANCE
SUBSTITUTION PROCEDURES
01 25 00 - 2
ADMINISTRATIVE
REQUIREMENTS
01 30 00 - 1
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Preconstruction meeting.
B. Site mobilization meeting.
C. Progress meetings.
D. Construction progress schedule.
E. Coordination drawings.
F. Submittals for review, information, and project closeout.
G. Number of copies of submittals.
H. Requests for Information (RFI) procedures.
I. Submittal procedures.
1.02 RELATED REQUIREMENTS
A. Section 01 32 16 - Construction Progress Schedule: Form, content, and administration of schedules.
B. Section 01 70 00 - Execution and Closeout Requirements: Additional coordination requirements.
C. Section 01 78 00 - Closeout Submittals: Project record documents; operation and maintenance data; warranties and bonds.
1.03 PROJECT COORDINATOR
A. Cooperate with the COR in allocation of mobilization areas of site; for field offices and sheds, for building access, traffic, and parking facilities.
B. During construction, coordinate use of site and facilities through the COR.
C. Comply with COR procedures for intra-project communications; submittals, reports and records, schedules, coordination drawings, and recommendations; and resolution of ambiguities and conflicts.
D. Comply with instructions of the COR for use of temporary utilities and construction facilities.
E. Coordinate field engineering and layout work under instructions of the COR F. Make the following types of submittals to Architect through the COR:
1. Requests for Information.
2. Requests for substitution.
3. Shop drawings, product data, and samples.
4. Test and inspection reports.
5. Design data.
6. Manufacturer's instructions and field reports.
7. Applications for payment and change order requests.
8. Progress schedules.
9. Coordination drawings.
10. Correction Punch List and Final Correction Punch List for Substantial Completion.
11. Closeout submittals.
ADMINISTRATIVE
REQUIREMENTS
01 30 00 - 2
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION
3.01 PRECONSTRUCTION MEETING
A. Schedule meeting after Notice of Award.
B. IHS (CO/COR) will schedule a meeting after Notice of Award.
C. Attendance Required:
1. IHS
2. HFG Architect
3. Contractor.
D. Agenda:
1. Execution.
2. Submission of executed bonds and insurance certificates.
3. Distribution of Contract Documents.
4. Submission of list of subcontractors, list of products, schedule of values, and progress schedule.
5. Designation of personnel representing the parties to Contract, IHS and Architect.
6. Procedures and processing of field decisions, submittals, substitutions, applications for payments, proposal request, Change Orders, and Contract closeout procedures.
7. Scheduling.
8. Owner review of Contractors procedures for "Dust and Infection Control"Construction
Phasing or Sequuencing of construction Activities and Life Safety Measures to ensure all fire exits are maintained and clear. Identify aa Staging Areas for Material and Contractor Personnel, Trash Dumbsters, Port A Potties etc. Owner approve before construction begins.
E. Record minutes and distribute copies within two days after meeting to participants, with two copies to Architect, Owner, participants, and those affected by decisions made.
3.02 SITE MOBILIZATION MEETING
A. IHS (CO/COR) will schedule a meeting at the Project site prior to Contractor occupancy.
B. Attendance Required:
1. Contractor.
2. IHS
3. HFG Architect
4. Special consultants.
5. Contractor's superintendent.
6. Major subcontractors.
C. Agenda:
1. Use of Premises by IHS and Contractor.
2. IHS Requirements
3. Construction facilities and controls provided by Owner.
4. Temporary utilities provided by Owner.
5. Security and housekeeping procedures.
6. Schedules.
7. Application for payment procedures.
8. Procedures for testing.
9. Procedures for maintaining record documents.
10. Requirements for start-up of equipment.
11. Inspection and acceptance of equipment put into service during construction period.
ADMINISTRATIVE
REQUIREMENTS
01 30 00 - 3
D. Record minutes and distribute copies within two days after meeting to participants, with two copies to Architect, Owner, participants, and those affected by decisions made.
