Attachment Drawings Addendum 1.pdf
PDF 6 MB Posted
- Solicitation number
- 36C26126R0004
About this file
This document is Addendum No. 1 to a federal construction solicitation (36C26126R0004) for the Improve Central Utility Plant (CUP) project at the VA Medical Center in Las Vegas, Nevada, issued on February 10, 2026. The addendum modifies the original Plans and Specifications and must be acknowledged by bidders on their bid proposal forms.
The addendum includes revisions to nine drawing sheets addressing structural bracing connection details, mechanical demolition and remodel plans, and flow control valve replacements. Specific changes require contractors to alert the Contracting Officer's Representative (COR) if existing shutoff valves do not close and seal properly, replace a shutoff valve with a new flow control valve on the cooling tower basin outlet, add strainers to condenser water piping, and remove an 18-inch equalizer requirement. Two new specifications are added: Section 13 05 41 (Seismic Restraint Requirements for Non-Structural Components) and Section 01 32 16.15 (Project Schedules for Small Projects—Design/Bid/Build). An architectural finish schedule specifying paint finishes for newly installed steel, hollow metal doors and frames, and large-diameter piping is attached. Plan holders are identified as the Las Vegas VAMC. The addendum establishes that all modifications become part of the original contract documents and take precedence over conflicting provisions.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFI Q-A Response 02-26-2026.pdf | ||
| Attachment SOW 02-26-2026.pdf | ||
| 36C26126R0004 0003.docx | DOCX document | |
| 36C26126R0004 0002.docx | DOCX document | |
| Attachment WAGE DETERMINATION NV20260038 01-30-2026.pdf | ||
| Sight Visit Sign-in Form 01-22-2026.pdf | ||
| 36C26126R0004 0001.docx | DOCX document | |
| Attachment Pre-solicitation Site Visit Presentation.pptx | PPTX presentation | |
| Attachment VAAR 852.219-75 JAN 2023 DEVIATION.pdf | ||
| Attachment APPENDIX.pdf | ||
| 36C26126R0004_2.docx | DOCX document | |
| Attachment REQUEST FOR INFORMATION FORM.docx | DOCX document | |
| Attachment PCRA- Pre-construction Risk Assessment.pdf | ||
| Attachment Specifications Combined Vol 1 of 2 dated 1-7-26.pdf | ||
| Attachment SOW 10-22-25.pdf | ||
| Attachment WAGE DETERMINATION NV20250038 01-02-2026.pdf | ||
| Attachment Price Breakdown.xlsx | XLSX spreadsheet | |
| Attachment Specifications Combined Vol 2 of 2 dated 1-7-26.pdf | ||
| Attachment Drawings.pdf |
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ARCHITECTURE | ENGINEERING | GIS | SURVEYING
517 Seventh Street Rapid City, SD 57701 p 605.342.9470 f 605.342-2377 www.4front.biz
36C26126R0004 IMPROVE CENTRAL UTILITY
PLANT (CUP) VAMC
Las Vegas, Nevada Project #23.2730.M01
February 10, 2026
ADDENDUM NO. 1
The following becomes a part of the original Plans and Specifications, just as if printed and bound therein, and takes precedence over any items that may conflict. The bidder shall acknowledge receipt of this Addendum on his bid proposal form, incorporating its provisions in his bid.
GENERAL INFORMORMATION:
Bid date or time change, alternates added, etc.
CHANGES AND CLARIFICATIONS TO DRAWINGS:
DRAWING SHEET :
1. Drawing Sheet S-120 CHILLER ROOM SECTION VIEWS – See drawing sheet for a revision to address vertical bracing connection detail now clarified on S-153.
2. Drawing Sheet S-140 BOILER ROOM SECTION VIEWS – See drawing sheet for a revision to address vertical bracing connection detail now clarified on S-153.
3. Drawing Sheet S-153 STRUCTURAL DETAILS – See drawing sheet, Detail 1, for a revision to address angle bracing connection at beam/column referenced on S-120 and S-
140.
4. Drawing Sheet MD-102 BUILDING 2 LEVEL 1 MECHCANICAL DEMOLITION
PLAN – See drawing sheet for a revision to keyed note #9 for shutoff valve replacement with new flow control valve. See drawing sheet for a revision to the last general mechanical note to alert the COR of any shutoff valves that do not close and seal off properly.
5. Drawing Sheet MD-103 BUILDING 2 CHILLER ROOM MEZZANINE
MECHCANICAL DEMOLITION PLAN – See drawing sheet for a revision to the last general mechanical note to alert the COR of any shutoff valves that do not close and seal off properly.
6. Drawing Sheet M-100 BUILDING 5 BASEMENT MECHCANICAL REMODEL PLAN
– See drawing sheet for a revision to the last general mechanical note to alert the COR of any shutoff valves that do not close and seal off properly.
7. Drawings Sheet M-101 BUILDING 2 BASEMENT & BUILDING 4 LEVEL 1
MECHCANICAL REMODEL PLANS – See drawing sheet for a revision to the last general mechanical note to alert the COR of any shutoff valves that do not close and seal off properly.
36C26126R0004 Addendum No. 1
8. Drawing Sheet M-102 BUILDING 2 LEVEL 1 NEW MECHCANICAL PLAN – See drawing sheet for a revision to remove keyed note #10 and new 18”Ø Equalizer requirement from detail #1. See drawing sheet for a revision to keyed note #12 for shutoff valve replacement with new flow control valve. See drawing sheet for a revision to the last general mechanical note to alert the COR of any shutoff valves that do not close and seal off properly. See drawing sheet for revision to add strainers in the condesnser water piping to the new condenser water pumps in details #1 and #3.
9. Drawings Sheet M-103 BUILDING 2 CHILLER ROOM MEZZANINE LEVEL NEW
MECHCANICAL PLAN – See drawing sheet for a revision to the last general mechanical note to alert the COR of any shutoff valves that do not close and seal off properly.
CHANGES TO AND CLARIFICATIONS TO SPECIFICATIONS:
SECTION :
1. Added Specification 13 05 41 Seismic Restraint Requirements for Non-Structural Components
2. Added Specification 01 32 16.15 Project Schedules (Small Projects- Design/Bid/Build)
OTHER ATTACHMENTS:
See attached architectural finish schedule for paint finishes of newly installed steel, hollow metal doors and frames, and large diameter piping.
PLAN HOLDERS:
Provided by Las Vegas VAMC.
END OF ADDENDUM NO. 1
GRADE LEVEL FF
100' - 0"
5 6 7
ROOF BEAMS
134' - 4"
2-RF
H
SS
9X 9X
1/
H
SS
9X 9X
1/
H
SS
9X 9X
1/
AHU
W18X40W18X40
STRUCTURAL COLUMN SIZE TO BE
FIELD CONFIRMED.
TYPICAL FOR ALL HSS9X9X1/2
L4X4X1/4 3"
BELOW TOP OF
STEEL TYP
EXISTING
CATWALK FF
118' - 6"
CHILLER ROOM
NEW WORK
PLATFORM TOS
121' - 2 1/2"
C6X10.5
W 6X
W8X18W8X18
W 6X
12' - 10 5/8" 10' - 6 3/4" 3' - 10 5/8" 26' - 0"
CHILLER ROOM
SOUTH NEW
PLATFORM TOS
123' - 2 1/2"
S-154
WT10.5X22 C6X10.5
S-153
TYP
1.
2.
3.
4.
5.
CONTRACTOR SHALL REMOVE EXISTING PIPE SUPPORTS
AND GUY WIRES THAT INTERFERE WITH THE INSTALLATION
OF THE CATWALK EXTENSIONS AND WORK PLATFORMS.
PRIOR TO THEIR REMOVAL, CONTRACTOR SHALL PROVIDE
AND MAINTAIN ANY TEMPORARY BRACING, SHORING,
GUYING, AND OTHER METHODS OF SUPPORT TO MAKE UP
FOR SUPPORTS TO BE REMOVED. THESE PROVISIONS
SHALL REMAIN IN PLACE AT ALL STAGES OF
CONSTRUCTION UNTIL SUFFICIENT PERMANENT MEMBERS
ARE CONSTRUCTED TO INSURE THE SAFETY, STABILITY
AND INTEGRITY OF THE STRUCTURE. THE CONTRACTOR
SHALL REINSTALL SUPPORTS AFTER THE INSTALLATION OF
THE CATWALK EXTENSIONS AND WORK PLATFORMS HAVE
BEEN COMPLETED. CONTRACTOR SHALL HIRE A
QUALIFIED ENGINEER TO DESIGN SUPPORTS THAT ARE IN
CONFLICT WITH NEW CATWALKS AND WORK PLATFORMS.
THE SHORING AND TEMPORARY BRACING DESIGN IS THE
COMPLETE RESPONSIBILITY OF THE CONTRACTOR.
TEMPORARY BRACING AND SHORING SHALL BE ADEQUATE
TO CARRY THE TOTAL WEIGHT OF THE STRUCTURAL
SYSTEM AND ANY TEMPORARY CONSTRUCTION LOADS TO
BE IMPOSED ON THE STRUCTURAL SYSTEM.
THE CONTRACTOR SHALL RELOCATE ALL MECHANICAL
PIPING, DUCTS, EQUIPMENT, ELECTRICAL CONDUITS,
WIRING AND PLUMBING AS INDICATED WHICH INTERFERE
WITH THE PROPOSED CONSTRUCTION. SERVICE SHALL
BEMAINTAINED TO ALL EQUIPMENT THAT IS SERVED BY
MECHANICAL, ELECTRICAL OR PLUMBING CONDUIT BEING
RELOCATED.
EXISTING STRUCTURAL MEMBERS AND TAGS SHOWN AS
HALFTONE.
