B-4852 ALAMITOS BAY ENTRANCE CHANNEL DREDGE_20250606.pdf
PDF 7 MB Posted
- Attached to
- R-7246 ALAMITOS BAY ENTRANCE CHANNEL DREDGING
- Solicitation number
- PW-25-642
- Issued by
- California
About this file
Alamitos Bay Entrance Channel Maintenance Dredging and Beach Nourishment - Construction Plans
These construction plans prepared for the City of Long Beach detail a maintenance dredging and beach nourishment project at Alamitos Bay Entrance Channel in Seal Beach, California. The project involves dredging the entrance channel to a depth of -18 feet Mean Lower Low Water (MLLW), with provisions for one foot of paid overdredge to -19 feet and a bid additive option for two additional feet of paid overdredge to -21 feet. The dredged material, excluding debris, will be hydraulically placed at an identified beach nourishment area with a target elevation of +10 feet MLLW and side slopes ranging between 20H:1V minimum to 20H:3V maximum. The project includes multiple basins within Alamitos Bay (Basins 1, 2, and 5) and an entrance channel dredge boundary defined by nine control points with specific state plane coordinates. Critical project constraints include environmental closure windows tied to project permits, avoidance of existing eelgrass areas where no dredging, anchoring, or spudding is permitted, and material from the EC-DU1 area must be dredged first and placed at the beach nourishment area nearest the north jetty. All work must comply with federal, state, and local permits, with the most stringent conditions applied where permit requirements vary.
The contractor assumes full responsibility for construction means, methods, site conditions, public safety, traffic control, utility coordination, and debris removal. Dredged material must reach the required -18 feet elevation in all areas for acceptance as complete, with excessive dredging below the non-pay overdredge limit of -22 feet prohibited and subject to regulatory fees and potential structural damage liability. Debris encountered during work must be segregated and disposed of at contractor-selected, owner-approved upland commercial landfill locations in accordance with federal, state, and local regulations. The contractor is responsible for installing and maintaining public safety measures including signage, barricades, and spotters around placement and staging areas. If hydraulic dredging is used, the pipeline must be primarily located outside the entrance channel except for the dredge attachment, fully submerged within navigation channels with buoy markers, and routed to avoid eelgrass disturbance. The contractor must propose a safe pipeline crossing route over the western jetty that maintains public safety and allows continuous vehicle access to the 72nd Place lifeguard station.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
T01
TITLE SHEET 1
NOTES:
1. HORIZONTAL DATUM: CALIFORNIA STATE PLANE
ZONE 5, NAD83, U.S. SURVEY FEET
2. VERTICAL DATUM: FEET MLLW, NTDE 1983-2001.
Ju n
, 2
2:
pm c he w et t
K :\P ro je ct s\
-C ity o f L on g
Be ac h\ Al am ito s B ay
E nt ra nc e Ch an ne l\C on st ru ct io n Pl an s\
P L
TI
TL
E.
dw g T0
ALAMITOS BAY ENTRANCE CHANNEL MAINTENANCE
DREDGING AND BEACH NOURISHMENT
CITY OF LONG BEACH
DRAWING INDEX
SHEET # DRAWING # TITLE
1 T01 TITLE SHEET
2 G01 GENERAL NOTES
3 G02 EXISTING CONDITIONS
4 C01 DREDGE PLAN VIEW (1)
5 C02 DREDGE PLAN VIEW (2)
6 C03 DREDGE CROSS SECTIONS (1)
7 C04 DREDGE CROSS SECTIONS (2)
8 C05 DREDGE CROSS SECTIONS (3)
9 C06 DREDGE CROSS SECTIONS (4)
10 C07 BEACH NOURISHMENT AREA
11 C08 PROPOSED DREDGING PIPELINE ROUTE
D. MASSARO
M. PRATSCHNER
M. COLLINS
T. WANG
AS NOTED
JUNE 2025
DRAFT - ISSUED FOR BID
DESCRIPTIONAPP'DDATE BY
REVISIONS
REV
O N
E
IN
CH
DESIGNED BY:
APPROVED BY:
CHECKED BY:
DRAWN BY:
DATE:
SCALE:
ALAMITOS BAY ENTRANCE CHANNEL
MAINTENANCE DREDGING AND BEACH
NOURISHMENT
SHEET # OF
PL
AN
IN
TE
N D
ED
T
O B
E
VI
EW
ED
IN
C
O
LO
R, A
D
JA
CE
N
T
BL
O
CK
IS
"B
LU
E"
AT
F
UL
L
SI
ZE
, I F
N O
T O
N E
IN
CH
S
CA
LE
A
CC
O
RD
IN
GL
Y
SCALE IN FEET
1000 2000
NORTH
LOCATION MAP SITE MAP
PROJECT
SITE
SCALE IN FEET
1000 2000
NORTH
SCALE IN MILES
1 2
NORTH
BASEMAP: ESRI 2024 AERIAL IMAGERY: ESRI 2024
SITE LOCATION
PACIFIC OCEAN
E OCEAN BLVD
ALAMITOS
BAY
PACIFIC COAST HWY
BEACH
NOURISHMENT
AREA
STAGING
AREA
michael.lau Text Box B-4852
G01
GENERAL NOTES 2
Ju n
, 2
2:
pm c he w et t
K :\P ro je ct s\
-C ity o f L on g
Be ac h\ Al am ito s B ay
E nt ra nc e Ch an ne l\C on st ru ct io n Pl an s\
P L
TI
TL
E.
dw g G0
D. MASSARO
M. PRATSCHNER
M. COLLINS
T. WANG
AS NOTED
JUNE 2025
DRAFT - ISSUED FOR BID
DESCRIPTIONAPP'DDATE BY
REVISIONS
REV
O N
E
IN
CH
DESIGNED BY:
APPROVED BY:
CHECKED BY:
DRAWN BY:
DATE:
SCALE:
ALAMITOS BAY ENTRANCE CHANNEL
MAINTENANCE DREDGING AND BEACH
NOURISHMENT
SHEET # OF
PL
AN
IN
TE
N D
ED
T
O B
E
VI
EW
ED
IN
C
O
LO
R, A
D
JA
CE
N
T
BL
O
CK
IS
"B
LU
E"
AT
F
UL
L
SI
ZE
, I F
N O
T O
N E
IN
CH
S
CA
LE
A
CC
O
RD
IN
GL
Y
DETAIL AND SECTION REFERENCING
DETAIL REFERENCE NUMBER
DRAWING ON WHICH DETAIL APPEARS
"-" INDICATES TYPICAL OR ON SAME DRAWING
DETAIL REFERENCE NUMBER
SECTION "A" IS SHOWN ON DRAWING "C02"
INDICATES DIRECTION
OF CUTTING PLANE
SECTION REFERENCE LETTER
C01
SCALE:
DETAIL1
C01 1" = 10'
A C02
SCALE:
SECTIONA
C01 1" = 10'DRAWING NUMBER WHICH SECTION WAS TAKEN
ABBREVIATIONS:
' FEET, MINUTES
" INCHES, SECONDS
° DEGREES
# NUMBER
APPROX APPROXIMATE
ASTM AMERICAN SOCIETY FOR TESTING AND MATERIALS
BM BENCHMARK
BMP BEST MANAGEMENT PRACTICE
CY CUBIC YARDS
DWG DRAWING
E EAST, EASTING
ELEV ELEVATION
EX EXISTING
FT FEET
FG FINISHED GRADE
H HORIZONTAL
L LENGTH
LF LINEAR FEET
MAX MAXIMUM
MIN MINIMUM
MLLW MEAN LOWER LOW WATER
N NORTH, NORTHING
NAD NORTH AMERICAN DATUM
NAVD NORTH AMERICAN VERTICAL DATUM
NTDE NATIONAL TIDAL DATUM EPOCH
NTS NOT TO SCALE
OD OVERDREDGE
PE PROFESSIONAL ENGINEER
ROW RIGHT-OF-WAY
STA STATION
TESC TEMPORARY EROSION AND SEDIMENT CONTROL
TOW TOP OF WALL
TYP TYPICAL
USCG UNITED STATES COAST GUARD
V, VERT VERTICAL
W/ WITH
WSEL WATER SURFACE ELEVATION
YR YEAR
CONTROL POINTS
FOR DREDGE BOUNDARY
POINT #
NORTHING
1726727.14
1726583.49
EASTING
6524689.05
6524951.82
1729634.72
1729777.14
6526652.63
6526672.75
1731121.39
1730761.86
6526385.89
6526155.86
1730038.04
1729862.23
6526310.32
6526313.22
9 1729578.46 6526277.85
CONTROL POINTS FOR
BEACH NOURISHMENT
POINT #
NORTHING
1730454.91
1730207.59
EASTING
6524378.72
6524449.40
1729962.75
1729196.20
6524859.04
6525835.27
1729302.97
1729388.98
6525852.78
6525852.78
16 1730054.45 6524993.40
NOTES
1. CONTRACT DOCUMENTS REFER TO THESE DRAWINGS,
CONSTRUCTION PERMITS, AND SPECIFICATIONS. NOTES AND
DETAILS ON THE CONTRACT DOCUMENTS SHALL TAKE
PRECEDENCE OVER GENERAL NOTES HEREIN.
