Attachment Specifications Combined Vol 1 of 2 dated 1-7-26.pdf
PDF 3 MB Posted
- Solicitation number
- 36C26126R0004
About this file
This file is a detailed specification document for the Improve Central Utility Plant project at the Las Vegas VA Medical Center (Project 593-22-350). The project involves replacing several pieces of equipment in the Central Utility Plant that have exceeded their serviceable life, including installing catwalk access for existing serviceable equipment currently inaccessible in the existing plant configuration. Key work components include replacement of heat recovery systems, water softener piping, condensate return tanks, extending catwalks, replacing windows and louvers, automating backup pumps and fuel oil systems, separating condenser pumps, upgrading lighting controls, and replacing various pumps and VFDs.
The specification document provides comprehensive technical requirements spanning multiple sections, including structural steel framing, metal fabrications, stairs, doors, hardware, and fire protection systems. The project will involve modifications to Building 2's boiler room, chiller room, and associated infrastructure, with specific requirements for equipment installation, testing, and commissioning. The work is to be completed between August 26, 2025, and December 31, 2026, with detailed specifications for materials, installation methods, quality control, safety procedures, and performance standards across mechanical, electrical, and structural systems.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment SOW 02-26-2026.pdf | ||
| 36C26126R0004 0003.docx | DOCX document | |
| Attachment Drawings Addendum 1.pdf | ||
| RFI Q-A Response 02-26-2026.pdf | ||
| 36C26126R0004 0002.docx | DOCX document | |
| Attachment WAGE DETERMINATION NV20260038 01-30-2026.pdf | ||
| Sight Visit Sign-in Form 01-22-2026.pdf | ||
| 36C26126R0004 0001.docx | DOCX document | |
| Attachment WAGE DETERMINATION NV20250038 01-02-2026.pdf | ||
| Attachment Price Breakdown.xlsx | XLSX spreadsheet | |
| Attachment Specifications Combined Vol 2 of 2 dated 1-7-26.pdf | ||
| Attachment Drawings.pdf | ||
| Attachment Pre-solicitation Site Visit Presentation.pptx | PPTX presentation | |
| Attachment VAAR 852.219-75 JAN 2023 DEVIATION.pdf | ||
| Attachment APPENDIX.pdf | ||
| 36C26126R0004_2.docx | DOCX document | |
| Attachment REQUEST FOR INFORMATION FORM.docx | DOCX document | |
| Attachment PCRA- Pre-construction Risk Assessment.pdf | ||
| Attachment SOW 10-22-25.pdf |
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Improve Central Util ity Plant
Las Vegas, NV 100% Specification 593-22-350 VOLUME #1
August 26th, 2025
U.S. DEPARTMENT OF
VETERAN AFFAIRS
LAS VEGAS VA MEDICAL CENTER
LAS VEGAS, NV
IMPROVE CENTRAL UTILITY PLANT
August 26, 2025
ARCHITECT
FourFront Design, Inc.
517 7TH Street
Rapid City, SD 57701
(605) 354-9740
Joel Simonyak, AIA
STRUCTURAL ENGINEER
Citrine
710 Kipling Street, Suite 406
Lakewood, CO 80215
(720) 556-0887
Adam Wietzki, PE
MECHANICAL ENGINEER
FourFront Design, Inc.
1211 Echelon Place, Suite B
Helena, MT 59601
(406) 501-6806
Ray Dawes, PE
ELECTRICAL ENGINEER
Citrine
710 Kipling Street, Suite 406
Lakewood, CO 80215
(720) 556-0887
Jeff Abbate, PE
08/26/2025
6/30/2026
DEC-31-2026
AUG-26-2025
08/26/25
FIRE PROTECTION ENGINEER
OLSSON, INC.