NEW 1 1/2" x 1/8" WELDED BAR GRATING (19W4).
NOTES
GRADE LEVEL FF
100' - 0"
5 6 7
ROOF BEAMS
134' - 4"
EXISTING
CATWALK FF
118' - 6"
CHILLER ROOM
NEW WORK
PLATFORM TOS
121' - 2 1/2"
2-RF
2-RF
L4X4X1/4 3"
BELOW TOP OF
STEEL TYP
H
SS
9X 9X
1/
H
SS
9X 9X
1/
H
SS
9X 9X
1/
W18X40
W24X55 W24X55
W24X55
W18X40
W18X40
9' - 6 5/8" 1' - 4 1/2" 6' - 10" 7' - 0" 3' - 11 1/4" 6' - 7 7/8" 2' - 11" 26' - 0"
W 6X
W 6X
W 6X
W 6X
W 6X
C6X10.5
W 6X
W8X18 W8X18 W8X18 W8X18 W8X18 W8X18
W8X18 W8X18 W8X18 W8X18 W8X18 W8X18 W8X18
CHILLER ROOM
SOUTH NEW
PLATFORM TOS
123' - 2 1/2"
S-120
C6X10.5 WT10.5X22
GRADE LEVEL FF
100' - 0"
CHILLER ROOM
SOUTH NEW
CATWALK TOS
119' - 6 1/2"
HJ
ROOF BEAMS
134' - 4"
EXISTING
CATWALK FF
118' - 6" L4X4X1/4 3"
BELOW TOP OF
STEEL TYP
3'
0" W
6X
W 6X
W 6X
W 6X
W 6X
W 6X
H
SS
9X 9X
1/
H
SS
9X 9X
1/
W24X55
C6X10.5
W
X4
W
X4
W T1
0.
5X
W T1
0.
5X
W 6X
W 6X
W 6X
W 6X
W8X18W8X18
W8X18W8X18W8X18W8X18W8X18W8X18
9' - 4 3/4" 1' - 8 3/8" 3' - 1 5/8" 7' - 9 3/8" 2' - 10 1/4" 17' - 9 3/4"
LADDER, SEE
SHEET S-156
FOR DETAILS
C6X10.5
S-153
TYP1
GRADE LEVEL FF
100' - 0"
CHILLER ROOM
SOUTH NEW
CATWALK TOS
119' - 6 1/2"
6 7
ROOF BEAMS
134' - 4"
EXISTING
CATWALK FF
118' - 6"
CHILLER ROOM
SOUTH NEW
PLATFORM TOS
123' - 2 1/2"
L4X4X1/4 3"
BELOW TOP OF
STEEL TYP
6' - 11 5/8" 8' - 6 5/8" 6' - 6 3/4" 3' - 11"
W 6X
W 6X
C6X10.5
W8X18
W8X18
W 6X
H
SS
9X 9X
1/
H
SS
9X 9X
1/
W18X35
W8X18 W8X18W8X18
C6X10.5
Project Number
Building Number
Drawing Number
Dwg.
DrawnCheckedDate
Location
Project TitleDrawing Title
COR / Project Engineer
CONSULTANTS:
DateRevisions:
VA FORM 08-6231
o n e e ig h th in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e in c h o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t th re e in c h e s o n e fo o t
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9 of
Office of Construction and Facilities Management
PhaseARCHITECT/ENGINEER OF RECORD:
U.S. Department of Veterans Affairs
STAMP:
STRUCTURAL AND ELECTRICAL ENGINEERS
CITRINE LLC
710 KIPLING STREET, SUITE 406
LAKEWOOD, COLORADO 80215
PH: 720-556-0887
POC: DAVID KEATING
FIRE PROTECTION ENGINEER
OLSSON, INC.
601 P STREET, SUITE 200
LINCOLN, NEBRASKA 68508
PH: 402-474-6311
POC: TODD HENRY
POC PH: 913-318-4766
COA: 9647
BUILDING 5
BUILDING 2
BUILDING 3
BUILDING 4
KEY PLAN
517 7TH STREET
RAPID CITY, SD 57701
PH: (605) 342-9470
POC: NAME
FFD PROJECT NO:
23.2730.M01
DESIGN IN C
ALEX NOBLES, COR
BERNIE BORJA, ALTERNATE COR
2/ 6/
:3
6:
P M
08/26/2025
CHILLER ROOM SECTION VIEWS
S-120
VA SOUTHERN NEVADA
HEALTHCARE SYSTEM IMPROVE
CENTAL UTILITY PLANT
CKPTT
6900 NORTH PECOS ROAD
LAS VEGAS, NEVADA 89086
100% CONSTRUCTION
DOCUMENT
593-22-350
1/4" = 1'-0"1
CHILLER ROOM NORTH NEW WORK
PLATFORM WEST SECTION VIEW
1/4" = 1'-0"2
CHILLER ROOM NORTH NEW WORK
PLATFORM EAST SECTION VIEW
1/4" = 1'-0"3
CHILLER ROOM SOUTH NEW CATWALK
SOUTH SECTION VIEW
1/4" = 1'-0"4
CHILLER ROOM SOUTH NEW WORK
PLATFORM EAST SECTION VIEW
REV 1: ADDENDUM #1 02/06/2026
02/06/2026
6/30/2026
GRADE LEVEL FF
100' - 0"
2 3 4 5
FAN WORK
PLATFORMS TOS
121' - 1 1/2"
ROOF BEAMS
134' - 4"
S-140
W18X35W18X35W18X35
W8X186'
8"
C6X10.5
C6X10.5
W 6X
W 6X
W 6X
W 6X
W 6X
W 6X
W8X18
L4X4X1/4 3"
BELOW TOP OF
STEEL TYP
NEW WORK
PLATFORM TOS
124' - 7 1/2"
NEW CATWALK
TOS
114' - 10 1/2"
W8X18 W8X18W8X18W8X18
13' - 1 1/2" 8' - 2 1/2"
1' - 3"
7' - 7" 8' - 0 1/4" 3' - 9 3/4"
0' - 6 1/4"
7' - 6 1/2" 5' - 8" 12' - 3 1/4"
W 6X
S-140
C6X10.5
C6X
.5
S-153
TYP
GRADE LEVEL FF
100' - 0"
C D
FAN WORK
PLATFORMS TOS
121' - 1 1/2"
ROOF BEAMS
134' - 4"
H
SS
9X 9X
1/
H
SS
9X 9X
1/
STRUCTURAL COLUMN SIZE TO
BE FIELD CONFIRMED.
TYPICAL FOR ALL HSS9X9X1/2
W18X35 W18X35 W18X35 W18X35 W18X35 W18X35 W18X35
W24X55
L4X4X1/4 3"
BELOW TOP OF
STEEL TYP
C6X10.5
W 6X
W 6X
W8X18W8X18
6'
8"
10' - 10"9' - 6 3/4"5' - 7 1/4"
C6X10.5
1.
2.
3.
4.
5.
CONTRACTOR SHALL REMOVE EXISTING PIPE SUPPORTS
AND GUY WIRES THAT INTERFERE WITH THE INSTALLATION
OF THE CATWALK EXTENSIONS AND WORK PLATFORMS.
PRIOR TO THEIR REMOVAL, CONTRACTOR SHALL PROVIDE
AND MAINTAIN ANY TEMPORARY BRACING, SHORING,
GUYING, AND OTHER METHODS OF SUPPORT TO MAKE UP
FOR SUPPORTS TO BE REMOVED. THESE PROVISIONS
SHALL REMAIN IN PLACE AT ALL STAGES OF
CONSTRUCTION UNTIL SUFFICIENT PERMANENT MEMBERS
ARE CONSTRUCTED TO INSURE THE SAFETY, STABILITY
AND INTEGRITY OF THE STRUCTURE. THE CONTRACTOR
SHALL REINSTALL SUPPORTS AFTER THE INSTALLATION OF
THE CATWALK EXTENSIONS AND WORK PLATFORMS HAVE
BEEN COMPLETED. CONTRACTOR SHALL HIRE A
QUALIFIED ENGINEER TO DESIGN SUPPORTS THAT ARE IN
CONFLICT WITH NEW CATWALKS AND WORK PLATFORMS.
THE SHORING AND TEMPORARY BRACING DESIGN IS THE
COMPLETE RESPONSIBILITY OF THE CONTRACTOR.
TEMPORARY BRACING AND SHORING SHALL BE ADEQUATE
TO CARRY THE TOTAL WEIGHT OF THE STRUCTURAL
SYSTEM AND ANY TEMPORARY CONSTRUCTION LOADS TO
BE IMPOSED ON THE STRUCTURAL SYSTEM.
THE CONTRACTOR SHALL RELOCATE ALL MECHANICAL
PIPING, DUCTS, EQUIPMENT, ELECTRICAL CONDUITS,
WIRING AND PLUMBING AS INDICATED WHICH INTERFERE
WITH THE PROPOSED CONSTRUCTION. SERVICE SHALL
BEMAINTAINED TO ALL EQUIPMENT THAT IS SERVED BY
MECHANICAL, ELECTRICAL OR PLUMBING CONDUIT BEING
RELOCATED.
EXISTING STRUCTURAL MEMBERS AND TAGS SHOWN AS
HALFTONE.
NEW 1 1/2" x 1/8" WELDED BAR GRATING (19W4).