2. CHANGES TO THE SPECIFICATIONS AND/OR CONSTRUCTION
SHOWN IN THESE DRAWINGS SHALL NOT BE MADE WITHOUT
APPROVAL FROM THE CITY OR AUTHORIZED REPRESENTATIVE.
3. THE CONTRACTOR SHALL FURNISH ALL MATERIALS,
EQUIPMENT, AND LABOR NECESSARY TO COMPLETE ALL THE
WORK AS INDICATED IN THE CONTRACT DOCUMENTS.
4. THE CONTRACTOR SHALL VISIT THE WORK SITE AND BE
RESPONSIBLE FOR ALL CONTRACT DOCUMENTS, FIELD
CONDITIONS, AND DIMENSIONS AND CONFIRMING THAT
THE WORK MAY BE ACCOMPLISHED AS SHOWN PRIOR TO
PROCEEDING WITH CONSTRUCTION. ANY DISCREPANCIES
ARE TO BE BROUGHT TO THE ATTENTION OF THE CITY OR
AUTHORIZED REPRESENTATIVE PRIOR TO PROCEEDING WITH
THE WORK.
5. THE CONTRACTOR SHALL RECEIVE, IN WRITING,
AUTHORIZATION TO PROCEED BEFORE STARTING THE WORK
ON ANY ITEM NOT CLEARLY DEFINED OR IDENTIFIED BY THE
CONTRACT DOCUMENTS. CONTRACTOR TO PROVIDE NOTICE
TO THE CITY OR AUTHORIZED REPRESENTATIVE PRIOR TO
COMMENCING CONSTRUCTION WORK. DREDGING SHALL
NOT START UNTIL THE CITY OR AUTHORIZED REPRESENTATIVE
APPROVES THE START DATE.
6. THE CONTRACTOR SHALL INSTALL ALL EQUIPMENT AND
MATERIALS IN ACCORDANCE WITH THE MANUFACTURER'S
RECOMMENDATIONS UNLESS SPECIFICALLY INDICATED
OTHERWISE BY THE CITY OR AUTHORIZED REPRESENTATIVE
OR WHERE LOCAL CODES OR REGULATIONS TAKE
PRECEDENCE.
7. ALL THE WORK PERFORMED AND MATERIALS INSTALLED
SHALL BE IN STRICT ACCORDANCE WITH ALL APPLICABLE
CODES, REGULATIONS, AND ORDINANCES.
8. THE CONTRACTOR SHALL ASSUME SOLE AND COMPLETE
RESPONSIBILITY FOR THE WORK SITE CONDITIONS DURING
THE COURSE OF CONSTRUCTION OF THIS PROJECT
INCLUDING SAFETY OF ALL PERSONS AND PROPERTY. THIS
REQUIREMENT SHALL APPLY CONTINUOUSLY AND NOT BE
LIMITED TO NORMAL WORKING HOURS.
9. THE CONTRACT DOCUMENTS REPRESENT THE FINISHED SITE
CONDITIONS. THEY DO NOT INDICATE THE METHOD OF
CONSTRUCTION. THE CONTRACTOR SHALL BE SOLELY
RESPONSIBLE FOR ALL CONSTRUCTION MEANS, METHODS,
TECHNIQUES, SEQUENCES, AND PROCEDURES AND FOR
COORDINATING ALL PORTIONS OF THE WORK UNDER THE
CONTRACT.
10. THE CONTRACTOR SHALL KEEP THE WORK SITE CLEAN AND
HAZARD-FREE. THE CONTRACTOR SHALL PROVIDE ALL
MEASURES NECESSARY TO PROTECT SITE CONDITIONS,
EXISTING STRUCTURES, UTILITIES, WORKERS, AND THE PUBLIC
DURING CONSTRUCTION. ANY DAMAGE TO ITEMS SHALL BE
REPAIRED BY THE CONTRACTOR AT THE CONTRACTOR'S
EXPENSE.
11. UNLESS NOTED OTHERWISE, ALL DEMOLISHED STRUCTURES
MATERIAL AND DEBRIS SHALL BECOME THE PROPERTY OF THE
CONTRACTOR AND SHALL BE DISPOSED OF AT AN APPROVED
DISPOSAL FACILITY OR RECYCLING FACILITY IN ACCORDANCE
WITH APPLICABLE FEDERAL AND STATE LAWS AND
REGULATIONS GOVERNING DISPOSAL.THE CONTRACTOR
SHALL DISPOSE OF ALL DIRT, DEBRIS, AND RUBBISH FOR
DURATION OF THE WORK. UPON COMPLETION OF THE WORK,
THE CONTRACTOR SHALL REMOVE ALL MATERIAL AND
EQUIPMENT NOT SPECIFIED AS REMAINING ON THE
PROPERTY.
12. TRAFFIC CONTROL SHALL BE THE RESPONSIBILITY OF THE
CONTRACTOR THROUGHOUT THE DURATION OF THE
PROJECT AND SUBJECT TO ALL LOCAL, STATE, AND/OR
FEDERAL REGULATIONS.
13. ALL THE WORK SHALL SATISFY CONDITIONS AND
REQUIREMENTS OF FEDERAL, STATE, AND LOCAL PERMITS, AS
APPLICABLE. IN CASES WHERE CONDITIONS AND/OR
REQUIREMENTS VARY FROM PERMIT TO PERMIT, THE MOST
STRINGENT CONDITION AND/OR REQUIREMENT SHALL BE
EMPLOYED.
14. IN-WATER WORK IS SUBJECT TO AN ENVIRONMENTAL
CLOSURE WINDOW. THE WORK DATES ARE PROVIDED IN THE
PROJECT PERMITS.
INFORMATION DISPLAYED, INCLUDING PROPERTY
BOUNDARIES, IS BASED ON AVAILABLE RECORDS
PROVIDED BY THE CITY OF LONG BEACH. THE
CONTRACTOR IS TO VERIFY ALL SITE INFORMATION PRIOR
TO CONSTRUCTION. ANY DISCREPANCIES SHALL BE
REPORTED TO THE CITY OR AUTHORIZED REPRESENTATIVE
PRIOR TO COMMENCING THE WORK.
THE CONTRACTOR SHALL NOTIFY ALL UTILITY COMPANIES
PRIOR TO COMMENCING THE WORK IN ACCORDANCE
WITH STATE AND LOCAL REQUIREMENTS. THE
CONTRACTOR SHALL BE RESPONSIBLE FOR VERIFICATION
OF THE SIZE AND LOCATION OF ALL EXISTING ABOVE AND
UNDERGROUND UTILITIES. EXISTING UTILITIES SHOWN
HAVE BEEN OBTAINED FROM AVAILABLE RECORDS. THE
CONTRACTOR SHALL BE RESPONSIBLE FOR ANY
ADDITIONAL UTILITY LOCATIONS NOT SHOWN. CARE
SHOULD BE TAKEN TO AVOID DAMAGE OR DISTURBANCE
TO EXISTING UTILITIES. THE CONTRACTOR SHALL BE
RESPONSIBLE FOR REPAIRING ANY DAMAGE CAUSED BY
THE CONTRACTOR'S ACTIVITIES.
