Attachment J-2 T-ARC(X) Data Requirements List 9 May 2020.docx

DOCX document 173 KB Posted

Attached to
Navy Cable Ship Replacement T-ARC(X) Federal contract opportunity
Solicitation number
N00024-20-R-2211
Issued by
Department of the Navy Naval Sea Systems Command

About this file

This document package includes an attachment and federal contract opportunity related to the Navy Cable Ship Replacement T-ARC(X) program.

The attachment is a Data Requirements List that specifies 139 data items the contractor must submit at various stages of the program. Key deliverables include design reviews, analyses, drawings, reports and other documentation related to ship design, systems design, regulatory compliance, and program management. Submittal schedules, distribution requirements and other administrative details are provided for each data item.

The federal contract opportunity is a Request for Proposal for Phase I of the program. Interested offerors are requested to respond by 2:00 PM EST on August 18, 2020 with no extensions allowed due to mission requirements. The solicitation is issued by the Department of the Navy Naval Sea Systems Command for an indefinite-delivery/indefinite-quantity contract.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT/PR NO.: N00024-20-R-2211

ATTACHMENT J-2

Navy Cable Ship, TARC(X)

DATA REQUIREMENTS LIST

FOR

INDUSTRY STUDIES

06 May 2020

Rev. -

“DISTRIBUTION STATEMENT D. Distribution authorized to the Department of Defense and U.S. DoD contractors only (Critical Technology) (01 October 2017). Other requests for this document shall be referred to PEO Ships PMS325, Washington Navy Yard, 1333 Isaac Hull Ave. SE, Washington, DC 20376-2101.”

WARNING - This document contains technical data whose export is restricted by the Arms Export Control Act (Title 22, U.S.C. Sec 2751 et seq.) or the Export Administration Act of 1979, as amended, Title 50, U.S.C., App 2401, et seq. Violations of these export laws are subject to severe criminal penalties. Disseminate per provisions of OPNAVINST 5510.161, Withholding of Unclassified Technical Data from Public Disclosure, 29 July 1985.

Navy Cable Ship, T-ARC(X)

INDUSTRY STUDIES

DESTRUCTION NOTICE - Classified Information, destroy in accordance with the SECNAV M-5510.36, DON Information Security Program June 2006 or DoD 5220.22-M, National Industrial Security Program Operating Manual (February 2006 with Change 1 of March 28, 2013. Controlled Unclassified Information (CUI), (e.g., FOUO, Distribution Statement controlled) shall be destroyed by any methods that will prevent disclosure of contents or reconstruction of the document.

x

DATA REQUIREMENTS LIST

FOREWORD

The Data Requirements List (DRL) identifies Contractor Data Item requirements in support of the Navy Cable Ship, T-ARC(X) Industry Studies. This Foreword provides general guidance to Contractor personnel and is intended to clarify issues of an administrative and procedural nature that are not otherwise addressed. Emergent issues that are not addressed herein or otherwise provided for in source documents should be referred to PEO SHIPS, PMS325.

Detailed information concerning the format and content of the data item requirements is provided in the Glossary. A complete listing of addressees for this DRL is provided following the Glossary.

I. CONTENT AND FORMAT OF SUBMITTALS

Data item submittals shall be prepared in the Contractor’s format, unless otherwise specified in the specific DRL. Data item submittals shall be clear, legible, and prepared in the English language. Data items shall be assigned a sequential one-character revision letter to reflect changes from the previous submittal. Revisions of submittals shall include a Revision Table describing revisions made in a sequential order and identifying effected area of the Drawing, or be prepared in a “redline” format to allow for identification of changes from the previous submittal. Data items shall include a list of abbreviations and a legend for symbols. A table of references shall also be provided. Symbols shall be in accordance with ASME Y14.100.

Electronic media and digital files shall be compatible with computers using Windows 10™ operating system, unless otherwise specified. The following electronic format products shall be utilized: Microsoft Office 2016 and/or Office 365 ™, Microsoft Project 2016 ™, Adobe Acrobat Professional DC ™, standard zip files openable by Windows 10™, and AutoCAD 2018™ unless otherwise specified. Alternative software or versions of software may be used if agreed to between the Government and the Contractor. Electronic files shall not be password protected.

Drawings shall be submitted in AutoCAD format and in PDF. Other documents shall not be submitted in PDF format unless specified within. Drawings shall not be submitted in “read only” formats. All engineering drawings and associated lists shall be as identified in TYPES AND APPLICATIONS OF ENGINEERING DRAWINGS, ASME Y14.24 and ASSOCIATED LISTS, ASME Y14.34M. Each drawing shall be assigned a Contractor drawing number.

Each data item shall be provided with a separate letter of transmittal. Multiple drawings may be submitted under the same letter of transmittal; however, subtitles, revision designations, and sheet quantities shall be identified. Each letter of transmittal shall be assigned a trackable correspondence serial number. Each letter of transmittal shall provide the following information:

1. Contractor's name, correspondence serial number, and actual date of transmittal.

2. The contract number, Data Item number and Data Item Title.

3. A revision letter and respective revision date.

4. Digital file name and respective digital file date.

5. Each transmittal letter shall provide a brief explanation of the submittal, the reason for a document’s change, or a more detailed discussion shall be included in the content of the submittal.

In accordance with DoDD 5230.24 and DoDD 5230.25, each Data Item submittal shall include Distribution Statement D at the bottom of each cover sheet as follows:

“DISTRIBUTION STATEMENT D. Distribution authorized to the Department of Defense and U.S. DoD contractors only (Critical Technology) (01October 2017). Other requests for this document shall be referred to PEO Ships PMS325, Washington Navy Yard, 1333 Isaac Hull Ave. SE, Washington, DC 20376-2101.”

II. QUALITY CONTROL

The Contractor shall maintain internal quality control to ensure submittals are complete and adequate and shall not rely on Government review comments to ensure the technical accuracy of data.

III. ACRONYMS

An alphabetical list of acronyms follows. The list includes those acronyms used most frequently in the Data Requirements List.