3.03 PROGRESS MEETINGS
A. Schedule and administer meetings throughout progress of the work at maximum bi-monthly intervals.
B. Make arrangements for meetings, prepare agenda with copies for participants, preside at meetings.
C. Attendance Required:
1. Contractor.
2. Owner.
3. Architect.
4. Special consultants.
5. Contractor's superintendent.
6. Major subcontractors.
D. Agenda:
1. Review minutes of previous meetings.
2. Review of work progress.
3. Field observations, problems, and decisions.
4. Identification of problems that impede, or will impede, planned progress.
5. Review of submittals schedule and status of submittals.
6. Review of RFIs log and status of responses.
7. Maintenance of progress schedule.
8. Corrective measures to regain projected schedules.
9. Planned progress during succeeding work period.
10. Maintenance of quality and work standards.
11. Effect of proposed changes on progress schedule and coordination.
12. Other business relating to work.
E. Record minutes and distribute copies within two days after meeting to participants, with two copies to Architect, Owner, participants, and those affected by decisions made.
3.04 CONSTRUCTION PROGRESS SCHEDULE
A. Within 10 days after date Contract, submit preliminary schedule defining planned operations for the first 60 days of work, with a general outline for remainder of work.
B. If preliminary schedule requires revision after review, submit revised schedule within 10 days.
C. Within 20 days after review of preliminary schedule, submit draft of proposed complete schedule for review.
1. Include written certification that major contractors have reviewed and accepted proposed schedule.
D. Within 10 days after joint review, submit complete schedule.
E. Submit updated schedule with each Application for Payment.
3.05 COORDINATION DRAWINGS
A. Provide information required by COR for preparation of coordination drawings.
B. Review drawings prior to submission to
3.06 REQUESTS FOR INFORMATION (RFI)
A. Definition: A request seeking one of the following:
1. An interpretation, amplification, or clarification of some requirement of Contract Documents arising from inability to determine from them the exact material, process, or system to be installed; or when the elements of construction are required to occupy the
ADMINISTRATIVE
REQUIREMENTS
01 30 00 - 4 same space (interference); or when an item of work is described differently at more than one place in Contract Documents.
2. A resolution to an issue which has arisen due to field conditions and affects design intent.
B. Preparation: Prepare an RFI immediately upon discovery of a need for interpretation of
Contract Documents. Failure to submit a RFI in a timely manner is not a legitimate cause for claiming additional costs or delays in execution of the work.
1. Prepare a separate RFI for each specific item.
2. Prepare in a format and with content acceptable to
3. Prepare using an electronic version of the form appended to this section.
3.07 SUBMITTALS FOR REVIEW
A. When the following are specified in individual sections, submit them for review:
1. Product data.
2. Shop drawings.
3. Samples for selection.
4. Samples for verification.
B. Submit to COR for review for the limited purpose of checking for compliance with information given and the design concept expressed in the contract documents.
C. Samples will be reviewed for aesthetic, color, or finish selection.
D. After review, provide copies and distribute in accordance with SUBMITTAL PROCEDURES article below and for record documents purposes described in Section 01 78 00 - Closeout Submittals.
3.08 SUBMITTALS FOR INFORMATION
A. When the following are specified in individual sections, submit them for information:
1. Design data.
2. Certificates.
3. Test reports.
4. Inspection reports.
5. Manufacturer's instructions.
6. Manufacturer's field reports.
7. Other types indicated.
B. Submit for COR knowledge as contract administrator or for Owner.
3.09 SUBMITTALS FOR PROJECT CLOSEOUT
A. Submit Correction Punch List for Substantial Completion.
B. Submit Final Correction Punch List for Substantial Completion.
C. When the following are specified in individual sections, submit them at project closeout in compliance with requirements of Section 01 78 00 - Closeout Submittals:
1. Project record documents.
2. Operation and maintenance data.
3. Warranties.
4. Bonds.
5. Other types as indicated.
D. Submit for Owner's benefit during and after project completion.
3.10 NUMBER OF COPIES OF SUBMITTALS
A. Electronic Documents: Submit one electronic copy in PDF format; an electronically-marked up file will be returned. Create PDFs at native size and right-side up; illegible files will be rejected.