NO IN-WATER STOCKPILING OF DEBRIS IS ALLOWED.
BATHYMETRIC SURVEY DATA COLLECTED BY ETRAC (A
WOOLPERT COMPANY), DATED JULY 12, 2023.
BATHYMETRY AT TIME OF DREDGING MAY DIFFER.
HORIZONTAL CONTROL: ETRAC BASE, 33°44'57.40631"
N, 118°6'56.37614" W
VERTICAL CONTROL: ETRAC BASE, ELEVATION -105.243
U.S. FT (ELLIPSOIDAL)
NAVD88 TO MLLW DATUM CONVERSION BASED ON
NOSS/NOS VDATUM IN THE SURVEY AREA. NAVD88 TO
MLLW IS -0.2 U.S. FT.
15.
16.
17.
18.
A.
B.
C.
michael.lau
© 2023 Microsoft Corporation © 2023 Maxar ©CNES (2023) Distribution Airbus DS
-27
-26 -25
-2 4 -2 3 -2
-2
-2
-1
-1
-1 7 -16 -15
-1
-1
-1 4 -13
-1 2 -11
-1 0 -9 -8
-7
-6 -5
-4 -3
-2 -1
-25 -24
-23
-22
-21
-20 -19-18
-17
-1
-16
-16
-15
-15 -15 -14
-14
-14
-13
-13 -13-12 -12
-12-11
-11-11 -10-10
-10
-9 -9 -8
-8 -7-7 -6-6 -5-5 -4-4 -9 -8 -7 -6 -4 -5
-5 -10-12-13
-14 -15
-11-12 -13
-14
-4-5-6-7 -8-9
-10-1
-1
-1
-2
-20
-15-10
-15
-1
-2 0-18
-17
-21 -20
-19
-1
-15
-18
-19 -21
-20
-21-5 -10
-15
-1 7-1
-15 -14 -13 -14 -13
-17-1 6-17
-1-2-3-4-5
-15 -20
-12
-14 -16
-2
-15
-20
-1
-10-12
-1
-2
-28 -27
-2
-25
-2
-23 -2 2 -21
-20
-19 -1
-1
-1
-1
-1
-13
-1
-1
-1
-12
-1
-1
-11
-1
-9 -8
-7 -6
-5
-5 -5
-4 -4
-4
-3
-3 -2
-1
-28
-27
-27-27
-26
-25
EXISTING
JETTIES
PACIFIC
OCEAN
SEAL BEACH,
CALIFORNIA
PE
NI
NS
UL
A
BE
AC
H
PL
AC
EM
EN
T
SI
TE ALAMITOS
BAY
FUEL DOCK
BASIN 1
BASIN 5
STAGING
AREA
-1
-1
-1
-5 0
-7
-8
-9
-5
HARBOR MASTER DOCK
BERTH 1
BERTH 2
NORTH
LONG DOCK
SOUTH
LONG DOCK
BASIN 2
ENTRANCE CHANNEL
DREDGE BOUNDARY
D. MASSARO
M. PRATSCHNER
M. COLLINS
T. WANG
AS NOTED
JUNE 2025
DRAFT - ISSUED FOR BID
DESCRIPTIONAPP'DDATE BY
REVISIONS
REV
O N
E
IN
CH
DESIGNED BY:
APPROVED BY:
CHECKED BY:
DRAWN BY:
DATE:
SCALE:
ALAMITOS BAY ENTRANCE CHANNEL
MAINTENANCE DREDGING AND BEACH
NOURISHMENT
SHEET # OF
PL
AN
IN
TE
N D
ED
T
O B
E
VI
EW
ED
IN
C
O
LO
R, A
D
JA
CE
N
T
BL
O
CK
IS
"B
LU
E"
AT
F
UL
L
SI
ZE
, I F
N O
T O
N E
IN
CH
S
CA
LE
A
CC
O
RD
IN
GL
Y
NORTH
SCALE IN FEET
300 600
LEGEND:
DREDGE BOUNDARY
EXISTING CONTOUR (5')
EXISTING CONTOUR (1')
EXISTING EELGRASS
G02
EXISTING CONDITIONS 3
NOTES:
1. HORIZONTAL DATUM: CALIFORNIA STATE PLANE
ZONE 5, NAD83, U.S. SURVEY FEET
2. VERTICAL DATUM: FEET MLLW, NTDE 1983-2001.
3. BATHYMETRIC SURVEY DATA COLLECTED BY
ETRAC (A WOOLPERT COMPANY), DATED JULY
12, 2023. BATHYMETRY AT TIME OF DREDGING
MAY DIFFER.
4. EELGRASS SURVEY BY MTS IN MARCH 2024.
AVOID DISTURBING EELGRASS AREAS. NO
DREDGING, ANCHORING, OR SPUDDING IS
ALLOWED WITHIN EELGRASS AREAS.
5. CONTRACTOR SHALL DREDGE MATERIAL FROM
EC-DU1 FIRST IN SEQUENCE. MATERIAL FROM
EC-DU1 SHALL BE PLACED AT THE BEACH
NOURISHMENT AREA NEAREST THE NORTH
JETTY AND SHALL BE BURIED AS OTHER
MATERIAL FROM WITHIN THE DREDGE
FOOTPRINT IS PLACED AT THE BEACH
NOURISHMENT AREA.
6. TEMPORARY AND OVERNIGHT MOORING IS
ALLOWED WITH OWNER APPROVAL ON SOUTH
LONG DOCK, NORTH LONG DOCK, BERTH 1,
BERTH 2 AND/OR HARBOR MASTER DOCK.
BERTHS 1 AND 2 HAVE CLOSED GANGPLANKS
MAKING LANDSIDE ACCESS NOT POSSIBLE.
EC-DU1
SEE NOTE 5
michael.lau
DC04CC03 FC04
BC03
AC03 EC04
-1
N:1728000
E:
N:1728000
E:
N:1727000
E:
DREDGE TO -18 FT MLLW
PAYABLE OVERDREDGE TO -19 FT MLLW
BID ADDITIVE 2' PAYABLE OVERDREDGE
TO -21 FT MLLW
PACIFIC
OCEAN
-19-19-19
-18 -17
-1
-16
-15
-15 -14
-14
-13
-13
-13-12
-12
-12 -11
-11
-11
-10 -10
-10
-9
-9 -8
-8 -7 -7 -6
-6 -5 -5 -4-4
-9 -8
-7 -6 -4
-5
-5 -10 -12 -13
-14 -15
-11 -12
-13
-14
-6
-7
-8 -9
-10
-1
-5
-1
-2
-15
-20
-1
-10-12
-1
PAYABLE SIDE SLOPE IS 2H:1V
D. MASSARO
M. PRATSCHNER
M. COLLINS
T. WANG
AS NOTED
JUNE 2025
DRAFT - ISSUED FOR BID
DESCRIPTIONAPP'DDATE BY
REVISIONS
REV
O N
E
IN
CH
DESIGNED BY:
APPROVED BY:
CHECKED BY:
DRAWN BY:
DATE:
SCALE:
ALAMITOS BAY ENTRANCE CHANNEL
MAINTENANCE DREDGING AND BEACH
NOURISHMENT
SHEET # OF
PL
AN
IN
TE
N D
ED
T
O B
E
VI
EW
ED
IN
C
O
LO
R, A
D
JA
CE
N
T
BL
O
CK
IS
"B
LU
E"
AT
F
UL
L
SI
ZE
, I F
N O
T O
N E
IN
CH
S
CA
LE
A
CC
O
RD
IN
GL
Y
NORTH
SCALE IN FEET
100 200
LEGEND:
DREDGE FOOTPRINT
DREDGE DAYLIGHT (TOP OF SLOPE)
DREDGE FOOTPRINT (TOE OF DREDGE SLOPE)
EXISTING CONTOUR (5')
EXISTING CONTOUR (1')
CONTROL POINT
C01
DREDGE PLAN VIEW (1) 4
NOTES:
1. HORIZONTAL DATUM: CALIFORNIA STATE PLANE
ZONE 5, NAD83, U.S. SURVEY FEET
2. VERTICAL DATUM: FEET MLLW, NTDE 1983-2001.
3. BATHYMETRIC SURVEY DATA COLLECTED BY
ETRAC (A WOOLPERT COMPANY), DATED JULY
12, 2023. BATHYMETRY AT TIME OF DREDGING
MAY DIFFER.