ABS
American Bureau of Shipping
ATSC
Advanced Television Systems Committee
CDE
Cable Drum Engine
CFD
Computational Fluid Dynamics
CLIN
Contract Line Item Number
CPCP
Corrosion Prevention and Control Plan
CUI
Controlled Unclassified Information
DAC
Days After Contract
DAOE
Days After Option Exercised
DARC
Days After Receipt of Comments
DD&C
Detail Design and Construction
DDS
Design Data Sheet
DMA
Design Maturity Assessment
DPS
Dynamic Positioning System
DPT
Days Prior To
DR
Design Review
DRL
Data Requirements List
EPLA
Electric Plant Load Analysis
ESWBS
Expanded Ship Work Breakdown Structure
FOUO
For Official Use Only
FP
Forward Perpendicular
GFM
Government Furnished Material
HP
Horsepower
HVAC
Heating, Ventilation, Air Conditioning
IACMS
Integrated Alarm Control Monitoring System
ICES
International Council for the Exploration of the Sea
IDES
Integrated Digital Environment Site
IGES
Initial Graphics Exchange Specification
IPR
In-Process Review
IPS
Integrated Power System
LARS
Launch and Recovery System
LBP
Length Between Perpendiculars
LCE
Linear Cable Engine
LOA
Length Overall
MBSS-DW
Multibeam Survey System - Deep Water
MCS
Machinery Control System
MEL
Major Equipment List
MSC
Military Sealift Command
MTEXT
Multiline Text
NAVSEA
Naval Sea Command
NLT
No Later Than
OEM
Original Equipment Manufacturer/Manufacturing
PAC
Post Award Conference
PD
Preliminary Design
PIIN
Procurement Instrument Identification Number
PR
Purchase Request
R/ASR
Revisions As Required
RFP
Request for Proposal
RP
Recommended Practice
SAWE
Society of Allied Weight Engineers
SCR
Specification Change Recommendation
SOW
Statement of Work
SSV
Single System Vendor
SWBS
Ship Work Breakdown Structure
TBD
To Be Determined
T&T
Test and Trials
TT
TRUETYPE
WBS
Work Breakdown Structure

IV. General Data Requirements

Drawings shall be prepared in electronic format as specified herein:

Drawings shall be submitted in AutoCAD© 2018.dwg format and shall be backwards compatible with AutoCAD 2013©. Drawing text font shall be TRUETYPE (TT) RomanS_IV25 and shall be multiline-text (MTEXT), including text in tables and lists. Ship object lines shall be created in "Model Space" at full scale. "Paper Space" shall be used for formats, title blocks, scaled views, revisions and general notes. Viewports shall be placed on one layer and locked prior to submittal to the Government. The Contractor shall identify the drawing layering convention used in order to identify the status of each layer, such as, on, off, or locked, as applicable. AutoCAD data shall be primarily presented in 2-D format. 3D views may be utilized where feasible. Paper Space drawing sheets shall have a white background with black format blocks, borders, and tables and black text, except where otherwise approved by the Government. Line types shall be continuous, except where dashed or phantom are necessary to clearly differentiate general structure and machinery/equipment and furniture arrangements. Piping systems shall each have a separate color, line type, and layer when depicted in the same drawing.

Drawings shall be provided with the standard letter heights outlined in Table IV.1 below.

Table IV.1 – Drawing Letter Heights and Sizes

USE
LETTER HEIGHTS, INCHES
DRAWINGS SIZES
Size A drawings; Drawing Title
MS Word 16 point font or AutoCAD 0.16
Size A
Size A drawings; Size, Cage Code, SWBS Drawing Number, Revision in title block, and general text
MS Word 12 point font or AutoCAD 0.12
Size A
Size A drawings; text inside tables
MS Word 10 point font or AutoCAD 0.10
Size A
Drawing Title, Size, Cage Code, SWBS, Drawing Number, and Revision in title block
0.188
All larger than Size A
Ship Name and Number, Scale, Drawings Type, Sheet Numbers, Approval Signatures and Dates in title block
0.125
Section and Tabulation Letters
0.240
Zone Letters and Numericals in border
0.175
Dimensions, Tolerances, Limits, Notes, Subtitles for Special Views, Tables, Revisions and Zone Letters for the body of drawings
0.125
Up to and including Size B
0.150
All larger than Size B
All other Characters
0.125
All larger than Size A

Appropriately plotted PDF Drawings and their associated lists shall be in accordance with sizes ANSI/ASME Y14.1 for Sizes A, B, F or H (where necessary to appropriately depict drawings). Drawings shall also be submitted as a PDF file in Black and White Monochrome, unless otherwise specified. All AutoCAD and PDF drawings, and all other documents shall not be submitted in “read only” formats. Each drawing shall be a graphical representation of an item, components or a system, based on a set of requirements. Drawings shall identify revisions, approval signatures, and issue dates. Drawings shall be capable of being used to maintain control of an item’s configuration by documenting applicable changes.

Drawings shall include graphics, supporting calculations, associated lists, revisions, and shall include but not be limited to: Title Block, Contractor Approval Block (when applicable), Drawing Border and Zone Markings, References, General Notes and Special Notes, Revision Block, List of Symbols, List of Abbreviations, Distribution Statement, Scale Bar, Frame Spacing, Plan/Elevation/Sections Views (Unless otherwise approved), Preliminary List of Materials/ Bill of Materials, “Salient Characteristics”, Preliminary System Design Data Table (Where Applicable), Preliminary Pump Data Table (Where applicable), equipment lists, weights, etc.

Drawings shall identify Contractor drawing numbers and shall use a three-digit SWBS at the beginning of the Drawing number.

Additional requirements are provided in applicable data items.

GLOSSARY

The items listed below are explanations of the headings and blocks on the Data Requirements List (DRL) and other terms used in this attachment.

1.PROGRAM NAME: The name of the program.
2.DRL PHASE: The acquisition phase of the program
3.CONTRACT/PR NO.: The Procurement Instrument Identification Number (PIIN) (i.e., the contract number, Purchase Request (PR) number, the Request for Proposal (RFP) number, or other appropriate designator).
4.CLIN: The Contract Line Item Number (CLIN) that is associated with the DRL.
5.CONTRACTOR: The Contractor's name.
6.PREPARED AND APPROVED BY: The name and organization responsible for preparation and approval of the data items.
7.DATE: The date the data item was signed by the Government Data Manager.
8.BLOCK 1-DATA ITEM NO.: An identification number to support each data item identified in the contract.
9.BLOCK 2-DATA ITEM TITLE: The title of the data item.
10.BLOCK 3-REFERENCE: The specific location within the contract which contains the tasking that generates a requirement for the data item.
11.BLOCK 4-DATA DESCRIPTION: Details regarding the content and format characteristics of the data item submittal are described in this block.
12.BLOCK 5-REVIEW REQUIREMENTS: The Government will review each Contractor submittal. The Government will not be approving Contractor deliverables, but reserves the right to provide comments, if necessary. The Government may elect not to submit review comments.
13.BLOCK 6-SUBMITTAL SCHEDULE: The scheduled date for initial data submission, incremental submittals, and re-submittals, as specified. In addition, details regarding Data Item submittal requirements are also included. Submittal dates are often based on contract events. Days are calendar days. Where the scheduled date for data submission falls on a Saturday, Sunday or Federal Government holiday, the submission due date shall be the following Government working day. If no changes have occurred to an incremental submission, a negative reply shall be provided. Revisions shall incorporate the resolution of Government comments.
14.BLOCK 7-DISTRIBUTION: The addressees and the number of copies to be provided for the applicable data item are provided in this block. Addressees’ Email addresses are provided in the Addressee Listing which follows. All copies shall be the soft versions provided to the PMS325 Integrated Digital Environment Site (IDES).

ADDRESSEE LISTING

ADDRESSEE INTRANET ADDRESSEE

PMS325PME www.pmses.navy.mil

OR

COMMANDER
NAVAL SEA SYSTEMS COMMAND
1333 ISSAC HULL AVENUE, S.E.
WASHINGTON NAVY YARD, DC 20376-2020
ATTN: (PMS325U)

EMAIL (To be provided after Contract Award)

15. SALIENT CHARACTERISTICS: Those particular characteristics that specifically describe the essential physical and functional features of the material or service required. They are features that are identified in the specifications as a mandatory requirement that a proposed "equal" product or material must possess.