B. Documents for Review:
ADMINISTRATIVE
REQUIREMENTS
01 30 00 - 5
1. Small Size Sheets, Not Larger Than 8-1/2 by 11 inches: Submit the number of copies that requires, plus two copies that will be retained by COR
2. Larger Sheets, Not Larger Than 36 by 48 inches: Submit the number of opaque reproductions that Contractor requires, plus two copies that will be retained by Architect
C. Documents for Information: Submit two copies.
D. Samples: Submit the number specified in individual specification sections; one of which will be retained by the COR
1. After review, produce duplicates.
2. Retained samples will not be returned to Contractor unless specifically so stated.
3.11 SUBMITTAL PROCEDURES
A. General Requirements:
1. Transmit using approved form.
2. Sequentially identify each item. For revised submittals use original number and a sequential numerical suffix.
3. Identify: Project; Contractor; subcontractor or supplier; pertinent drawing and detail number; and specification section number and article/paragraph, as appropriate on each copy.
4. Apply Contractor's stamp, signed or initialed certifying that review, approval, verification of products required, field dimensions, adjacent construction work, and coordination of information is in accordance with the requirements of the work and Contract Documents.
5. Deliver each submittal on date noted in submittal schedule, unless an earlier date has been agreed to by all affected parties, and is of the benefit to the project.
a. Deliver submittals to Architect at business address.
6. Schedule submittals to expedite the Project, and coordinate submission of related items.
a. For each submittal for review, allow 15 days excluding delivery time to and from the
Contractor.
7. Provide space for Contractor and Architect review stamps.
8. When revised for resubmission, identify all changes made since previous submission.
9. Distribute reviewed submittals. Instruct parties to promptly report inability to comply with requirements.
10. Submittals not requested will not be recognized or processed.
ADMINISTRATIVE
REQUIREMENTS
01 30 00 - 6
CONSTRUCTION PROGRESS
SCHEDULE
01 32 16 - 1
SECTION 01 32 16
CONSTRUCTION PROGRESS SCHEDULE
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Preliminary schedule.
B. Construction progress schedule, bar chart type.
1.02 RELATED SECTIONS
A. Section 01 10 00 - Summary: Work sequence.
1.03 SUBMITTALS
A. Within 10 days after date of Contract, submit preliminary schedule B. If preliminary schedule requires revision after review, submit revised schedule within 10 days.
C. Within 20 days after review of preliminary schedule, submit draft of proposed complete schedule for review.
D. Within 10 days after joint review, submit complete schedule.
E. Submit updated schedule with each Application for Payment.
F. Submit the number of opaque reproductions that Contract requires, plus two copies that will be retainby COR G. Submit under transmittal letter form specified in Section 01 30 00 - Administrative
Requirements.
1.04 QUALITY ASSURANCE
1.05 SCHEDULE FORMAT
A. Listings: In chronological order according to the start date for each activity. Identify each activity with the applicable specification section number.
B. Sheet Size: Multiples of 8-1/2 x 11 inches.
C. Scale and Spacing: To allow for notations and revisions.
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION
3.01 PRELIMINARY SCHEDULE
A. Prepare preliminary schedule in the form of a horizontal bar chart.
3.02 CONTENT
A. Show complete sequence of construction by activity, with dates for beginning and completion of each element of construction.
B. Identify each item by specification section number.
C. Identify work of separate stages and other logically grouped activities.
D. Show accumulated percentage of completion of each item, and total percentage of Work completed, as of the first day of each month.
E. Provide legend for symbols and abbreviations used.
3.03 BAR CHARTS
A. Include a separate bar for each major portion of Work or operation.
B. Identify the first work day of each week.
CONSTRUCTION PROGRESS
SCHEDULE
01 32 16 - 2
3.04 REVIEW AND EVALUATION OF SCHEDULE
A. Participate in joint review and evaluation of schedule with Architect at each submittal.
B. Evaluate project status to determine work behind schedule and work ahead of schedule.
C. After review, revise as necessary as result of review, and resubmit within 10 days.
3.05 UPDATING SCHEDULE
A. Maintain schedules to record actual start and finish dates of completed activities.
B. Indicate progress of each activity to date of revision, with projected completion date of each activity.
C. Annotate diagrams to graphically depict current status of Work.
D. Identify activities modified since previous submittal, major changes in Work, and other identifiable changes.
E. Indicate changes required to maintain Date of Substantial Completion.
F. Submit reports required to support recommended changes.
3.06 DISTRIBUTION OF SCHEDULE
A. Distribute copies of updated schedules to Contract project site file, to subcontractors, suppliers, Architect, Owner, and other concerned parties.
