Attachment_V_-_AIRS_Process_Guide.pdf
PDF 112 KB Posted
- Solicitation number
- 1305M224Q0182
About this file
This document is an Additional Item Requirements (AIR) Process Guide for the Fiscal Year 2025 Drydock Repairs of NOAA SHIP OSCAR ELTON SETTE under solicitation 1305M224Q0182.
The guide outlines the process for executing AIRs during the contract performance period. It details the steps for the contractor to submit Condition Found Reports, the COR's response and issuance of AIRs, the contractor's pricing response, and the review and negotiation process by the Contracting team and Contracting Officer. The process aims to minimize contract modifications by consolidating multiple AIRs into a single modification once authorized. The document also includes details on the technical and pricing requirements for the contractor's AIR response.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment V 1305M224Q0182
NATIONAL OCEANIC AND ATMOSPHERIC ADMINISTRATION (NOAA)
EASTERN ACQUISITION DIVISION
Additional Item Requirements (AIR) Process Guide for the Fiscal Year 2025 Drydock Repairs of NOAA SHIP OSCAR ELTON SETTE:
Pursuant to Commerce Acquisition Regulation 1352.271-72 ADDITIONAL ITEM REQUIREMENTS (AIR) - GROWTH WORK (APR 2010) , the following process shall be used throughout the performance of the contract to execute AIRs. Exceptions to this process are expected throughout the period of performance (PoP) and will be addressed on a case by case basis.
1. Contractor submits Condition Found Report (CFR) to the Contracting Officer’s Representative (COR) and copies the Contracting Team (Contracting). For this contract, Contracting includes Contract Specialist Kelani Lawrence and Contracting Officer (CO) Ashley Perry .
2. COR issues Condition Report Response and sends it back to the Contractor and copies Contracting. The response will include:
a) Acknowledgment of receipt of the Condition Report.
b) Additional information and/or comments from the Government, if needed.
c) Notice that an AIR will be issued, if needed.
3. If an AIR is required the COR will send the AIR form to Contracting ONLY. The AIR is an internal document from the COR to the Contracting Officer requesting to add an item to the requirement (contract). Not every AIR will have a related CFR as some represent additional requirements identified by the COR.
AIR Submission to Contracting:
(a) All details in the AIR shall be filled out and signed.
(b) An IGW shall be attached with the AIR.
4. Unless Contracting has additional questions for the COR, the Contracting Team will issue a Request for Pricing to the Contractor.
5. The Contractor shall respond to the AIR with a quotation for the additional work requested within three days of receipt of the AIR. Contractors shall provide quotes to Contracting ONLY.
Contractor response to AIR shall include an analysis of the requirements against the production chart and shall include the following additional information:
a. A firm statement concerning impacts to the production chart: This statement shall either confirm that the additional work can be accomplished within the current PoP, or it shall state that the additional work will affect the PoP completion date. In case of the latter, the quote shall note the primary and any secondary work items that would be affected, Attachment V 1305M224Q0182 including an excerpt of the contractor’s planning production chart showing the impact to the project.
b. The contractor shall also provide an analysis and alternative proposal to maintain existing PoP, including such things as alternative procedures, accelerated and/or premium labor efforts, or any other solutions contractor may present to avoid contract PoP extensions.
6. Upon receipt of the quote from the Contractor, the quote will be reviewed by Contracting who will consult with the COR if necessary.
7. Negotiations may take place prior to accepting the pricing to address any issues/concerns that the Government has with the quote (omissions, justification of materials/hours, etc).
8. Contracting will prepare a brief summary of the pricing acceptance/negotiation for the CO and submit it to the CO for review.
9. The CO reviews the entire package (CR, CRR, IGE, pricing, technical review, and summary of pricing acceptance/negotiation).
10. Once all aspects of the AIR have been negotiated, if necessary, and agreed by both the Contractor and Contracting, the CO signs a Notice to Proceed (NTP).
11. Contracting distributes NTP, this AIR is now considered a part of the contract and work can start.
12. To reduce the amount of modifications to the contract, once a number of AIRs have been authorized through an NTP a consolidated modification will be issued memorializing the agreed-to AIRs.