This document is a detailed performance specification for drydock repairs and modifications to the NOAA Ship Oscar Elton Sette. It contains requirements for drydocking and routine drydock work, temporary services, dock and sea trials, switchboard cleaning, sea valve overhauls, underwater hull maintenance, ABS special survey, freeboard preservation, clear flow system service, and various structural and pipe repairs. Key details include:

The repairs are required to address issues identified at the end of the ship's sailing season, perform upgrades to mission and ship systems, and address any emergent work. The work must be completed to meet regulatory requirements and habitability standards. Specific tasks include renewing hull/sea chest zincs, overhauling sea valves, preserving the underwater hull and freeboard, servicing the clear flow system, and repairing various steel structures and piping. The work is to be completed during a scheduled drydock period, with dock and sea trials required prior to the ship's departure. The contractor must coordinate with the American Bureau of Shipping for inspections and surveys throughout the project.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NOAA SHIP OSCAR ELTON SETTE

SPECIFICATION FOR DRYDOCK REPAIRS

Fiscal Year (FY) 2025

Revision 3

FY 2025 DRYDOCK REPAIRS for NOAA Ship Oscar Elton Sette

TABLE OF CONTENTS

DESCRIPTION/TITLE PAGE NUMBER

1.0 SCOPE………………………………………………………………………………………………………………………………………4

2.0 GENERAL…………………………………………………………………………………………………………………………………5

3.0 BASE ORF ITEMS……………………………………………………………………………………………………………11

3.1 Drydock & Routine Drydock Work…………………………………………………………………11

3.2 Temporary Services…………………………………………………………………………………………………16

3.3 Dock and Sea Trials………………………………………………………………………………………………21

3.4 Switchboard Cleaning……………………………………………………………………………………………23

3.5 Sea Valve Overhauls………………………………………………………………………………………………25

3.6 Underwater Hull Maintenance Coat……………………………………………………………32

3.7 ABS Special Survey Inspection……………………………………………………………………36

3.8 Freeboard Preservation………………………………………………………………………………………44

3.9 Service Clear Flow System………………………………………………………………………………46

3.10 Miscellaneous Steel Repairs…………………………………………………………………………48

3.11 Miscellaneous Pipe Repairs……………………………………………………………………………51

3.12 Main Motor Thrust Bearing, Inspect, Clean & Oil Change…60

3.13 Bow Thruster Inspection and Service……………………………………………………63

3.14 GMDSS/Radar Groom……………………………………………………………………………………………………66

3.15 Annual Life Raft Inspection…………………………………………………………………………67

3.16 Annual Fire Inspection………………………………………………………………………………………69

3.17 Hose Renewals………………………………………………………………………………………………………………74

3.18 Galley and Crews Mess Decking Top Coat Removal………………………76

3.19 HVAC Cleaning………………………………………………………………………………………………………………78

3.20 Ladderwell Deck Covering Renewal……………………………………………………………82

3.21 Head Repairs…………………………………………………………………………………………………………………86

3.22 Annual Marine Sanitation Device (MSD) Service…………………………88

3.23 Small Boat Maintenance………………………………………………………………………………………90

3.24 Antenna Replacement/Restoration……………………………………………………………102

3.25 Open and Inspect of MCT …………………………………………………………………………………104

3.26 Upper Deck Crane Mods & Aft Deck Crane Cable Replacement……… 106

3.27 Transducer Pod Redesign…………………………………………………………………………………109

3.28 Miscellaneous Electrical………………………………………………………………………………116

3.29 Stateroom Carpet Cleaning……………………………………………………………………………117

3.30 MG Set #1 and #2 Clean/Inspect/Replace Bearings…………………119

3.31 Annual Weight Testing of Weight Handling Equipment…………123

3.32 Ballast Water Management System Annual Service……………………125

3.33 Valve & Strainer Replacement……………………………………………………………………127

3.34 Fabrication of Gasoline Tank……………………………………………………………………130

3.35 Alfa Laval Fuel Purifier Service/Overhaul…………………………………135

3.36 Potable Water Tank Painting………………………………………………………………………136

3.37 Small Boat Tall Cradle Stand Preservation…………………………………138

4.0 BASE PAC ITEMS…………………………………………………………………………………………………………140

4.1 #2 and #3 SSDG Generator Overhaul………………………………………………………140

4.2 10,000 Hour CAT D398 Engine Overhaul………………………………………………143

4.3 Transducer Trunk Shell Plate Repair…………………………………………………151

4.4 No. 3 Chiller Plant Overhaul……………………………………………………………………153

4.5 Overhaul ASW Pump…………………………………………………………………………………………………157

4.6 Fan Overhauls……………………………………………………………………………………………………………159

4.7 Dial Telephone & Public Address/General Alarm Systems Upgrade ………161

4.8 Profinet Upgrade Support………………………………………………………………………………167

5.0 ADDITIONAL WORK ORF……………………………………………………………………………………………169

6.0 ADDITIONAL WORK PAC……………………………………………………………………………………………171

7.0 ORF OPTION ITEMS……………………………………………………………………………………………………173

7.1 Bridge Weather Doors…………………………………………………………………………………………173

7.2 Port CTD Winch Overhaul…………………………………………………………………………………175

7.3 Trawl Winch Repairs……………………………………………………………………………………………176

8.0 PAC OPTION ITEMS……………………………………………………………………………………………………177

8.1 IX BLUE Gyrocompass Upgrade………………………………………………………………………177

9.0 Post-Industrial Berthing Period Option Item……………………………180

1. SCOPE

1.1. These Performance Specifications contain the requirements for drydock repairs and modifications to NOAA Ship Oscar Elton Sette .

1.2. The National Oceanic and Atmospheric Administration (NOAA) operates a fleet of research vessels that supports research and mapping for the National Marine Fisheries Service, National Ocean Service, Office of Atmospheric Research and the National Weather Service, as well as provides support to other Federal agencies. These research missions are time sensitive and therefore the data must be collected at specific times during the sailing season to be meaningful. At the end of each sailing season the vessels enter a repair period (drydock or dockside) to address repairs that have been previously identified, perform upgrades to mission systems or ship systems that either extend the life of the ship or provide new data collection capabilities or for safer operations of ships systems as well as address any emergent work that would adversely affect the ship's ability to safely perform its mission on schedule, while meeting all regulatory body requirements (American Bureau of Shipping and United States Coast Guard) and all habitability requirements, including any that may be required as a result of contracts for personnel to augment ship staff.