B. Instruct recipients to promptly report, in writing, problems anticipated by projections indicated in schedules.
SECURITY PROCEDURES
01 35 53 - 1
SECTION 01 35 53
SECURITY PROCEDURES
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Security measures including formal security program, entry control, personnel identification, guard service, miscellaneous restrictions, and _____.
1.02 RELATED REQUIREMENTS
A. Section 01 10 00 - Summary: use of premises and occupancy.
B. Section 01 50 00 - Temporary Facilities and Controls: Temporary lighting.
1.03 SECURITY PROGRAM
A. Protect Work, existing premises and Owner's operations from theft, vandalism, and unauthorized entry.
B. Initiate program at project mobilization.
C. Initiate program in coordination with Owner's existing security system at project mobilization.
D. Maintain program throughout construction period until Owner occupancy.
1.04 ENTRY CONTROL
A. Restrict entrance of persons and vehicles into Project site and existing facilities.
B. Allow entrance only to authorized persons with proper identification.
1.05 PERSONNEL IDENTIFICATION
A. Provide identification badge to each person authorized to enter premises.
B. Badge To Include: Personal photograph, name, assigned number, expiration date and employer.
C. Require return of badges at expiration of their employment on the Work.
1.06 GUARD SERVICE
1.07 RESTRICTIONS
A. Do not allow cameras on site or photographs taken except by written approval of Owner.
SECURITY PROCEDURES
01 35 53 - 2
QUALITY REQUIREMENTS
01 40 00 - 1
SECTION 01 40 00
QUALITY REQUIREMENTS
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Submittals.
B. Quality assurance.
C. References and standards.
D. Testing and inspection agencies and services.
E. Control of installation.
F. Tolerances.
G. Manufacturers' field services.
H. Defect Assessment.
1.02 RELATED REQUIREMENTS
A. Section 01 21 00 - Allowances: Allowance for payment of testing services.
B. Section 01 30 00 - Administrative Requirements: Submittal procedures.
C. Section 01 42 16 - Definitions.
D. Section 01 60 00 - Product Requirements: Requirements for material and product quality.
1.03 REFERENCE STANDARDS
A. ASTM C1021 - Standard Practice for Laboratories Engaged in Testing of Building Sealants;
2008 (Reapproved 2014).
B. ASTM C1077 - Standard Practice for Agencies Testing Concrete and Concrete Aggregates for
Use in Construction and Criteria for Testing Agency Evaluation; 2017.
C. ASTM C1093 - Standard Practice for Accreditation of Testing Agencies for Masonry; 2015a, with Editorial Revision (2016).
D. ASTM D3740 - Standard Practice for Minimum Requirements for Agencies Engaged in the
Testing and/or Inspection of Soil and Rock as Used in Engineering Design and Construction;
2012a.
E. ASTM E329 - Standard Specification for Agencies Engaged in Construction Inspection, Testing, or Special Inspection; 2018.
1.04 SUBMITTALS
A. See Section 01 30 00 - Administrative Requirements, for submittal procedures.
B. Design Data: Submit for knowledge as contract administrator for the limited purpose of assessing compliance with information given and the design concept expressed in the contract documents, or for Owner's information.
1.05 REFERENCES AND STANDARDS
A. For products and workmanship specified by reference to a document or documents not included in the Project Manual, also referred to as reference standards, comply with requirements of the standard, except when more rigid requirements are specified or are required by applicable codes.
B. Comply with reference standard of date of issue current on date of Contract Documents, except where a specific date is established by applicable code.
C. Obtain copies of standards where required by product specification sections.
D. Maintain copy at project site during submittals, planning, and progress of the specific work, until
Substantial Completion.
QUALITY REQUIREMENTS
01 40 00 - 2
E. Should specified reference standards conflict with Contract Documents, request clarification fbefore proceeding.
F. Neither the contractual relationships, duties, or responsibilities of the parties in Contract nor those of Architect shall be altered from Contract Documents by mention or inference otherwise in any reference document.
