Attachment J-3 Key Requirements Verification Matrix Rev A.xlsx

XLSX spreadsheet 11 KB Posted

Attached to
Navy Cable Ship Replacement T-ARC(X) Federal contract opportunity
Solicitation number
N00024-20-R-2211
Issued by
Department of the Navy Naval Sea Systems Command

About this file

This document contains an attachment with key requirements for a Navy cable ship replacement solicitation. The attachment lists over 20 technical requirements the Navy is seeking to procure including a minimum bollard pull of 120 metric tons, sustained speed of 15 knots, unrefueled range of 10,000 nautical miles at 15 knots, accommodations, bubble sweepdown flow, ice class, and seakeeping capabilities for cable operations, ROVs, sea plows and moonpools through sea states up to 5. Additional requirements include diesel engine emissions standards, dynamic positioning capabilities in redundant configurations through sea state 5, mission sonar systems, cable pathways, capacities for main and spare cable tanks, capabilities for cable deployment and recovery equipment, sea plow burial depth and speed, and ROV burial depth and speed. Interested parties should respond to solicitation N00024-20-R-2211 for the Navy Cable Ship Replacement T-ARC(X) program by submitting proposals no later than 2:00 PM EST on August 18, 2020, with no extensions permitted due to mission requirements.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Attachment J-3 Key Requirements Verification Matrix
Requirement NameRequirement DescriptionSpec SectionContractor VerificationVerification MethodRelated DI
Bollard pullAt least 120 MT3.070.3
Sustained Speed15 knots3.070.3
Unrefueled Range10,000 nm at 15 knots3.070.3
AccommodationsTotal number of accommodations3.070.3
Bubble SweepdownFlow streamlines requirement with respect to the MBSS-DW3.073.3
Ice ClassABS Baltic 1C3.070.12
Seakeeping - Cable OpsCable operations through SS53.079
Seakeeping - ROVROV LARS through SS53.079, 3.573.5.3
Seakeeping - Sea PlowSea Plow LARS through SS53.079, 3.573.5.4
Seakeeping - MoonpoolMoonpool UUV and Package LARS through SS3 and Package Heavy Lift through SS33.079, 3.573.5.5, 3.573.5.6
Diesel engine emissionsEmission requirements per regulatory bodies3.233
DP Capability - EnvironmentPosition keeping and trackline through SS53.420
DP Capability - RedundancyABS DPS-23.420
Mission Sonar SystemsMission sonar system transducer arrangements and sonar self-noise levels3.073.2 and 3.461
Cable PathwaysPathway to/from each cable tank to/from each of the three main CHE (two CDE and one LCE)3.595.1.1
Cable Tank CapacityMain cable tanks at least 3,200 m3 and 4,812 MT; Spare cable tanks at least 500 m3 and 688 MT3.595.2
CDE CapabilityCDE overboarding tension at least 50 MT; Hold two simultaneously up to 40 MT each3.595.5.1
LCE Capability25,000 lb tension3.595.5.2
Sea Plow Capability3m burial to 1,500 m depth up to 1.5 km/hr3.595.6
ROV Capability1m burial to 3,000 m depth up to 400 m/hr3.595.7
Moonpool SizeSized to accommodate payloads3.595.9

File details come from the government source that posted it. Updated .