601 P Street, Suite 200
Lincoln, NE 68508
(402) 474-6311
Patrick Turner, PE
08/26/2025
05-01-21
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
SECTION NO. DIVISION AND SECTION TITLES DATE
DIVISION 00 - SPECIAL SECTIONS
00 01 15 List of Drawing Sheets 05-20
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 05-21
01 33 23 Shop Drawings, Product Data, and Samples 05-17
01 35 26 Safety Requirements 07-20
01 42 19 Reference Standards 11-20
01 45 00 Quality Control 02-21
01 45 29 Testing Laboratory Services 11-18
01 45 35 Special Inspections 03-19
01 57 19 Temporary Environmental Controls 01-21
01 74 19 Construction Waste Management 01-21
01 91 00 General Commissioning Requirements 04-22
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 08-17
DIVISION 05 – METALS
05 12 00 Structural Steel Framing 11-18
05 50 00 Metal Fabrications 08-18
05 51 00 Metal Stairs 01-21
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 60 00 Flashing and Sheet Metal 01-21
07 84 00 Firestopping 01-21
07 92 00 Joint Sealants 10-17
DIVISION 08 - OPENINGS
08 11 13 Hollow Metal Doors and Frames 01-21
08 71 00 Door Hardware 01-21
08 80 00 Glazing 01-21
08 90 00 Louvers and Vents 01-21
DIVISION 09 – FINISHES
09 91 00 Painting 01-21
DIVISION 21- FIRE SUPPRESSION
00 01 10-2
SECTION NO. DIVISION AND SECTION TITLES DATE
21 13 13 Wet-Pipe Sprinkler Systems 06-15
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 09-20
22 05 12 General Motor Requirements for Plumbing Equipment 09-20
22 05 19 Meters and Gages for Plumbing Piping 09-20
22 05 23 General-Duty Valves for Plumbing Piping 09-20
22 07 11 Plumbing Insulation 09-19
22 08 00 Commissioning of Plumbing Systems 11-16
22 11 00 Facility Water Distribution 05-21
22 11 23 Domestic Water Pumps 09-15
22 31 11 Water Softeners 09-15
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 10 Common Work Results for Boiler Plant and Steam
Generation
04-20
23 05 11 Common Work Results for HVAC 02-20
23 05 12 General Motor Requirements for HVAC and Steam
Generation Equipment
02-20
23 05 93 Testing, Adjusting, and Balancing for HVAC 02-20
23 07 11 HVAC and Boiler Plant Insulation 02-20
23 08 00 Commissioning of HVAC Systems 02-20
23 09 11 Instrumentation and Control for Boiler Plant 02-20
23 09 23 Direct-Digital Control System for HVAC 09-11
23 21 11 Boiler Plant Piping Systems 02-20 23 21 13 Hydronic Piping 02-20 23 21 23 Hydronic Pumps 02-20 23 50 11 Boiler Plant Mechanical Equipment 11-17 23 65 00 Cooling Towers 03-20
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 01-16
26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17
26 05 26 Grounding and Bonding for Electrical Systems 01-17
26 05 33 Raceway and Boxes for Electrical Systems 01-18
26 27 26 Wiring Devices 01-18
26 29 11 Motor Controllers 11-22
26 29 21 Enclosed Switches and Circuit Breakers 01-17
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 05 13 Conductors and Cables for Electronic Safety and
Security
10-18
28 08 00 Commissioning of Electronic Safety and Security Systems 11-16
28 31 00 Fire Detection and Alarm 10-11
00 01 10-3
SECTION NO. DIVISION AND SECTION TITLES DATE
28 05 28.33 Conduits and Backboxes for Electronic Safety and
Security
06-15
05-01-20
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
G-000 COVER SHEET
G-001 LOCATION MAP
G-002 SHEET INDEX, ABBREVIATIONS, SYMBOLS, & LEGENDS
G-100 LIFE SAFETY PLAN
G-101 PHASING PLANS
ARCHITECTURAL