2. GENERAL

2.1. Intent:

2.1.1. Provide general requirements and information.

2.2. References:

2.2.1. NOAA Standard Specification No. AMC-000-1G, “General

Requirements for Ship Repair Work on NOAA Ships.”

2.2.2. NOAA Standard Specification S1600, “Structural Access Cuts.”

2.2.3. NOAA Standard Specification, S2906, “Arc Welding on

Waterborne Vessels.”

2.2.4. NOAA Standard Specification MOC-631-2D, “Coating Systems for Steel Surfaces.”

2.2.5. Drawing No. OS-830-002, “NOAA Ship Oscar Elton Sette Booklet of General Plans.”

2.2.6. Drawing No. OS-800-004, NOAA Ship Oscar Elton Sette Tank

Soundings Tables.”

2.2.7. NOAA Weight Report Form, Microsoft XL Format, “Weight

Report.xls”

2.2.8. Drydock Worksheet

2.3. Government Furnished Equipment: None additional

2.4. Requirements:

2.4.1. Reference 2.2.1 forms a part of these Performance

Specifications. All provisions and requirements contained therein are applicable to all work items, including all additional work items which are authorized by the Contracting Officer.

2.4.2. References 2.2.2 and 2.2.3 are amplifications of the

requirements contained in reference 2.2.1 sections 4.17 and 4.21.

2.4.3. Some of the ship’s drawings have not been updated to reflect modifications to the ship during activation and conversion in 2002. Contractor shall be responsible for verifying all current configuration, construction, and arrangement changes, as necessary, to comply with and perform the work requirements of these specifications. Contractors are encouraged to review the ship's drawings and to perform a field inspection of the ship and her equipment prior to submitting a bid proposal.

2.4.4. Ship’s drawings and technical publications may be borrowed during the performance period . It would be preferable for the contractor to make copies of these drawing and technical publications if their intended use will be outside an office environment. All reference materials borrowed by the Contractor shall be signed for, and then returned to the COR after no further use of the reference materials is required.

2.4.5. Provide and maintain a status report of all American Bureau of Shipping (ABS) inspections and technical reviews required by ABS, during the course of this contract, to ensure the ship’s ABS certification requirements are in compliance.

Submit weekly ABS status reports to the COR, along with the preliminary progress reports.

2.4.6. Provide a copy of ABS-approved welding procedures and

maintain a list of currently qualified welders.

2.4.7. Develop, in consultation with the American Bureau of

Shipping (ABS) Surveyor, a written survey schedule that lists the items to be inspected and the scheduled dates and times of the inspections. Submit the survey schedule to the COR within 48 hours after the start of the contract performance period. Provide the survey schedule with all initial inspections required by the ABS Surveyor. In addition, schedule the services of an ABS Surveyor as required by ABS for performing inspections of all new installations, hull modifications, tank inspections, gauging inspections, and load tests. NOAA will pay for all ABS surveys under a separate purchase agreement with ABS.

2.4.8. All visual examination, hydrostatic testing, and

non-destructive testing shall be in accordance with ABS Rules for Building and Classing Steel Vessels, Survey After Construction 2005, Part 7. All contractors performing NDT and hull gauging shall be certified under the ABS external specialists program.

2.4.9. On the first day of the contract performance period, provide the COR a detailed production schedule. Then, o n a weekly basis (on the day preceding the Weekly Progress Meeting) provide the COR a revised and updated production schedule reflecting actual work progress. These deliverables shall be in Microsoft Project electronic format and 3 paper copies.

2.4.10. All new equipment and furnishings purchased by the

Contractor for installation on the vessel shall be provided with factory supplied technical manuals, or data sheets, complete with parts listings. Electronic/emailed copies of this information are required. This documentation shall be turned over to the COR after installation is completed.

Equipment technical manuals shall provide detailed information necessary to operate, maintain, troubleshoot, and repair the equipment. The manuals shall include detailed procedures for disassembly of equipment, parts lists, drawings, inspection criteria, troubleshooting, and test procedures. Provide four paper copies of each manual, plus one electronic copy in Adobe Acrobat .pdf format.

2.4.11. Submit all inspection, test, and quality reports to the COR in Microsoft Word electronic software format, in addition to providing hard paper copies.

2.4.12. Weigh all materials and items removed, installed, or

relocated on the ship. Provide a summary report to the COR indicating the total weight in pounds of items and a breakdown of their locations by space, deck, frame, distance from centerline, and height above the deck. Reference 2.2.7 has been provided for the Contractor to identify, record, and document all weight changes for submitting the summary reports. The contractor may use their own weight report form for documenting weight changes. All the information required must be tracked and documented on any form provided.

2.4.13. Unless otherwise stated in the individual work items, prepare and coat all new steel, all existing steel surfaces identified to be cleaned and painted, and all paint systems disturbed while accomplishing work items, in accordance with Reference 2.1.4. Finish coat colors and paint type shall match those of the surrounding, unmodified area.

2.4.14. Ship’s force will maintain a minimal presence during

accomplishment of work to these specifications. Their availability to operate ship’s equipment will be limited.

Crew availability is generally limited to the hours of 0800 and 1500 local time, Monday through Friday. Unless otherwise specified, provide a minimum of two working days’ prior notice for any equipment operations.

2.4.15. All new and disturbed machinery and services shall be operated for a period sufficient to indicate satisfactory performance, but not less than one hour, after all adjustments and deficiency corrective actions have been made, without further adjustment.

2.4.16. Provide manufacturer’s technical representatives where required in the individual work items, to witness and to provide technical guidance during operational testing of equipment and systems. All tests and trials of equipment or systems shall be witnessed by the COR, ABS, and/or USCG as applicable, to ensure compliance with regulatory body requirements to maintain the ship’s ABS class certification, and to complete all requirements of these specifications.

