Attachment R - Foundation Inspection Scope of Work.pdf
PDF 158 KB Posted
- Attached to
- Cumberland Communications Facility
- Solicitation number
- BPM057831
- Issued by
- Allegany County, Maryland
About this file
Foundation Inspection Scope of Work - CATS+ FA13 Tower Construction
This Attachment R is a foundational inspection and testing scope of work established by the Maryland Department of Information Technology (DoIT) for tower construction vendors performing work on CATS+ FA13 projects. The scope mandates that all concrete poured and foundation installations undergo comprehensive testing and inspections conducted by independent third parties to verify proper quality, strength, dimensions, rebar configuration, and soil compaction. All test results must be supplied, reviewed, and approved by DoIT prior to any structures being set on foundations, tower erection, or backfilling operations. The vendor must utilize Maryland State Highway Administration (SHA) approved concrete mixes per specification section 900.10.03 in the MD SHA grey book, with each concrete batch (6–9 cubic yards) accompanied by a corresponding batch report from the supplier included in closeout documentation.
The mandatory testing and inspection requirements include verification of excavated foundation dimensions by construction inspectors; compaction testing of tower foundation excavated materials per AASHTO T99 standards; bearing pressure testing of foundation subgrades per geotechnical specifications; verification of rebar size, dimension, grade, configuration, and layout prior to concrete pours; recording of ambient air temperature and weather conditions at time of delivery; concrete slump testing per AASHTO T119 for each continuously poured caisson section or every fifty cubic yards; concrete temperature measurement per AASHTO T309 standards; air entrainment testing per AASHTO T152 or T196 maintained at 5–8% or per designer specification; and compressive strength testing at both 7 and 28 days per AASHTO T23 standards with a minimum of one set of four cylinders per continuously poured section or every fifty cubic yards. Compressive strength must achieve a minimum of 4,000 PSI at 28 days or the foundation designer's specification, whichever is greater, with tower erection permitted only after 7-day tests meet requirements. Test cylinders must be cured on site with adequate insulation provided by the vendor as weather conditions dictate. Shelter foundations require a minimum of 3,000 PSI at 28 days and one set of four cylinders per shelter foundation, with the inspector authorized to halt work if specifications are not met.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT R – FOUNDATION INSPECTION SCOPE OF WORK
SUMMARY: Tower construction vendors shall incorporate the following series of tests and inspections to ensure proper quality/strength of all concrete poured and the proper foundation installation on all CATS+ FA13 jobs. These inspections shall also incorporate verification of foundation dimensions, rebar dimensions, rebar layout and soil compaction. Test results shall be supplied, reviewed and approved by DoIT prior to any structures being set on foundations, tower erection or backfilling operations. Field testing shall be conducted by an independent, third party.
DETAILS: Each concrete batch (6-9 cubic yards) shall have a corresponding batch report provided by the supplier. These shall be included in the closeout documentation. Batches shall be uniquely identified on the batch report. The vendor shall use MD SHA approved concrete mixes for all FA13 projects. Mix tables and more information on concrete specifications can be found in section 900.10.03 in the MD SHA grey book.
The following mandatory tests/inspections shall take place for the tower and shelter foundations:
1. Construction inspectors shall verify the excavated foundation dimensions are correct.
2. The compaction of the tower foundation excavated materials shall be tested in accordance with AASHTO T99 (Standard Proctor Test). Compaction results shall be in accordance with the tower foundation designer’s specification or the geotechnical report provided, whichever is greater. Excavated fill will only be used to backfill the foundation if they pass the compaction test.
3. The bearing pressure of the foundations’ sub grade shall be tested. Bearing results shall be in accordance with the foundation designer’s specifications or the geotechnical report provided, whichever is greater. In the event the vendor cannot meet the required bearing pressure, it shall solicit advice from the foundation designer, inspector and/or geotechnical engineer to achieve the desired results.
4. Construction inspectors shall verify the proper rebar size, dimension, grade, configuration, layout, fastener/wire ties and other provisions as specified by the foundation designer are correct prior to any concrete pours.
5. Ambient air temperature and general weather conditions shall be recorded and noted by the inspector. Readings shall be taken at the time of delivery.
6. Concrete slump shall be tested for each continuously poured section of caisson or every fifty
(50) cubic yards of concrete on a pad and pier foundation. The slump shall be tested in accordance with ASSHTO T119 testing standard. The slump shall meet the tower foundation designer’s specification. If none are noted, then the Slump will be measured in accordance with SHA Grey Book Specification 902.10.03, Chart A. Results shall be recorded and supplied prior to acceptance of the given foundation. Work may be halted if the slump is not deemed acceptable. Alternative slumps can be offered based on site or conditions such as pump requirements.
7. Concrete temperature shall be measured for each continuously poured section of a caisson or every fifty (50) cubic yards of concrete on a pad and pier foundation. Temperatures shall be tested in accordance with ASSHTO T309 testing standard. Temperature shall be in accordance with the foundation designer’s specification. If no specifications are supplied, then the temperature will be measured in accordance with SHA Grey Book Specification
902.10.03, Chart A. Results shall be recorded and supplied prior to acceptance of the given foundation.
8. Air entrainment shall be tested and documented in accordance with ASSHTO T152 or T196.
The results shall be documented for each continuously poured caisson or 50 cubic yards for a pad and pier foundation. Air content shall be within the foundation designer’s specification or no more than 5-8%.
9. Compressive strength shall be measured at 7 days after pour and 28 days after pour.
Compressive strength tests shall be tested in accordance with ASSHTO T23 testing standard. A minimum of one (1) set of four (4) cylinders shall be taken for each continuously poured section of caisson or every fifty (50) cubic yards of concrete on a pad and pier foundation. Compressive strength shall be a minimum of the tower foundation’s specification or 4000 psi at 28 days, whichever is greater. At least one cylinder per set shall be broken at
7 days and one at 28 days. If all 7 day sets have reached the required compressive strength, then back fill operations and/or tower erection can commence. 14 day tests can be conducted if the 7 day tests are not within specification to expedite construction. 28 day tests shall be conducted even if 7 day tests are deemed acceptable. Written results shall be provided to the State Project Manager prior to tower erection. Shelter foundations shall be at least 3000 psi or the shelter foundation designer’s requirements, whichever is greater, at 28 days. Shelter foundations shall require one (1) set of four (4) cylinders for both shelter foundations. Test cylinders shall be cured on site. As weather conditions dictate, the vendor shall provide a cure box to adequately insulate the test cylinders as they cure.
The inspector shall provide photographs if necessary. If specifications are not met, then the inspector has the authority to stop work until specifications are met.