Change Record Revision Number

Date
Change

Table of Contents

Data Item Number
Contract Reference
Data Item

Titles and Subtitles Change Status

A001
C.3.2.1
POST AWARD CONFERENCE AGENDA, PRESENTATION, AND MINUTES
BASIC
A002
C.3.2.2
DESIGN REVIEW AGENDAS, PRESENTATIONS, AND MINUTES AND TECHNICAL EXCHANGE MEETING MINUTES
BASIC
A003
C.3.3
MANAGEMENT PLAN
BASIC
A004
C.3.3
MASTER SCHEDULE
BASIC
A005
C.3.4
REGULATORY BODY COMMUNICATIONS AND CORRESPONDENCE
BASIC
A006
C.3.4.1
BASELINE DESIGN DESCRIPTION REPORT
BASIC
A007
C.3.4.1.1
REGULATORY GAP ANALYSIS REPORT
BASIC
A008
C.3.4.1.2
EMERGENT REGULATIONS STUDY REPORT
BASIC
A009
C.3.4.1.2
CABLE STOWAGE AND HANDLING STUDY
BASIC
A009-01
C.3.4.2.1
CABLE STOWAGE AND HANDLING STUDY REPORT
BASIC
A009-02
C.3.4.2.1
CABLE HANDLING AND STOWAGE LOCATION
BASIC
A009-03
C.3.4.2.1
CABLE GEAR STOWAGE AND HANDLING DRAWING
BASIC
A010
C.3.4.2.2
SEA PLOW SYSTEM STUDY
BASIC
A010-01
C.3.4.2.2
SEA PLOW SYSTEM STUDY REPORT
BASIC
A010-02
C.3.4.2.2
SEA PLOW SYSTEM ARRANGEMENT
BASIC
A011
C.3.4.2.3
ROV SYSTEM STUDY
BASIC
A011-01
C.3.4.2.3
ROV SYSTEM STUDY REPORT
BASIC
A011-02
C.3.4.2.3
ROV SYSTEM ARRANGEMENT
BASIC
A012
C.3.4.2.4
MOONPOOL STUDY
BASIC
A012-01
C.3.4.2.4
MOONPOOL STUDY REPORT
BASIC
A012-02
C.3.4.2.4
MOONPOOL ARRANGEMENT
BASIC
A012-03
C.3.4.2.4
MOONPOOL LARS ARRANGEMENT
BASIC
A013
C.3.4.2.5
INTEGRATION STUDY REPORT
BASIC
A014
C.3.4.2.6
OBJECTIVE TRADE STUDIES
BASIC
A014-01
C.3.4.2.6.1
UNREFUELED RANGE OBJECTIVE TRADE STUDY REPORT
BASIC
A014-02
C.3.4.2.6.2
DRY MOONPOOL OBJECTIVE TRADE STUDY REPORT
BASIC
A014-03
C.3.4.2.6.3
SEA STATE 5 MOONPOOL OBJECTIVE TRADE STUDY REPORT
BASIC
A015
C.3.4.3.1
SPECIFICATION CHANGE RECOMMENDATIONS
BASIC
A016
C.3.4.3.2
AFFOERDABILITY STUDY REPORT
BASIC
A017
C.3.4.4.2
DRAWINGS
BASIC
A017-01
C.3.4.4.2
GENERAL ARRANGEMENT
BASIC
A017-02
C.3.4.4.2
HULL LINES DRAWING AND OFFSETS DATABASE
BASIC
A017-03
C.3.4.4.2
APPENDAGE DRAWING
BASIC
A017-04
C.3.4.4.2
MIDSHIP SECTION DRAWING
BASIC
A017-05
C.3.4.4.2
HULL DECK, PLATFORM AND LONGITUDINAL BULKHEAD AND SUPERSTRUCTURE SCANTLING DRAWINGS
BASIC
A017-06
C.3.4.4.2
SONAR SYSTEMS ARRANGEMENT
BASIC
A017-07
C.3.4.4.2
DECK SYSTEMS ARRANGEMENT
BASIC
A018
C.3.4.4.3
AREA/VOLUME AND TANKAGE REPORT
BASIC
A019
C.3.4.4.4
HABITABILITY AND SPECIAL PURPOSE SPACES DESIGN REPORT
BASIC
A020
C.3.4.4.5
WEIGHT CONTROL PLAN
BASIC
A021
C.3.4.4.5
WEIGHT ESTIMATE
BASIC
A022
C.3.4.4.5
INTACT AND DAMAGE STABILITY REPORT
BASIC
A023
C.3.4.4.6
SPEED AND POWER REPORT
BASIC
A024
C.3.4.4.6
SEAKEEPING PERFORMANCE REPORT
BASIC
A025
C.3.4.4.6
MANEUVERING PERFORMANCE REPORT
BASIC
A026
C.3.4.4.6
DYNAMIC POSITIONING SYSTEM PERFORMANCE REPORT
BASIC
A027
C.3.4.4.6
BUBBLE SWEEPDOWN COMPUTATIONAL FLUID DYNAMICS REPORT
BASIC
A028
C.3.4.4.7
MODEL TEST PLAN
BASIC
A029
C.3.4.4.7
MODEL TEST REPORTS
BASIC
A030
C.3.4.4.7
MODEL TEST DATA, VIDEOS, AND PHOTOGRAPHS
BASIC
A031
C.3.4.4.8
HULL GIRDER LONGITUDINAL STRENGTH ANALYSIS REPORT
BASIC
A032
C.3.4.4.8
STRUCTURAL DESIGN CRITERIA REPORT
BASIC
A033
C.3.4.4.9
MAIN MACHINERY STUDY
BASIC
A033-01
C.3.4.4.9
MAIN MACHINERY STUDY REPORT
BASIC
A033-02
C.3.4.4.9
MACHINERY SPACE ARRANGEMENT
BASIC
A033-03
C.3.4.4.9
MAJOR EQUIPMENT LIST
BASIC
A033-04
C.3.4.4.9
ELECTRIC PLANT LOAD ANALYSIS
BASIC
A033-05
C.3.4.4.9
ELECTRICAL ONE-LINE BLOCK DIAGRAM
BASIC
A033-06
C.3.4.4.9
ENDURANCE AND ANNUAL FUEL CONSUMPTION CALCULATIONS
BASIC
A034
C.3.4.4.10
AUXILIARY, FIREFIGHTING, AND HVAC SYSTEMS DESIGN REPORT
BASIC
A035
C.3.4.4.11
NOISE CONTROL APPROACH REPORT
BASIC
A036
C.3.4.4.12
CORROSION PREVENTION AND CONTROL PLAN
BASIC
A037
C.3.4.4.13
DESIGN SUMMARY REPORT
BASIC
A038
C.3.4.4.14
COST ESTIMATES
BASIC
A039
C.3.4.4.15
NOTIONAL DETAIL DESIGN & CONSTRUCTION SCHEDULE
BASIC
BLOCK 1-DATA ITEM NO.:
A001
BLOCK 2-DATA ITEM TITLE:
POST AWARD CONFERENCE AGENDA, PRESENTATION, AND

MINUTES

BLOCK 3-REFERENCE:
SOW SEC C.3.2.1

BLOCK 4-DATA DESCRIPTION:

1. The Post Award Conference (PAC) Agenda shall identify the meeting name, date, time, and location of the PAC. Materials to be presented during the PAC shall be provided with the agenda. The agenda and presentation shall include as a minimum a discussion of the following:

a. Introductions

b. Organizations and Points of Contact

1. All major organizations involved in the contract (such as PEO SHIPS, NAVSEA, Contractor, Design Agent (if used), and others).

