This is a Statement of Work (SOW) for cleaning, inspection, and hazardous waste removal services for two 10,000-gallon Oil/Water Separators (OWS) located at the Minneapolis-St. Paul Air Reserve Base POL facility. The contractor must complete all work within 60 calendar days from contract award during normal business hours (Monday-Friday, 0600-1630, excluding Federal holidays), with any outside-hour work requiring prior written approval from the Contracting Officer's Representative (COR). The contractor is responsible for providing all personnel, equipment, tools, materials, vehicles, supervision, and services necessary to perform complete cleaning, inspection, and waste disposal in compliance with SQG environmental standards and Air Force environmental compliance policies.

The specific tasks include: (1) pre-cleaning sampling and testing to determine if contents meet hazardous waste criteria; (2) if non-hazardous, pumping and evacuation of all oil, sludge, and waste with transport to approved off-base disposal facilities; (3) thorough interior cleaning of separators with proper capture and management of secondary wash water; (4) comprehensive inspection per API Publication 421 examining structural integrity, internal components, seals, gaskets, plumbing, and valves; and (5) system restoration by refilling with clear water to re-establish operational seal. If hazardous waste is identified, the contractor must immediately terminate work and contact the COR and environmental office, then utilize a certified hazardous waste transporter and prepare EPA Uniform Hazardous Waste Manifests (signed only by authorized COR personnel) for transport to a permitted RCRA Treatment, Storage, and Disposal Facility. Deliverables include a written Service and API 421 Inspection Report detailing findings and maintenance recommendations, and hazardous waste manifests with tracking documents. All contractor personnel must complete appropriate hazardous waste training (HAZWOPER) and comply with installation security requirements.

View the file

Other files

File Type Posted
Vendor questions RV3.pdf PDF
Attch 3. CLSExport_FA663326QA011 Rv1.pdf PDF
Vendor questions RV2.pdf PDF
20260812 Combo RV3.pdf PDF
Vendor questions RV1.pdf PDF
20260806 Combo RV1.pdf PDF
Picture1.jpg JPG image
Picture3.jpg JPG image
Picture5.jpg JPG image
Vendor questions.pdf PDF
Attch 1. MN ARB PWS-POL.pdf PDF
OWS 1 - Bldg 602.pdf PDF
OWS 2 - Bldg 606.pdf PDF
Picture2.png PNG image
Picture4.jpg JPG image
Attch 3. CLSExport_FA663326QA011.pdf PDF
20260723 Combo.pdf PDF
Attch 2. WD 2015-4945 RV 31.pdf PDF
Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CUI

STATEMENT OF WORK (SOW)

Cleaning, Inspection, and Hazardous Waste Removal for Two 10,000-Gallon Oil/Water Separators

1.0 Scope of Work

The contractor shall provide all personnel, equipment, tools, materials, vehicles, supervision, and other items and services necessary to perform the complete cleaning, inspection, and waste disposal for two (2) 10,000-gallon Oil/Water Separators (OWS) located at the POL facility. The installation operates as a Small Quantity Generator (SQG), and all waste management must comply with applicable SQG environmental standards and Air Force environmental compliance policies.

1.1 Location: Minneapolis-St. Paul ARB / POL facility

1.2. Period Of Performance

The total period of performance shall not exceed 60 calendar days from the date of contract award. All on-site work and final waste disposal must be completed within this timeframe.

1.3 Work Hours

Normal work hours are Monday through Friday, 0600 to 1630, excluding Federal holidays.

Work outside these hours requires prior written approval from the Contracting Officer's Representative (COR).

2.0 Applicable Directives and References

The contractor shall comply with all applicable federal, state, and local laws, as well as Air Force and industry regulations, including but not limited to:

• Occupational Safety & Health Administration (OSHA):

o 29 CFR 1910, Occupational Safety and Health Standards o 29 CFR 1910.120, Hazardous Waste Operations and Emergency Response

(HAZWOPER)

o 29 CFR 1910.146, Permit-Required Confined Spaces

• Environmental Protection Agency (EPA):

o 40 CFR Part 279, Standards for the Management of Used Oil o 40 CFR Part 112, Oil Pollution Prevention o 40 CFR Part 110, Discharge of Oil o 40 CFR Parts 260-282, Hazardous Waste

• Department of Transportation (DOT):

o 49 CFR Parts 171-180, Hazardous Materials Regulations

• Department of the Air Force Manual (DAFMAN):

o DAFMAN 32-7002, Environmental Compliance o DAFI 91-203, Air Force Consolidated Occupational Safety Instruction

• State & Local:

o Minnesota Rules, Chapter 7045, Hazardous Waste

2.1 Spills

Spill protection is required of the contractor. The contractor shall carry spill supplies such as absorbent material capable of emergency cleanup of spills or drips. In the event of a spill, the contractor shall notify the Contracting Officer’s Representative (COR) as soon as it is safe to do so.