2.4.17. Habitability

2.4.17.1. The ship shall be deemed uninhabitable when any one or a combination of the following conditions exist and it is impossible for management to correct the problem in a timely manner (4 hours or as noted below):

a. Heat and/or air conditioning is not furnished.

b. Potable water (hot or cold) is not provided for a period of 12 or more consecutive hours.

c. When a working toilet, shower and sanitary drainage are not furnished.

d. At all times when the vessel is in drydock overnight, unless the ship is fully habitable with all facilities including heat and/or air conditioning, lights, hot and cold running water, shower and sanitary facilities (working toilets and sanitary drainage). Portable toilets do not meet the requirements for sanitary facilities.

e. Work such as chipping, welding, riveting, hammering and/or pounding, or other noises of a similar nature are being performed in or around vessel personnel quarters or noxious fumes are present that disrupts the employees ability to rest for more than three

(3) hours. Note: Wage mariners not assigned to a watch, are assigned to work during eight (8) hours of duty between 0700 and 1530, Monday through Friday.

f. Flooding of quarters or common areas due to bilge or sewage backup not repaired within 24 hours.

2.4.17.2. When a vessel is in port and declared uninhabitable, no employee will be allowed to live on board. Individual quarters may be deemed uninhabitable when the respective quarters have been painted, the paint is not absolutely dry, and other suitable quarters are not furnished aboard. It is also not intended that any wage mariner shall be assigned to sleep in a flooded berthing area.

2.4.18. On repairs or overhauls of existing equipment, follow Original Equipment Manufacturer’s (OEM’s) recommendations for parts and service in such a manner that the manufacturer’s warranty on parts and labor is not voided .

Unless specified elsewhere in the detail specification, all replacement parts shall be new parts from the OEM.

2.4.19. These Detailed Specifications are a combination of

“performance specifications” and “design specifications.”

Whenever possible, the Government has provided performance specifications, giving the Contractor the opportunity to accomplish the work requirements as best as he or she sees fit, while providing a fully functional repair and/or equipment/system installation in accordance with all work requirements. When specific details are required, the Government will provide design/detail specifications; this will be more the exception, than the rule.

2.4.20. Frame numbers and space names are derived from ship’s drawings. All equipment changes and space modifications over the ship’s life span may not all be reflected in the referenced drawings. Contractors are encouraged to review all referenced drawings and to perform a field inspection of the ship prior to submitting a bid. Copies of drawings and technical manuals not included herein may be made available for review during any scheduled pre-bid inspection and during the performance period. Contractors may review available drawings and technical manuals on board ship.

2.4.21. All equipment changes and space modifications over the ship’s life span may not all be reflected in the referenced drawings. Contractors are encouraged to review all referenced drawings and to perform a field inspection of the ship prior to submitting a bid.

2.4.22. The Order of Precedence when interpreting these Government specification and requirements is as follows:

Detailed Specifications, Standard Specifications, General Requirements, Drawings, General Provisions, referenced industry standards, and others.

2.4.23. Whether specified in the individual specification item or not, all surface preparation and painting shall be accomplished by a SSPC QP1 certified painting contractor.

2.4.24. Zinc chromate paint is known to exist on the ship on

interior steel surfaces from original construction.

Contractor is advised to anticipate encountering zinc chromate paint in the course of this repair work and to take necessary precautions to minimize hazards associated with the same (i.e., use solvent to remove zinc chromate from suspected areas before cutting, grinding, etc.).

2.4.25. Project Management

2.4.25.1. An on-site Project Manager, solely dedicated to completion of this contract, shall be provided by the contractor.

2.4.25.2. Project Manager will provide administrative support as needed for execution of the contract.

2.4.25.3. Project Manager will provide weekly status reports and tracking reports by time and date established by the COR, that reflect current statuses. Hardcopies and electronic copies to be provided.

2.4.25.4. Project Manager will support weekly status meets and well as daily deckplate meetings to discuss plans of the day.

2.4.25.5. Project Manager will provide written Plan of the Day (POD) that clearly depicts expected efforts, start/stop times, Subs/vendor plans and status, material statuses, forecasted hot work for the following two days, impacted areas of the vessel due to work, specific areas where cleaning or other work will continue, etc., and other information deemed necessary by the COR. PAST dates for incomplete items will be updated using strikethrough and red test, leaving the old dates in place. Hardcopies to be provided as well as an electronic version sent out the evening prior.

2.5. Quality Assurance: None additional

2.6. Notes:

2.6.1. The following descriptive data of the ship is provided for information:

Length, Overall......................................224’ 0” Length, BP...........................................194’ 0” Beam, Molded..........................................43’ 0” Mean Draft, Loadline..................................15’ 1” Displacement, Loadline.............................2311.5 LT Displacement, Lightship............................1591.2 LT Cruising Speed......................................11 knots Officer & Crew Size Scientists and Technicians Electric Service.......450 VAC, 60 Hz, 3 PH, 800 Amp Service Propulsion.......................Diesel electric, twin screw

2.6.2. NOAA Ship Oscar Elton Sette is classed A1, E, AMS, and ACCU and identified with the following:

Official Number - CG014936

ABS ID - 8801905

IMO NUMBER – 8835097

3. BASE ITEMS

3.1. Drydocking and Routine Drydock Work

3.1.1. Intent:

3.1.1.1. Requirements for drydocking and drydock work

3.1.2. References:

3.1.2.1. NOAA Standard Specification AMC-997-1A, “Drydocking and Routine Drydock Work”

3.1.2.2. Drawing No. SE-085-002, “Docking Drawing”

3.1.2.3. Drawing No. 562-6233911, “Rudder Stock Carrier Bearing Arrgt and Details”

3.1.2.4. NOAA Standard Specification S1205, “Zinc Protectors”

3.1.2.5. Drawing No. 633-6233582, “Zincs Arr & Details”

3.1.2.6. NOAA Standard Specification MOC-100-1A, “ABS Load Line Survey”

3.1.2.7. Form S0700, “NOAA Docking Report”

3.1.2.8. Drydock Worksheet

3.1.3. Government Furnished Equipment: None additional

3.1.4. Requirements:

3.1.4.1. To allow the Government to evaluate the certification of the drydock and other services, complete the Drydock Worksheet (Reference 3.1.2.8) and submit along with the bid/proposal. Submit a separate completed drydock worksheet for each drydock Contractor may use.

3.1.4.2. If the diesel oil is to be removed from the ship and later to be returned to the ship, pump and meter the fuel to clean shore-side storage tanks. Upon return to the ship, pump and meter the fuel through a 10 micron filter system with a hygroscopic (moisture absorbing) component when it is returned to the ship. Fuel oil removed and returned shall be sampled and tested by a chemist prior to being removed and prior to being returned to ensure the fuel is in good condition. Provide sample results to the COR.