2. Roles and Responsibilities of Organizations and Points of Contact.

c. Program Overview

1. Schedule of Industry Studies Conferences and Reviews.

2. Contractor Facilities Access Control.

3. Model Testing.

4. Government Expectations.

5. Contractor Expectations.

d. Program Administration

1. Management.

2. Contracts Administration.

e. Communications

1. Authorized Government Representatives.

2. Authorized Contractor Representatives.

3. Web-based Project Management System.

4. Email and Letter Correspondence.

5. Regulatory Body Correspondence.

6. Submission of Data Requirements List.

f. Action Item Review

g. Conclusion

2. The PAC Minutes shall identify date, time, and location of the PAC and a chronological listing of each topic discussed. The minutes shall include applicable discussions, concerns, action items assigned and completed, and a list of the documentation discussed. A list of attendees with contact information shall be included. Copies of each presentation or document reviewed at the conference shall also be included and identified in the minutes by document name, document revision, document date, and the digital file name and date.

BLOCK 5-REVIEW REQ.:

Allow 3 days for Government review and comment.

BLOCK 6-SUBMITTAL SCHEDULE:

NLT 7 DPT PAC; R/ASR 3 DARC. Draft of materials to be presented during the PAC shall be provided with the agenda; Minutes and final presentation materials to be submitted NLT 7 days after the Post Award Conference; R/ASR NLT 7 DARC. Revisions shall incorporate resolution of Government comments.

BLOCK 7-DISTRIBUTION:
Addressee
QTY
PMS325PME
1

Navy Cable Ship, T-ARC(X)

INDUSTRY STUDIES DATA REQUIREMENTS

CONTRACT NO: N00024-20-R-2211 CLIN: 0001/0002 CONTRACTOR: TBD

Reviewed and approved by DIEGO KING, Data Manager PMS325.06 May 2020
BLOCK 1-DATA ITEM NO.:
A002
BLOCK 2-DATA ITEM TITLE:
DESIGN REVIEW AGENDAS, PRESENTATIONS, AND MINUTES AND TECHNICAL EXCHANGE MEETING MINUTES
BLOCK 3-REFERENCE:
SOW SEC C.3.2.2

BLOCK 4-DATA DESCRIPTION:

1. Design Review (DR) Agendas shall identify the meeting name, date, time, and location of each DR. Drafts of materials to be presented during each DR meeting shall be provided with the agenda.

2. DR Agendas and Presentations shall provide information regarding risks, potential issues and decisions. Information regarding ship design status and results shall also be discussed. Items that will be updated prior to the next DR shall also be discussed.

3. The Design Review Agendas and Presentations shall include discussion on the following topics, as applicable.

a. Updated Industry Studies Master Schedule.

b. Detailed status of the evolving design.

c. Primary design drivers, constraints and other issues that are influencing the ship design

d. Risk review including mitigation plans for all moderate and high risks.

e. Key Requirements Verification Matrix status. Show how design is meeting key requirements as shown in Attachment J-3.

f. System Specification requirements. Address assumptions and/or interpretations related to omissions, inconsistencies, and conflicts, if any, in the System Specification.

g. Efforts accomplished by subcontractors including the design agent (if used), Propulsion Single Systems Vendor (SSV), Cable System Consultant, and Noise Control Consultant.

h. Model Test Status.

i. American Bureau of Shipping (ABS) status, including other regulatory body issues.

j. Technical analyses, tradeoffs, discussions of supporting calculations, and resulting derived design details.

k. Supporting data required by the Industry Studies DRLs, Attachment J-2.

l. Design Maturity Assessment as defined by the Design Summary Report (final DR only).

4. DR Minutes shall identify date, time, and location of the applicable review and a chronological listing of each topic discussed. The minutes shall include applicable discussions, concerns, action items assigned and completed, and a list of the documentation discussed. A list of attendees with contact information shall be included. Copies of each presentation or document reviewed shall also be included and identified in the minutes by document name, document revision, document date, and the digital file name and date.

5. Technical Exchange Meeting Minutes shall identify date, time, and location of the applicable review and a chronological listing of each topic discussed. The minutes shall include applicable discussions, concerns, and action items assigned and completed. A list of attendees with contact information shall be included.

BLOCK 5-REVIEW REQ.:

Allow 3 days for Government review and comment.

BLOCK 6-SUBMITTAL SCHEDULE:

Agendas NLT 7 DPT each DR. Draft of materials to be presented during each DR shall be provided with each agenda; Minutes and final presentation material to be submitted NLT 7 days after each DR; R/ASR 3 DARC. Revisions shall incorporate resolution of Government comments.

BLOCK 7-DISTRIBUTION:
Addressee
QTY
PMS325PME
1
BLOCK 1-DATA ITEM NO.:
A003
BLOCK 2-DATA ITEM TITLE:
MANAGEMENT PLAN
BLOCK 3-REFERENCE:
SOW SEC C.3.3

The Management Plan shall include, but not be limited to:

1. Describe the technical approach including objectives, constraints, scope, methodology, and products to be accomplished under CLIN 0001 (and CLIN 0003, if exercised).

2. The Management Plan shall include how the Contractor’s program planning and implementation of that planning will manage concurrent and interactive efforts of all the design disciplines.

3. The Plan shall present an organizational chart and supporting narrative defining the organizational responsibilities.

4. Describe the plan for identifying, tracking, and addressing risks, issues and opportunities.

BLOCK 5-REVIEW REQ.:

Allow 7 days for Government review and comment.

BLOCK 6-SUBMITTAL SCHEDULE:

7 DPT PAC

BLOCK 7-DISTRIBUTION:
Addressee
QTY
PMS325PME
1
BLOCK 1-DATA ITEM NO.:
A004
BLOCK 2-DATA ITEM TITLE:
MASTER SCHEDULE
BLOCK 3-REFERENCE:
SOW SEC C.3.3

BLOCK 4-DATA DESCRIPTION:

The Master Schedule shall portray in chronological sequence, the actions, events and requirements with planned start and end dates. It shall include but not be limited to planned dates for Design Reviews, Design Maturity Assessment, model testing, major subcontractors’ purchase order issue dates, and initial submission and planned revisions of documentation. The timelines shall highlight the critical paths. This deliverable shall be Microsoft Project compatible.