1.06 INFECTION CONTROL MEASURES
A. The owner will prepare an infection control risk assessment at each major work area and will impose requirements on the project to control the spread of dust and airborne patogens disturbed during construction operations and to prevent mirgration of such into sensitive areas of the facilty. The contractor shall be prepared to address these requirements, which may include the following elements.
1. Provide sticky tack mats at entrances and exits from construction areas, as required.
2. Provide units capable of supplying negative pressure in active construction areas. if units recirculate air within this space, the units will be capable of filtering the air utilizing hepa filtration.
3. Contractor will be required to cover any construction debris and wipe down carts before traveling through any patient care area.
4. Contractor will be required to seal all holes, pipes and conduit and other wall penetrations, as required, at barriers between construction operations and adjacent patient care areas.
5. If construction areas are in proximity to high risk patient populations, contractor may be required to build ante room for personnel to pass through, so the personnel can be vacuumed using a hepa vacuum prior to leaving the work site.
6. Construction personnel may be required to wear sterile personal protective equipment when working in high risk patient care areas.
7. Contractor shall familiarize himself with the infection control risk assessment matrix attached as an appendix to this project manual for all measures that may be required in this project.
8. When project is to be completed in phases, or as otherwise noted, provide temporary paritions and / or ceilings as required to separate work areas from owner occpied areas, to prevent penetration of dust and moisture into owner occupied areas, and to prevent damage to existing materials and equipment.
a. in occupied areas, in areas where extensive remodel work is being performed over an extended period of time, temporary partitions shall, wat a minimum, consist of 5/8" type-x gypsum board each side over steel studs or fire retardant wood studs at 24" o.c.. these areas need not be taped unless in a rated egress area. walls shall provide a one-hour barrier and doors, if required shall be 60 minute rated.
b. where subject to human impact loads, including but not limited to enclosures around elevator and other shafts and temporary partitions in corridors, 3/4" fire retardant plywood shall be used in lieu of 5/8" type-x gypsum board specified above.
c. dust proof partitions may be constructed of fire retardant plastic over steel studs.
d. dust partitions shall extend from floor to deck above.
e. consult with architect for exact placement of dust proof partitions prior to installation.
f. dust proof partitions shall be maintained in good repair throughout the construction period, and shall be installed and removed in a manner which will not damage the permanent building finishes. repair of any finishes damaged by installation or removal of dust partitions shall be made at no additional cost to owner.
9. refer to mechanical and electrical specifications for information regarding sealing and cleaning of ductwork and other operational measures that may be required.
QUALITY REQUIREMENTS
01 40 00 - 3
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION
3.01 CONTROL OF INSTALLATION
A. Monitor quality control over suppliers, manufacturers, products, services, site conditions, and workmanship, to produce work of specified quality.
B. Comply with manufacturers' instructions, including each step in sequence.
C. Should manufacturers' instructions conflict with Contract Documents, request clarification before proceeding.
D. Comply with specified standards as minimum quality for the work except where more stringent tolerances, codes, or specified requirements indicate higher standards or more precise workmanship.
E. Have work performed by persons qualified to produce required and specified quality.
F. Verify that field measurements are as indicated on shop drawings or as instructed by the manufacturer.
G. Secure products in place with positive anchorage devices designed and sized to withstand stresses, vibration, physical distortion, and disfigurement.
3.02 MANUFACTURERS' FIELD SERVICES
A. When specified in individual specification sections, require material or product suppliers or manufacturers to provide qualified staff personnel to observe site conditions, conditions of surfaces and installation, quality of workmanship, start-up of equipment, test, adjust, and balance equipment as applicable, and to initiate instructions when necessary.
B. Report observations and site decisions or instructions given to applicators or installers that are supplemental or contrary to manufacturers' written instructions.
3.03 DEFECT ASSESSMENT
A. Replace Work or portions of the Work not complying with specified requirements.
B. If, in the opinion of Architect, it is not practical to remove and replace the work, Architect will direct an appropriate remedy or adjust payment.