3.1.4.3. Assist the Chief Engineer in transferring remaining fuel within the ship as necessary to satisfy repair requirements. Coordinate this activity with the Dock Master and the ship’s Chief Engineer so as not to interfere with other work or cause an issue with safety or stability while on the drydock.

3.1.4.4. Drydock the vessel within the first 7 days of the

contract performance period, unless otherwise approved by the COR. Provide drydocking and routine drydock work in accordance with Reference 3.1.2.1. When washing the propellers with high pressure water per paragraph 3.4.1 of Reference 3.2.1.1, the water pressure shall not exceed 10,000 psi.

3.1.4.5. The following information and additional requirements apply:

3.1.4.5.1. Connect electrical power and cooling water in the

drydock in accordance with Item 3.2 prior to the ship being lifted out of the water.

3.1.4.5.2. Block the ship with a minimum of four feet clearance under the keel (forward and aft of the Transducer Fairing Unit) in Docking Position No. 1.

3.1.4.5.3. When the vessel is set on the keel blocks, prior to lifting it out of the water, have divers ascertain that the bilge blocks are contacting the hull properly and not landing on any underwater appendages, and transducers. The divers shall inform the Dockmaster and COR and then lifting shall continue.

3.1.4.5.4. Provide rudder clearance readings to the COR within the first seven days of ship drydocking during the contract performance period.

3.1.4.5.5. In the presence of the ABS surveyor, open drain plugs on rudders. Drain liquid, if any, from rudder interiors. Conduct a 2 psi air test on rudders. Apply an environmentally friendly float coat to rudder interiors by the fill and drain method. See Note 3.1.6.3.

3.1.4.5.6. Clean the P/S propeller and bow thruster blades to bright metal by power brushing. Hard tools and wire brushes shall not be used. See Note 3.1.6.1.

3.1.4.5.7. Perform NDT inspection of the propeller blades using the Dye Penetrant method.

3.1.4.5.8. Perform the following inspection on the port and

starboard rudders:

3.1.4.5.8.1. Jack the rudders forward and aft. Using a dial

indicator, measure the amount of travel at the lower end of the lower rudder bearing.

3.1.4.5.8.2. Jack the rudders port and starboard. Using a dial indicator, measure the amount of travel at the lower end of the lower rudder bearing.

3.1.4.5.8.3. With the rudder centered forward and aft and port and starboard, jack the rudder up and down. With a dial indicator, measure the amount of travel.

3.1.4.5.8.4. Submit a report to the COR indicating the amounts of travel in the rudder bearings for both port and starboard rudders.

3.1.4.6. Provide the ABS Surveyor with prior notice and the

opportunity to inspect any or all portions of ongoing work ordered by this item.

3.1.4.7. Renew hull, sea chest, bow thruster tunnel, and shaft strut zinc anodes as designated by the COR in accordance with References 3.1.2.4 and 3.1.2.5. See Note 3.1.6.2.

3.1.4.7.1. Remove and scrap 84 existing zinc anodes. Clean, prime and paint the areas behind the zincs per Underwater Body Coating item prior to installing the new zinc anodes.

3.1.4.7.2. Install 84 new zinc anodes type ZHC-23 conforming to MIL-A-18001K, same size and type, and in the same location as those removed. Provide and install up to 10 new studs and fasteners for those damaged or missing.

The new finished zinc plates shall weigh twenty three

(23) pounds each. Provide certification to the COR that the new zinc anodes are in conformance with

MIL-A-18001K.

3.1.4.7.3. Zinc attachment points and damaged hull paint shall be cleaned and painted after installation in accordance with Underwater Body Coating item. No paint or other permanent coatings are to be applied to the exposed zinc surfaces, which shall be clean bare metal. The underwater body side of the zinc shall not contact the hull.

3.1.4.7.4. After completion of all zinc anode renewals, visually inspect each new zinc anode to determine proper attachment, and to ensure that the anodes were not painted during painting of the hull.

3.1.4.8. Prepare and accomplish ultrasonic testing (UT) on the ship’s three sea chests in accordance with Reference 3.1.1.6, section 3.3, “Ultrasonic Tests (UT) for Thickness Gaging.” Take a minimum of 30 UT readings per sea chest. Thickness gauges shall not be taken before the hull has been water washed, and shall be completed before painting of the underwater body. Note: Original plate thickness in sea chests is 7/16” (17.85# plate).

3.1.4.8.1. Submit a Condition Report to the COR with

recommendations for additional work, if any. Any additional work will be subject to the approval of the Contracting Officer.

3.1.4.8.2. Submit an Inspection and Service Report from the

manufacturer’s field engineer to the COR.

3.1.5. Quality Assurance:

3.1.5.1. After the blocks have been set and before lowering the drydock for hauling the ship, conduct a final inspection of the blocking with the COR and the dockmaster. Recheck measurements as necessary to satisfy the COR that the block locations are in accordance with the contract requirements. Acceptance of the blocking arrangement by the COR in no way relieves the Contractor of the responsibility for safely dry docking the ship without strain or damage.

3.1.5.2. Record all measurements and observations required on NOAA Docking Report, Reference 3.1.2.7.

3.1.6. Notes:

3.1.6.1. The ship’s propellers are an anti-singing design. The leading and trailing edges of these propellers are finely finished, and care must be taken not to damage these areas. Exercise caution when polishing the propeller surfaces to minimize removal of metal.

3.1.6.2. Reference 3.1.2.5 shows type ZHS-23 (weld-on strap type) zincs. These were subsequently replaced by type ZHC-23 (bolt-on) zincs as specified in paragraph 3.1.4.7.

3.1.6.3. The following products are acceptable environmentally friendly float coats for rudder interiors:

Eureka Fluid Film NAS Kellsport Products 22 Boomer St.

Fall River, MA 02720 Tel: (888) 341-4600

Cortec® M-645 Float Coat Cortec Corporation White Bear Mountain, MN Tel: (800) 426)-7832 Fax: (651) 429-1122

END OF ITEM

3.2. Temporary Services

3.2.1. Intent:

3.2.1.1. Provide required temporary services.

3.2.2. References:

3.2.2.1. NOAA Standard Specification AMC-000-2C, "Temporary

Services at Contractor Facilities"

3.2.3. Government-Furnished Material: None additional

3.2.4. Requirements:

3.2.4.1. Provide all temporary services required in accordance with Reference 3.2.2.1.

3.2.4.2. The following additional information and requirements apply:

3.2.4.2.1. Electric power: Provide two 450 VAC, 3 Phase, 60 Hertz, 400 Amp circuits [800 amps total] with NATO plugs and pigtails. The Contractor shall provide properly rated shore power cables. All power supplied to the ship shall be clean, with no indications of ground faults on the ship’s main switchboard. Total Harmonic Distortion (THD) shall not be greater than 6%. Voltage at the ship’s switchboard shall not vary by more than 3% the prescribed 450 VAC requirement. All ground fault deficiencies associated with the Contractor’s power supplied to the ship, shall be corrected at the Contractor’s expense. Such expense shall include housing allowance for the ship's crew, if the ship is still habitable at the time the deficiency is noted.