4. CONTRACTOR SHALL DREDGE MATERIAL FROM
EC-DU1 FIRST IN SEQUENCE. MATERIAL FROM
EC-DU1 SHALL BE PLACED AT THE BEACH
NOURISHMENT AREA NEAREST THE NORTH
JETTY AND SHALL BE BURIED AS OTHER
MATERIAL FROM WITHIN THE DREDGE
FOOTPRINT IS PLACED AT THE BEACH
NOURISHMENT AREA.
-5
-1
EC-DU1
SEE NOTE 4
michael.lau
JC06
HC05
IC06
GC05
N:1730000
E:
N:1730000
E:
N:1731000
E:
PACIFIC
OCEAN
Alamitos Bay
Basin 5
Basin 1
-1 0 -9
-8
-7 7
-1
-16
-15
-15 -14-13-12-11
-4-5-6
-7
-5
-2
-20
-15
-10
-15
-1
-2
-18
-17
-21
-20
-19
-1
-15
-18
-19 -21
-20
-21-5
-10
-15
-1
-1
-15 -14
-13 -14
-13
-17
-1 6-17
-1 -2-3-4
-15 -20
-12
-14
-16
PAYABLE SIDE SLOPE IS 2H:1V
DREDGE TO -18 FT MLLW
PAYABLE OVERDREDGE TO -19 FT MLLW
BID ADDITIVE 2' PAYABLE OVERDREDGE
TO -21 FT MLLW
D. MASSARO
M. PRATSCHNER
M. COLLINS
T. WANG
AS NOTED
JUNE 2025
DRAFT - ISSUED FOR BID
DESCRIPTIONAPP'DDATE BY
REVISIONS
REV
O N
E
IN
CH
DESIGNED BY:
APPROVED BY:
CHECKED BY:
DRAWN BY:
DATE:
SCALE:
ALAMITOS BAY ENTRANCE CHANNEL
MAINTENANCE DREDGING AND BEACH
NOURISHMENT
SHEET # OF
PL
AN
IN
TE
N D
ED
T
O B
E
VI
EW
ED
IN
C
O
LO
R, A
D
JA
CE
N
T
BL
O
CK
IS
"B
LU
E"
AT
F
UL
L
SI
ZE
, I F
N O
T O
N E
IN
CH
S
CA
LE
A
CC
O
RD
IN
GL
Y
NORTH
SCALE IN FEET
100 200
C02
DREDGE PLAN VIEW (2) 5
NOTES:
1. HORIZONTAL DATUM: CALIFORNIA STATE PLANE
ZONE 5, NAD83, U.S. SURVEY FEET
2. VERTICAL DATUM: FEET MLLW, NTDE 1983-2001.
3. BATHYMETRIC SURVEY DATA COLLECTED BY ETRAC
(A WOOLPERT COMPANY), DATED JULY 12, 2023.
BATHYMETRY AT TIME OF DREDGING MAY DIFFER.
4. EELGRASS SURVEY BY MTS IN MARCH 2024.
AVOID DISTURBING EELGRASS AREAS. NO
DREDGING, ANCHORING, OR SPUDDING IS
ALLOWED WITHIN EELGRASS AREAS.
LEGEND:
DREDGE FOOTPRINT
DREDGE DAYLIGHT (TOP OF SLOPE)
DREDGE FOOTPRINT (TOE OF DREDGE SLOPE)
EXISTING CONTOUR (5')
EXISTING CONTOUR (1')
EXISTING EELGRASS
CONTROL POINT
-10
-8
SOUTH LONG DOCK
NORTH LONG DOCK
CLOSED (NOT TO BE USED)
BERTH 2
BERTH 1
michael.lau
EL
EV
AT
IO
N
IN
F
EE
T
HORIZONTAL DISTANCE IN FEET
2X VERTICAL EXAGGERATION
-25
-20
-15
-10
-5
-25
-20
-15
-10
-5
-20 -10 0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250 260 270 280 290 300 310 320 330 340 350
A A'
EL
EV
AT
IO
N
IN
F
EE
T
HORIZONTAL DISTANCE IN FEET
2X VERTICAL EXAGGERATION
-25
-20
-15
-10
-5
-25
-20
-15
-10
-5
-20 -10 0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250 260 270 280 290 300 310 320 330 340 350
B B'
EL
EV
AT
IO
N
IN
F
EE
T
HORIZONTAL DISTANCE IN FEET
2X VERTICAL EXAGGERATION
-25
-20
-15
-10
-5
-25
-20
-15
-10
-5
-20 -10 0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250 260 270 280 290 300 310 320 330 340 350
C C'
HORIZONTAL SCALE:
VERTICAL SCALE:
SECTIONA
C01 1" = 20'
1" = 10'
HORIZONTAL SCALE:
VERTICAL SCALE:
SECTIONB
C01 1" = 20'
1" = 10'
HORIZONTAL SCALE:
VERTICAL SCALE:
SECTIONC
C01 1" = 20'
1" = 10'
REQUIRED DREDGE ELEVATION (-18')
1' PAID OVERDREDGE (-19')
BID ADDITIVE 2' PAID OVERDREDGE (-21' MLLW)
1V 2H1V
2H
1V 2H
1V 2H
1V 2H
1V 2H
EXISTING MUDLINE
EXISTING MUDLINE
EXISTING MUDLINE
REQUIRED DREDGE ELEVATION (-18')
1' PAID OVERDREDGE (-19')
BID ADDITIVE 2' PAID OVERDREDGE (-21' MLLW)
REQUIRED DREDGE ELEVATION (-18')
1' PAID OVERDREDGE (-19')
BID ADDITIVE 2' PAID OVERDREDGE (-21' MLLW)
ALLOWABLE OVERDREDGE (-22' MLLW)
ALLOWABLE OVERDREDGE (-22' MLLW)
ALLOWABLE OVERDREDGE (-22' MLLW)
D. MASSARO
M. PRATSCHNER
M. COLLINS
T. WANG
AS NOTED
JUNE 2025
DRAFT - ISSUED FOR BID
DESCRIPTIONAPP'DDATE BY
REVISIONS
REV
O N
E
IN
CH
DESIGNED BY:
APPROVED BY:
CHECKED BY:
DRAWN BY:
DATE:
SCALE:
ALAMITOS BAY ENTRANCE CHANNEL
MAINTENANCE DREDGING AND BEACH
NOURISHMENT
SHEET # OF
PL
AN
IN
TE
N D
ED
T
O B
E
VI
EW
ED
IN
C
O
LO
R, A
D
JA
CE
N
T
BL
O
CK
IS
"B
LU
E"
AT
F
UL
L
SI
ZE
, I F
N O
T O
N E
IN
CH
S
CA
LE
A
CC
O
RD
IN
GL
Y
C03
DREDGE CROSS SECTIONS (1) 6
LEGEND:
REQUIRED DREDGE ELEVATION (-18' MLLW)
1' PAID OVERDREDGE (-19' MLLW)
BID ADDITIVE 2' PAID OVERDREDGE (-21' MLLW)
EXISTING MUDLINE
REQUIRED DREDGING TO -18' MLLW
NOTES:
1. DREDGED MATERIAL EXCLUDING DEBRIS SHALL
BE PLACED AT THE IDENTIFIED BEACH
NOURISHMENT AREA.