BLOCK 5-REVIEW REQ.:

Allow 7 days for Government review and comment.

BLOCK 6-SUBMITTAL SCHEDULE:

7 DPT PAC

BLOCK 7-DISTRIBUTION:
Addressee
QTY
PMS325PME
1
BLOCK 1-DATA ITEM NO.:
A005
BLOCK 2-DATA ITEM TITLE:
REGULATORY BODY COMMUNICATIONS AND CORRESPONDENCE
BLOCK 3-REFERENCE:
SOW SEC C.3.4

BLOCK 4-DATA DESCRIPTION:

1. Copies of all incoming and outgoing Regulatory Body Communications and Correspondence, including attachments/enclosures, between the Contractor and Regulatory Bodies and between Subcontractors and the Regulatory Bodies shall be provided in electronic format, wherever possible.

2. Communications include letters, faxes, memos, electronic mail, and memos of phone conversations. Attachments/enclosures include drawings, sketches, photographs, slides, viewgraphs, presentations, specifications, manuals, studies, calculations, analyses, requests for change of class, applications for inspection, Contracts, scopes of work, and related communications.

3. Communications shall be assigned serial numbers and shall be indexed by the serial numbers, topic, and applicable dates.

BLOCK 5-REVIEW REQ.:

The Government will not be approving Contractor deliverables, but reserves the right to provide comments, if necessary. The Government may elect not to submit review comments.

BLOCK 6-SUBMITTAL SCHEDULE:

NLT 3 days after each incoming or outgoing communications and correspondence have been issued or received.

BLOCK 7-DISTRIBUTION:
Addressee
QTY
PMS325PME
1
BLOCK 1-DATA ITEM NO.:
A006
BLOCK 2-DATA ITEM TITLE:
BASELINE DESIGN DESCRIPTION REPORT
BLOCK 3-REFERENCE:
SOW SEC C.3.4.1

BLOCK 4-DATA DESCRIPTION:

1. The Baseline Design Description Report shall document the Contractor’s selected baseline. The report shall document how the selected baseline represents a ship meeting the intent of the T-ARC(X) System Specification, Attachment J-1. The report shall include design approach (modified existing design or new design), description of the baseline design, degree of maturity, technical risk areas, design tools used and planned including assumptions and level of verification and validation, regulatory gap analysis summary, and usability of existing drawings, if applicable.

2. If an existing design is used as the baseline, then the report shall also include the following:

a. Identify the required design modifications to meet System Specification requirements, including requirements in the Key Requirements Verification Matrix.

b. The Contractor shall provide previously developed drawings including the following:

i. General Arrangement

ii. Hull Lines

iii. Hull Structure

iv. Weight Estimate

v. Major Equipment List (MEL)

vi. Machinery Arrangement

BLOCK 5-REVIEW REQ.:

Allow 14 days for Government review and comment.

BLOCK 6-SUBMITTAL SCHEDULE:

45 DAC. Revisions shall incorporate resolution of Government comments.

BLOCK 7-DISTRIBUTION:
Addressee
QTY
PMS325PME
1
BLOCK 1-DATA ITEM NO.:
A007
BLOCK 2-DATA ITEM TITLE:
REGULATORY GAP ANALYSIS STUDY REPORT
BLOCK 3-REFERENCE:
SOW SEC C.3.4.1.1

BLOCK 4-DATA DESCRIPTION:

The Regulatory Gap Analysis Study Report shall identify potential design changes required for the vessel to become ABS Classed to the latest ABS MVR. The report shall also address any other significant gaps with other regulatory body requirements.

Note: This report is only required if the design approach is to modify an existing baseline design.

BLOCK 5-REVIEW REQ.:

BLOCK 6-SUBMITTAL SCHEDULE:

7 DPT the First and Final DRs.

BLOCK 7-DISTRIBUTION:
Addressee
QTY
PMS325PME
1
BLOCK 1-DATA ITEM NO.:
A008
BLOCK 2-DATA ITEM TITLE:
EMERGENT REGULATIONS STUDY REPORT
BLOCK 3-REFERENCE:
SOW SEC C.3.4.1.2

BLOCK 4-DATA DESCRIPTION:

The Emergent Regulations Study Report shall document design impacts, acquisition, and lifecycle cost of each applicable pending regulation and those that came into effect on or after Jan 1st 2020 that impact the design and operation of the vessel. The report shall discuss the various options for complying with applicable emergent regulations.

BLOCK 5-REVIEW REQ.:

BLOCK 6-SUBMITTAL SCHEDULE:

7 DPT the Second and Final DRs

BLOCK 7-DISTRIBUTION:
Addressee
QTY
PMS325PME
1
BLOCK 1-DATA ITEM NO.:
A009
BLOCK 2-DATA ITEM TITLE:
CABLE STOWAGE AND HANDLING STUDY

(See Attachment 1 to Data Item A009)

BLOCK 3-REFERENCE:
(See Attachment 1 to Data Item A009)

BLOCK 4-DATA DESCRIPTION:

(See Attachment 1 to Data Item A009)

BLOCK 5-REVIEW REQ.:

The Government will not be approving Contractor deliverables, but reserves the right to provide comments, if necessary. The Government may elect not to submit review comments.

BLOCK 6-SUBMITTAL SCHEDULE:

(See Attachment 1 to Data Item A009).

BLOCK 7-DISTRIBUTION:
Addressee
QTY
PMS325PME
1

ATTACHMENT 1 TO DATA ITEM NO. A009 CABLE STOWAGE AND HANDLING STUDY

ATTACH 1 TO DATA ITEM NO. (BLOCK 1)
DATA ITEM SUBTITLE AND REFERENCE (BLOCKS 2 AND 3)

DATA DESCRIPTION

(BLOCK 4)

SUBMITTAL SCHEDULE

(BLOCK 6)

DISTRIBUTION

(BLOCK 7)

A009-01
Cable Stowage and Handling Study Report

SOW SEC C.3.4.2.1

The report shall describe the means by which the Contractor’s proposed design meet the cable stowage and handling requirements in Attachment J-1, System Specification. The report shall address the following:

· Cable deck arrangements

· Cable pathways from cable tanks to overboarding sheaves

· Cable tanks (main and spare) size and arrangements

· Cable handling equipment (CHE) and cable haulers

· CHE control system(s)

· Cable deck overhead handling devices

· Repeater stowage and handling

· Cable gear stowage and handling

· Accommodations for the cable highway to pass the moonpool if applicable

14 DPT the Second, Third, and Final DR
Addressee

PMS325PME

QTY

A009-02
Cable Stowage and Handling Drawing

SOW SEC C.3.4.2.1

The drawing shall include:

· Cable Deck Arrangement:

· Cable highway and aft working deck

· Cable tank locations

· CHE location and arrangement

· Cable hauler locations

· Cable pathways from all cable tanks to overboarding sheaves including fairings, troughing, and cable bending radii

· Cable loading pathways including turning quadrants and rollers, and forward loading hatch location

· Splice shop

· Repeater stowage locations

· Cable Tank Arrangement. For main and spare cable tanks, show tank geometry, location of bight slot, access ladders, geometry of cone, geometry of divider rings (Spare cable tanks only), and fairings at top of tank.