QUALITY REQUIREMENTS
01 40 00 - 4
DEFINITIONS
01 42 16 - 1
SECTION 01 42 16
DEFINITIONS
PART 1 GENERAL
1.01 SUMMARY
A. This section supplements the definitions contained in the General Conditions.
B. Other definitions are included in individual specification sections.
1.02 DEFINITIONS
A. Furnish: To supply, deliver, unload, and inspect for damage.
B. Install: To unpack, assemble, erect, apply, place, finish, cure, protect, clean, start up, and make ready for use.
C. Product: Material, machinery, components, equipment, fixtures, and systems forming the work result. Not materials or equipment used for preparation, fabrication, conveying, or erection and not incorporated into the work result. Products may be new, never before used, or re-used materials or equipment.
D. Project Manual: The book-sized volume that includes the procurement requirements (if any), the contracting requirements, and the specifications.
E. Provide: To furnish and install.
F. Supply: Same as Furnish.
PART 2 PRODUCTS - NOT USED
DEFINITIONS
01 42 16 - 2
TEMPORARY FACILITIES AND
CONTROLS
01 50 00 - 1
SECTION 01 50 00
TEMPORARY FACILITIES AND CONTROLS
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Temporary utilities.
B. Temporary telecommunications services.
C. Temporary sanitary facilities.
D. Temporary Controls: Barriers, enclosures, and fencing.
E. Security requirements.
F. Vehicular access and parking.
G. Waste removal facilities and services.
H. Project identification sign.
I. Field offices.
1.02 RELATED REQUIREMENTS
A. Section 01 51 00 - Temporary Utilities.
B. Section 01 52 13 - Field Offices and Sheds.
C. Section 01 55 00 - Vehicular Access and Parking.
D. Section 01 58 13 - Temporary Project Signage.
1.03 TEMPORARY UTILITIES - SEE SECTION 01 51 00
A. Provide and pay for all electrical power, lighting, water, heating and cooling, and ventilation required for construction purposes.
B. Existing facilities may not be used.
C. New permanent facilities may not be used.
D. Use trigger-operated nozzles for water hoses, to avoid waste of water.
1.04 TELECOMMUNICATIONS SERVICES
A. Provide, maintain, and pay for telecommunications services to field office at time of project mobilization.
B. Telecommunications services shall include:
1. Windows-based personal computer dedicated to project telecommunications, with necessary software and laser printer.
2. Telephone Land Lines: One line, minimum; one handset per line.
3. Internet Connections: Minimum of one; DSL modem or faster.
4. Email: Account/address reserved for project use.
5. Facsimile Service: Fax-to-email software on personal computer.
1.05 TEMPORARY SANITARY FACILITIES
A. Provide and maintain required facilities and enclosures. Provide at time of project mobilization.
B. Use of existing facilities is not permitted.
C. New permanent facilities may not be used during construction operations.
D. Maintain daily in clean and sanitary condition.
E. At end of construction, return facilities to same or better condition as originally found.
TEMPORARY FACILITIES AND
CONTROLS
01 50 00 - 2
1.06 BARRIERS
A. Provide barriers to prevent unauthorized entry to construction areas, to prevent access to areas that could be hazardous to workers or the public, to allow for owner's use of site and to protect existing facilities and adjacent properties from damage from construction operations and demolition.
B. Provide barricades and covered walkways required by governing authorities for public rights-of-way and for public access to existing building.
C. Protect non-owned vehicular traffic, stored materials, site, and structures from damage.
D. Traffic Controls: ______.
1.07 FENCING
A. Provide 6 foot high fence around construction site; equip with vehicular and pedestrian gates with locks.
1.08 INTERIOR ENCLOSURES
A. Provide temporary partitions and ceilings as indicated to separate work areas from Owner-occupied areas, to prevent penetration of dust and moisture into Owner-occupied areas, and to prevent damage to existing materials and equipment.
1.09 SECURITY - SEE SECTION 01 35 53
A. Provide security and facilities to protect Work, existing facilities, and Owner's operations from unauthorized entry, vandalism, or theft.
B. Coordinate with Owner's security program.
1.10 VEHICULAR ACCESS AND PARKING - SEE SECTION 01 55 00
A. Coordinate access and haul routes with governing authorities and Owner.
B. Provide and maintain access to fire hydrants, free of obstructions.
C. Provide means of removing mud from vehicle wheels before entering streets.
D. Provide temporary parking areas to accommodate construction personnel. When site space is not adequate, provide additional off-site parking.