2. CONTRACTOR SHALL DREDGE THE SIDE SLOPES
IDENTIFIED IN THE DRAWING. THE SIDE SLOPE
VOLUME ASSOCIATED WITH THE MAXIMUM PAY
LIMIT IS INCLUDED IN THE DREDGING BID ITEM
QUANTITIES.
3. DREDGING OF SEDIMENT OUTSIDE THE
DREDGING LIMITS AND/OR BELOW THE
NON-PAY OVERDREDGE ELEVATION IS DEFINED
AS EXCESSIVE DREDGING AND IS PROHIBITED.
CONTRACTOR WILL NOT BE PAID FOR EXCESSIVE
DREDGING AND WILL BE RESPONSIBLE FOR ANY
REGULATORY AGENCY FEES AND/OR FINES
INCURRED AS A RESULT OF EXCESSIVE
DREDGING. ADDITIONALLY, IF EXCESSIVE
DREDGING RESULTS IN DAMAGE OR
UNDERMINING TO EXISTING STRUCTURES, THE
CONTRACTOR SHALL RECTIFY TO THE CITY OR
AUTHORIZED REPRESENTATIVE'S SATISFACTION
PRIOR TO CLOSE OF THE CONTRACT.
4. THE REQUIRED DREDGE ELEVATION MUST BE
ACHIEVED IN ALL AREAS FOR IT TO BE
ACCEPTED AS COMPLETE. CONTRACTOR MUST
REMOVE ALL SLOUGH MATERIAL FROM THE
REQUIRED DREDGE AREA IN ORDER FOR WORK
TO BE ACCEPTED BY THE CITY OR AUTHORIZED
REPRESENTATIVE. THE CITY OR AUTHORIZED
REPRESENTATIVE WILL COMPARE THE PRE- AND
POST-DREDGE SURVEYS TO ENSURE THAT
DREDGED SEDIMENT FROM ALL OF THE DREDGE
AREA IS REMOVED FROM THE SITE.
5. CONTRACTOR MUST REMOVE ALL DEBRIS TO
CONDUCT THE DREDGING WORK. THE
CONTRACTOR SHALL TAKE CARE TO AVOID
CONTACT WITH THE NEARBY BANK DURING
DEBRIS REMOVAL ACTIVITIES.
6. ANY DEBRIS ENCOUNTERED AND REMOVED
DURING THE WORK SHALL BE REMOVED BY THE
CONTRACTOR AND PROPERLY DISPOSED OF AT
A CONTRACTOR-SELECTED AND
OWNER-APPROVED OFF-SITE UPLAND
COMMERCIAL LANDFILL LOCATION IN
ACCORDANCE WITH FEDERAL, STATE, AND
LOCAL LAWS AND REGULATIONS. NO DEBRIS IS
ALLOWED TO BE PLACED WITHIN THE BEACH
NOURISHMENT AREA AND MUST BE
SEGREGATED FROM THE SANDS.
michael.lau
AT
IO
N
IN
F
EE
T
HORIZONTAL DISTANCE IN FEET
2X VERTICAL EXAGGERATION
-25
-20
-15
-10
-5
-25
-20
-15
-10
-5
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250 260 270 280 290 300 310 320 330 340 350 360 370
D D'
EL
EV
AT
IO
N
IN
F
EE
T
HORIZONTAL DISTANCE IN FEET
2X VERTICAL EXAGGERATION
-25
-20
-15
-10
-5
-25
-20
-15
-10
-5
-20 -10 0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250 260 270 280 290 300 310 320 330 340 350
E E'
EL
EV
AT
IO
N
IN
F
EE
T
HORIZONTAL DISTANCE IN FEET
2X VERTICAL EXAGGERATION
-25
-20
-15
-10
-5
-25
-20
-15
-10
-5
-20 -10 0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250 260 270 280 290 300 310 320 330 340 350
F F'
1V 2H
1V 2H
EXISTING MUDLINE
1V 2H
1V 2H
EXISTING MUDLINE
1V 2H
1V 2H
EXISTING MUDLINE
HORIZONTAL SCALE:
VERTICAL SCALE:
SECTIOND
C01 1" = 20'
1" = 10'
HORIZONTAL SCALE:
VERTICAL SCALE:
SECTIONE
C01 1" = 20'
1" = 10'
HORIZONTAL SCALE:
VERTICAL SCALE:
SECTIONF
C01 1" = 20'
1" = 10'
REQUIRED DREDGE ELEVATION (-18')
1' PAID OVERDREDGE (-19')
BID ADDITIVE 2' PAID OVERDREDGE (-21' MLLW)
REQUIRED DREDGE ELEVATION (-18')
1' PAID OVERDREDGE (-19')
BID ADDITIVE 2' PAID OVERDREDGE (-21' MLLW)
REQUIRED DREDGE ELEVATION (-18')
1' PAID OVERDREDGE (-19')
BID ADDITIVE 2' PAID OVERDREDGE (-21' MLLW)
ALLOWABLE OVERDREDGE (-22' MLLW)
ALLOWABLE OVERDREDGE (-22' MLLW)
ALLOWABLE OVERDREDGE (-22' MLLW)
D. MASSARO
M. PRATSCHNER
M. COLLINS
T. WANG
AS NOTED
JUNE 2025
DRAFT - ISSUED FOR BID
DESCRIPTIONAPP'DDATE BY
REVISIONS
REV
O N
E
IN
CH
DESIGNED BY:
APPROVED BY:
CHECKED BY:
DRAWN BY:
DATE:
SCALE:
ALAMITOS BAY ENTRANCE CHANNEL
MAINTENANCE DREDGING AND BEACH
NOURISHMENT
SHEET # OF
PL
AN
IN
TE
N D
ED
T
O B
E
VI
EW
ED
IN
C
O
LO
R, A
D
JA
CE
N
T
BL
O
CK
IS
"B
LU
E"
AT
F
UL
L
SI
ZE
, I F
N O
T O
N E
IN
CH
S
CA
LE
A
CC
O
RD
IN
GL
Y
C04
DREDGE CROSS SECTIONS (2) 7
NOTES:
1. DREDGED MATERIAL EXCLUDING DEBRIS SHALL
BE PLACED AT THE IDENTIFIED BEACH
NOURISHMENT AREA.
2. CONTRACTOR SHALL DREDGE THE SIDE SLOPES
IDENTIFIED IN THE DRAWING. THE SIDE SLOPE
VOLUME ASSOCIATED WITH THE MAXIMUM PAY
LIMIT IS INCLUDED IN THE DREDGING BID ITEM
QUANTITIES.
3. DREDGING OF SEDIMENT OUTSIDE THE
DREDGING LIMITS AND/OR BELOW THE
NON-PAY OVERDREDGE ELEVATION IS DEFINED
AS EXCESSIVE DREDGING AND IS PROHIBITED.
CONTRACTOR WILL NOT BE PAID FOR EXCESSIVE
DREDGING AND WILL BE RESPONSIBLE FOR ANY
REGULATORY AGENCY FEES AND/OR FINES
INCURRED AS A RESULT OF EXCESSIVE
DREDGING. ADDITIONALLY, IF EXCESSIVE
DREDGING RESULTS IN DAMAGE OR
UNDERMINING TO EXISTING STRUCTURES, THE
CONTRACTOR SHALL RECTIFY TO THE CITY OR
AUTHORIZED REPRESENTATIVE'S SATISFACTION
PRIOR TO CLOSE OF THE CONTRACT.
4. THE REQUIRED DREDGE ELEVATION MUST BE
ACHIEVED IN ALL AREAS FOR IT TO BE
ACCEPTED AS COMPLETE. CONTRACTOR MUST
REMOVE ALL SLOUGH MATERIAL FROM THE
REQUIRED DREDGE AREA IN ORDER FOR WORK
TO BE ACCEPTED BY THE CITY OR AUTHORIZED
REPRESENTATIVE. THE CITY OR AUTHORIZED
REPRESENTATIVE WILL COMPARE THE PRE- AND
POST-DREDGE SURVEYS TO ENSURE THAT
DREDGED SEDIMENT FROM ALL OF THE DREDGE
AREA IS REMOVED FROM THE SITE.