NOTES
GRADE LEVEL FF
100' - 0"
C D
FAN WORK
PLATFORMS TOS
121' - 1 1/2"
ROOF BEAMS
134' - 4"
NEW WORK
PLATFORM TOS
124' - 7 1/2"
8' - 7 1/4"5' - 4"
0' - 9 3/4"
3' - 4 1/2"
0' - 6 1/4"
7' - 4 1/4"
W 6X
W 6X
W 6X
W 6X
W 6X
C6X10.5
W8X18
W8X18
H
SS
9X 9X
1/
H
SS
9X 9X
1/
W8X18 W8X18
W18X35
W24X55
W18X35W18X35W18X35
STRUCTURAL COLUMN SIZE TO
BE FIELD CONFIRMED.
TYPICAL FOR ALL HSS9X9X1/2
LOCATION OF FAN TO
BE FIELD VERIFIED
Project Number
Building Number
Drawing Number
Dwg.
DrawnCheckedDate
Location
Project TitleDrawing Title
COR / Project Engineer
CONSULTANTS:
DateRevisions:
VA FORM 08-6231
o n e e ig h th in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e in c h o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t th re e in c h e s o n e fo o t
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9 of
Office of Construction and Facilities Management
PhaseARCHITECT/ENGINEER OF RECORD:
U.S. Department of Veterans Affairs
STAMP:
STRUCTURAL AND ELECTRICAL ENGINEERS
CITRINE LLC
710 KIPLING STREET, SUITE 406
LAKEWOOD, COLORADO 80215
PH: 720-556-0887
POC: DAVID KEATING
FIRE PROTECTION ENGINEER
OLSSON, INC.
601 P STREET, SUITE 200
LINCOLN, NEBRASKA 68508
PH: 402-474-6311
POC: TODD HENRY
POC PH: 913-318-4766
COA: 9647
BUILDING 5
BUILDING 2
BUILDING 3
BUILDING 4
KEY PLAN
517 7TH STREET
RAPID CITY, SD 57701
PH: (605) 342-9470
POC: NAME
FFD PROJECT NO:
23.2730.M01
DESIGN IN C
ALEX NOBLES, COR
BERNIE BORJA, ALTERNATE COR
2/ 6/
:3
6:
P M
08/26/2025
BOILER ROOM SECTION VIEWS
S-140
VA SOUTHERN NEVADA
HEALTHCARE SYSTEM IMPROVE
CENTAL UTILITY PLANT
CKPTT
6900 NORTH PECOS ROAD
LAS VEGAS, NEVADA 89086
100% CONSTRUCTION
DOCUMENT
593-22-350
1/4" = 1'-0"1 BOILER ROOM EAST SECTION VIEW
1/4" = 1'-0"2
BOILER ROOM NORTH NEW WORK
PLATFORM SECTION VIEW
1/4" = 1'-0"3
BOILER ROOM NORTH NEW WORK
PLATFORM SECTION VIEW
REV 1: ADDENDUM #1 02/06/2026
SE
E
FR
AM
IN
G
P
LA
N
BRACING
GUSSET PLATE
BEAM/COLUMN
SECTION A-A
(3" - 6" SPA)
(3) 3/4"Ø BOLTS
A
A
WP
L3X3X1/4 - 12"
LONG
3"
1"
3/8" GUSSET PLATE
(2) 3/4"DIA. BOLTS
ANGLE BRACE
SEE PLAN/SECTION
BEAM/COLUMN
STD. GAGE
1/4
1/4
1/4
1/4
WELDED
OPTION IN
LIEU OF
BOLTS
3"
BRACING
GUSSET PLATE
BEAM
SECTION A-A
A
A
3"
3"
4 1/8"
L4X4X1/4, 6" LONG
W/(2) 3/4"DIA. BOLTS
WP
3/8" GUSSET PLATE
L4X4X1/4, 6" LONG
W/(2) 3/4"DIA. BOLTS
(2) 3/4" DIA.
BOLTS
L BRACE
SEE PLAN
1" MIN
(HORIZONTAL BRACING AT BEAM)
A
A
3/8" GUSSET PLATE
L4X4X1/4, 6" LONG
W/(2) 3/4"DIA. BOLTS
L BRACE
SEE PLAN
4 1/8"
30° MIN
WP 3"
3"
L4X4X1/4, 6" LONG
W/(2) 3/4"DIA. BOLTS
(2) 3/4"DIA.
BOLTS
COLUMN
SEE PLAN
(HORIZONTAL BRACING AT COLUMN)
1/4
1/4 WELDED
OPTION IN
LIEU OF
BOLTS
SCALE: 1" = 1'-0"
TYP ANGLE BRACE AT BEAM/COLUMN END
SCALE: 1" = 1'-0"
TYPICAL HORIZONTAL BRACE CONNECTION DETAILS
Project Number
Building Number
Drawing Number
Dwg.
DrawnCheckedDate
Location
Project TitleDrawing Title
COR / Project Engineer
CONSULTANTS:
DateRevisions:
VA FORM 08-6231
o n e e ig h th in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e in c h o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t th re e in c h e s o n e fo o t
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9 of
Office of Construction and Facilities Management
PhaseARCHITECT/ENGINEER OF RECORD:
U.S. Department of Veterans Affairs
STAMP:
STRUCTURAL AND ELECTRICAL ENGINEERS
CITRINE LLC
710 KIPLING STREET, SUITE 406
LAKEWOOD, COLORADO 80215
PH: 720-556-0887
POC: DAVID KEATING
FIRE PROTECTION ENGINEER
OLSSON, INC.
601 P STREET, SUITE 200
LINCOLN, NEBRASKA 68508
PH: 402-474-6311
POC: TODD HENRY
POC PH: 913-318-4766
COA: 9647
517 7TH STREET
RAPID CITY, SD 57701
PH: (605) 342-9470
POC: NAME
FFD PROJECT NO:
23.2730.M01
DESIGN IN C
ALEX NOBLES, COR
BERNIE BORJA, ALTERNATE COR
2/ 6/
:3
6:
P M
08/26/2025
STRUCTURAL DETAILS
S-153
VA SOUTHERN NEVADA
HEALTHCARE SYSTEM IMPROVE
CENTAL UTILITY PLANT
CKPTT
6900 NORTH PECOS ROAD
LAS VEGAS, NEVADA 89086
100% CONSTRUCTION
DOCUMENT
593-22-350
REV 1: ADDENDUM #1 02/06/2026
UP
A B C D E F G H J
HE
1(E)
T 2(E)
T 1(E)
EXISTING SURGE TANK TO BE
BYPASSED AT TOP OF STRUCTURE
(EXISTING VALVING) DURING TANK
REPLACEMENT PROCESS
EXISTING JCI DDC PANEL
"DDC-B2-FTHL" TO REMAIN
EXISTING WATER
SOFTENER ISOLATION
VALVE TO REMAIN
EXISTING WATER SOFTENER
ISOLATION VALVE TO REMAIN
EXISTING
CONDENSATE
PUMP CONTROLLER
EXISTING BOILER SYSTEM
CONTROL PANEL CABINET
TO REMAIN
WS
1(E)
WFS
1(E)DWP
3(E)
DWP
2(E)
MD-102
B 1(E)
B 2(E)
B 3(E)
CWP
1(E)
CWP
2(E)
CWP
3(E)
CWP
4(E)
CWP
5(E)
24"ø CWS
"ø
C W
R
"ø
C W
S
24"ø CWS
18"ø EQ
"ø
C W
S
CT
3(E)
CT
1(E)
CT
5(E)
CT
2(E)
CT
4(E)
7 7 7 7
MD-102
TEMPORARILY RELOCATE EXISTING
CONDENSATE PUMP CONTROLLER
TO THIS APPROXIMATE LOCATION
FOR SURGE TANK REMOVAL AND
REPLACEMENT
REMOVE EXISTING 2" DOUBLE-
CHECK BACKFLOW
PREVENTER AND DSW PIPING
SERVING HEAT RECOVERY
SYSTEM
CHP
1(E)
CHP
3(E)
CHP
4(E)
CHP
5(E)
CHP
2(E) 3
9 9 9 9 9
4"ø CD
4" ø
C D
4"ø CW-S
6"ø CD
4"ø CD
6"ø STM-V
B 3(E)
DEMOLISH EXISTING 8"
STEAM NON-RETURN FOR
REPLACEMENT WITH NEW
8" STEAM ANGLED NON-
RETURN VALVE
EXISTING 8" STEAM
PIPING AND SOV
(TO REMAIN)
CWP
1(E)
REMOVE EXISTING
CONDENSER WATER
PUMP, AND 12"∅
CHECK VALVE FOR
REPLACEMENT
"ø
C W
S
10"ø
24"ø CWS
12"ø
24"ø CWS
CWP
2(E)
CWP
3(E)
CWP
4(E)
CWP
5(E)
REMOVE EXISTING SOV AND
CONDENSER WATER PIPING
FOR REPLACEMENT. PROVIDE
LINE STOPS FOR SOV AND
PIPING REPLACEMENT
AOM TN AN
E E
N
No. 19926PE
SC
L I E N DE
SS
R O
F E
P
LI O AN
NG
E
I
R
RAYMOND
E. DAWES
Project Number
Building Number
Drawing Number
Dwg.
DrawnCheckedDate
Location
Project TitleDrawing Title
COR / Project Engineer
CONSULTANTS:
DateRevisions:
VA FORM 08-6231
o n e e ig h th in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e in c h o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t th re e in c h e s o n e fo o t
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9 of
Office of Construction and Facilities Management
Phase
ARCHITECT/ENGINEER OF RECORD:
U.S. Department of Veterans Affairs
STAMP:
STRUCTURAL AND ELECTRICAL ENGINEERS
CITRINE LLC
710 KIPLING STREET, SUITE 406
LAKEWOOD, COLORADO 80215
PH: 720-556-0887
POC: DAVID KEATING
FIRE PROTECTION ENGINEER
OLSSON, INC.