3.2.4.2.2. High-Speed Internet Service/cable tv: Provide

high-speed, broadband internet connectivity via a local Internet Service Provider (ISP), or privately owned, internal internet connection. High-speed, broadband internet is defined as Digital Subscriber Service (DSL), Cable Network, or Fiber Optic Network services with minimum download speeds of 320 Mbps. The service provided shall be a business-type account that supports Virtual Private Network (VPN) connections, if available. Provide the proper number of connections necessary to satisfy the ship’s wet berth and drydock locations, as well as the ship and COR’s dockside office space(s). All necessary cabling, DSL or cable modem(s), or fiber translators shall be provided for an RJ-45 network connection to the ship and office(s) routers. Provide a minimum of one Internet Protocol (IP) address with Directory Name Server (DNS) service for each of the ship and dockside office(s) locations.

The ship’s electronic technician (ET) will provide the necessary routers and switches needed.

3.2.4.2.3. Dedicated Security Service. In addition to Reference

3.2.2.1 requirements, increase security round frequency from two-hour intervals to one-hour intervals. The dedicated Security must be provided from 1530 to 0730 during the weekdays and 24 hours a day during weekends and holidays observed by the ship and COR. This shall start on the first day of the period of performance and last until the ship departs. In addition, no watch stander shall stand watch for more than a 12 hour watch without relief.

3.2.4.2.4. Air: Provide 125 psi dry, filtered, compressed air to a manifold on deck. No connection shall be made by the contractors or their subcontractors to the ship’s compressed air distribution system.

3.2.4.2.5. Cooling Water: Provide 300 gpm @ 80 psig capacity, with a separately priced option for an additional 300 gpm @ 80 psig if needed, for ship’s auxiliary sea water system which supports all refrigeration plant cooling water, air conditioning plant cooling water, and sanitary system toilet flushing needs (NOTE, the ship’s sea water system provides 600 gpm for full load). In the event the sea water or cooling water provided to these systems is disrupted or disabled, an alternate means of providing water service to these systems shall be the Contractor’s responsibility. Provide a pressure regulator on the discharge side of the Contractor’s cooling water supply to the ship’s systems capable of regulating pressure between 25 psig and 80 psig.

Contractor may provide separate cooling water service connections to meet the ship’s cooling water systems needs at designated hook-up locations. See ship’s Chief Engineer for individual cooling water service hook-up locations and pressure requirements for the separate systems. Make-up temporary by-pass hose and/or piping arrangements to support the ship’s AC and refrigeration plant cooling water needs, in conjunction with the work requirements of other items in these specifications.

3.2.4.2.6. Protective Covering: In addition to the protective coverings specified in paragraph 4.5.1 of Reference 3.2.2.1, place a layer of heavy duty (minimum thickness of 4 mils) plastic sheeting between the deck and the protective covering. No interior space shall be open to the environment without a protective covering.

3.2.4.2.7. Parking Spaces: Provide ten reserved vehicle parking spaces within 100 feet of the dockside office spaces.

Identify additional parking spaces for up to 15 vehicles, within or outside the shipyard, which may be available for parking by ship’s personnel and other NOAA representatives.

3.2.4.2.8. Office Spaces: Provide two secure locked office spaces (one office space for the COR and one for ship’s office space). Increase office size to 12-feet x 20-feet.

Provide three sets of keys to each space to the COR.

COR’s office shall be made available three days prior to the ship’s arrival at the Contractor’s facility and shall remain so until three days after the ship has departed. If the ship’s office space is more than 100 feet from the location of the ship for any reason the contractor shall provide two (2) dedicated 4-person vehicles for use by the COR and ship’s crew. There shall be parking at or near the vessel.

3.2.4.2.9. Restrooms are to also be available within 100 yards of the ship at all times. Portable toilets with hand wash stations are also acceptable.

3.2.4.2.10. Ship’s dockside office shall contain three desks along with six chairs. Provide high speed internet service as required above.

3.2.4.2.11. COR's dockside office space shall contain two desks and two chairs. Provide high speed internet service as required in above. Provide one copy machine capable of multiple copying, sorting, and paper size conversion (enlarging/reducing) of documents, in paper size ranges from letter (8.5 x 11 inches), legal (8.5 x 14 inches), and “D“ size drawings (11 x 17 inches).

3.2.4.2.12. Storage Container: Provide (two) closed, lockable storage container, or space, for ship’s personnel use, with minimum nominal dimensions of eight feet high by eight feet wide by forty feet deep. Provide COR three sets of keys to the lock for this storage container.

3.2.4.2.13. Oily Waste Disposal: Pump the bilge oily water holding tanks 4-60-3 and 4-60-4 (estimate 1500 gallons on board, up to 3000 gallons maximum), and the sludge tank 3-50-2-F (estimate 50 gallons on board, up to 100 gallons maximum). Pumping of the bilge oily water holding tanks and the sludge tank shall be done at the beginning of the contract performance period.

Additional pumping will be required whenever liquid is added to these tanks or spaces as a result of contractor washing down in order to maintain gas-free certification, or other incidental liquid drainage into these spaces as a result of the performance of work.

The goal of this paragraph is for the ship to leave the contractor’s facility with empty waste tanks.

3.2.4.2.14. Bilge Cleaning: Pump Generator Room and Propulsion Motor room bilges at the beginning of the contract period and at the end of the period. Pressure wash, pump, and clean all debris from the bilge at the end of the contract period. Protect all electrical controllers and machinery from overspray and debris prior to pressure washing. Clean out all bilge rose boxes after pressure washing.