5. CONTRACTOR MUST REMOVE ALL DEBRIS TO
CONDUCT THE DREDGING WORK. THE
CONTRACTOR SHALL TAKE CARE TO AVOID
CONTACT WITH THE NEARBY BANK DURING
DEBRIS REMOVAL ACTIVITIES.
6. ANY DEBRIS ENCOUNTERED AND REMOVED
DURING THE WORK SHALL BE REMOVED BY THE
CONTRACTOR AND PROPERLY DISPOSED OF AT
A CONTRACTOR-SELECTED AND
OWNER-APPROVED OFF-SITE UPLAND
COMMERCIAL LANDFILL LOCATION IN
ACCORDANCE WITH FEDERAL, STATE, AND
LOCAL LAWS AND REGULATIONS. NO DEBRIS IS
ALLOWED TO BE PLACED WITHIN THE BEACH
NOURISHMENT AREA AND MUST BE
SEGREGATED FROM THE SANDS.
LEGEND:
REQUIRED DREDGE ELEVATION (-18' MLLW)
1' PAID OVERDREDGE (-19' MLLW)
BID ADDITIVE 2' PAID OVERDREDGE (-21' MLLW)
EXISTING MUDLINE
REQUIRED DREDGING TO -18' MLLW
michael.lau
AT
IO
N
IN
F
EE
T
HORIZONTAL DISTANCE IN FEET
2X VERTICAL EXAGGERATION
-25
-20
-15
-10
-5
-25
-20
-15
-10
-5
-20 -10 0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250 260 270 280 290 300 310 320 330 340 350
G G'
EL
EV
AT
IO
N
IN
F
EE
T
HORIZONTAL DISTANCE IN FEET
2X VERTICAL EXAGGERATION
-25
-20
-15
-10
-5
-25
-20
-15
-10
-5
-20-20 -10 0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250 260 270 280 290 300 310 320 330 340 350 360
H H'
1V 2H
1V 2H
EXISTING MUDLINE
1V 2H
1V 2H
EXISTING MUDLINE
HORIZONTAL SCALE:
VERTICAL SCALE:
SECTIONG
C02 1" = 20'
1" = 10'
HORIZONTAL SCALE:
VERTICAL SCALE:
SECTIONH
C02 1" = 20'
1" = 10'
REQUIRED DREDGE ELEVATION (-18')
1' PAID OVERDREDGE (-19')
BID ADDITIVE 2' PAID OVERDREDGE (-21' MLLW)
REQUIRED DREDGE ELEVATION (-18')
1' PAID OVERDREDGE (-19')
BID ADDITIVE 2' PAID OVERDREDGE (-21' MLLW)
ALLOWABLE OVERDREDGE (-22' MLLW)
ALLOWABLE OVERDREDGE (-22' MLLW)
D. MASSARO
M. PRATSCHNER
M. COLLINS
T. WANG
AS NOTED
JUNE 2025
DRAFT - ISSUED FOR BID
DESCRIPTIONAPP'DDATE BY
REVISIONS
REV
O N
E
IN
CH
DESIGNED BY:
APPROVED BY:
CHECKED BY:
DRAWN BY:
DATE:
SCALE:
ALAMITOS BAY ENTRANCE CHANNEL
MAINTENANCE DREDGING AND BEACH
NOURISHMENT
SHEET # OF
PL
AN
IN
TE
N D
ED
T
O B
E
VI
EW
ED
IN
C
O
LO
R, A
D
JA
CE
N
T
BL
O
CK
IS
"B
LU
E"
AT
F
UL
L
SI
ZE
, I F
N O
T O
N E
IN
CH
S
CA
LE
A
CC
O
RD
IN
GL
Y
C05
DREDGE CROSS SECTIONS (3) 8
NOTES:
1. DREDGED MATERIAL EXCLUDING DEBRIS SHALL
BE PLACED AT THE IDENTIFIED BEACH
NOURISHMENT AREA.
2. CONTRACTOR SHALL DREDGE THE SIDE SLOPES
IDENTIFIED IN THE DRAWING. THE SIDE SLOPE
VOLUME ASSOCIATED WITH THE MAXIMUM PAY
LIMIT IS INCLUDED IN THE DREDGING BID ITEM
QUANTITIES.
3. DREDGING OF SEDIMENT OUTSIDE THE
DREDGING LIMITS AND/OR BELOW THE
NON-PAY OVERDREDGE ELEVATION IS DEFINED
AS EXCESSIVE DREDGING AND IS PROHIBITED.
CONTRACTOR WILL NOT BE PAID FOR EXCESSIVE
DREDGING AND WILL BE RESPONSIBLE FOR ANY
REGULATORY AGENCY FEES AND/OR FINES
INCURRED AS A RESULT OF EXCESSIVE
DREDGING. ADDITIONALLY, IF EXCESSIVE
DREDGING RESULTS IN DAMAGE OR
UNDERMINING TO EXISTING STRUCTURES, THE
CONTRACTOR SHALL RECTIFY TO THE CITY OR
AUTHORIZED REPRESENTATIVE'S SATISFACTION
PRIOR TO CLOSE OF THE CONTRACT.
4. THE REQUIRED DREDGE ELEVATION MUST BE
ACHIEVED IN ALL AREAS FOR IT TO BE
ACCEPTED AS COMPLETE. CONTRACTOR MUST
REMOVE ALL SLOUGH MATERIAL FROM THE
REQUIRED DREDGE AREA IN ORDER FOR WORK
TO BE ACCEPTED BY THE CITY OR AUTHORIZED
REPRESENTATIVE. THE CITY OR AUTHORIZED
REPRESENTATIVE WILL COMPARE THE PRE- AND
POST-DREDGE SURVEYS TO ENSURE THAT
DREDGED SEDIMENT FROM ALL OF THE DREDGE
AREA IS REMOVED FROM THE SITE.
5. CONTRACTOR MUST REMOVE ALL DEBRIS TO
CONDUCT THE DREDGING WORK. THE
CONTRACTOR SHALL TAKE CARE TO AVOID
CONTACT WITH THE NEARBY BANK DURING
DEBRIS REMOVAL ACTIVITIES.
6. ANY DEBRIS ENCOUNTERED AND REMOVED
DURING THE WORK SHALL BE REMOVED BY THE
CONTRACTOR AND PROPERLY DISPOSED OF AT
A CONTRACTOR-SELECTED AND
OWNER-APPROVED OFF-SITE UPLAND
COMMERCIAL LANDFILL LOCATION IN
ACCORDANCE WITH FEDERAL, STATE, AND
LOCAL LAWS AND REGULATIONS. NO DEBRIS IS
ALLOWED TO BE PLACED WITHIN THE BEACH
NOURISHMENT AREA AND MUST BE
SEGREGATED FROM THE SANDS.