3.0 Specific Tasks and Performance Requirements

3.1 Pre-Cleaning Sampling and Testing

Prior to any cleaning and pumping operations, the contractor shall perform appropriate tests of the OWS contents (including floating materials, liquids, and sludge) to determine if the materials meet the criteria for hazardous waste.

• Hazardous Contingency: If tests indicate the presence of hazardous materials, the contractor shall immediately terminate servicing and contact the COR and the installation environmental office. The environmental office will determine the subsequent requirements for the disposal of hazardous contents.

3.2 Pumping, Evacuation, and Packaging

If the contents are confirmed as non-hazardous, the contractor shall proceed with the cleaning operations. The contractor shall pump all oil, oil residue, sludge, and other waste from both 10,000-gallon separators, draining them completely.

• Discharge Prohibition: In accordance with DAFMAN 32-7002 and related local supplements, the contractor shall not discharge any OWS residue, wash water, or industrial waste to the environment, sanitary sewer, or stormwater sewer systems under any circumstances without explicit written approval from the Installation Environmental Office.

• The contractor shall be responsible for the safe transport and legal disposal of all pump-out waste (oil, water, and sludge). Disposal must occur at an approved off-base facility in accordance with environmental regulations.

3.3 Cleaning Procedures

The contractor shall thoroughly wash and clean the interior of the separators. Any reusable coalescing media or internal filters must be carefully removed, cleaned, and fully dried before reinstallation. All secondary wash water generated during this process must be captured, containerized, and managed in accordance with all relevant regulations.

3.4 API 421 Inspection Protocol

While the separators are empty and clean, the contractor shall conduct a comprehensive inspection in accordance with API Publication 421. The inspection protocol must include:

• Structural Integrity: Inspection of the vault bottom and walls for cracks, leaks, corrosion, and overall structural degradation.

• Internal Components: Checking the condition and alignment of coalescing plate packs, baffles, and skimmer mechanisms.

• Seals and Gaskets: Inspecting all access ports, hatches, and pump seals for degrading gaskets.

• Plumbing and Valves: Inspecting associated transfer pumps, effluent pumps, and non-return (check) valves.

3.5 System Restoration

Following the washing and inspection phase, the contractor shall refill the separators with clear water to re-establish the proper operational seal, ensuring no residue is flushed into the discharge line during restart.

3.6 Hazardous Waste Tracking and Disposal (DAFMAN 32-7002 Compliance) In the event that the waste material is hazardous, the contractor shall utilize a certified hazardous waste transporter to safely remove the containerized waste from the installation.

• Tracking/Manifesting: The contractor must prepare the EPA Uniform Hazardous Waste Manifest utilizing the base's SQG EPA ID number. In no event shall the contractor sign the manifest. Only a COR with active manifest-signing certification shall sign the manifest.

• Disposal: The waste must be transported to a fully permitted Resource Conservation and Recovery Act (RCRA) Treatment, Storage, and Disposal Facility

(TSDF).

4.0 Deliverables

• 4.1 Service and API 421 Inspection Report: The contractor shall provide a written report to the Contracting Officer Representative (COR) detailing the API 421 inspection findings, the condition of the OWS units, and recommendations for future maintenance.

• 4.2 Hazardous Waste Manifests & Tracking Documents: The contractor must submit the initial signed Uniform Hazardous Waste Manifests upon departure from the base and provide the final TSDF-signed return-to-generator manifests to the base environmental office within the required timeframe for SQGs. Additionally, any waste tracking documents related to non-hazardous waste shall be submitted to the COR.

5.0 Security and Safety Requirements

• 5.1 Training Certification: In accordance with DAFMAN 32-7002, all contractor personnel handling hazardous waste must have successfully completed HW training appropriate to their job responsibilities as required by 40 CFR Part 262, Subpart A (e.g., HAZWOPER) prior to executing this work.

• 5.2 Installation Security: All contractor personnel must adhere to installation security requirements, including obtaining necessary gate passes and maintaining a safe working environment.

CUI
STATEMENT OF WORK (SOW)
1.0 Scope of Work
2.0 Applicable Directives and References
Occupational Safety & Health Administration (OSHA):
Environmental Protection Agency (EPA):
Department of Transportation (DOT):
Department of the Air Force Manual (DAFMAN):
State & Local:
2.1 Spills
3.0 Specific Tasks and Performance Requirements
3.2 Pumping, Evacuation, and Packaging
3.3 Cleaning Procedures
3.4 API 421 Inspection Protocol
3.5 System Restoration
3.6 Hazardous Waste Tracking and Disposal (DAFMAN 32-7002 Compliance)
4.0 Deliverables
5.0 Security and Safety Requirements