3.2.4.2.15. Crane Service: Provide crane operator and riggers for ship's force equipment and material lifts needed during normal working hours. Provide crane lifts with a 5-ton minimum capacity. The COR will provide a minimum of four hours’ notice prior to any lifting required for the ship's force needs. In addition, provide adequate pier space and vehicle access for staging mission equipment and loading provisions during the last two weeks of the contract period.

3.2.4.2.16. Toilet Facilities & Sewage Disposal: Provide temporary toilet facilities and perform sewage system effluent and turbid water disposal at any time the ship’s sanitary system and marine sanitation plant and gray water system operation is disrupted, due to work performance on any other item of these specifications where disruption of these systems will be required .

Ships' sanitary systems are to be for the ship's crew only. All shipyard personnel and shipyard subcontractors will have their own bathroom and sanitary facilities separate from the ship. Post signs prominently to make all personnel aware of this rule.

3.2.4.2.17. Grey and Black Water Discharge: Provide a connection for the ship’s grey water overboard discharges, located on the port side near frame 30, just forward of the Plimsoll mark. Collect and properly dispose of all grey water overboard discharges which shall meet the same requirements for sewage and turbid water disposal, in accordance with paragraph 3.10 of Reference 2.1.1. (400 Feet Black Water and 400 Feet Grey Water)

3.2.4.2.18. Service Interruption: Contractor shall make every effort to maintain all facilities and services required by this specification in a safe manner, so as not to render the ship uninhabitable.

3.2.5. Quality Assurance:

3.2.5.1. In accordance with Reference 3.2.2.1.

3.2.6. Notes: None additional

3.3. Dock and Sea Trials

3.3.1. Intent:

3.3.1.1. Requirements to conduct Dock and Sea Trials

3.3.2. References: - None additional

3.3.3. Government Furnished Equipment: - None additional

3.3.4. Requirements:

3.3.4.1. Conduct Dock Trials

3.3.4.1.1. Approximately one week before the ship is scheduled to leave the Contractor’s facility, conduct one working day of dock trials. The date for the dock trials must be approved by the COR.

3.3.4.1.2. Submit a schedule to the COR at least 48 hours before dock trials for testing all equipment and systems on which the Contractor has performed work.

3.3.4.1.3. All equipment will be operated by ship’s force

personnel.

3.3.4.1.4. During the dock trials, all utilities, except telephone service, will be transferred to the ship.

3.3.4.1.5. Schedule testing during normal working hours.

3.3.4.1.6. No Contractor work shall be performed during dock

trials without the prior approval of the COR.

3.3.4.1.7. Provide a supervisor with access to Contractor

personnel in all trades to oversee the repair/adjustment of equipment repaired by the Contractor.

3.3.4.1.8. Provide a dock trial report including all deficiencies and their resolutions in a CFR.

3.3.4.2. Conduct Sea Trials

3.3.4.2.1. Following satisfactory completion of dock trials, schedule and participate in a one-day sea trial to witness testing of all repaired or newly installed equipment and machinery. The sea trial shall be underway at sea condition for a duration of at least eight hours, departing from and returning to the contractor’s facility. Transits in a river and/or channel, to and from the contractor’s facility shall not constitute an underway at sea condition. The COR may elect to shorten the duration of the sea trial in consultation with the ship’s command, depending on the performance of all ship’s equipment and systems to be operated and tested. The contractor shall coordinate the sea trial date with manufacturers’ technical representatives as required, and provide at least 72 hours’ notice.

3.3.4.2.2. The date for the sea trial must be approved by the COR.

The sea trial agenda shall be set for no less than eight hours and no more than 24 hours. Prior to departure, submit a list of Contractor/Subcontractor’s personnel who will ride the ship for sea trials and include Name, Citizenship, Address and telephone number of person to be notified in case of an emergency.

3.3.4.2.3. Correct all dock trial discrepancies prior to the sea trial.

3.3.4.2.4. All equipment will be operated by the ship's force.

3.3.4.2.5. No Contractor work will be allowed during the sea trial without the prior approval of the COR.

3.3.4.2.6. Provide a sea trial report including all deficiencies and their resolutions.

3.3.4.2.7. Correct all sea trial discrepancies before the ship leaves the Contractor’s facility.

3.3.5. Quality Assurance:

3.3.5.1. Tests, inspections, and reports shall be in accordance with the approved schedule.

3.3.6. Notes:

3.3.6.1. Provide the American Bureau of Shipping surveyor with prior notice and the opportunity to inspect any or all portions of ongoing work during the dock trials or the sea trials. Provide ABS the option to ride the ship for sea trials.

3.4. Switchboard Cleaning

3.4.1. Intent:

3.4.1.1. Perform switchboard and transformer cleaning

3.4.2. References:

3.4.2.1. US Standard Bus Connection Bolt Torque Values

3.4.2.2. NOAA Standard Specification 300-2B Circuit Breaker

Overhaul

3.4.2.3. Drawing 320-6233663 – Electrical One-Line Diagram as built

3.4.2.4. Drawing OE-320-001 – Electrical One-Line Diagram

3.4.3. Government Furnished Material: None additional

3.4.4. Requirements:

3.4.4.1. Clean and inspect the 600 volt switchboard, the 450 volt ships service switchboard, the Emergency 450 VAC switchboard, and the 600/450 volt step-down transformers as follows. Torque bus bar connections to values in Reference 3.4.2.1.

3.4.4.2. Switchboards are located in Main Control Space 2-52-0-E and Emergency Diesel Generator (EDG) Space 01-6-0-E.

Switchboards include Main Propulsion Controls and Power, Ships Service Generator Controls and Power, Ships Service Power Distribution, EDG Control and Power Distribution, 24-Volt Power Distribution, and Machinery Control Console [MCC] with associated Uninterruptible Power Supply (UPS).

3.4.4.3. Transformers are located in Generator Room 3-34-0-E.

Transformers are rated at 600 volt and 450 volt.

3.4.4.4. Remove all dust and debris from inside switchboards, on all switchboard wiring, circuit breakers, and other switchboard components; clean all transformers in a similar manner. Contractor shall use hand tools that will not scratch/ gouge finish, brushes, lint-free rags and vacuum cleaners. Use dry filtered compressed air only when necessary, being careful to minimize blowing dust.

The use of cleaning solvents, the type of cleaning solvents and what components are being cleaned with solvents of any type is to be coordinated with the COR prior to use of such materials. No solvents or chemicals containing chlorides will be permitted.