AD100 BUILDING 2 LEVEL 2 DEMOLITION PLAN
A-101 BUILDING 2 OVERALL LEVEL 1 FLOOR PLAN
A-102 BUILDING 2 OVERALL LEVEL 2 FLOOR PLAN
A-111 BUILDING 2 ENLARGED CATWALK PLAN BOILER
A-112 BUILDING 2 ENLARGED CATWALK PLAN CHILLER
A-200 BUILDING 2 EXTERIOR ELEVATIONS
A-300 BUILDING 2 SECTIONS
A-400 SECTIONS, ELEVATIONS & DETAILS
A-401 LOUVER SECTIONS, ELEVATIONS, & DETAILS
A-600 BUILDING 2 DOOR SCHEDULE, ELEVATIONS & DETAILS
STRUCTURAL
S-100 STRUCTURAL GENERAL
S-110 CHILLER ROOM ROOF PLAN
S-115 CHILLER ROOM CATWALK STEEL FRAMING PLAN
S-120 CHILLER ROOM SECTION VIEWS
S-130 BOILER ROOM ROOF PLAN
S-135 BOILER ROOM CATWALK STEEL FRAMING PLAN
S-140 BOILER ROOM SECTION VIEWS
S-150 STRUCTURAL DETAILS
S-151 STRUCTURAL DETAILS
S-152 STRUCTURAL DETAILS
S-153 STRUCTURAL DETAILS
S-154 STRUCTURAL DETAILS
S-155 FIXED INDUSTRIAL STEEL STAIR DETAILS
00 01 15 - 2
S-156 FIXED LADDERS AND CAGES DETAILS
MECHANICAL
M-000 MECHANICAL COVER SHEET
M-001 MECHANICAL SITE PLAN
M-002 MECHANICAL SCHEDULES AND DETAILS
MD102 BUILDING #2 LEVEL 1 MECHANICAL DEMOLITION PLAN
MD103 BUILDING #2 CHILLER ROOM MEZZANINE LEVEL
MECHANICAL DEMOLITION PLAN
M-100 BUIDLING #5 BASEMENT MECHANICAL REMODEL PLAN
M-101 BUILDING #2 BASEMENT AND BUILDING #4 LEVEL 1
MECHANICAL REMODEL PLANS
M-102 BUILDING #2 LEVEL 1 NEW MECHANICAL PLAN
M-103 BUILDING #2 CHILLER ROOM MEZZANINE LEVEL NEW
MECHANICAL PLAN
M-200 BUILDINGS #2, #4, & #5 MECHANICAL CONTROL PLANS
ELECTRICAL
E-000 ABBREVIATIONS, SYMBOLS, AND GENERAL NOTES
ED100 BUILDING 2 FLOOR 1- ELECTRICAL LAYOUT
DEMOLITION
ED101 BUILDING 2 BASEMENT- ELECTRICAL LAYOUT
DEMOLITION
ED102 BUILDING 5 BASEMENT- ELECTRICAL LAYOUT
DEMOLITION
ED400 BUILDING 2 FLOOR 1- ENLARGED GROUNDING LAYOUT
DEMOLITION
ED500 COOLING TOWER/ CHILLER PUMP VFD CONTROL PANEL-
DEMOLITION
ED501 HAYS CLEVELAND ANNUNCIATOR LAYOUT- DEMOLITION
ED502 JOHNSON CONTROLS PANEL (DDC-B4-FUEL OIL PANEL)-
DEMO
ED503 VEEDER ROOT TLS-350 CONTROL PANEL- DEMOLITION
ED504 LIGHTING CONTROL BASIS OF DESIGN- DEMOLITION
ED505 LIGHTING CONTROL BASIS OF DESIGN- DEMOLITION
ED506 LIGHTING CONTROL BASIS OF DESIGN- DEMOLITION
E-100 BUILDING 2 FLOOR 1 – ELECTRICAL LAYOUT
E-101 BUILDING 2 FLOOR 2 – ELECTRICAL LAYOUT
00 01 15 - 3
E-102 BUILDING 2 BASEMENT- ELECTRICAL LAYOUT
E-103 BUILDING 4 FLOOR 1- ELECTRICAL LAYOUT
E-104 BUILDING 5 BASEMENT – ELECTRICAL LAYOUT
E-400 BUILDING 2 FLOOR 1- ENLARGED ELECTRICAL LAYOUT
E-401 BUILDING 2 FLOOR 1- ENLARGED GROUNDING LAYOUT
E-402 CUP FUEL-OIL SYSTEM CONTROL RACEWAY ROUTING
E-500 COOLING TOWER/ CHILLER PUMP VFD CONTROL PANEL
E-501 VENTILATION DAMPER LAYOUT AND WIRING
E-502 WATER SOFTENER SKID LAYOUT AND WIRING
E-503 FUEL SYSTEM ONE-LINE
E-504 TANK LEVEL CONFIGURATION WIRING DIAGRAM
E-505 HAYS CLEVELAND ANNUNCIATOR LAYOUT
E-506 JOHNSON CONTROLS PANEL (DDC-B4-FUEL OIL PANEL)
E-507 VEEDER ROOT TLS-350 CONTROL PANEL
E-508 BOOSTER PUMP SKID WIRING
E-509 LIGHTING CONTROL BASIS OF DESIGN
E-510 LIGHTING CONTROL BASIS OF DESIGN
E-511 LIGHTING CONTROL BASIS OF DESIGN
E-600 ELECTRICAL PANEL SCHEDULES
FIRE PROTECTION
FA101 FIRE ALARM PLAN
FA601 FIRE ALARM INPUT- OUTPUT MATRIX
FP101 FIRE PROTECTION PLAN- PLATFORMS
FP102 FIRE PROTECTION PLAN- LEVEL 2
- - - E N D - - -
11-01-21
01 00 00 -1
SECTION 01 00 00
GENERAL REQUIREMENTS
GENERAL
1.1 SAFETY REQUIREMENTS
A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for “Las Vegas Improve Central Utility Plant, Las
Vegas, NV” as required by drawings and specifications.