E. Existing parking areas may be used for construction parking.
1.11 WASTE REMOVAL
A. Provide waste removal facilities and services as required to maintain the site in clean and orderly condition.
B. Provide containers with lids. Remove trash from site periodically.
C. If materials to be recycled or re-used on the project must be stored on-site, provide suitable non-combustible containers; locate containers holding flammable material outside the structure unless otherwise approved by the authorities having jurisdiction.
D. Open free-fall chutes are not permitted. Terminate closed chutes into appropriate containers with lids.
1.12 PROJECT SIGNS - SEE SECTION 01 58 13
1.13 PROJECT IDENTIFICATION
A. Provide project identification sign of design, construction, and location approved by Owner.
B. No other signs are allowed without Owner permission except those required by law.
1.14 FIELD OFFICES - SEE SECTION 01 52 13
A. Office: Weathertight, with lighting, electrical outlets, heating, cooling equipment, and equipped with sturdy furniture, drawing rack, and drawing display table.
TEMPORARY FACILITIES AND
CONTROLS
01 50 00 - 3
B. Provide space for Project meetings, with table and chairs to accommodate 6 persons.
C. Locate offices a minimum distance of 30 feet from existing and new structures.
1.15 REMOVAL OF UTILITIES, FACILITIES, AND CONTROLS
A. Remove temporary utilities, equipment, facilities, materials, prior to Date of Substantial
Completion inspection.
B. Clean and repair damage caused by installation or use of temporary work.
C. Restore existing facilities used during construction to original condition.
D. Restore new permanent facilities used during construction to specified condition.
PART 2 PRODUCTS - NOT USED
TEMPORARY FACILITIES AND
CONTROLS
01 50 00 - 4
TEMPORARY UTILITIES
01 51 00 - 1
SECTION 01 51 00
TEMPORARY UTILITIES
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Temporary Utilities: Provision of electricity, lighting, heat, ventilation, and water.
1.02 REFERENCE STANDARDS
A. 29 CFR 1926 - U.S. Occupational Safety and Health Standards; current edition.
1.03 TEMPORARY ELECTRICITY
A. Cost: By Owner.
B. Provide temporary electric feeder from existing building electrical service at location as directed.
C. Provide power outlets for construction operations, with branch wiring and distribution boxes located as required. Provide flexible power cords as required.
D. Provide main service disconnect and over-current protection at convenient location and meter.
E. Permanent convenience receptacles may be utilized during construction.
F. Provide adequate distribution equipment, wiring, and outlets to provide single phase branch circuits for power and lighting.
1.04 TEMPORARY LIGHTING FOR CONSTRUCTION PURPOSES
A. Provide and maintain LED, compact fluorescent, or high-intensity discharge lighting as suitable for the application for construction operations in accordance with requirements of 29 CFR 1926 and authorities having jurisdiction.
B. Provide branch wiring from power source to distribution boxes with lighting conductors, pigtails, and lamps as required.
C. Maintain lighting and provide routine repairs.
1.05 TEMPORARY HEATING
A. Cost of Energy: By Owner.
B. Provide heating devices and heat as needed to maintain specified conditions for construction operations.
C. Maintain minimum ambient temperature of 50 degrees F in areas where construction is in progress, unless indicated otherwise in specifications.
1.06 TEMPORARY COOLING
A. Cost of Energy: By Owner.
B. Provide cooling devices and cooling as needed to maintain specified conditions for construction operations.
C. Maintain maximum ambient temperature of 75 degrees F in areas where construction is in progress, unless indicated otherwise in specifications.
1.07 TEMPORARY VENTILATION
A. Utilize existing ventilation equipment. Extend and supplement equipment with temporary fan units as required to maintain clean air for construction operations.
1.08 TEMPORARY WATER SERVICE
A. Cost of Water Used: By Owner.
B. Provide and maintain suitable quality water service for construction operations at time of project mobilization.
C. Connect to existing water source.
1. Exercise measures to conserve water.
TEMPORARY UTILITIES
01 51 00 - 2
PART 2 PRODUCTS - NOT USED
FIELD OFFICES AND SHEDS
01 52 13 - 1
SECTION 01 52 13
FIELD OFFICES AND SHEDS
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Temporary field offices for use of Contractor.