3.4.4.5. Rack out, remove arc chutes, inspect contacts, clean, lubricate and adjust the following circuit breakers IAW Reference 3.4.2.2:

3.4.4.5.1. Four (4) SSDG Breakers (in place)

3.4.4.5.2. One (1) EDG breaker (in place)

3.4.4.5.3. Two (2) Propulsion Motor Breakers

3.4.4.5.4. One (1) Bow Thruster Breaker

3.4.4.5.5. Three (3) ship’s service transformer feeder breakers

3.4.4.6. All other 600 VAC and 45 VAC power breakers shall be cleaned and inspected

3.4.4.7. Open, clean, inspect, and provide primary and secondary megger readings on all three of the 600V/450V transformers located in the aft starboard corner of the Main Generator Room

3.4.4.8. Test each SSDG circuit breaker in place for proper

mechanical and electrical operation.

3.4.5. Quality Assurance:

3.4.5.1. CME and COR witness satisfactory testing of breakers.

3.4.6. Notes:

3.4.6.1. A recommended contractor is:

N. Waller & Associates Nat “Buddy” Waller N_Waller@Prodigy.net 1-251-421-7040 Mobile, Alabama

END OF ITEM

mailto:N_Waller@Prodigy.net

3.5. Sea Valve Overhauls

3.5.1. Intent: Overhaul or renewal of all sea valves

3.5.2. References:

3.5.2.1. NOAA Standard Specification AMC-505-1B, "Valve Overhaul and Test"

3.5.2.2. NOAA Standard Specification MOC-631-2D, "Coating Systems for Steel Surfaces"

3.5.2.3. Drawing No. 342-6233836, “Main Engine Sea Water Cooling Sys Arrgt.”

3.5.2.4. Drawing No. 524-6233839, “Auxiliary Sea Water Cooling Sys Arrgt.”

3.5.2.5. Drawing No. 524-6233814, “Auxiliary Sea Water System Diagram”

3.5.3. Government Furnished Equipment: None additional

3.5.4. Requirements:

3.5.4.1. Remove, overhaul, test, and reinstall the valves listed in the table below in accordance with Reference 3.5.2.1, except as otherwise required below.

3.5.4.2. All valves 2 inches and under shall be renewed in kind rather than overhauled. New valves shall have bronze bodies with monel trim. New valves must undergo and pass hydrostatic testing, same as overhauled valves .

3.5.4.3. All valves not being overhauled are to be returned to the ship's engineers for determination of possible reuse elsewhere on the ship.

No. Description Frame/ Location Size/Type Waster

Piece

Valve Location when in a Confined Space

TSG High Suction

4-B-0-W Frame 4C 2” Gate

Inside Forepeak Ballast Tank

BT Cooling

OVBD

BT Room 2-9-2 Frame 9P 1-1/4" Gate

BT Cooling

OVBD

Fuel Oil Tank 4-6-2-F

1-1/4" Swing Check

Inside FO Tank 4-6-2

BT Cooling Suction

Bow Thruster Space Frame 9P 1-1/4" Gate

BT Cooling Suction

FO Tank/Fry Stores

1-1/4" Swing Check

Inside FO Tank 4-6-1

BT BlowDown

Bow Thruster Space 1-1/4" Globe

Refrig Drain OVBD Frame 22S 2" Flapper

2" x 12"

Inside FO Tank 4-14-1

Refrig Drain OVBD Frame 22S

2" Swing Check

Inside FO Tank 4-14-1

Doppler Speed Log

Void Below Laundry Deck Frame 23S 10" Gate

In Xducer trunk 4-23-1-T

1 Xducer Sea Chest Vent

Void Below Laundry Deck Frame 23S 1” Globe

In Xducer trunk 4-23-1-T

1 Speed Log Blow Down

Void Below Laundry Deck Frame 23S 1” Globe

In Xducer trunk 4-23-1-T

1 TSG Low Suction Frame 24C 2” Gate

In 4-23-0-W Ballast Tank

1 Sewage Disch OVBD Frame 29S

4" Swing Check

Sewage Machy Rm 2-28-3-Q

Sewage Diverter Valve Frame 29S 4" 3-Way Ball

Sewage Machy Rm 2-28-3-Q

1 Sewage & Gray Water OVBD Frame 29S

4" Swing Check

Sewage Machy Rm 2-28-3-Q

Gray Water Diverter Valve Frame 29S 4" 3-Way Ball

Sewage Machy Rm 2-28-3-Q

1 Sewage & Gray Water OVBD Frame 29S

6" Swing Check

Sewage Machy Rm 2-28-3-Q

1 Sewage Disch OVBD Frame 29S 2” Gate

Sewage Machy Rm 2-28-3-Q

1 A/C Cooling OVBD Frame 32P 6" Globe

6" x 16"

A/C Machy Space 2-27-2

2 A/C Cooling OVBD Frame 32P

6" Swing Check

A/C Machy Space 2-27-2

Port Sea Chest Isolation Frame 37P

10” Angle Globe

10" x 12"

Main Generator Space 3-34-0

2 Sea Chest Duplex Strainer Frame 37P 10” Butterfly

2 Sea Chest Duplex Strainer Frame 37P 10” Butterfly

2 Sea Chest Duplex Strainer Frame 38P 10” Butterfly

2 Sea Chest Duplex Strainer Frame 38P 10” Butterfly

2 Port Sea Chest Vent Frame 37P 2" Gate

Main Generator Space 3-34-0

Port Sea Chest Blow Down Frame 37P 1" Globe

Main Generator Space 3-34-0

Stbd Sea Chest Isolation Frame 37S

10” Angle Globe

10" x 12"

Main Generator Space 3-34-0

2 Stbd Sea Chest Duplex Strainer Frame 37S 10” Butterfly

2 Stbd Sea Chest Duplex Strainer Frame 37S 10” Butterfly

2 Stbd Sea Chest Duplex Strainer Frame 38S 10” Butterfly

2 Stbd Sea Chest Duplex Strainer Frame 38S 10” Butterfly

2 Stbd Sea Chest Vent Frame 37S 2" Gate

Main Generator Space 3-34-0

Port Sea Chest Blow Down Frame 37S 1" Globe

Main Generator Space 3-34-0

Port SSDG Cooling Water OVBD Frame 42P

8" Swing Check

Inside Void 4-34-01-V

Port SSDG Cooling Water

OVBD

Main Generator Room Frame 42P

8" Motor-Operate d Butterfly

8" x 10"