B. Visits to the site by Bidders may be made only by appointment with the Contracting officer’s Representative
C. Offices of FourFront Design Inc., 517 7th Street Rapid City, SD 57701 , as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.
D. Before placement and installation of work subject to tests by testing laboratory retained by the Contractor, the
Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three workdays unless otherwise designated by the COR.
01 00 00 -2
E. All employees of general contractor and subcontractors shall comply with the VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
1.3 STATEMENT OF BID ITEM(S)
A. ITEM I, GENERAL CONSTRUCTION: BASE BID: Work includes replacement of several pieces of equipment in the Central
Utility Plant that are beyond their serviceable life, as well as providing catwalk access for existing serviceable equipment that is currently inaccessible in the existing plant configuration. The work also includes corrections to cooling tower heights and incorporation of fuel oil monitoring into the automated controls, and automation of back-up pumps..
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
01 00 00 -3
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer and the
Contracting Officer’s Representative so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer. Patients and staff are not to be photographed at any time.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The
General Contractor may return to the site only with the written approval of the Contracting Officer.
C. Key Control:
1. The General Contractor shall provide door hardware compatible with the Las Vegas VA Central Utility Plant.
See Section 08 71 00, DOOR HARDWARE and coordinate.
D. Document Control:
1. Before starting any work, the General Contractor/Sub
Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
01 00 00 -4
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or
“Sensitive Unclassified”. Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of
“sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an
Engineering Document Management Software (EDMS).
Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.
“Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
E. Motor Vehicle Restrictions
1.A limited number of 5parking permits shall be issued for
General Contractor and its employees for parking in designated areas only. Contractor to coordinate with VA
Medical Center Facility Manager.
01 00 00 -5
1.6 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer’s
Representative. The Contractor shall hold and save the
Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the Contracting Officer’s Representative and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting Officer, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the
Contracting Officer’s Representative, use only established roadways, or use temporary roadways constructed by the
Contractor when and as authorized by the Contracting
Officer’s Representative. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage.
The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
01 00 00 -6
D. Working space and space available for storing materials shall be as determined by the COR .
E. Workers are subject to rules of Medical Center applicable to their conduct.
F. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.
G. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others.
Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by
Department of Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of
Contractor's materials and equipment will be permitted subject to fire and safety requirements.
H. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility
01 00 00 -7 services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR . All such actions shall be coordinated with the COR or Utility Company involved:
1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the
Contractor.
I. Phasing:
1. The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks.
The work to be outlined shall include, but not be limited to:
a. Replacement of the heat recovery system in the boiler room of Building 2.
b. Replacement of the existing water softener copper piping with new stainless steel piping and addition of polisher for a redundant system.
c. Reconfiguration of the non-return valve at the top of
Boiler #3 into a horizontal configuration.
d. Replacement of the existing corroded condensate return/ surge tank with a new stainless steel tank.
01 00 00 -8
e. Extend/connect the existing catwalk above boiler room for access to air handlers.
f. Replacement of windows with operable louvers in boiler room above overhead door in Building 2.
g. Automate back-up pumps located in Building 5 basement.
h. Automate fuel oil system located in Building 3 and locate controls in Building 2 boiler room.
i. Integrate fuel tank system to Hayz Cleveland controls in Building 2 boiler room.
j. Separate 2 of the 5 condenser pumps onto their own dedicated power source bank (MCC.)
k. Replacement of 5 existing condenser pumps with high efficiency double impeller or raise the cooling towers and extend screen wall around cooling tower yard.
l. Install secondary water supply to cooling towers from
10” waterline at east side of CUP.
m. Upgrade facility-wide Lutron lighting controls for single point monitoring in CUP control room.
n. Add ladders/ stairs and extend catwalks in chiller room for improved access to serviceable equipment.
o. Automate back-up pumps located in Building 5 basement.
p. Replacement of existing cooling tower VFD with new like-for-like.
q. Replacement of failing existing chilled water pump
VFDs.
r. Replacement of existing chilled water pumps with new high efficiency domestically sourced pumps with readily available domestic parts to match the new condenser pumps.
s. Replacement of failing existing industrial water pump
VFDs with new.