601 P STREET, SUITE 200
LINCOLN, NEBRASKA 68508
PH: 402-474-6311
POC: TODD HENRY
POC PH: 913-318-4766
517 7TH STREET
RAPID CITY, SD 57701
PH: (605) 342-9470
POC: NAME
FFD PROJECT NO:
23.2730.M01
DES IGN INC
BUILDING 5
BUILDING 2
BUILDING 3
BUILDING 4
KEY PLAN
08/26/25
/6
/2
8:
:5
A M
08/26/2025
BUILDING 2 LEVEL 1 MECHANICAL
DEMOLITION PLAN
MD-102
VA SOUTHERN NEVADA
HEALTHCARE SYSTEM IMPROVE
CENTRAL UTILITY PLANT
PMRD
6900 NORTH PECOS ROAD
LAS VEGAS, NEVADA 89086
100% CONSTRUCTION
DOCUMENTS
19.2487.A01
• COORDINATE WORK WITH PHASING PLAN ON SHEET
G-101.
• COORDINATE ALL WORK SHOWN WITH ALL RELEVANT
DISCIPLINES AND TRADES.
• EQUIPMENT, AND PIPING SHOWN IN GRAY ARE EXISTING
AND TO REMAIN.
• PROTECT EXISTING PIPING/EQUIPMENT FOR
RECONNECTION TO NEW PIPING.
• TAGS AND LABELS SHOWN ARE SPECIFIC TO THESE
PLANS. CONTRACTOR TO COORDINATE FINAL TAGS AND
LABELING REQUIREMENTS WITH THE VA.
• CONTRACTOR TO PROVIDE LINE STOPS IN ANY PIPING
WHEN REPLACING SHUTOFF VALVES. IF SHUTOFF VALVE
DOES NOT CLOSE AND SEAL OFF PROPERLY, ALERT THE
COR FOR DIRECTION. COORDINATE ALL SHUTDOWN
REQUIREMENTS WITH THE COR.
GENERAL MECHANICAL NOTES
1/8" = 1'-0"1 BUILDING 2 LEVEL 1 MECHANICAL DEMOLITION PLAN
1/4" = 1'-0"2
BOILER NON-RETURN VALVE
DEMOLITION SECTION
1/4" = 1'-0"3
CONDENSER WATER PUMP
DEMOLITION SECTION
KEYED MECHANICAL DEMOLITION NOTES
REMOVE EXISTING NON-FUNCTIONAL HEAT RECOVERY
HEAT EXCHANGER HE-1(E). EXISTING BLOWDOWN
PIPING, SOFT WATER PIPING, CONDENSATE PIPING, AND
STEAM RECOVERY PIPING TO REAMING FOR
RECONNECTION TO NEW HEAT EXCHANGER. REFER TO
DETAIL 3 ON SHEET M-002 FOR PIPING DETAIL.
REMOVE EXISTING BLOWDOWN TANK FOR RELOCATION
ON PLATFORM ABOVE T-1(E) TO MAKE ROOM FOR NEW
CATWALK LADDER. EXISTING CONDENSATE, VENT AND
MAKEUP WATER PIPING TO BE EXTENDED TO
RELOCATED BLOWDOWN TANK.
REMOVE EXISTING CHILLED WATER PUMPS CHP-1(E),
2(E), 3(E), 4(E), 5(E) FOR REPLACEMENT. REMOVE AND
REPLACE ONE PUMP AT A TIME KEEPING THE
REMAINING PUMPS IN SERVICE.
REMOVE EXISTING CONDENSATE RETURN/SURGE TANK
T-1(E) FOR REPLACEMENT. TANK CAN BE TEMPORARILY
BYPASSED IN ORDER TO REMOVE THE EXISTING TANK
AND INSTALL THE NEW TANK. EXISTING PIPING TO
REMAIN FOR RECONNECTION TO NEW TANK. EXISTING
CONTROL PANEL IN FRONT OF CONDENSATE RETURN
TANK TO BE TEMPORARILY RELOCATED TO ALLOW FOR
REMOVAL AND REPLACEMENT OF TANK. TWO WATER
MAKEUP CONTROL COMPONENTS (PRIMARY AND
BACKUP) ARE CONTROLLED FROM THIS LOCATION. THIS
SECTION OF CONTROLLER TO ONLY BE TEMPORARILY
SHUTDOWN TO RELOCATE PANEL AND THEN REUSED
WHILE TANK REPLACEMENT IS IN PROCESS.
REMOVE EXISTING 8"∅ NON-RETURN VALVE ON TOP OF
BOILER #3(E) EXISTING 8"∅ STEAM PIPING TO REMAIN
FOR RECONNECTION TO NEW STEAM ANGLE NON-
RETURN VALVE. REFER TO SECTION DETAIL 2 ON THIS
SHEET.
EXISTING BOILER SYSTEM CONTROL PANEL CABINET.
FUEL OIL TANK HIGH AND LOW ALARMS TO BE
INTEGRATED TO CONTROL PANEL FOR MONITORING.
REFER TO ELECTRICAL CONTROLS DRAWINGS.
REMOVE EXISTING COOLING TOWER CONDENSER
WATER PUMPS CWP-1(E), 2(E), 3(E), 4(E), 5(E) FOR
REPLACEMENT. REMOVE AND REPLACE ONE PUMP AT A
TIME KEEPING THE REMAINING PUMPS IN SERVICE.
REFER TO SECTION DETAIL 3 ON THIS SHEET.
REMOVE EXISTING COOLING TOWER CT-1(E), 2(E), 3(E),
4(E) GALVANIZED UPPER SECTIONS FOR
REPLACEMENT. REMOVE AND REPLACE ONE TOWER
UPPER SECTION AT A TIME KEEPING THE REMAINING
COOLING TOWERS IN SERVICE. REFER TO DETAIL 4 ON
SHEET M-002.
REMOVE EXISTING 14" VERTICAL SHUTOFF VALVE ON
OUTLET OF COOLING TOWER BASIN FOR
REPLACEMENT WITH NEW FLOW CONTROL
VALVE.
DECOMMISSION EXISTING FILTERED WATER BOOSTER
PUMP SYSTEM DWP-3(E) AND ALL FILTERED WATER
PIPING IN THIS AREA TO PROVIDE ACCESS FOR
REMOVAL OF EXISTING FILTRATION SYSTEM AND
INSTALLATION OF WATER SOFTENER/POLISHER
SYSTEM. TEMPORARILY REMOVE EXISTING DOUBLE
CHECK BACKFLOW PREVENTER (ONLY SERVES
MAKEUP TO THE BOILER BLOWDOWN HEAT RECOVERY
SYSTEM) FOR WATER FILTER REMOVAL AND NEW
WATER SOFTENER INSTALLATION.
REMOVE EXISTING WATER FILTER SYSTEM SKID IN ITS
ENTIRETY. REFER TO DETAIL 2 ON SHEET M-002 FOR
NEW WATER SOFTENER PIPING DETAIL AND
CONNECTION TO EXISTING WATER PIPING.
REMOVE ALL WATER SOFTENER WS-1(E) COPPER
PIPING (4" AND 2") FROM EXISTING WATER SOFTENER
INCOMING SOV TO THE EXISTING WATER SOFTENER
OUTGOING SOV, INCLUDING TANK INTERCONNECTION
PIPING, CONTROLLER INTERCONNECTION PIPING,
DRAINS, AND BYPASS LINE FOR REPLACEMENT WITH
NEW STAINLESS STEEL PIPING. REFER TO DETAIL 1 ON
SHEET M-002 FOR PIPING REPLACEMENT DETAIL.
LOCATION OF EXISTING STEAM MAKEUP WATER
CONTROL VALVES. KEEP IN OPERATION WHEN SURGE
TANK IS BEING BYPASSED FOR REPLACEMENT.
PHASE A (SHEET G-101)
PHASE E (SHEET G-101)
PHASE F (SHEET G-101)
PHASE G (SHEET G-101)
PHASE H (SHEET G-101)
PHASE I (SHEET G-101)
GENERAL NOTE
PHASE B (SHEET G-101)
33 75
1 - BIDDING REVISION 02-06-2026
1 1
F G H J
K
EXISTING 1-1/4" CHS/CHR
AND 1" HWS/HWR OFFSET
DOWN BELOW EXISTING
CATWALK LEVEL
24"ø CWS
"ø
C W
R
"ø
C W
S
RF
2(E)
RF
3(E)
FCU
2(E)
EF
2(E)
"ø
C H
S
"ø
C H
S
AOM TN AN
E E
N
No. 19926PE
SC
L I E N DE
SS
R O
F E
P
LI O AN
NG
E
I
R
RAYMOND
E. DAWES
Project Number
Building Number
Drawing Number
Dwg.
DrawnCheckedDate
Location
Project TitleDrawing Title
COR / Project Engineer
CONSULTANTS:
DateRevisions:
VA FORM 08-6231
o n e e ig h th in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e in c h o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t th re e in c h e s o n e fo o t
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9 of
Office of Construction and Facilities Management
Phase
ARCHITECT/ENGINEER OF RECORD:
U.S. Department of Veterans Affairs
STAMP:
STRUCTURAL AND ELECTRICAL ENGINEERS
CITRINE LLC
710 KIPLING STREET, SUITE 406
LAKEWOOD, COLORADO 80215
PH: 720-556-0887
POC: DAVID KEATING
FIRE PROTECTION ENGINEER
OLSSON, INC.