Stbd SSDG Cooling Water

OVBD

Main Generator Room Frame 42S

6" Swing Check

Inside Void 4-34-0-V

Stbd SSDG Cooling Water

OVBD

Main Generator Room Frame 42S

6" Motor-Operate d Butterfly

6" x 10"

3 Bilge Pump Overboard Frame 45S 3” Gate

3" x 16"

3 Bilge Pump Overboard Frame 45S

3” Swing Check

Inside Void 4-34-0-V

3 Galley Drain OVBD Frame 49S

3" Swing Check

Inside Void 4-34-01-V

3 Galley Drain OVBD Frame 49S 3" 3-Way Ball

3" x 12"

Inside Void 4-34-01-V

OWS Ovbd Frame 51S 2” Gate

OWS Overboard Frame 51S

2” Swing Check

Inside Void 4-34-0-V

3 Main Motor Cooling OVBD

Prop Motor Room Frame 66S 4" Butterfly

4" x 19"

4 Main Motor Cooling OVBD

Prop Motor Room Frame 66S

4" Swing Check

Inside FO tank 4-60-1

4 Aft Lift Station OVBD

Prop Motor Room Frame 71P 4" 3-Way Ball

4 Aft Lift Station OVBD

Prop Motor Room Frame 71P 4" 3-Way Ball

4 Aft Lift Station

Prop Motor Room Frame 67P

4" Swing Check

4 Aft Lift Station OVBD

Prop Motor Room Frame 67P

4" Swing Check

4 Aft Lift Station OVBD

Prop Motor Room Frame 64P

4" Swing Check

4 Aft Sea Chest Suction

Prop Motor Room Frame 68C

4" Angle Globe

4" x 12"

4 Aft Sea Chest Vent

Prop Motor Room Frame 69C 2" Gate

4 Aft Sea Chest Blowdown

Prop Motor Room Frame 69C 3/4" Globe

Main Motor Oil Cooling

OVBD

Prop Motor Room Frame 68 Port

2-1/2" Butterfly

2-1/2" x 20"

Main Motor Oil Cooling OVBD Frame 67P

2" Swing Check

Inside FO tank 4-60-2

5 Dive Locker Drain OVBD Frame 73S 2" Gate

Inside Anti-Roll Tank 2-72-0-W

5 Dive Locker Drain OVBD Frame 74S

2" Swing Check

Inside Anti-Roll Tank 2-72-0-W

TSG Overboard

HPU Room Frame 78P 2” Gate

5 HPU Cooling Water OVBD

HPU Room Frame 82P 2-1/2" Gate

5 HPU Cooling Water OVBD

HPU Room Frame 82P

2-1/2" Swing Check

5 Wet Lab Sink Drain

HPU Room Frame 82P 2-1/2” Gate

3.5.4.4. The following additional requirements apply:

3.5.4.4.1. Match mark all flanges and spool pieces prior to removal from the ship to identify valve location and orientation for re-installation following shop overhaul.

3.5.4.4.2. Fabricate and install new SCH 160 spool/waster pieces.

Paint and replace the insides of sea suction pipe spool pieces in accordance with the Underwater Body Coating

System Base Item.

3.5.4.4.3. Install new overhaul kits in all butterfly valves (boot, o-rings, o-ring fasteners, teflon bushing).

3.5.4.4.4. Renew all cotter pins and swing check clapper pins with a monel.

3.5.4.4.5. After reassembly and prior to shop hydro test, prime coat all ferrous valves with blue wash primer or equal.

3.5.4.4.6. Prior to reinstalling on the ship, prime and paint two finish coats of enamel paint on all valves and spool pieces worked in this item. Retain existing color code.

Bronze and stainless steel valves will not require exterior coating, but do require a color coded stripe applied on the valve body, as required by the ship’s engineering department representative to be determined by what the system is..

3.5.4.4.7. Prior to installing and tightening up on threads, liberally coat all stainless steel bolts and stud threads with an anti-seize extreme pressure lubricant designed to protect metal parts against corrosion, rust, galling, and seizure in salt water environments.

“Never-Seez Mariners Choice” anti-seize is an acceptable lubricant for this purpose.

3.5.4.5. Renew all waster pieces listed in the table above.

Locations and material requirements shall be in accordance with Reference 3.9.2.5. Conduct a magnetic particle test of all new welds. Hydrostatically test all new water pieces to 50 psi. Do not paint the interior of waste pieces.

3.5.5. Quality Assurance:

3.5.5.1. As required by reference 3.5.2.1.

3.5.5.2. In the presence of the COR and Chief Engineer, prove proper operation of reach rod assemblies after the installation of all valves.

3.5.5.3. Watertight integrity of all overhauled and replaced valves shall be checked and inspected in coordination with and witnessed by the COR during the undocking evolution, 48 hours after undocking the vessel and during sea trials.

3.5.5.4. Material certificate for new valves shall be provided to the COR prior to installation.

3.5.5.5. All valves shall be hydrostatically tested to the

satisfaction of the onsite ABS surveyor prior to installation. A CFR outlining the test results shall be provided to the COR.

3.5.5.6. All valves shall be cycled at least three times in the presence of the COR after installation.

3.5.5.7. Notes:

3.5.5.7.1. The contractor will be responsible for opening, cleaning, and the gas free certification for tanks and voids with valves inside as part of the ABS Survey.

3.5.5.7.2. All new valves shall be ordered within the first 7 days of the contract performance period with a copy of the invoice provided to the COR.

3.6. Underwater Hull Maintenance Coat

3.6.1. Intent:

3.6.1.1. Prepare and paint the underwater hull

3.6.2. References:

3.6.2.1. NOAA Standard Specification S0100; Implementation and Conduct of Checkpoints

3.6.2.2. Steel Structures Painting Council, Surface Preparation Specification No. 10, Near White Blast Cleaning (SPCC-10)

3.6.2.3. Steel Structures Painting Council, Surface Preparation Specification No. 6, Commercial Blast Cleaning (SPCC-6)

3.6.2.4. NOAA Standard Specification 631-1 – Underwater Body

Preservation

3.6.3. Government Furnished Equipment : None additional

3.6.4. Requirements:

3.6.4.1. General Requirements

3.6.4.1.1. Protect the propellers, thrusters, shafts and all

scientific equipment mounted on the hull prior to commencing the preservation activities.

3.6.4.1.2. All work on this item…