01 00 00 -9
t. Replacement of failing existing industrial water pumps with new.
2. To ensure such executions, Contractor shall furnish the
COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof.
Arrange such phasing dates to ensure accomplishment of this work in successive phases mutually agreeable to
Medical Center Director, COR, and Contractor.
3. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
a. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.
b. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire
Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from Contractor's employee or watchman.
4. Utilities Services: Maintain existing utility services for Medical Center and Central Utility Plant at all times. Provide temporary facilities, labor, materials, 01 00 00 -10 equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
a. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR . Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to specification Sections
26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS,
27 05 11 REQUIREMENTS FOR COMMUNICATIONS INSTALLATIONS
and 28 05 00, COMMON WORK RESULTS FOR ELECTRONIC
SAFETY AND SECURITY for additional requirements.
b. Contractor shall submit a request to interrupt any such services to COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
c. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time
01 00 00 -11 approved by Medical Center may occur at other than
Contractor's normal working hours.
d. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the
COR.
e. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
f. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
5. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, shall be removed back to their source. Those which are indicated to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from.
The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
6. To minimize interference of construction activities with flow of Medical Center traffic, comply with the following:
a. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of
01 00 00 -12 construction materials, debris and standing construction equipment and vehicles.
b. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.
7. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting Officer. This report shall list by rooms and spaces:
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of buildings.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be
01 00 00 -13 nonexistent, or in opinion of COR , to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by
Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING
SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-
4).
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved.
They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by
Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workers in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in
01 00 00 -14 place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the
Government are noted on drawings or in specifications as items to be stored. Items that remain property of the
Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.
2. Items not reserved shall become property of the
Contractor and be removed by Contractor from Medical
Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government.
When rooms and spaces are vacated by the Department of
Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the
Government in advance of work to avoid interfering with
Contractor's operation.
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,
UTILITIES, AND IMPROVEMENTS (FAR 52.236-9)
A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and
01 00 00 -15 grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting
Officer.
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The
Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL
CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and "Operations and Storage
Areas" for additional instructions concerning repair of damage to structures and site improvements.
1.10 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown
01 00 00 -16 or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged. Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by
Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES" (FAR 52.243-4) and "DIFFERING SITE CONDITIONS" (FAR 52.236-2).
01 00 00 -17
1.11 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.12 WARRANTY MANAGEMENT
A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21
Warranty of Construction and submit four sets of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved. Warranty information made available during the construction phase must be submitted to the Contracting
Officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The
01 00 00 -18 construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4 month and 9 month warranty inspection will be conducted, measured from time of acceptance, by the
Contactor and the Contracting Officer. Include in the warranty management plan, but not limited to, the following:
1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the
Contractor, subcontractors, manufacturers or suppliers involved.
2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.
3. Listing and status of delivery of all Certificates of
Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.
4. A list for each warranted equipment item, feature of construction or system indicating:
a. Name of item.
b. Model and serial numbers.
c. Location where installed.
d. Name and phone numbers of manufacturers and suppliers.
e. Name and phone numbers of manufacturers or suppliers.
f. Names, addresses and phone numbers of sources of spare parts.
g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the
01 00 00 -19 starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.
h. Starting point and duration of warranty period.
i. Summary of maintenance procedures required to continue the warranty in force.
j. Cross-reference to specific pertinent Operation and
Maintenance manuals.
k. Organizations, names and phone numbers of persons to call for warranty service.
l. Typical response time and repair time expected for various warranted equipment.
5. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.
6. Procedure and status of tagging of all equipment covered by extended warranties.
7. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.
B. Performance & Payment Bonds: The Performance & Payment
Bonds must remain effective throughout the construction period.
1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.
01 00 00 -20
2. In the event sufficient funds are not available to cover the construction warranty work performed by the
Government at the contractor’s expenses, the Contracting
Officer will have the right to recoup expenses from the bonding company.
3. Following oral or written notification of required construction warranty repair work, the Contractor shall respond in a timely manner. Written verification will follow oral instructions. Failure to respond will be cause for the Contracting Officer to proceed against the
Contractor.