B. Maintenance and removal.
1.02 RELATED REQUIREMENTS
A. Section 01 10 00 - Summary: use of premises and responsibility for providing field offices.
B. Section 01 50 00 - Temporary Facilities and Controls:
1. Temporary telecommunications services for administrative purposes.
2. Temporary sanitary facilities required by law.
1.03 USE OF EXISTING FACILITIES
A. Designated existing spaces may be used for field offices: Where approved by the COR.
PART 2 PRODUCTS
2.01 MATERIALS, EQUIPMENT, FURNISHINGS
2.02 ENVIRONMENTAL CONTROL
A. Heating, Cooling, and Ventilating: Automatic equipment to maintain comfort conditions.
2.03 CONTRACTOR OFFICE AND FACILITIES
A. Size: For Contractor's needs and to provide space for project meetings.
B. Telephone: As specified in Section 01 50 00.
C. Furnishings in Meeting Area: Conference table and chairs to seat at least eight persons; racks and files for Contract Documents, submittals, and project record documents.
PART 3 EXECUTION
3.01 PREPARATION
A. Fill and grade sites for temporary structures to provide drainage away from buildings.
3.02 MAINTENANCE AND CLEANING
A. Weekly janitorial services for offices; periodic cleaning and maintenance for offices.
B. Maintain approach walks free of mud, water, and snow.
3.03 REMOVAL
A. At completion of Work remove buildings, foundations, utility services, and debris. Restore areas.
FIELD OFFICES AND SHEDS
01 52 13 - 2
VEHICULAR ACCESS AND
PARKING
01 55 00 - 1
SECTION 01 55 00
VEHICULAR ACCESS AND PARKING
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Access roads.
B. Parking.
C. Existing pavements and parking areas.
D. Permanent pavements and parking facilities.
E. Construction parking controls.
F. Haul routes.
G. Traffic signs and signals.
H. Maintenance.
I. Removal, repair.
J. Mud from site vehicles.
1.02 RELATED REQUIREMENTS
A. Section 01 10 00 - Summary: For access to site, work sequence, and occupancy.
B. Section 01 58 13 - Temporary Project Signage: Post Mounted and Wall Mounted Traffic
Control and Informational Signs.
PART 2 PRODUCTS
2.01 MATERIALS
A. Temporary Construction: Contractor's option.
B. Materials for Permanent Construction: As specified in product specification sections, including earthwork, paving base, and topping.
2.02 SIGNS, SIGNALS, AND DEVICES
A. Traffic Cones and Drums, Flares and Lights: As approved by local jurisdictions.
B. Flag Person Equipment: As required by local jurisdictions.
PART 3 EXECUTION
3.01 PREPARATION
A. Clear areas, provide surface and storm drainage of road, parking, area premises, and adjacent areas.
3.02 ACCESS ROADS
A. Use of designated existing on-site streets and driveways for construction traffic is permitted.
B. Tracked vehicles not allowed on paved areas.
C. Location as indicated.
D. Provide unimpeded access for emergency vehicles. Maintain 20 foot width driveways with turning space between and around combustible materials.
E. Provide and maintain access to fire hydrants free of obstructions.
3.03 PARKING
A. Use of designated areas of existing parking facilities by construction personnel is permitted.
B. Use of designated areas of new parking facilities by construction personnel is permitted.
C. When site space is not adequate, provide additional off-site parking.
VEHICULAR ACCESS AND
PARKING
01 55 00 - 2
D. Locate as indicated.
3.04 HAUL ROUTES
A. Confine construction traffic to designated haul routes.
B. Provide traffic control at critical areas of haul routes to regulate traffic, to minimize interference with public traffic.
3.05 TRAFFIC SIGNS AND SIGNALS
A. At approaches to site and on site, install at crossroads, detours, parking areas, and elsewhere as needed to direct construction and affected public traffic.
B. Relocate as work progresses, to maintain effective traffic control.
3.06 MAINTENANCE
A. Maintain traffic and parking areas in a sound condition free of excavated material, construction equipment, products, mud, snow, and ice.
B. Maintain existing paved areas used for construction; promptly repair breaks, potholes, low areas, standing water, and other deficiencies, to maintain paving and drainage in original, or specified, condition.
3.07 REMOVAL, REPAIR
A. Repair existing facilities damaged by use, to original condition.