LEGEND:
REQUIRED DREDGE ELEVATION (-18' MLLW)
1' PAID OVERDREDGE (-19' MLLW)
BID ADDITIVE 2' PAID OVERDREDGE (-21' MLLW)
EXISTING MUDLINE
REQUIRED DREDGING TO -18' MLLW
michael.lau
AT
IO
N
IN
F
EE
T
HORIZONTAL DISTANCE IN FEET
2X VERTICAL EXAGGERATION
-25
-20
-15
-10
-5
-25
-20
-15
-10
-5
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250 260 270 280 290 300 310 320 330 340 350 360 370 380 390 400 410 420 430 440 450
I I'
EL
EV
AT
IO
N
IN
F
EE
T
HORIZONTAL DISTANCE IN FEET
2X VERTICAL EXAGGERATION
-25
-20
-15
-10
-5
-25
-20
-15
-10
-5
-40 -30 -20 -10 0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250 260 270 280 290 300 310 320 330 340
J J'
1V 2H
EXISTING MUDLINE
1V 2H
EXISTING MUDLINE
1V 2H
HORIZONTAL SCALE:
VERTICAL SCALE:
SECTIONI
C02 1" = 20'
1" = 10'
HORIZONTAL SCALE:
VERTICAL SCALE:
SECTIONJ
C02 1" = 20'
1" = 10'
EXISTING FLOATING DOCKS
REQUIRED DREDGE ELEVATION (-18')
1' PAID OVERDREDGE (-19')
BID ADDITIVE 2' PAID OVERDREDGE (-21' MLLW)
REQUIRED DREDGE ELEVATION (-18')
1' PAID OVERDREDGE (-19')
BID ADDITIVE 2' PAID OVERDREDGE (-21' MLLW)
ALLOWABLE OVERDREDGE (-22' MLLW)
ALLOWABLE OVERDREDGE (-22' MLLW)
D. MASSARO
M. PRATSCHNER
M. COLLINS
T. WANG
AS NOTED
JUNE 2025
DRAFT - ISSUED FOR BID
DESCRIPTIONAPP'DDATE BY
REVISIONS
REV
O N
E
IN
CH
DESIGNED BY:
APPROVED BY:
CHECKED BY:
DRAWN BY:
DATE:
SCALE:
ALAMITOS BAY ENTRANCE CHANNEL
MAINTENANCE DREDGING AND BEACH
NOURISHMENT
SHEET # OF
PL
AN
IN
TE
N D
ED
T
O B
E
VI
EW
ED
IN
C
O
LO
R, A
D
JA
CE
N
T
BL
O
CK
IS
"B
LU
E"
AT
F
UL
L
SI
ZE
, I F
N O
T O
N E
IN
CH
S
CA
LE
A
CC
O
RD
IN
GL
Y
C06
DREDGE CROSS SECTIONS (4) 9
NOTES:
1. DREDGED MATERIAL EXCLUDING DEBRIS
SHALL BE PLACED AT THE IDENTIFIED
BEACH NOURISHMENT AREA.
2. CONTRACTOR SHALL DREDGE THE SIDE
SLOPES IDENTIFIED IN THE DRAWING.
THE SIDE SLOPE VOLUME ASSOCIATED
WITH THE MAXIMUM PAY LIMIT IS
INCLUDED IN THE DREDGING BID ITEM
QUANTITIES.
3. DREDGING OF SEDIMENT OUTSIDE THE
DREDGING LIMITS AND/OR BELOW THE
NON-PAY OVERDREDGE ELEVATION IS
DEFINED AS EXCESSIVE DREDGING AND
IS PROHIBITED. CONTRACTOR WILL NOT
BE PAID FOR EXCESSIVE DREDGING AND
WILL BE RESPONSIBLE FOR ANY
REGULATORY AGENCY FEES AND/OR
FINES INCURRED AS A RESULT OF
EXCESSIVE DREDGING. ADDITIONALLY, IF
EXCESSIVE DREDGING RESULTS IN
DAMAGE OR UNDERMINING TO
EXISTING STRUCTURES, THE
CONTRACTOR SHALL RECTIFY TO THE
CITY OR AUTHORIZED
REPRESENTATIVE'S SATISFACTION PRIOR
TO CLOSE OF THE CONTRACT.
4. THE REQUIRED DREDGE ELEVATION
MUST BE ACHIEVED IN ALL AREAS FOR IT
TO BE ACCEPTED AS COMPLETE.
CONTRACTOR MUST REMOVE ALL
SLOUGH MATERIAL FROM THE
REQUIRED DREDGE AREA IN ORDER FOR
WORK TO BE ACCEPTED BY THE CITY OR
AUTHORIZED REPRESENTATIVE. THE CITY
OR AUTHORIZED REPRESENTATIVE WILL
COMPARE THE PRE- AND POST-DREDGE
SURVEYS TO ENSURE THAT DREDGED
SEDIMENT FROM ALL OF THE DREDGE
AREA IS REMOVED FROM THE SITE.
5. CONTRACTOR MUST REMOVE ALL
DEBRIS TO CONDUCT THE DREDGING
WORK. THE CONTRACTOR SHALL TAKE
CARE TO AVOID CONTACT WITH THE
NEARBY BANK DURING DEBRIS
REMOVAL ACTIVITIES.
6. ANY DEBRIS ENCOUNTERED AND
REMOVED DURING THE WORK SHALL BE
REMOVED BY THE CONTRACTOR AND
PROPERLY DISPOSED OF AT A
CONTRACTOR-SELECTED AND
OWNER-APPROVED OFF-SITE UPLAND
COMMERCIAL LANDFILL LOCATION IN
ACCORDANCE WITH FEDERAL, STATE,
AND LOCAL LAWS AND REGULATIONS.
NO DEBRIS IS ALLOWED TO BE PLACED
WITHIN THE BEACH NOURISHMENT
AREA AND MUST BE SEGREGATED FROM
THE SANDS.
7. CONTRACTOR IS RESPONSIBLE FOR
CLEANING MATERIAL FROM ANY
SURFACES, DOCKS, OR PROPERTY AS
SOON AS POSSIBLE OR BY THE END OF
EACH WORK DAY.
LEGEND:
REQUIRED DREDGE ELEVATION (-18' MLLW)
1' PAID OVERDREDGE (-19' MLLW)
BID ADDITIVE 2' PAID OVERDREDGE (-21' MLLW)
ALLOWABLE OVERDREDGE (-22' MLLW)
EXISTING MUDLINE
REQUIRED DREDGING TO -18' MLLW
michael.lau
-11
-10
-9
-8
-7 -6
-5 -4
-3-2-10 1 2 3 4 5 6 7 8 9
-16
-16
-15
-1
-14
-1
-13
-1
-12
-1
-10 -9
-8
-4 -5
-6 -7
-8 -9
-25 -20
-1
-10
-15
-18
-17
-15
-18
-1
-21
-20
-21
-5
-10
-1
-17
-16
-1
-1
-13
-1
-1
-1
-16
-17
-1-2
-3 -4
-5
-15 -20
-1
-14 -16
-14
-13
-12
-11
-10
-9 -8
-7
5 6 7 8 9 10
EXISTING
JETTIES
SEAL BEACH, CALIFORNIA
ALAMITOS
BAY
ENTRANCE
CHANNEL DREDGING
(SEE SHEETS C01 & C02)
BASIN 5
-10
-5
-5
K C0
PROPOSED STAGING AREA
11 12
EL
EV
AT
IO
N
IN
F
EE
T
HORIZONTAL DISTANCE IN FEET
2X VERTICAL EXAGGERATION
-30
-20
-10
-30
-20
-10
0 20 40 60 80 100 120 140 160 180 200 220 240 260 280 300 320 340 360 380 400 420 440 460 480 500 520 540 560 580 600 620 640 660 680 700
K K'
+10' MLLW TOP ELEVATION TARGET
WITH +/- 2' VERTICAL TOLERANCE
OVER BEACH NOURISHMENT AREA.
HORIZONTAL SCALE:
VERTICAL SCALE:
SECTIONK
C07 1" = 40'
1" = 20'
EXISTING GROUND
TARGET SIDE SLOPE TO RANGE BETWEEN
20H:1V MINIMUM TO 20H:3V MAXIMUM
IN BEACH NOURISHMENT AREA.