C. Contractor’s Response to Construction Warranty Service
Requirements:
D. Following oral or written notification by the Contracting
Officer, the Contractor shall respond to construction warranty service requirements in accordance with the
“Construction Warranty Service Priority List” and the three categories of priorities listed below. Submit a report on any warranty item that has been repaired during the warranty period. Include within the report the cause of the problem, date reported, corrective action taken, and when the repair was completed. If the Contractor does not perform the construction warranty within the timeframe specified, the Government will perform the work and back charge the construction warranty payment item established.
1. First Priority Code 1. Perform onsite inspection to evaluate situation, and determine course of action within
4 hours, initiate work within 6 hours and work continuously to completion or relief.
2. Second Priority Code 2. Perform onsite inspection to evaluate situation, and determine course of action within
01 00 00 -21
8 hours, initiate work within 24 hours and work continuously to completion or relief.
3. Third Priority Code 3. All other work to be initiated within 3 work days and work continuously to completion or relief.
4. The “Construction Warranty Service Priority List” is as follows:
a) Code 1-Life Safety Systems
Fire suppression systems.
Fire alarm system(s).
b) Code 1 Doors
Overhead doors not operational, causing a security, fire or safety problem.
1) Interior, exterior personnel doors or hardware, not functioning properly, causing security, fire or safety problem.
c) Code 3-Doors
Overhead doors not operational.
Interior/exterior personnel doors or hardware not functioning properly.
d) Code 1-Electrical
Power failure (entire area or any building operational after 1600 hours).
Security lights.
Smoke detectors.
e) Code 2-Electrical
Power failure (no power to a room or part of building). Receptacle and lights not operational (in a room or part of building).
f) Code 3-Electrical
Exterior lights not operational.
01 00 00 -22
g) Code 1-Gas
Leaks and pipeline breaks.
h) Code 1-Heat
Power failure affecting heat.
i) Code 1-Plumbing
Hot water heater failure.
2) Leaking water supply pipes
j) Code 2-Plumbing
Flush valves not operating properly
Fixture drain, supply line or any water pipe leaking.
k) Code 3- Plumbing
l) Code 3-Interior
Floors damaged.
Paint chipping or peeling.
m) Code 1-Roof Leaks
Damage to property is occurring.
n) Code 2-Water
No water to facility.
o) Code 3
All work not listed above.
E. Warranty Tags: At the time of installation, tag each warranted item with a durable, oil and water-resistant tag approved by the Contracting Officer. Attach each tag with a copper wire and spray with a silicone waterproof coating.
Also submit tworecord copies of the warranty tags showing the layout and design. The date of acceptance and the QC signature must remain blank until the project is accepted for beneficial occupancy. Show the following information on the tag.
01 00 00 -23
Warranty Tags
Type of product/material
Model number
Serial number
Contract number
Warranty period from/to
Inspector’s signature
Construction Contractor
Address
Telephone number
Warranty Contact
Address
Telephone number
Warranty response time priority code
1.13 USE OF ROADWAYS
A. For hauling, use only established public roads and roads on
Medical Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.
B. When certain buildings (or parts of certain buildings) are required to be completed in advance of general date of completion, all roads leading thereto must be completed and available for use at time set for completion of such buildings or parts thereof.
01 00 00 -24
1.14 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:
1. Permission to use each unit or system must be given by
COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the COR will withdraw permission for use of the equipment.
2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted. Installation of temporary electrical equipment or devices shall be in accordance with NFPA 70, National Electrical Code, (2014 Edition), Article 590, Temporary Installations. Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.
3. Units shall be properly lubricated, balanced, and aligned. Vibrations must be eliminated.
4. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze-up damage.
01 00 00 -25
5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be replaced at completion of construction and prior to testing and balancing of system.
6. All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use; maintained to prevent corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the
Government. Boilers, pumps, feedwater heaters and auxiliary equipment must be operated as a complete system and be fully maintained by operating personnel. Boiler water must be given complete and continuous chemical treatment.
B. Prior to final inspection, the equipment or parts used which show wear and tear beyond normal as determined by the
COR, shall be replaced with identical replacements, at no additional cost to the Government.
C. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.
D. Any damage to the equipment or excessive wear due to prolonged use will be repaired or replaced by the contractor at the contractor’s expense.
1.15 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract.
