This is a Past Performance Questionnaire template issued by the Air Force Civil Engineering Center Installations Directorate (AFCEC/CI) under Air Force Materiel Command (AFMC) for solicitation FA8903-27-R-0014, dated 21 October 2026. The questionnaire is designed to collect performance information from past customers and contracting officers who have worked with offerors bidding on Air Force Privatization Management Programs (PMP) and Housing, Enhanced Use Lease, Lodging, and Utility (HELU) Privatization Management contracts. These are long-term, cradle-to-grave Advisory & Assistance Services (A&AS) contracts for Asset, Acquisition, and Portfolio Management services supporting privatized Air Force housing and utility programs throughout the United States. Completed questionnaires must be submitted within 10 calendar days of receipt to Mark Ingle (mark.ingle.2@us.af.mil) and Michael I Grasso (michael.grasso.2@us.af.mil), the Contracting Officer.

The questionnaire requires respondents to rate contractor performance across multiple categories using a five-point scale (Exceptional, Very Good, Satisfactory, Marginal, Unsatisfactory, or Not Applicable). Evaluation categories include technical performance on housing, Enhanced Use Lease, and utility requirements; quality of technical data and reports; program management effectiveness; transition and phase-in capabilities; employee retention and attraction; small business participation compliance; and cost performance. Respondents must provide supporting information for each rating and identify their role, tenure on the contract, and position (e.g., Program Manager, Contracting Officer). The questionnaire also requests identification of the past contract, including contractor name and CAGE code, contract number, contract type, program title, period of performance, dollar value, description of work performed, and customer or agency information. A final section requests the respondent's overall assessment of whether they would award to the contractor again and solicits additional information relevant to government evaluation.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA8903-27-R-0014 21 Oct 2026 Attachment L-5 For Official Use Only When completed, this document is Source Selection Information IAW FAR 2.101 and 3.104.

Section L: Present/Past Performance Questionnaire The Air Force Civil Engineering Center Installations Directorate (AFCEC/CI) of the Air Force Material Command (AFMC) is in the process of competitively selecting a source(s) for Air Force (AF) Privatization Management Programs (PMP) and Housing, Enhanced Use Lease, Lodging and Utility (HELU) Privatization Management for long-term cradle to grave management of Advisory & Assistance Services (A&AS) in support of the AF privatized programs. This includes Asset, Acquisition and Portfolio Management services in support of HEU throughout the United States.

One of the considerations in proposal evaluation is the verification of the Offerors' past performance for Housing and Utility Privatization contracts or other work efforts which reflect the Offeror's ability to perform on the proposed effort. We depend on information received from organizations such as yours, which have had first-hand experience with the Offeror, for the evaluation of the Offeror's performance on those contracts or work efforts.

Our areas of interest regarding the Offeror are summarized in the enclosed questionnaire. In order to meet the acquisition milestones, we request your written response no later than 10 calendar days after your receipt of this letter. This schedule will allow us sufficient time to analyze the data prior to the start of negotiations.

To assist you in preparing your response and expediting your reply, submit the questionnaire electronically and e-mail to Mark Ingle, email: mark.ingle.2@us.af.mil and Michael I Grasso, email: michael.grasso.2@us.af.mil. Please call or email Michael I. Grasso, email: michael.grasso.2@us.af.mil, Contracting Officer at M: 210-395-8730/C; 210-347-9488, if you have any questions. Title of email: RFP FA8903-27-R-0014, Present/Past Performance Questionnaire. Your completed questionnaire will become a part of the official Source Selection records.

Your assistance is greatly appreciated and your prompt response will be one of the keys to the successful and timely completion of this Source Selection.

MICHAEL I GRASSO

Contracting Officer Date : 21 Oct 2026

1 Atch Past Performance Questionnaire

Section 1: Contract Identification

A. Contractor (Company/Division):

B. Contractor Cage Code:

C. Contract Number:

D. Contract Type (e.g., FFP, FPIF, CPIF, CPFF, etc.):

E. Program Title:

F. Brief Program Description:

G. Program Phase (e.g., Engineering & Manufacturing Development (EMD)):

H. Period of Performance

1. Original Schedule (assuming all options exercised):

Beginning Date _________ through ____________

2. Current Schedule (assuming all options exercised):

Beginning Date _________ through ____________

3. Reason for difference (if applicable):

I. Contract Dollar Value

1. Original maximum contract dollar value (assuming all options exercised): $

2. Current maximum contract dollar value (assuming all options exercised): $

3. Reasons for difference between original and current contract dollar value (if applicable):

J. Description of work performed:

K. For projects that are actively being performed, provide the percent complete as of the date of solicitation for this contract:

L. Was this a competitively awarded contract? ☐ Yes ☐ No

M. Contractor’s Role: ☐ Prime Contractor ☐ Subcontractor ☐ Key Personnel

Section 2: Customer or Agency Identification

A. Customer or agency name:

B. Customer or agency description (if applicable):

C. Geographic description of services under this contract (i.e., local, nationwide, worldwide, other Commands):

Section 3: Respondent Identification

A. Respondent’s name:

B. Respondent’s title:

C. Respondent’s phone number / fax number / e-mail address:

D. Respondent’s position (e.g., Program Manager, PCO/ACO, etc.):

E. Length of time (number of years/months) respondent worked on subject contract and description of responsibility/position/role:

F. Other suggested points of contact:

Section 4: Performance Information

In the tables below, indicate your rating for the contractor’s performance by placing an “X” in the appropriate block to the right of each question. Provide supporting information for each response in the space provided. Attach additional pages if more space is needed. The performance rating scale is defined as follows:

Code Performance Rating

EEXCEPTIONAL –. During the contract period, contractor performance is meeting (or met) all
contract requirements and consistently exceeding (or exceeded) many. Very few, if any, minor
problems encountered. Contractor took immediate and effective corrective action.

V VERY GOOD – During the contract period, contractor is meeting (or met) all contract requirements and consistently exceeding (or exceeded) some. Some minor problems encountered. Contractor took timely corrective action.

S SATISFACTORY – During the contract period, contractor performance is meeting (or met) all contract requirements. For any problems encountered, contractor took effective corrective action.

M MARGINAL – During the contract period, contractor performance is not meeting (or did not meet) some contract requirements. For problems encountered, corrective action appeared only marginally effective, not effective, or not fully implemented. Customer involvement was required.

UUNSATISFACTORY – During the contract period, contractor performance is failing (or fail) to
meet most contract requirements. Serious problems encountered Corrective actions were either
ineffective or non-existent. Extensive Customer oversight and involvement was required.

N/A NOT APPLICABLE – Unable to provide a rating. Contract did not include performance for this aspect. Do not know.

Technical Performance
E
V
S
M
U
N/A

T1. How well did the contractor meet the technical requirements of the PWS for:

-Housing -EUL -UP

SUPPORTING INFORMATION:

T2. How was the quality/integrity of technical data/report preparation efforts?

T3. How accurate, complete and on time were the contractors submitted data/reports?

T4. How well did the contractor provide innovative solutions to the identified issues from the data/reports?

T5. How well did the contractor understand/comply with customer objectives and technical requirements?

Program Management
E
V
S
M
U
N/A

P1. How effective was overall contract management (including ability to effectively lead, manage, control and deliver on-time)?

P2. How reasonable and cooperative was the contractor when dealing with program interested parties, (i.e. Government, public sector) including the ability to successfully resolve disagreements/disputes?

P3. How timely and effectively did the contractor resolve contract problems without extensive customer guidance?

P4. How well did the contractor manage quality/effectiveness of subcontracted efforts?

P5. How effective was the contractor’s proposed alternative method/processes that provided cost savings, enhanced efficiency or quality?

P6. To what degree did the contractor implement responsive/flexible processes to improve quality and timeliness of support?

P7. How effective was the contractor in developing/implementing strategies to coordinate, gather and analyze data from multiple stakeholders and report to each management level?

P8. How effective was the contractor in providing real time access and dissemination of program/project data and documents?

Transition / Phase-in
E
V
S
M
U
N/A

TP1. How smoothly did the contractor transition resources and personnel?

TP2. How effective was the contractor in maintaining continuity of mission support while transitioning/phasing in resources and personnel to support other efforts?

Employee Retention / Attraction
E
V
S
M
U
N/A

E1. How effectively was the contractor able to hire/apply a qualified workforce to this effort?

E2. How effectively was the contractor able to retain a qualified workforce on this effort?

Small and Small Disadvantaged Business Participation
E
V
S
M
U
N/A

S1. If the contract included FAR 52.219-9, to what degree was the contractor able to meet or exceed small business and small disadvantaged business goals set forth in the approved subcontracting plan?

(Please state if FAR 52.219-9 was not included in the contract)

S2. If the contract included FAR 52.219-8, how effectively did the contractor manage small business participation to meet technical performance?

(Please state if FAR 52.219-8 was not included in the contract)

Cost Performance
E
V
S
M
U
N/A

C1. How well did the contractor meet forecasted costs and perform within contract costs?

C2. How successfully did the contractor alert the Government of unforeseen costs before they occurred?

Government Contracts Only: Was this contract partially or completely terminated for default or convenience, or are there any pending terminations?

☐ Yes ☐ Default ☐ Convenience ☐ Pending Terminations ☐ No

If yes, please explain (e.g., inability to meet cost, performance, or delivery schedules).

SECTION 5: GENERAL COMMENT

Given what I know today about the contractor’s ability to execute what he promised in his proposal, I [ click and select an item ] award to him today given that I had a choice.

REMARKS:

Is there any additional information (positive or negative) regarding this contractor that the Government should be aware of?

Is there anyone else we should contact regarding this contract?

REFERENCE Name
Phone
Email

[click and pick the date]

Respondent’s Signature Date

Thank you for your prompt response and assistance!

Please return this completed questionnaire to:

E-Mail to: Linda L. Cavazos; linda.cavazos@us.af.mil Michael Grasso; michael.grasso.3@us.af.mil

For Official Use Only Page 1 of 8

File details come from the government source that posted it. Updated .