MHHW 5.5'
BEACH TO BE NOURISHED WITH DREDGED
MATERIAL UP TO THE TOTAL ALLOWABLE VOLUME
D. MASSARO
M. PRATSCHNER
M. COLLINS
T. WANG
AS NOTED
JUNE 2025
DRAFT - ISSUED FOR BID
DESCRIPTIONAPP'DDATE BY
REVISIONS
REV
O N
E
IN
CH
DESIGNED BY:
APPROVED BY:
CHECKED BY:
DRAWN BY:
DATE:
SCALE:
ALAMITOS BAY ENTRANCE CHANNEL
MAINTENANCE DREDGING AND BEACH
NOURISHMENT
SHEET # OF
PL
AN
IN
TE
N D
ED
T
O B
E
VI
EW
ED
IN
C
O
LO
R, A
D
JA
CE
N
T
BL
O
CK
IS
"B
LU
E"
AT
F
UL
L
SI
ZE
, I F
N O
T O
N E
IN
CH
S
CA
LE
A
CC
O
RD
IN
GL
Y
NORTH
SCALE IN FEET
200 400
LEGEND:
EXISTING CONTOUR (5')
EXISTING CONTOUR (1')
BEACH NOURISHMENT PLACEMENT AREA
HAUL ROUTE FOR OFFSITE DISPOSAL OF DEBRIS
C07
BEACH NOURISHMENT AREA 10
NOTES:
1. HORIZONTAL DATUM: CALIFORNIA STATE PLANE
ZONE 5, NAD83, U.S. SURVEY FEET
2. VERTICAL DATUM: FEET MLLW, NTDE 1983-2001.
3. BATHYMETRIC SURVEY DATA COLLECTED BY
ETRAC (A WOOLPERT COMPANY), DATED JULY
12, 2023. BATHYMETRY AT TIME OF DREDGING
MAY DIFFER.
4. CONTRACTOR RESPONSIBLE FOR INSTALLING,
MAINTAINING, AND REMOVING PUBLIC SAFETY
MEASURES AROUND BEACH PLACEMENT AND
STAGING AREAS. SAFETY MEASURES SHALL
INCLUDE, BUT NOT BE LIMITED TO, SIGNAGE,
BARRICADES, FENCING WITH GATES, SPOTTERS,
AND CORDONED OFF ACTIVE WORK AREAS. SEE
SPECIFICATIONS FOR PUBLIC SAFETY
REQUIREMENTS.
5. CONTRACTOR SHALL PLACE DREDGED MATERIAL
IN BEACH NOURISHMENT AREA USING
HYDRAULIC PLACEMENT METHODS FROM
EITHER HYDRAULIC DREDGING DISCHARGE
PIPELINE, OR HYDRAULIC DISCHARGE FROM A
HAUL BARGE IF MECHANICAL DREDGING IS
USED.
6. CONTRACTOR TO CONFIRM EXTENTS AND
LOCATION OF STAGING AREA WITH CITY.
7. CONTRACTOR TO OBTAIN OWNER APPROVAL
PRIOR TO TEMPORARILY STOCKPILING DEBRIS
AT THE SITE.
SCALE IN FEET
200 400
BEACH TO BE NOURISHED WITH DREDGED
MATERIAL UP TO THE TOTAL ALLOWABLE VOLUME.
michael.lau
© 2024 Microsoft Corporation © 2024 Maxar ©CNES (2024) Distribution Airbus DS
-26
-24
-22
-20
-18
-16
-14 -14
-14
-12
-10
-8
-6
-4
-2
-2 4 -2 2 -2
-1
-16
-1
-16
-1
-1
-14 -1
-1
-1 2 -1
-1
-1 0 -8
-8
-6
-6
-4 -4
-8
-6 -4
-1 0 -1
-1
-1
-1
-4
-6
-8
-1
-12
-20
-10
-20-18
-20 -18
-18
-20
-1
-16
-14
-14
-16
-2
-4
-20
-12
-14 -16
-20
-20
-10 -12
-14
-22
-20
-18
-16
-14
-12
-10
-8
-6
-4
-2
-2
EXISTING
JETTIES
SEAL BEACH, CALIFORNIA
PACIFIC
OCEAN
ALAMITOS
BAY
ENTRANCE
CHANNEL DREDGING
(SEE SHEETS C01 & C02)
BASIN 5
BEACH
NOURISHMENT
AREA
0-2-4
-6
BASIN 2
BASIN 1
-1
-16
-14
0-2 -4
-6
D. MASSARO
M. PRATSCHNER
M. COLLINS
T. WANG
AS NOTED
JUNE 2025
DRAFT - ISSUED FOR BID
DESCRIPTIONAPP'DDATE BY
REVISIONS
REV
O N
E
IN
CH
DESIGNED BY:
APPROVED BY:
CHECKED BY:
DRAWN BY:
DATE:
SCALE:
ALAMITOS BAY ENTRANCE CHANNEL
MAINTENANCE DREDGING AND BEACH
NOURISHMENT
SHEET # OF
PL
AN
IN
TE
N D
ED
T
O B
E
VI
EW
ED
IN
C
O
LO
R, A
D
JA
CE
N
T
BL
O
CK
IS
"B
LU
E"
AT
F
UL
L
SI
ZE
, I F
N O
T O
N E
IN
CH
S
CA
LE
A
CC
O
RD
IN
GL
Y
NORTH
SCALE IN FEET
300 600
LEGEND:
EXISTING CONTOUR (5')
EXISTING CONTOUR (1')
BEACH NOURISHMENT PLACEMENT AREA
CONCEPTUAL PIPELINE ROUTE OVER JETTY IF
FEASIBLE AND APPROVED (SEE NOTE 6)
EXISTING EELGRASS
C08
POTENTIAL HYDRAULIC DREDGE
PIPELINE ROUTE 11
NOTES:
1. HORIZONTAL DATUM: CALIFORNIA STATE PLANE
ZONE 5, NAD83, U.S. SURVEY FEET
2. VERTICAL DATUM: FEET MLLW, NTDE 1983-2001.
3. BATHYMETRIC SURVEY DATA COLLECTED BY ETRAC
(A WOOLPERT COMPANY), DATED JULY 12, 2023.
BATHYMETRY AT TIME OF DREDGING MAY DIFFER.
4. THE HYDRAULIC PIPELINE, IF USED TO PERFORM THE
DREDGING, SHALL BE PRIMARILY LOCATED OUTSIDE
OF THE ENTRANCE CHANNEL LIMITS EXCEPT FOR
THE PORTION OF THE PIPELINE ATTACHED TO THE
HYDRAULIC DREDGE OPERATING WITHIN THE
ENTRANCE CHANNEL BOUNDARIES. ALL FLOATING
PIPELINES SHALL BE MARKED WITH LIGHTS MEETING
USCG REGULATIONS. CONTRACTOR SHALL FULLY
SUBMERGE THE HYDRAULIC PIPELINE PORTIONS
LOCATED WITHIN THE NAVIGATION CHANNEL FOR
SAFE VESSEL PASSAGE. SUBMERGED PIPELINES
SHALL BE MARKED WITH BUOYS ALONG ITS
LENGTH. PIPELINES SHALL NOT DISTURB EELGRASS
AREAS.
5. EELGRASS SURVEY BY MTS IN MARCH 2024. AVOID
DISTURBING EELGRASS AREAS. NO DREDGING,
ANCHORING, SPUDDING, OR PIPELINE ROUTING IS
ALLOWED WITHIN EELGRASS AREAS.
6. CONTRACTOR SHALL PROPOSE A PIPELINE ROUTE
TO SAFELY CROSS OVER THE WESTERN JETTY.
PUBLIC SAFETY MUST BE MAINTAINED
THROUGHOUT THE WORK. PIPELINE MUST BE
PLACED WATERWARD OF THE 72ND PI LIFEGUARD
STATION, ALLOWING FOR CONTINUOUS VEHICLE
ACCESS TO 72ND STATION FROM THE ROAD.
STAGING
AREA
NORTH
SCALE IN FEET
100 200
72ND PI
LIFEGUARD
STATION
EC-DU1
michael.lau
| Sheets and Views |
| 1 0548 PL TITLE - T01 |
| 2 0548 PL TITLE - G01 |
| 3 0548 PL EXISTING - G02 |
| 4 0548 PL DREDGE - C01 |
| 5 0548 PL DREDGE - C02 |
| 6 0548 PL XSEC - C03 |
| 7 0548 PL XSEC - C04 |
| 8 0548 PL XSEC - C05 |
| 9 0548 PL XSEC - C06 |
| 10 0548 PL BEACH NOURISHMENT - C07 |
| 11 0548 PL PIPELINE - C08 |
File details come from the government source that posted it. Updated .