01 00 00 -26
1.16 TESTS
A. As per specification Section 23 05 93 the contractor shall provide a written testing and commissioning plan complete with component level, equipment level, sub-system level and system level breakdowns. The plan will provide a schedule and a written sequence of what will be tested, how and what the expected outcome will be. This document will be submitted for approval prior to commencing work. The contractor shall document the results of the approved plan and submit for approval with the as built documentation.
B. Pre-test mechanical and electrical equipment and systems and make corrections required for proper operation of such systems before requesting final tests. Final test will not be conducted unless pre-tested.
C. Conduct final tests required in various sections of specifications in presence of an authorized representative of the Contracting Officer. Contractor shall furnish all labor, materials, equipment, instruments, and forms, to conduct and record such tests.
D. Mechanical and electrical systems shall be balanced, controlled and coordinated. A system is defined as the entire system which must be coordinated to work together during normal operation to produce results for which the system is designed. For example, air conditioning supply air is only one part of entire system which provides comfort conditions for a building. Other related components are return air, exhaust air, steam, chilled water, refrigerant, hot water, controls and electricity, etc.
Another example of a system which involves several components of different disciplines is a boiler installation. Efficient and acceptable boiler operation depends upon the coordination and proper operation of fuel, 01 00 00 -27 combustion air, controls, steam, feedwater, condensate and other related components.
E. All related components as defined above shall be functioning when any system component is tested. Tests shall be completed within a reasonable period of time during which operating and environmental conditions remain reasonably constant and are typical of the design conditions.
F. Individual test result of any component, where required, will only be accepted when submitted with the test results of related components and of the entire system.
1.17 INSTRUCTIONS
A. Contractor shall furnish Maintenance and Operating manuals
(hard copies and electronic) and verbal instructions when required by the various sections of the specifications and as hereinafter specified.
B. Manuals: Maintenance and operating manuals and one compact disc (four hard copies and one electronic copy each) for each separate piece of equipment shall be delivered to the
COR coincidental with the delivery of the equipment to the job site. Manuals shall be complete, detailed guides for the maintenance and operation of equipment. They shall include complete information necessary for starting, adjusting, maintaining in continuous operation for long periods of time and dismantling and reassembling of the complete units and sub-assembly components. Manuals shall include an index covering all component parts clearly cross-referenced to diagrams and illustrations.
Illustrations shall include "exploded" views showing and identifying each separate item. Emphasis shall be placed on the use of special tools and instruments. The function of each piece of equipment, component, accessory and control
01 00 00 -28 shall be clearly and thoroughly explained. All necessary precautions for the operation of the equipment and the reason for each precaution shall be clearly set forth.
Manuals must reference the exact model, style and size of the piece of equipment and system being furnished. Manuals referencing equipment similar to but of a different model, style, and size than that furnished will not be accepted.
C. Instructions: Contractor shall provide qualified, factory-trained manufacturers' representatives to give detailed training to assigned Department of Veterans
Affairs personnel in the operation and complete maintenance for each piece of equipment. All such training will be at the job site. These requirements are more specifically detailed in the various technical sections. Instructions for different items of equipment that are component parts of a complete system, shall be given in an integrated, progressive manner. All instructors for every piece of component equipment in a system shall be available until instructions for all items included in the system have been completed. This is to assure proper instruction in the operation of inter-related systems. All instruction periods shall be at such times as scheduled by the COR and shall be considered concluded only when the COR is satisfied in regard to complete and thorough coverage. The contractor shall submit a course outline with associated material to the COR for review and approval prior to scheduling training to ensure the subject matter covers the expectations of the VA and the contractual requirements.
The Department of Veterans Affairs reserves the right to request the removal of, and substitution for, any instructor who, in the opinion of the COR, does not
01 00 00 -29 demonstrate sufficient qualifications in accordance with requirements for instructors above.
06-01-21
01 33 23 - 1
SECTION 01 33 23
SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES
PART 1 – GENERAL
1.1 DESCRIPTION
A. This specification defines the general requirements and procedures for submittals. A submittal is information submitted for VA review to establish compliance with the contract documents.
B. Detailed submittal requirements are found in the technical sections of the contract specifications. The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective technical specifications at no additional cost to the government.
C. VA approval of a submittal does not relieve the Contractor of the responsibility for any error which may exist. The Contractor is responsible for fully complying with all contract requirements and the satisfactory construction of all work, including the need to check, confirm, and coordinate the work of all subcontractors for the project.
Non-compliant material incorporated in the work will be removed and replaced at the Contractor’s expense.
1.2…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .