Attachment G - Seed Project SOW.pdf
PDF 75 KB Posted
- Solicitation number
- N6945020R0036
About this file
This statement of work outlines the requirements for replacing timber with composite materials at two ferry landings at Naval Station Guantanamo Bay, Cuba. The scope of work includes removing existing deteriorated timbers and installing new marine-grade timbers with high density polyethylene fender panels. Additional work includes repairing and painting steel structures, replacing damaged railings and light fixtures, repairing concrete, and installing new electrical components. The contractor must follow all applicable codes and specifications, complete debris removal and waste disposal, obtain necessary approvals, and protect the environment. The work must be completed within 120 calendar days of award.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N6945020R0036_Amend 0004.pdf | ||
| PPI Responses_9JUN2020_FINAL.pdf | ||
| N6945020R0036_Amend 0003.pdf | ||
| N6945020R0036_Amend 0002.pdf | ||
| Attachment E (rev.1) - Safety Data Sheet.docx | DOCX document | |
| N6945020R0036_Amend 0001.pdf | ||
| PPI Responses_13MAY2020.pdf | ||
| Attachment B - AMAG.xlsx | XLSX spreadsheet | |
| Attachment F - Past Performance Questionnaire.docx | DOCX document | |
| Attachment A - PPI Log.xlsx | XLSX spreadsheet | |
| Solicitation N6945020R0036.pdf | ||
| Attachment D - Construction Experience Project Data Sheet.docx | DOCX document | |
| Attachment H - Seed Project Photos.pdf | ||
| Attachment C - SECNAV 5512.pdf | ||
| Attachment E - Safety Data Sheet.docx | DOCX document |
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LW & WW FERRY LANDINGS Replace timber with composite WR:# 1614876
NAVFAC SE PWD GUANTANAMO BAY CUBA 12/4/2019
Prepared by E. Goodson
12/4/2019
SCOPE OF WORK
WW & LW FERRY LANDINGS Replace timber with composite
U.S. NAVAL STATION, GUANTANAMO BAY, CUBA
1.) GENERAL INTENTION:
The existing ferry landing timbers are deteriorated and past their useful service life. The main project is to install horizontal HPDE fender sheets on top of new timbers where ferry come in contact with the ramp.
Side projects will include :
- sanding and painting of the existing steel structures and bollards at both ferry landings, at windward U boat ramp and at stair at leeward.
- removing and replacing cracked concrete slabs at in front of Windward ferry landing ramp
- Electrical SOW at Leeward U boat ramp
Refer to SOW below and drawings for full extent of the work
2.) GENERAL DESCRIPTION:
The Contractor shall furnish all labor, management, supervision, tools, materials, equipment, incidental engineering and transportation necessary to provide facility improvements in this scope of work in accordance with contract requirements and with paragraph 3- Technical requirement and specifications.
Work at Windward and Leeward Ferry Landings, includes the following
- Remove and dispose of existing wood timbers at Windward and Leeward Ferry Landing Transfer ramps
- Prepare concrete to receive new timber
- Provide and install new, full length (approx. 21 feet), marine grade (use category US5C) timbers with a minimum stress rating of 1,500 psi sized to match existing elevations. Approximate timber sizes for each landing are 21’x12”x12”, 21’x12”x8”, and 21’x12”x4”. Timbers built up shall match existing refer drawings.
- Provide and install new High Density Polyethylene (HDPE) pile fenders on timbers to be protected from contact. Fenders shall cover entire surface area of fenders with a thickness of 2”.
- Remove rust from all steel ramp support structures by sand blasting or other appropriate means (approximately 2,000 Sqft). If lead based paint is found proper abatement measures will be taken.
- Repair corroded steel on steel ramp support structures and prepare steel for finishes.
- Paint all steel support structure with high performance coating (HPC) (approximately 2,000 Sqft).
- Remove bumpers on water side and paint steel structure underneath with high performance coating (HPC). Reinstall bumper once paint has properly dried.
- All bollards to have rust removed by sandblasting (approximately 280 Sqft.), steel to be prepared for finishes, and painted with high performance coating (HPC). If lead based paint is found proper abatement measures will be taken.
- Concrete wing walls by timbers on concrete ramp (approx.
4’x16”x6”) to be demolished and recast with dowelsF.
- Saw cut 12” wide band on concrete at a minimum 6” deep. Cast new high strength marine concrete (approximately 2.2 cubic yards total) (5,800 PSI) edge. Anchored with HPC steel angle at edge with counter sunk anchors.
- Concrete side walls with cracks to be repaired, grouted, and or patched (approximately 200 linear feet).
- Provide and install two new steel cleats onto side steel structure for ferry tie on exact location to be coordinated on field.
- Remove cracked concrete slab in front of Windward Ferry Landing and pour new 5,000 PSI high strength marine concrete in area of approximately 675 Sqft.
Work at metal stairs next to Leeward ferry landing, includes the following
- Steel stair to be sandblasted for rust removal and painted with high performance coating(HPC) (approximately 300 Sqft).
If lead based paint is found proper abatement measures will be taken.
Work at U boat ramp next to Windward ferry landing, includes the following
- steel repair and preparation for finishes. Sand blast rusted bollards(12), two 5’ long railings, sixteen base plates, corner angles(70 linear feet), sheet piling (approx. 100 Sq.
Ft.), six 18” wide cleats located on wood pier.
- Remove and store existing conduit for reinstallation (approx.
70 LF) )
- Remove and replace damaged stainless steel cable railing (approx. 25LF)
- Replace light fixture and 10’ high pole at end of pier to match or exceed existing conditions.
- Procure and install new above ground conduit and connector junction box. Underground circuit to remain. (approx. 170 LF)
Sequence of work to be performed:
FERRY LANDING RAMP AND FENDERS (WINDWARD & LEEWARD)
- Contractor shall remove and properly dispose of existing timbers, ensuring concrete pedestal is not damaged during the removal process.
- Contractor to demolish and remove wing walls and remove 12” wide band of concrete a minimum of 6” deep along the approximately 21’ long ledge per enclosure.
- Contractor to saw concrete along straight lines to a depth of a minimum 50 mm 2 inch. Make each cut in walls perpendicular to the face and in alignment with the cut in the opposite face. Break out the remainder of the concrete provided that the broken area is concealed in the finished work, and the remaining concrete is sound. At locations where the broken face cannot be concealed, grind smooth or saw cut entirely through the concrete.
- Contractor shall remove rust and loose mill scale on Steel support structures, metal stairs, two 5’ long railing, 16 base plates, corner angles and all bollards. Clean using methods recommended in writing by coating manufacturer.
Conform to SSPC 7/NACE No.4 for blast cleaning.
- Contractor to mix and prepare coating materials in accordance with the coating manufacturer's printed instructions for applying the particular material and coat. Keep materials which are not in actual use in closed containers. Coating materials that have been mixed with an automatic shaker are allowed to stand to let air bubbles escape, then given a final hand mixing before application. Stir materials so as to produce a mixture of uniform density. Stir at frequent intervals during application to prevent skinning. Do not stir film which may form on the surface of the material. Remove film and strain, if necessary.
- Do not perform exterior painting in damp or rainy weather.
Painting is not allowed below 10 degrees C 50 degrees F or above 35 degrees C 95 degrees F. Apply paint in accordance with the coating manufacturer's recommendations, and as specified. Ensure coating application is done by skilled applicators. Apply coatings to clean and properly prepared surfaces. Apply coatings with clean, high-quality application equipment. Allow sufficient time between coats to ensure complete drying and curing. Sand and dust surfaces between coatings, as required, to produce a surface free of visible defects. Lightly sand high gloss coatings and clear finishes between coats to ensure bond of following coats. Apply coats to the surfaces in an even film. Cloudiness, spotting, holidays, laps, application marks, runs, sags, and other similar surface imperfections are not acceptable. Remove defective coating applications and re-coat as directed.
Ensure coating lines such as wainscots are sharp, true, and well-defined. Tape may be used to establish coating lines, providing tape is removed before ragging or sawtooth edges form. Ensure surfaces, including edges, corners, crevices, welds, and other similar changes in surface plane, meet the dry-film thickness not less than specified.
- Contractor to use clean, proper size brushes for high-quality application of the specified coating materials. Brush out slow-dry coatings. Brush out quick-dry coatings only enough to spread out evenly.
- Apply a minimum two coats of coating with a dry-film thickness of a minimum 0.1 millimeter 4 mils.
- At end of each workday contractor to remove rubbish, empty cans, rags, and other discarded materials from project site.
After completing coating application, clean spattered surfaces. Remove spattered coatings by washing, scraping, or other methods. Do not scratch or damage adjacent finished surfaces. Clean application equipment promptly and thoroughly with a suitable solvent after each use and stored in a clean, covered, well-ventilated container.
- Contractor to provide wood, plywood, or steel for materials used for concrete forms. Use plywood or steel forms where a smooth form finish is required. Lumber shall be square edged or tongue-and-groove boards, free of raised grain, knotholes, or other surface defects. Plywood: APA PS 1, B-B concrete form panels or better. Steel form surfaces shall not contain irregularities, dents, or sags.
- Contractor to provide formwork with clean-out openings to permit inspection and removal of debris. Formwork shall be gasketed or otherwise rendered sufficiently tight to prevent leakage of paste or grout under heavy, high-frequency vibration. Use a release agent that does not cause surface dusting. Limit reuse of plywood to no more than three times.
Reuse may be further limited by the Contracting Officer if it is found that the pores of the plywood are clogged with paste so that the wood does not absorb air and some of the high water-cementitious materials ratio paste that may be trapped in pockets between the form and the concrete. Comply with ACI 301M ACI 301. Concrete for footings may be placed in excavations without forms upon inspection and approval by the Contracting Officer. Excavation width shall be a minimum of 100 mm 4 inches greater than indicated. Set forms rigidly, mortar-tight, and true to line and grade. Chamfer above grade exposed joints, edges, and external corners of concrete 20 mm
0.75 inch unless otherwise indicated. Forms submerged in water shall be watertight. Patch form tie holes with a no shrink patching material in accordance with the manufacturer's recommendations and subject to approval.