601 P STREET, SUITE 200
LINCOLN, NEBRASKA 68508
PH: 402-474-6311
POC: TODD HENRY
POC PH: 913-318-4766
517 7TH STREET
RAPID CITY, SD 57701
PH: (605) 342-9470
POC: NAME
FFD PROJECT NO:
23.2730.M01
DES IGN INC
BUILDING 5
BUILDING 2
BUILDING 3
BUILDING 4
KEY PLAN
08/26/25
/6
/2
8:
:5
A M
08/26/2025
BUILDING 2 CHILLER ROOM MEZZANINE
LEVEL MECHANICAL DEMOLITION PLAN
MD-103
VA SOUTHERN NEVADA
HEALTHCARE SYSTEM IMPROVE
CENTRAL UTILITY PLANT
PMRD
6900 NORTH PECOS ROAD
LAS VEGAS, NEVADA 89086
100% CONSTRUCTION
DOCUMENTS
19.2487.A01
1/4" = 1'-0"1 BUILDING 2 MEZZANINE MECHANICAL DEMOLITION PLAN
REMOVE EXISTING 1-1/4" CHS/CHR AND 1" HWS/HWR
DOWN BELOW EXISTING CATWALK LEVEL TO MAKE
ROOM FOR NEW CATWALK.
KEYED MECHANICAL NOTES
• COORDINATE WORK WITH PHASING PLAN ON SHEET
G-101.
• COORDINATE ALL WORK SHOWN WITH ALL RELEVANT
DISCIPLINES AND TRADES.
• EQUIPMENT, AND PIPING SHOWN IN GRAY ARE EXISTING
AND TO REMAIN.
• PROTECT EXISTING PIPING/EQUIPMENT FOR
RECONNECTION TO NEW PIPING.
• TAGS AND LABELS SHOWN ARE SPECIFIC TO THESE
PLANS. CONTRACTOR TO COORDINATE FINAL TAGS AND
LABELING REQUIREMENTS WITH THE VA.
• CONTRACTOR TO PROVIDE LINE STOPS IN ANY PIPING
WHEN REPLACING SHUTOFF VALVES. IF SHUTOFF VALVE
DOES NOT CLOSE AND SEAL OFF PROPERLY, ALERT THE
COR FOR DIRECTION. COORDINATE ALL SHUTDOWN
REQUIREMENTS WITH THE COR.
GENERAL MECHANICAL NOTES
PHASE B (SHEET G-101)
34 75
1 - BIDDING REVISION 02-06-2026
EMERGENCY DOMESTIC
COLD WATER BACKUP
PUMPS SKID
EXISTING 4" BACKUP DCW
TO BUILDINGS #1 AND #5
EXISTING JCI "DHWS
CONTROL PANEL"
4" SOV BU-2
2" SOV BU-2A TO SUMP
BP
.4" DCW (E)
S
S
4" DCW (E)
REPLACE EXISTING BUILDING #1 AND #5 BACKUP
DOMESTIC COLD WATER PUMP SKID WITH NEW BP-1. BP-1
TO BE INTEGRATED TO EXISTING BAS SYSTEM VIA
EXISTING JCI PANEL "DHWS CONTROL PANEL". BP-1 TO BE
ABLE TO BE REMOTELY CONTROLLED FROM THE
CENTRAL UTILITY PLANT (BUILDING #2) CONTROL ROOM.
REPLACE EXISTING 4" CROSS CONNECT VALVE (BU-2)
AND 2" DRAIN VALVE (BU-2A) WITH 120V DDC CONTROL
VALVES TO ALLOW REMOTE SWITCHOVER TO SUPPLY
BUILDING #1 AND BUILDING #5 FROM THE CENTRAL
UTILITY PLANT CONTROL ROOM. BP-1 AND CONTROL
VALVES ARE NOT TO BE AUTOMATIC FOR SWITCH OVER
AND PUMP ENABLE, BUT CONTROLLED REMOTELY FROM
THE CENTRAL UTILITY PLANT CONTROL ROOM. REFER TO
ELECTRICAL CONTROL DRAWINGS.
KEYED MECHANICAL NOTES
PHASE D (SHEET G-101)
· COORDINATE WORK WITH PHASING PLAN ON SHEET
G-101.
· COORDINATE ALL WORK SHOWN WITH ALL RELEVANT
DISCIPLINES AND TRADES.
· EQUIPMENT, AND PIPING SHOWN IN GRAY ARE
EXISTING AND TO REMAIN.
· PROTECT EXISTING PIPING/EQUIPMENT FOR
RECONNECTION TO NEW PIPING.
· TAGS AND LABELS SHOWN ARE SPECIFIC TO THESE
PLANS. CONTRACTOR TO COORDINATE FINAL TAGS
AND LABELING REQUIREMENTS WITH THE VA.
· INSTALL ALL PIPING/COMPONENTS SO THAT THERE IS
ENOUGH SPACE TO INSULATE PIPING AND
COMPONENTS.
· CONTRACTOR TO PROVIDE LINE STOPS IN ANY
PIPING WHEN REPLACING SHUTOFF VALVES. IF
SHUTOFF VALVE DOES NOT CLOSE AND SEAL OFF
PROPERLY, ALERT THE COR FOR DIRECTION.
COORDINATE ALL SHUTDOWN REQUIREMENTS WITH
THE COR.
GENERAL MECHANICAL NOTES
BUILDING #5 BASEMENT
MECHANICAL REMODEL PLAN
POC: JOEL SIMONYAK
Project Number
Building Number
Drawing Number
Dwg.
DrawnCheckedDate
Location
Project TitleDrawing Title
COR / Project Engineer
CONSULTANTS:
DateRevisions: of
Office of Construction and Facilities Management
PhaseARCHITECT/ENGINEER OF RECORD:
U.S. Department of Veterans Affairs
STAMP:
STRUCTURAL AND ELECTRICAL ENGINEERS
CITRINE LLC
710 KIPLING STREET, SUITE 406
LAKEWOOD, COLORADO 80215
PH: 720-556-0887
POC: DAVID KEATING
FIRE PROTECTION ENGINEER
OLSSON, INC.
601 P STREET, SUITE 200
LINCOLN, NEBRASKA 68508
PH: 402-474-6311
POC: TODD HENRY
/2
6/
:4 1:
A
M
08/26/2025
VA SOUTHERN NEVADA
HEALTHCARE SYSTEM IMPROVE
CENTRAL UTILITY PLANT
PMRD
6900 NORTH PECOS ROAD
LAS VEGAS, NEVADA 89086
100% CONSTRUCTION
DOCUMENTS
593-22-350
POC PH: 913-318-4766
517 7TH STREET
RAPID CITY, SD 57701
PH: (605) 342-9470 FFD PROJECT NO:
23.2730.M01 75
E E
N
No. 19926PE
AOM TN AN
SCL I EN DE
SS
R O
FE
P
LI O AN NG
E
I R
RAYMOND
E. DAWES
08/26/25
02-06-20261 - BIDDING REVISION
M-100
BUILDING 2
BUILDING 3
BUILDING 4
KEY PLANBUILDING #5 BASEMENT MECHANICAL REMODEL PLAN
SCALE: 1/4" = 1'1
BUILDING 5
IWP
EXISTING 6" SOV (x2)
6"
IW
(E
6"
IW
(E
EXISTING 6" INDUSTRIAL
WATER PUMP BYPASS
INTEGRATE EXISTING FUEL OIL TANK MONITORING
STATION (VEEDER ROOT TLS-350) TO EXISTING BAS VIA
JCI PANEL "DDC-B4-FUEL OIL". READINGS FROM EXISTING
FLOATS TO BE INTEGRATED TO EXISTING BOILER PLANT
CONTROL PANEL. REAL TIME TANK LEVELS AND FUEL OIL
CONSUMPTION DATA (PER DAY, WEEK, MONTH, ETC.) TO
BE VISIBLE VIA EXISTING BAS NETWORK. REFER TO
ELECTRICAL CONTROL DRAWINGS.
EXISTING JCI BAS PANEL "DDC-B4-FUEL OIL" TO BE USED
FOR INTEGRATION OF FUEL OIL LEVEL MONITORING AND
BOILER FUEL OIL TRANSFER PUMPS TO BOILER PLANT
CONTROL PANEL AND EXISTING BAS NETWORK. REFER
TO ELECTRICAL CONTROL DRAWINGS
EXISTING BOILER FUEL OIL TRANSFER PUMPS CONTROL
PANEL. INTEGRATE CONTROL PANEL INTO EXISTING BAS
VIA EXISTING JCI PANEL "DDC-B4-FUEL OIL" FOR REMOTE
PUMP OPERATION FROM BOILER PLANT CONTROL ROOM.
LOCAL USER INTERFACE TO BE UPGRADED FOR MORE
USER FRIENDLY OPERATION. REFER TO ELECTRICAL
CONTROL DRAWINGS.
EXISTING 10"Ø DCW (SHOWN IN DARK FOR CLARITY).
EXISTING 6"Ø DCW (SHOWN IN DARK FOR CLARITY).
NEW 6"Ø DCW FOR BACKUP CONDENSER WATER MAKEUP
FROM EXISTING 10"Ø DCW.
NEW 6"Ø DCW UP THROUGH CHILLER ROOM FLOOR.
CORE DRILL, SLEEVE, AND SEAL PENETRATION.
CONTRACTOR TO CONDUCT GPR PRIOR TO PENETRATING
THE DECK.
REPLACE EXISTING INDUSTRIAL WATER PUMP SKID WITH
NEW IWP-1. IWP-1 CONTROL PANEL TO BE INTEGRATED
TO EXISTING JCI BAS SYSTEM. COORDINATE AND
SCHEDULE SHUTDOWN WITH VA STAFF FOR PUMP SKID
REPLACEMENT. CONNECT TO EXISTING 6" SCH 105 SS
INDUSTRIAL WATER PIPING.
KEYED MECHANICAL NOTES
PHASE F (SHEET G-101)
PHASE I (SHEET G-101)
EXISTING FUEL OIL LEVEL
MONITORING PANEL
EXISTING JCI DDC PANEL
"DDC-B4-FUEL OIL"
EXISTING BOILER FUEL
OIL TRANSFER PUMPS
CONTROL PANEL
· COORDINATE WORK WITH PHASING PLAN ON SHEET
G-101.
· COORDINATE ALL WORK SHOWN WITH ALL RELEVANT
DISCIPLINES AND TRADES.
· EQUIPMENT, AND PIPING SHOWN IN GRAY ARE
EXISTING AND TO REMAIN.
· PROTECT EXISTING PIPING/EQUIPMENT FOR
RECONNECTION TO NEW PIPING.
· TAGS AND LABELS SHOWN ARE SPECIFIC TO THESE
PLANS. CONTRACTOR TO COORDINATE FINAL TAGS
AND LABELING REQUIREMENTS WITH THE VA.
· INSTALL ALL PIPING/COMPONENTS SO THAT THERE IS
ENOUGH SPACE TO INSULATE PIPING AND
COMPONENTS.
· CONTRACTOR TO PROVIDE LINE STOPS IN ANY
PIPING WHEN REPLACING SHUTOFF VALVES. IF
SHUTOFF VALVE DOES NOT CLOSE AND SEAL OFF
PROPERLY, ALERT THE COR FOR DIRECTION.
COORDINATE ALL SHUTDOWN REQUIREMENTS WITH
THE COR.
GENERAL MECHANICAL NOTES
BUILDING #2 BASEMENT & BUILDING #4
LEVEL 1 MECHANICAL REMODEL PLANS
POC: JOEL SIMONYAK
Project Number
Building Number
Drawing Number
Dwg.
DrawnCheckedDate
Location
Project TitleDrawing Title
COR / Project Engineer
CONSULTANTS:
DateRevisions: of
Office of Construction and Facilities Management
PhaseARCHITECT/ENGINEER OF RECORD:
U.S. Department of Veterans Affairs
STAMP:
STRUCTURAL AND ELECTRICAL ENGINEERS
CITRINE LLC
710 KIPLING STREET, SUITE 406
LAKEWOOD, COLORADO 80215
PH: 720-556-0887
POC: DAVID KEATING
FIRE PROTECTION ENGINEER
OLSSON, INC.
601 P STREET, SUITE 200
LINCOLN, NEBRASKA 68508
PH: 402-474-6311
POC: TODD HENRY
/2
6/
:4 1:
A
M
08/26/2025
VA SOUTHERN NEVADA
HEALTHCARE SYSTEM IMPROVE
CENTRAL UTILITY PLANT
PMRD
6900 NORTH PECOS ROAD
LAS VEGAS, NEVADA 89086
100% CONSTRUCTION
DOCUMENTS
593-22-350
POC PH: 913-318-4766
517 7TH STREET
RAPID CITY, SD 57701
PH: (605) 342-9470 FFD PROJECT NO:
23.2730.M01 75
E E
N
No. 19926PE
AOM TN AN
SCL I EN DE
SS
R O
FE
P
LI O AN NG
E
I R
RAYMOND
E. DAWES
08/26/25
02-06-20261 - BIDDING REVISION
BUILDING 5
BUILDING 2
BUILDING 3
BUILDING 4
KEY PLAN
M-101
2, 4
BUILDING #2 BASEMENT MECHANICAL REMODEL PLAN
SCALE: 1/4" = 1'1 BUILDING #4 LEVEL 1 MECHANICAL REMODEL PLAN
SCALE: 1/4" = 1'2
A B C D E F G H J
K
T 2(E)
EXISTING JCI DDC PANEL
"DDC-B2-FTHL" (TO REMAIN)
EXISTING WATER
SOFTENER
ISOLATION VALVE
(TO REMAIN)
EXISTING WATER SOFTENER
ISOLATION VALVE (TO REMAIN)
EXISTING CONDENSATE
PUMP CONTROLLER
EXISTING BOILER SYSTEM
CONTROL PANEL CABINET
(TO REMAIN)
WS
1(E)
DWP
2(E)
B 1(E)
B 2(E)
B 3(E)
24"ø CWS
"ø
C W
R
"ø
C W
S
24"ø CWS
18"ø EQ
"ø
C W
S
CT
5(E)
M-102
M-102
CT
CT
CT
CT
WS
T
CWP
CWP
CWP
CWP
CWP
HE
8 8 8 8
6"ø DCW
6"ø DCW
11 11 11 11
REINSTALL EXISTING 2"
DOUBLE-CHECK
BACKFLOW PREVENTER
AND DSW PIPING SERVING
HEAT RECOVERY SYSTEM
LV
LV
"ø
C H
S
"ø
C H
S
CHP
CHP
CHP
CHP
4 CHP
12 12 12 12 12
4"ø CD
4" ø
C D
4"ø CW-S
6"ø CW-S
EXISTING SURGE TANK TO BE
BYPASSED AT TOP OF STRUCTURE
(EXISTING VALVING) DURING TANK
REPLACEMENT PROCESS
6"ø CD
4"ø CW-S
6"ø STM-V
SOV (TYP)
B 3(E)
NEW POWELL API 600 8"
ANGLE STEAM NON-
RETURN VALVE, OR EQUAL.
CONNECT TO EXISTING 8"
STEAM PIPING
EXISTING 8" STEAM
PIPING AND SOV
(TO REMAIN)
INSTALL NEW SOVS, PIPING,
CONDENSER WATER PUMP,
FLEXIBLE INLET/OUTLET
CONNECTIONS AND NEW 12"∅
TRIPLE DUTY VALVE.
"ø
C W
S
24"ø CWS
24"ø CWS
CWP
NEW SOV
12"ø CWS
CWP
CWP
CWP
CWP
12"ø CWS
NEW SOV
VICTAULIC 732, OR
EQUAL, STRAINER
AOM TN AN
E E
N
No. 19926PE
SC
L I E N DE
SS
R O
F E
P
LI O AN
NG
E
I
R
RAYMOND
E. DAWES
Project Number
Building Number
Drawing Number
Dwg.
DrawnCheckedDate
Location
Project TitleDrawing Title
COR / Project Engineer
CONSULTANTS:
DateRevisions:
VA FORM 08-6231
o n e e ig h th in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e in c h o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t th re e in c h e s o n e fo o t
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9 of
Office of Construction and Facilities Management
Phase
ARCHITECT/ENGINEER OF RECORD:
U.S. Department of Veterans Affairs
STAMP:
STRUCTURAL AND ELECTRICAL ENGINEERS
CITRINE LLC
710 KIPLING STREET, SUITE 406
LAKEWOOD, COLORADO 80215
PH: 720-556-0887
POC: DAVID KEATING
FIRE PROTECTION ENGINEER
OLSSON, INC.
601 P STREET, SUITE 200
LINCOLN, NEBRASKA 68508
PH: 402-474-6311
POC: TODD HENRY
POC PH: 913-318-4766
517 7TH STREET
RAPID CITY, SD 57701
PH: (605) 342-9470
POC: NAME
FFD PROJECT NO:
23.2730.M01
DES IGN INC
BUILDING 5
BUILDING 2
BUILDING 3
BUILDING 4
KEY PLAN
08/26/25
/2
/2
0:
:4
A
M
08/26/2025
BUILDING 2 LEVEL 1 NEW MECHANICAL
PLAN
M-102
VA SOUTHERN NEVADA
HEALTHCARE SYSTEM IMPROVE
CENTRAL UTILITY PLANT
PMRD
6900 NORTH PECOS ROAD
LAS VEGAS, NEVADA 89086
100% CONSTRUCTION
DOCUMENTS
19.2487.A01
1/8" = 1'-0"1 BUILDING 2 LEVEL 1 NEW MECHANICAL PLAN
1/4" = 1'-0"2
BOILER 3 NEW
NON-RETURN VALVE SECTION
INSTALL NEW HEAT RECOVERY HEAT EXCHANGER HE-1. CONNECT TO EXISTING BLOWDOWN PIPING, SOFT WATER PIPING, CONDENATE PIPING, AND STEAM RECOVERY PIPING. REFER TO DETAIL 3 ON
SHEET M-002 FOR PIPING DETAIL.
RELOCATE EXISTING BLOWDOWN TANK ON PLATFORM ABOVE T-1 TO MAKE ROOM FOR NEW CATWALK LADDER. RE-ROUTE AND RECONNECT EXISTING CONDENSATE, VENT AND MAKEUP WATER PIPING TO
RELOCATED BLOWDOWN TANK.
INSTALL NEW LV-1 AND LV-2 IN REMOVED WINDOW LOCATIONS. REFER TO ARCH FOR LOCATION.
REFER TO ELECTRICAL FOR CONTROLS.
INSTALL NEW CHILLED WATER PUMPS CHP-1, 2, 3, 4, 5 IN EXSITING LOCATIONS. CONNECT TO EXISTING CHILLED WATER PIPING INSTALL ONE PUMP AT A TIME KEEPING THE REMAINING PUMPS IN SERVICE.
INSTALL NEW POWELL API 600 8"∅ ANGLE STEAM NON-RETURN VALVE, OR EQUAL. CONNECT TO
EXISTING STEAM PIPING. REFER TO SECTION DETAIL 2 ON THIS SHEET.
INSTALL NEW STAINLESS STEEL CONDENSATE RETURN/SURGE TANK T-1 IN EXISTING SURGE TANK LOCATION. CONNECT TO EXISTING PIPING TO/FROM EXISTING TANK. EXISTING CONDENSATE PUMP
CONTROL PANEL TO BE MOVED BACK TO ORIGINAL LOCATION AFTER NEW T-1 IS ISNTALLED.
EXISTING BOILER SYSTEM CONTROL PANEL CABINET. FUEL OIL TANK HIGH AND LOW ALARMS TO BE INTEGRATED TO CONTROL PANEL FOR MONITORING. REFER TO ELECTRICAL CONTROLS DRAWINGS.
INSTALL NEW COOLING TOWER CONDENSER WATER PUMPS CWP-1, 2, 3, 4, 5 IN EXSITING LOCATIONS.
CONNECT TO EXISTING CONDENSER WATER PIPING INSTALL ONE PUMP AT A TIME KEEPING THE
REMAINING PUMPS IN SERVICE. REFER TO SECTION DETAIL 3 ON THIS SHEET.
INSTALL NEW COOLING TOWER CT-1, 2, 3, 4 STAINLESS STEEL UPPER SECTIONS. INSTALL ONE TOWER UPPER SECTION AT A TIME KEEPING THE REMAINING COOLING TOWERS IN SERVICE. CONNECT TO EXISTING 14"∅ CONDENSER WATER RETURN PIPING TO EACH TOWER UPPER SECTION. REFER TO
DETAIL 5 ON SHEET M-002.
NOT USED.
TAP TOP OF EXISTING 24" CONDENSER WATER SUPPLY PIPING TO ADD NEW 3/4" AUTOMATIC AIR VENT
WITH SHUTOFF VALVE.
REPLACE EXISTING MANUAL SHUTOFF VALVE IN VERTICAL PIPING FROM COOLING TOWER BASIN OUTLET WITH NEW 8" CA-VAL 40-01 FLOW CONTROL VALVE, OR EQUAL. SET INITIAL FLOW RATE TO
2400GPM.
NEW 6"∅ DCW UP THROUGH CHILLER ROOM FLOOR FROM DOMESTIC PUMPS ROOM TO BELOW
MEZZANINE CATWALKS. CORE DRILL, SLEEVE, AND SEAL PENETRATION. CONTRACTOR TO CONDUCT
GPR PRIOR TO PENETRATING THE DECK.
NEW 6"∅ DCW FOR BACKUP COOLING TOWER WATER MAKEUP FROM ABOVE TO EXISTING COOLING
TOWER CONDENSER WATER WITH SOV AND CHECK VALVE.
INSTALL NEW WS-2 IN REMOVED FILTER SYSTEM LOCATION. REFER TO DETAIL 2 ON SHEET M-002 FOR NEW WATER SOFTENER PIPING DETAIL AND CONNECTION TO EXISTING WATER PIPING. NEW WATER
SOFTENER SYSTEM TO FUNCTION AS WATER POLISHER IN CONJUNCTION WITH EXISTING WATER
SOFTENER SYSTEM AS WELL AS A BACKUP/REDUNDANT WATER SOFTENER SYSTEM. PROVIDE WITH STAINLESS STEEL MANIFOLD. NEW WATER SOFTENER TO INTEGRATE TO EXISTING BAS VIA EXISTING
JCI PANEL "DDC-B2-LTHW" LOCATED ON BOILER ROOM WALL WITH INSTANTANEOUS FLOW AND
TOTALIZATION FLOW MEASUREMENT. REINSTALL EXISTING DOUBLE CHECK BACKFLOW PREVENTER IN
PIPING TO SERVE NEW HEAT RECOVERY SYSTEM AFTER NEW WS-2 IS INSTALLED.
INSTALL NEW STAINLESS STEEL PIPING (4" AND 2") IN EXISTING WS-1(E) FROM EXISTING WATER SOFTENER INCOMING SOV TO THE EXISTING WATER SOFTENER OUTGOING SOV, INCLUDING TANK INTERCONNECTION PIPING, CONTROLLER INTERCONNECTION PIPING, DRAINS, AND BYPASS LINE.
REFER TO DETAIL 1 ON SHEET M-002 FOR PIPING REPLACEMENT DETAIL.
LOCATION OF EXISTING STEAM MAKEUP WATER CONTROL VALVES. KEEP IN OPERATION WHEN SURGE
TANK IS BEING BYPASSED FOR REPLACEMENT.
KEYED MECHANICAL NOTES
1/4" = 1'-0"3
NEW CONDENSER WATER
PUMP SECTION DETAIL
• COORDINATE WORK WITH PHASING PLAN ON
SHEET G-101.
• COORDINATE ALL WORK SHOWN WITH ALL
RELEVANT DISCIPLINES AND TRADES.
• EQUIPMENT, AND PIPING SHOWN IN GRAY ARE
EXISTING AND TO REMAIN.
• PROTECT EXISTING PIPING/EQUIPMENT FOR
RECONNECTION TO NEW PIPING.
• TAGS AND LABELS SHOWN ARE SPECIFIC TO
THESE PLANS. CONTRACTOR TO COORDINATE
FINAL TAGS AND LABELING REQUIREMENTS
WITH THE VA.
• INSTALL ALL PIPING/COMPONENTS SO THAT
THERE IS ENOUGH SPACE TO INSULATE PIPING
AND COMPONENTS.
• CONTRACTOR TO PROVIDE LINE STOPS IN ANY
PIPING WHEN REPLACING SHUTOFF VALVES. IF
SHUTOFF VALVE DOES NOT CLOSE AND SEAL
OFF PROPERLY, ALERT THE COR FOR
DIRECTION. COORDINATE ALL SHUTDOWN
REQUIREMENTS WITH THE COR.
GENERAL MECHANICAL NOTES
PHASE A (SHEET G-101)
PHASE C (SHEET G-101)
PHASE E (SHEET G-101)
PHASE F (SHEET G-101)
PHASE G (SHEET G-101)
PHASE H (SHEET G-101)
PHASE I (SHEET G-101)
PHASE J (SHEET G-101)
GENERAL NOTE
PHASE B (SHEET G-101)
37 75
1 - BIDDING REVISION 02-20-2026
1 1 1
02-06-2026
F G H J
K
24"ø CWS
"ø
C W
R
"ø
C W
S
RF
2(E)
RF
3(E)
FCU
2(E)
EF
2(E)
NEW 1-1/4" CHS/CHR AND
1" HWS/HWR FROM
EXISTING ABOVE NEW
CATWALK
1 2
6"ø DCW
6" ø
D C
W 6" ø D
C W
6" ø
D C
W
"ø
C H
S24 "ø
C H
S
24"ø CHS
24"ø CHS
FROM BASEMENT BELOW
AOM TN AN
E E
N
No. 19926PE
SC
L I E N DE
SS
R O
F E
P
LI O AN
NG
E
I
R
RAYMOND
E. DAWES
Project Number
Building Number
Drawing Number
Dwg.
DrawnCheckedDate
Location
Project TitleDrawing Title
COR / Project Engineer
CONSULTANTS:
DateRevisions:
VA FORM 08-6231
o n e e ig h th in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e in c h o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t th re e in c h e s o n e fo o t
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9 of
Office of Construction and Facilities Management
Phase
ARCHITECT/ENGINEER OF RECORD:
U.S. Department of Veterans Affairs
STAMP:
STRUCTURAL AND ELECTRICAL ENGINEERS
CITRINE LLC
710 KIPLING STREET, SUITE 406
LAKEWOOD, COLORADO 80215
PH: 720-556-0887
POC: DAVID KEATING
FIRE PROTECTION ENGINEER
OLSSON, INC.
601 P STREET, SUITE 200
LINCOLN, NEBRASKA 68508
PH: 402-474-6311
POC: TODD HENRY
POC PH: 913-318-4766
517 7TH STREET
RAPID CITY, SD 57701
PH: (605) 342-9470
POC: NAME
FFD PROJECT NO:
23.2730.M01
DES IGN INC
BUILDING 5
BUILDING 2
BUILDING 3
BUILDING 4
KEY PLAN
08/26/25
/6
/2
8:
:1
A M
08/26/2025
BUILDING 2 CHILLER ROOM MEZZANINE
LEVEL NEW MECHANICAL PLAN
M-103
VA SOUTHERN NEVADA
HEALTHCARE SYSTEM IMPROVE
CENTRAL UTILITY PLANT
PMRD
6900 NORTH PECOS ROAD
LAS VEGAS, NEVADA 89086
100% CONSTRUCTION
DOCUMENTS
19.2487.A01
1/4" = 1'-0"1 BUILDING 2 MEZZANINE NEW MECHANICAL PLAN
EXTEND NEW 1-1/4" CHS/CHR AND 1" HWS/HWR PIPING
FROM EXISTING ABOVE NEW CATWALK. SUPPORT AND
SEISMICALLY BRACE.
OFFSET NEW 1-1/4" CHS/CHR AND 1" HWS/HWR PIPING
DOWN BELOW CATWALK LEVEL AND RECONNECT TO
EXISTING PIPING.
NEW 6"∅ DCW FOR BACKUP COOLING TOWER WATER
MAKEUP BELOW CATWALKS FROM BASEMENT. TO BE
SUPPORTED AND SEISMICALLY BRACED BY EXISTING
AND NEW CATWALK STRUCTURES AND EXISTING ROOF
STRUCTURE.
NEW 6"∅ DCW FOR BACKUP COOLING TOWER WATER
MAKEUP DOWN TO EXISTING COOLING TOWER
CONDENSER WATER SUPPLY PIPING.
KEYED MECHANICAL NOTES
• COORDINATE WORK WITH PHASING PLAN ON SHEET
G-101.
• COORDINATE ALL WORK SHOWN WITH ALL RELEVANT
DISCIPLINES AND TRADES.
• EQUIPMENT, AND PIPING SHOWN IN GRAY ARE EXISTING
AND TO REMAIN.