· Repeater handling and stowage arrangement, including rack design and arrangement, bight pathways from cable tank bight slot to repeaters, repeater movement from the repeater racks into the troughing, and repeater movement from loading point to the repeater racks.

· Arrangement of troughing, quadrants, fairings and all necessary accommodations to work around the moonpool installation if applicable.

· Means for moving portable troughing and cable transporters around the cable bay and past the moonpool if applicable

· CHE arrangement including plan and elevation views of all CHE, foundations, maintenance access areas, CHE control console(s), and preliminary electrical distribution concept.

· Cable deck overhead handling system(s) arrangement, including coverage areas, capacities, vertical clearance, and hook height.

· Hauler arrangement, including cable hauler locations for cable loading, unloading, and tank-to-tank cable transfers, foundations, and paths for tank-to-tank transfers.

14 DPT each DR
PMS325PME
1
A009-03
Cable Gear Stowage and Handling Drawing

SOW SEC C.3.4.2.1

The drawing shall include:

· Locations and geometry of the rope tanks and bins

· Stowage for buoys, anchors, grapnels, and miscellaneous cable gear

· Means for lifting and/or transporting ropes, buoys, anchors, grapnels, and miscellaneous cable gear between stowage locations and aft working deck

· Rope pathway between rope tanks, CHE, and overboarding location

· Buoy systems including launch and recovery locations and means for deploying and recovering buoys.

· Means for deploying and recovering anchors and grapnels off the stern

· Means for moving cable gear, including Buoys, anchors, etc., past the moonpool to the back deck and back

14 DPT the Second, Third, and Final DR
PMS325PME
1
BLOCK 1-DATA ITEM NO.:
A010
BLOCK 2-DATA ITEM TITLE:
SEA PLOW SYSTEM STUDY

(See Attachment 1 to Data Item A010)

BLOCK 3-REFERENCE:
(See Attachment 1 to Data Item A010)

BLOCK 4-DATA DESCRIPTION:

BLOCK 5-REVIEW REQ.:

The Government will not be approving Contractor deliverables, but reserves the right to provide comments, if necessary. The Government may elect not to submit review comments.

BLOCK 6-SUBMITTAL SCHEDULE:

BLOCK 7-DISTRIBUTION:
Addressee
QTY
PMS325PME
1

ATTACHMENT 1 TO DATA ITEM NO. A010 SEA PLOW SYSTEM STUDY

ATTACH 1 TO DATA ITEM NO. (BLOCK 1)
DATA ITEM SUBTITLE AND REFERENCE (BLOCKS 2 AND 3)

DATA DESCRIPTION

(BLOCK 4)

SUBMITTAL SCHEDULE

(BLOCK 6)

DISTRIBUTION

(BLOCK 7)

A010-01
Sea Plow System Study Report

SOW SEC C.3.4.2.2

The report shall address:

· Sea Plow system description, including make/model, system characteristics, LARS, control system, and system interfaces

· Arrangements, including stern frame/Sea Plow LARS, tow winch, and umbilical winch system

· Structural and stability impacts

· Hydrodynamic analysis to meet SS 5 requirement, including any required motion compensation systems

· Moving the Sea Plow from loading location to stowage location to LARS location

· Impacts to machinery and auxiliary systems

14 DPT the Second, Third, and Final DR
Addressee

PMS325PME

QTY

A010-02
Sea Plow System Arrangement

SOW SEC C.3.4.2.2

The drawing shall include plan and elevation views for the following:

· Sea Plow

· Stern Frame/Sea Plow LARS including docking head and system interfaces

· Tow wire and tow wire winch

· Umbilical and umbilical winch system

· Power cable and power cable winch if applicable

· External HPU

· Sea Plow motion compensation system, if used

· Control console and preliminary electrical distribution concept

· Stern frame positions for inboard, outboard, and vertical

14 DPT each DR
PMS325PME
1
BLOCK 1-DATA ITEM NO.:
A011
BLOCK 2-DATA ITEM TITLE:
ROV SYSTEM STUDY

(See Attachment 1 to Data Item A011)

BLOCK 3-REFERENCE:
(See Attachment 1 to Data Item A011)

BLOCK 4-DATA DESCRIPTION:

BLOCK 5-REVIEW REQ.:

The Government will not be approving Contractor deliverables, but reserves the right to provide comments, if necessary. The Government may elect not to submit review comments.

BLOCK 6-SUBMITTAL SCHEDULE:

BLOCK 7-DISTRIBUTION:
Addressee
QTY
PMS325PME
1

ATTACHMENT 1 TO DATA ITEM NO. A011 ROV SYSTEM STUDY

ATTACH 1 TO DATA ITEM NO. (BLOCK 1)
DATA ITEM SUBTITLE AND REFERENCE (BLOCKS 2 AND 3)

DATA DESCRIPTION

(BLOCK 4)

SUBMITTAL SCHEDULE

(BLOCK 6)

DISTRIBUTION

(BLOCK 7)

A011-01
ROV System Study Report

SOW SEC C.3.4.2.3

The report shall address:

· ROV system description, including make/model, system characteristics, LARS, control system, and system interfaces

· Arrangements, including ROV LARS and umbilical winch system

· Structural and stability impacts

· Hydrodynamic analysis to meet SS 5 requirement, including any required motion compensation systems

· Capability of the ROV and ROV LARS to operate with integrated 1m burial system.

· Impacts to machinery and auxiliary systems

14 DPT the Second, Third, and Final DR
Addressee

PMS325PME

QTY

A011-02
ROV System Arrangement

SOW SEC C.3.4.2.3

The drawing shall include plan and elevation views for the following:

· ROV, including burial capability

· ROV LARS including docking head and system interfaces

· Umbilical and umbilical winch system and traction winch system, if used

· External HPU

· Control console and preliminary electrical distribution concept

· ROV LARS positions for inboard and outboard

· ROV motion compensation system, if used

· ROV stowage location

14 DPT each DR
PMS325PME
1
BLOCK 1-DATA ITEM NO.:
A012
BLOCK 2-DATA ITEM TITLE:
MOONPOOL STUDY

(See Attachment 1 to Data Item A012)

BLOCK 3-REFERENCE:
(See Attachment 1 to Data Item A012)

BLOCK 4-DATA DESCRIPTION:

BLOCK 5-REVIEW REQ.:

The Government will not be approving Contractor deliverables, but reserves the right to provide comments, if necessary. The Government may elect not to submit review comments.

BLOCK 6-SUBMITTAL SCHEDULE:

BLOCK 7-DISTRIBUTION:
Addressee
QTY
PMS325PME
1

ATTACHMENT 1 TO DATA ITEM NO. A012 MOONPOOL STUDY

ATTACH 1 TO DATA ITEM NO. (BLOCK 1)
DATA ITEM SUBTITLE AND REFERENCE (BLOCKS 2 AND 3)

DATA DESCRIPTION

(BLOCK 4)

SUBMITTAL SCHEDULE

(BLOCK 6)

DISTRIBUTION

(BLOCK 7)

A012-01
Moonpool Study Report

SOW SEC C.3.4.2.4

The report shall describe the moonpool design solution capable of launching and recovering the UUV and launching the Package through SS3 per the T-ARC(X) System Specification, Attachment J-1. The report shall address:

· Moonpool size and configuration,

· Moonpool location with assessment of impact on cable operations,

· Impacts to locations of cable tanks, bow thruster, and sonar systems,

· Structural design and impacts,

· Design and characteristics of Moonpool LARS system for UUV and Package and any required motion compensation systems,

· Design and characteristics of Moonpool Heavy Lift System for deploying payloads,

· Design and characteristics of Moonpool Staging Bay Overhead Gantry,

· Payload stowage location(s) and means to move payloads from loading location to stowage location(s) to staging location and to moonpool,

· Means to reduce water column motions in the moonpool and minimize overtopping,

· Means to reduce air pressure fluctuations in the moonpool bay,

· Design and characteristics of moonpool lower and upper door(s),

· Impacts to machinery and auxiliary systems, including hydraulic and HVAC.

The report shall include a seakeeping analysis of the moonpool, including overtopping analysis, with a description of the methodology, any models used and model assumptions, and any empirical data used. The analysis shall account for baffles and any other dampening features, if used.

The report shall include an analysis that predicts the amount of air venting that is required to stay within the pressure threshold as defined in the T-ARC(X) System Specification Attachment J-1.

14 DPT the Second, Third, and Final DR
Addressee

PMS325PME

QTY

A012-02
Moonpool Arrangement

SOW SEC C.3.4.2.4

The drawing shall include the following:

· Moonpool size and configuration

· Moonpool structure, including baffle design

· Lower moonpool door(s) arrangement, including hold down method

· Upper moonpool door(s) arrangement

· Moonpool LARS

· Moonpool Heavy Lift System

· Hydraulic system arrangement diagram

· Staging bay size and configuration, including notional venting arrangement

· Moonpool Staging Bay Overhead Gantry arrangement

· Payload loading, stowage, and staging locations (if applicable)

· Moonpool Staging Bay climate control concept including any bulkheads required and how they affect mission operations

14 DPT each DR
PMS325PME
1
A012-03
Moonpool LARS Arrangement

SOW SEC C.3.4.2.4

The drawing shall include plan and elevation views for the following:

· Moonpool LARS including system interfaces for payloads

· Heavy Lift System for deploying payloads

· Moonpool LARS control console and preliminary electrical distribution concept

· Location and interfaces with the rail and cursor system

· Moonpool LARS motion compensation system, if used

14 DPT each DR
PMS325PME
1
BLOCK 1-DATA ITEM NO.:
A013
BLOCK 2-DATA ITEM TITLE:
INTEGRATION STUDY REPORT
BLOCK 3-REFERENCE:
SOW SEC C.3.4.2.5

BLOCK 4-DATA DESCRIPTION:

The Integration Study Report shall document the following steps and the results of the various evaluations:

1. Selection of systems, equipment, and approaches from the individual trade-off studies the Contractor has performed, including methodology and assumptions

2. Analysis of how the design solutions are integrated, including potential interferences with the primary mission.

3. Evaluation of the selections for any compatibility issues or compounding impacts The report shall also include the current status of the Key Requirements Verification Matrix provided in Attachment J-3. The Contractor shall include a description of the methodology and assumptions used to make their assessment.

BLOCK 5-REVIEW REQ.:

The Government will not be approving Contractor deliverables, but reserves the right to provide comments, if necessary. The Government may elect not to submit review comments.

BLOCK 6-SUBMITTAL SCHEDULE:

Initial Submittal NLT 21 days after the Second DR. Final Submittal NLT 21 DPT the Third DR.

BLOCK 7-DISTRIBUTION:
Addressee
QTY
PMS325PME
1
BLOCK 1-DATA ITEM NO.:
A014
BLOCK 2-DATA ITEM TITLE:
OBJECTIVE TRADE STUDIES

(See Attachment 1 to Data Item A014)

BLOCK 3-REFERENCE:
(See Attachment 1 to Data Item A014)

BLOCK 4-DATA DESCRIPTION:

BLOCK 5-REVIEW REQ.:

The Government will not be approving Contractor deliverables, but reserves the right to provide comments, if necessary. The Government may elect not to submit review comments.

BLOCK 6-SUBMITTAL SCHEDULE:

BLOCK 7-DISTRIBUTION:
Addressee
QTY
PMS325PME
1

ATTACHMENT 1 TO DATA ITEM NO. A014 OBJECTIVE TRADE STUDIES

ATTACH 1 TO DATA ITEM NO. (BLOCK 1)
DATA ITEM SUBTITLE AND REFERENCE (BLOCKS 2 AND 3)

DATA DESCRIPTION

(BLOCK 4)

SUBMITTAL SCHEDULE

(BLOCK 6)

DISTRIBUTION

(BLOCK 7)

A014-01
Unrefueled Range Objective Trade Study Report

SOW SEC C.3.4.2.6.1

The report shall assess the design impacts of increasing unrefueled range to 1217,500 nm and 15,000 nm.. The report shall address impacts on overall ship size, fuel and ballast systems, arrangements, machinery, structural, stability, weight, seakeeping, DP, and maneuvering. The report shall include conceptual drawings addressing the following:

Fuel and ballast tank arrangements General Arrangement Area/Volume and Tankage Report Hull Lines Weight Estimate

The report shall provide a cost estimate for increased unrefueled range and characterize the accuracy of the estimate. A discussion of the overall impacts to acquisition cost and operating and support cost shall also be provided.

14 DPT the Third and Final DR
Addressee

PMS325PME

QTY

A014-02
Dry Moonpool Objective Trade Study Report

SOW SEC C.3.4.2.6.2

The report shall assess the design impacts of a dry moonpool. The report shall include conceptual drawings addressing the following:

· Pumps and valves capable of flooding or de-watering the moonpool in 1 hour

· Lower door(s) design and characteristics, including seals and hold-downs

· LARS interface (if any)

The report shall provide a cost estimate for a dry moonpool and characterize the accuracy of the estimate. A discussion of the overall impacts to acquisition cost and operating and support cost shall also be provided.

14 DPT the Third and Final DR
Addressee

PMS325PME

QTY

A014-03
Sea State 5 Moonpool Objective Trade Study Report

SOW SEC C.3.4.2.6.3

The report shall assess the design impacts of moonpool operations through sea state 5. The report shall address the following:

· Seakeeping analysis including sea states 4 and 5.

· LARS design and heavy lift system

· Motion compensation systems

· Impacts on baseline moonpool size and location

· Structural impacts

· Mitigations to reduce water column motions in the moonpool and air pressure fluctuations in the moonpool bay

· Machinery and auxiliary systems

The Moonpool Arrangement and the Moonpool LARS Arrangement shall be updated to reflect any changes required due to the Sea State 5 requirement, including Moonpool Staging Bay venting.