• PROTECT EXISTING PIPING/EQUIPMENT FOR
RECONNECTION TO NEW PIPING.
• TAGS AND LABELS SHOWN ARE SPECIFIC TO THESE
PLANS. CONTRACTOR TO COORDINATE FINAL TAGS AND
LABELING REQUIREMENTS WITH THE VA.
• INSTALL ALL PIPING/COMPONENTS SO THAT THERE IS
ENOUGH SPACE TO INSULATE PIPING AND
COMPONENTS.
• CONTRACTOR TO PROVIDE LINE STOPS IN ANY PIPING
WHEN REPLACING SHUTOFF VALVES. IF SHUTOFF VALVE
DOES NOT CLOSE AND SEAL OFF PROPERLY, ALERT THE
COR FOR DIRECTION. COORDINATE ALL SHUTDOWN
REQUIREMENTS WITH THE COR.
GENERAL MECHANICAL NOTES
PHASE B (SHEET G-101)
PHASE I (SHEET G-101)
38 75
1 - BIDDING REVISION 02-06-2026
12-01-2025
01 32 16.15 - 1
SECTION 01 32 16.15
PROJECT SCHEDULES
(SMALL PROJECTS – DESIGN/BID/BUILD)
1.1 DESCRIPTION
A. The Contractor will develop a fully Resource loaded (cost) Network
Analysis System (NAS) plan/diagram and computer generated schedule demonstrating fulfillment of the entire contract requirements, will keep the plan and computer generated schedule up-to-date in accordance with the specification requirements of this section and will utilize the plan for scheduling, coordinating, mitigating and monitoring work under this contract (including all activities of subcontractors, equipment vendors and suppliers) and verification of every Periodic
Progress Schedule Updates and Progress Payment Submission of the work under this contract.
1.2 PROJECT SCHEDULER
A. The scheduler must have previous scheduling experience on at least three (3) projects of similar size and scope.
B. The scheduler must be prepared to discuss, in detail, the proposed sequence of work and methods of operation, and how that information will be communicated through the progress schedule at the preconstruction meeting.
C. The scheduler is required to attend a monthly schedule meeting and make site visits to prepare, develop, and maintain the progress schedules.
1.3 SUBMITTALS
A. Initial Schedule:
1. Submit an initial schedule within 7 calendar days after Notice to
Proceed (NTP).
a. Include full schedule details for the first 60 calendar days of work starting on the NTP date and show the schedule ending on or before the Contract Completion Date (CCD).
b. Provide a summary bar chart schedule (acceptable formats include, but are not limited to, Microsoft Excel, Microsoft Project, Oracle Primavera P6, and Gantt Chart).
c. Show the proposed sequence, durations, early and late start dates for major work activities.
d. Show the proposed calendar dates for starting and finishing initial contract activities including, but not limited to, set up
01 32 16.15 - 2 of construction site, site layouts, travel routes, waste, and staffing areas.
2. Conduct a schedule review meeting with the Government within 14 calendar days after NTP. At this meeting, plan to discuss the proposed schedule for the entire project, including both the detailed first 60-day period covered by the initial schedule as well as the following summary schedule. If deviations to the staging, phasing, or sequencing required by the contract documents are proposed, be prepared to discuss these deviations.
3. The Government will respond by approving the initial schedule, rejecting the schedule and identifying the reason for rejection, or by asking the contractor for additional information clarifying the proposed schedule activities and timelines.
4. The Government will use the approved initial schedule to monitor progress until the baseline schedule is approved.
5. The Government may withhold progress payments until the initial schedule is approved.
B. Schedule of Costs.
1. No more than 30 calendar days after receipt of the Notice to
Proceed, prepare and submit a schedule of costs to the Government for review, in accordance with the technical and schedule submittal requirements listed in this specification.
2. The approved Schedule of Costs will serve as a tool in addition to the required monthly schedule update to determine progress payments to the Contractor for work completed.
3. The costs shown on the Schedule of Costs must represent true costs and the work activities/events match the project schedule work activities/events. The VA Contracting Officers Representative (VA
COR) may require the Contractor to submit its original estimate sheets or other supporting documentation to substantiate the detailed makeup of the cost schedule.
4. The total costs of all work activities/events listed on the Schedule of Costs must equal the total contract price. The breakdown must include all line items specified in the contract and work activities shown on the schedule.
5. The Contractor is responsible for regularly updating the Schedule of
Costs to reflect any approved changes to the contract scope or cost structure. Updates must be submitted for approval to the Contracting
01 32 16.15 - 3
Officer Representative to ensure continued accuracy and compliance with contract requirements.
6. Failure to submit or maintain an accurate and approved Schedule of
Costs may result in delayed progress payments and potential penalties as outlined in the contract agreement.
7. All documentation related to the Schedule of Costs, including original estimate sheets and cost substantiation documents, must be maintained and made available for review upon request by the
Contracting Officer or VA COR.
C. Baseline Schedule.
1. No more than 30 calendar days after approval of the initial schedule, prepare and submit a baseline schedule to the Government for review, in accordance with the technical and schedule submittal requirements listed in this specification.
2. The Government will respond by accepting the baseline schedule, rejecting the schedule and identifying the reason for rejection, or by asking for more information.
3. Address the reasons for rejection or provide the information requested and resubmit the revised baseline schedule no more than 10 calendar days after the Government’s response.
4. The Government may withhold progress payments until the baseline schedule is approved.
5. No stored material work activities will be shown or approved be on the baseline schedule.
6. The Baseline Schedule Critical Path of the project shall be limited to:
a. No more than 20% of the work activities shall be on the critical and near-critical path(s). Critical path is defined as activities with zero (0) day total float. Near-Critical path(s) is defined as activities with one (1) to twenty (20) days of total float.
b. Multiple Critical paths will not be allowed.
7. The Baseline Schedule shall contain sufficient detail such that no more than 5% of work activities have durations exceeding 20 work days, in accordance with DCMA 14-point Schedule Assessment
Guidelines.
D. Monthly Schedule Update.
1. Prepare and submit a monthly schedule update to the Government that depicts the status of the project as of the end of the month, in
01 32 16.15 - 4 accordance with the technical and schedule submittal requirements listed in this specification.
2. The update must reflect a new data date, work performed up to, but not including, the new data date, and the plan for completing the project.
3. Submit the schedule update by the first Monday of the following month.
4. The Government may withhold progress payments until the monthly schedule update is approved.
5. Each monthly schedule update must be submitted with the associated schedule log.
E. Revised Schedule.
1. The Government has the right to request a revised schedule.
2. Circumstances leading to such a request include, but are not limited to:
a. A projected or forecasted delay to scheduled interim or project completion dates.
b. A significant difference between the actual sequence or duration of work and that depicted in the schedule.
3. Prepare and submit the revised schedule no more than 10 calendar days after the Government’s request in accordance with the technical and schedule submittal requirements listed in this specification.
4. The Government will respond by accepting the revised schedule, rejecting the schedule and identifying the reasons for rejection, or by requesting more information. Address the reasons for rejection or submit the information requested no more than 10 calendar days after the Government’s request.
5. The Government may withhold progress payments until the revised schedule is approved.
F. Final Schedule.
1. Within 30 calendar days of final acceptance of the project, submit a final schedule with actual start and finish dates for each activity.
2. Include with the submission a certification signed by a principal of the firm stating: “To the best of my knowledge, the enclosed final schedule reflects the actual start and finish dates of the activities contained herein.”
G. The Government’s approval of any schedule, whether initial, baseline, update, or revised, does not modify the contract or constitute
01 32 16.15 - 5 endorsement or validation by the Government of the Contractor's logic, activity durations, or assumptions in creating the schedule. By approving the schedule, the Government does not guarantee that the project can be performed or completed as scheduled. If the Contractor or the Government discover errors after the schedule has been approved, correct the error(s) in the next schedule submission.
1.4 WORK ACTIVITY/EVENT COST DATA
A. The Contractor shall cost load all work activities/events except procurement activities. The cumulative amount of all cost-loaded work activities/events (including alternates) shall equal the total contract price. Distribute overhead, profit, and general conditions proportionally across all work activities/events along the project's length (critical path). The contractor shall generate from this information cash flow curves indicating graphically the total percentage of work activity/event dollar value scheduled to be in place on early finish and late finish. These cash flow curves will be used by the Contracting Officer to assist him in determining approval or disapproval of the cost loading. Negative work activity/event cost data will not be acceptable, except on VA issued contract changes.
B. The Contractor shall cost load work activities/events for guarantee period services, test, balance and adjust various systems in accordance with the provisions in Article, FAR 52.232 – 5 (PAYMENT UNDER FIXED
PRICE CONSTRUCTION CONTRACTS) and VAAR 852.232 – Article 70 Without
NAS-CPMfor (PAYMENTS UNDER FIXED PRICE CONSTRUCTION).
C. In accordance with FAR 52.236 – 1 (PERFORMANCE OF WORK BY THE
CONTRACTOR), the Contractor shall submit, simultaneously with the cost per work activity/event of the construction schedule required by this
Section, a responsibility code for all activities/events of the project for which the Contractor's forces will perform the work.
D. The Contractor shall cost load work activities/events for all Bid
Items. The sum of each Bid Item work shall equal the value of the bid item in the Contractors' bid.
E. With prior written approval from the Contracting Officer, the
Contractor may request payment for suitably stored and maintained materials/equipment that conform to specifications and are ready for installation, in accordance with the provisions in VAAR 852.232 –
Article 70 Without NAS-CPMfor (PAYMENTS UNDER FIXED PRICE
CONSTRUCTION). Requests must include comprehensive documentation, such
01 32 16.15 - 6 as invoices, proof of payment, and evidence of secure storage with appropriate insurance.