The report shall provide a cost estimate for moonpool operations through sea state 5 and characterize the accuracy of the estimate. A discussion of the overall impacts to acquisition cost and operating and support cost shall also be provided.

14 DPT the Third and Final DR
Addressee

PMS325PME

QTY

BLOCK 1-DATA ITEM NO.:
A015
BLOCK 2-DATA ITEM TITLE:
SPECIFICATION CHANGE RECOMMENDATIONS
BLOCK 3-REFERENCE:
SOW SEC C.3.4.3.1

BLOCK 4-DATA DESCRIPTION:

The Contractor shall submit Specification Change Recommendations (SCRs) using the matrix provided as Attachment J-4 and in accordance with SOW C.3.4.3.1.

Only one (1) SCR shall be entered per SCR form. All pages of a SCR submittal shall be numbered with the SCR form always being page one (1). The SCR forms may be submitted at any time during the period of performance.

BLOCK 5-REVIEW REQ.:

The Government will not be approving Contractor deliverables, but reserves the right to provide comments, if necessary. The Government may elect not to submit review comments.

BLOCK 6-SUBMITTAL SCHEDULE:

As identified, with final recommendations NLT 30 DPT end of contract

BLOCK 7-DISTRIBUTION:
Addressee
QTY
PMS325PME
1
BLOCK 1-DATA ITEM NO.:
A016
BLOCK 2-DATA ITEM TITLE:
AFFORDABILITY STUDY REPORT
BLOCK 3-REFERENCE:
SOW SEC C.3.4.3.2

BLOCK 4-DATA DESCRIPTION:

The report shall include the Contractors review of the design for approaches, methods, and trade-offs that will improve affordability of the ship during construction and during service life. The report shall include:

1. Approaches and methods that will enhance the producibility of the ship during construction.

2. Approaches that will reduce fuel and energy consumption over the life cycle.

3. Approaches that will reduce manning, maintenance and upgrade costs.

Cite projected savings in dollars and characterize the accuracy of the estimate.

The report shall also include any risks, trade-off options, and recommendations between acquisition and lifecycle costs.

BLOCK 5-REVIEW REQ.:

The Government will not be approving Contractor deliverables, but reserves the right to provide comments, if necessary. The Government may elect not to submit review comments.

BLOCK 6-SUBMITTAL SCHEDULE:

7 DPT the Second and Final DRs.

BLOCK 7-DISTRIBUTION:
Addressee
QTY
PMS325PME
1
BLOCK 1-DATA ITEM NO.:
A017
BLOCK 2-DATA ITEM TITLE:
DRAWINGS

(See Attachment 1 to Data Item A017)

BLOCK 3-REFERENCE:
(See Attachment 1 to Data Item A017)

BLOCK 4-DATA DESCRIPTION:

BLOCK 5-REVIEW REQ.:

The Government will not be approving Contractor deliverables, but reserves the right to provide comments, if necessary. The Government may elect not to submit review comments.

BLOCK 6-SUBMITTAL SCHEDULE:

BLOCK 7-DISTRIBUTION:
Addressee
QTY
PMS325PME
1

ATTACHMENT 1 TO DATA ITEM NO. A017 DRAWINGS

ATTACH 1 TO DATA ITEM NO. (BLOCK 1)
DATA ITEM SUBTITLE AND REFERENCE (BLOCKS 2 AND 3)

DATA DESCRIPTION

(BLOCK 4)

SUBMITTAL SCHEDULE

(BLOCK 6)

DISTRIBUTION

(BLOCK 7)

A017-01
General Arrangement

SOW SEC C.3.4.4.2

The drawing shall show compartmentation, external arrangements, general access, adjacency and separation, deck heights, and line-of-sight.

The drawing shall show topside, bow, stern, inboard profile, outboard profile and deck plan views, and define watertight subdivisions, bulkheads, access and passageways and fire zone boundaries for the hull and superstructure. All compartments (including cable tanks, tanks and voids), and exterior deck areas shall be shown and labeled. Major equipment such as CHE, cranes, masts, davits, lifeboats, rescue boat, workboat, and other major topside equipment shall be shown.

Frame numbering shall start from the forward perpendicular (FP), defined as the intersection of the stem and the design waterline. The numbers shall coincide with the frame locations regardless of the spacing, throughout the entire length of the ship. Frame labeling forward of the FP will be alphabetical with "A" being the first frame forward of the FP. Frame numbers and spacings, deck heights, air draft, and design waterlines shall be labeled.

14 DPT each DR

A017-02
Hull Lines Drawing and Offsets Database

SOW SEC C.3.4.4.2

The Hull Lines Drawing shall include the following:

· At least 20 stations including the forward and aft perpendiculars.

· Waterlines at least every 1 meter.

· Buttock lines at least every 1 meter.

· Locations of knuckle lines.

· Location of bilge keel trace.

· Location of decks, buttlines of skegs, rudders, propellers, and thrusters (if provided).

· A Table of Offsets showing the station, or frame number, waterline, and buttock intersections, and chines, knuckles, shear lines, flats and decks, to at least the nearest 0.08 inches (2 millimeters).

The Hull model shall be provided in Initial Graphics Exchange Specification (IGES) format.

14 DPT each DR

A017-03
Appendage Drawing

SOW SEC C.3.4.4.2

The drawing shall show sizes and locations of appendages, including bilge keels, thruster openings and, if provided, skegs, shafts, struts, rudders and steerable thrusters.

14 DPT the Second, Third and Final DR

A017-04
Midship Section Drawing

SOW SEC C.3.4.4.2

The drawing shall show typical transverse structure on one half of the section and typical longitudinal structure on the other half and shall include calculations necessary to substantiate the structural details depicted. The strength deck shall be identified. A typical transverse bulkhead shall be included. A table of the vessel’s principal dimensions and design information shall be provided and shall include but is not limited to length (length between perpendiculars (LBP), length overall (LOA)), beam, depth, scantling draft, design draft, design displacement. The drawing shall be dimensioned and include typical frame spacing information.

Structural calculations necessary to substantiate the scantlings shall be provided.

14 DPT each DR ABS preliminary review shall be incorporated into the final submittal.

A017-05
Hull Deck, Platform and Longitudinal Bulkhead and Superstructure Scantling Drawings

The drawing shall show the scantlings of all hull decks, platforms and longitudinal bulkheads along the full length of the hull and major equipment foundations and any significant deviations from standard scantlings. Show the mast, superstructure decks, sides, internal bulkheads and the scantlings to be used. Calculations necessary to substantiate the scantlings specified in the drawing shall be included. Frame markings, deck heights, and design waterlines shall be depicted.

14 DPT the Second, Third and Final DR ABS preliminary review shall be incorporated into the final submittal

A017-06
Sonar System Arrangement

The drawing shall depict the location of each hull mounted mission sonar system including locations of transducers, sea chests and transceivers.

14 DPT the Second, Third and Final DR

A017-07
Deck Systems Arrangement

The drawing shall include plans for all topside decks, levels and platforms, depicting bulkheads and openings, as well as outboard…