- Before concrete placement contractor to coat the contact surfaces of forms with a no staining mineral oil, no staining form coating compound, or two coats of nitrocellulose lacquer. Do not use mineral oil on forms for surfaces to which adhesive, paint, or other finish material is to be applied.
- Contractor to place concrete into forms that replicate the previously demolished concrete in both shape and size.
- After placing concrete, forms shall remain in place for the time periods specified in ACI 347R, except for concrete placed underwater, forms shall remain in place a minimum of 48 hours.
Prevent concrete damage during form removal.
- Contractor to provide angle iron on edge of new ledge in accordance with ASTM A36/A36M, for embedment as indicated.
Galvanize embedded items exposed to the elements in accordance with ASTM A123/A123M.
- Contractor to install the new steel cleat at location to be determined and coordinated on site on both steel structures.
Steel cleat to be welded on steel structure and test fit with ferry in position.
- Contractor to control all operations to minimize the amount of dust, dirt, debris and laitance in the work area. Clean all dirt, dust, debris, or laitance from coring or concreting operations, from the pavement surfaces prior to final acceptance.
- The top of the grounding rod shall be set at or not more than 6 mm 1/4 inch below the pavement surface grade. A recess 70 mm 2-3/4 inches wide, and not more than 150 mm 6 inches long, with a smooth rounded edge shall be provided in the pavement around the grounding point anchor eye to permit the entrance of lines into the eye and to allow for attachment of the grounding cable. The depth of the recess shall be no deeper than the bottom of the opening of the grounding point eye.
- Install grounding rods in holes cored through the rigid pavement using rotary, non-percussion drilling techniques.
The core holes shall have a minimum diameter of 150 mm 6 inches. The grounding rod shall be installed by pushing or driving the rod through the pavement base courses and subgrade. The installation technique chosen shall not damage the grounding rod or the pavement. Installation shall be completed by placing concrete around the grounding rod in two lifts with each lift consolidated with spud vibrators.
- Contractor shall prepare pedestal area ensuring there is an even bearing for installation of new timbers.
- Contractor shall field treat all cuts, holes and injuries to the new timbers with copper naphthenate solution containing a minimum 2.0% copper metal, in accordance with AWAP M4-15.
Bored holes for connectors and bolts may be treated by pumping cold-tar roofing cement into the holes ensuring complete coverage.
- Contractor shall bolt timbers to concrete pedestal using ¾” diameter 316 stainless steel wedge anchors, securely fastening the timber to pedestal. Anchors shall be a maximum of 32” apart and extend a minimum of 6” into concrete pedestal. Contractor shall cap all anchors with cold-tar roofing cement ensuring complete coverage.
- Contractor shall provide and install new HPDE fender panels in accordance with manufactures recommendations. Fender panels shall be 2” thick and all hardware shall be 316 stainless steel.
- Cleanup site debris and dispose of construction waste as per NSGB environmental requirements.
U BOAT RAMP (WINDWARD)
- Remove existing above ground conduits and store for reinstallation (approximately 70 LF).Salvage conduit except where embedded in concrete or masonry. Consider corroded, bent, or damaged conduit as scrap metal. Sort straight and undamaged lengths of conduit according to size and type.
- Contractor to replace damaged stainless steel cable railing (Approximately 25 LF).
- Contractor to procure and install above ground conduit, Ensure rigid nonmetallic conduit complies with NEMA TC 2, NEMA TC 3, and UL 651 as applicable with a wall thickness not less than Schedule 40.
- Procure and install junction box. Ensure outlet boxes for use with conduit systems are in accordance with NEMA FB 1 UL 514A, UL 514B, UL 514C and ANSI/NEMA OS 1 ANSI/NEMA OS 2 SECTION 26 05 00.00 40 Page 14 and are not less than 40 millimeter 1- 1/2 inches deep. Furnish all pull and junction boxes with screw-fastened covers.
- Replace Light fixture and 10’ high pole to match or exceed existing conditions and Windward Ferry Landing U boat pier.
3.) TECHNICAL REQUIREMENTS AND SPECIFICATIONS:
All aspects of this SOW will comply with all applicable codes. All equipment procured will equal to or better than the ones use in base of design.
Material Specification:
- Timbers shall be solid sawn lumber of stress rated Southern Pine, Douglas Fir-Larch, or Red Pine with a stress rating of at least 1,500 psi. All timbers shall have a dual treatment of creosote with a minimum retention of 20.0 lbs per cubic foot in accordance with AWPA UC5C standards.
- Fender sheets shall be solid construction using Ultra High Molecular Weight Polyethylene with a minimum density of 0.94 g/cc in accordance with ASTM D792
- All hardware shall be 316 stainless steel manufactured to meet ASTM/ASME: UNS S31600 / S31603 standards.
- Cementitious materials shall be portland cement or cement blended with supplementary cementing materials. New submittals are required when the cementitious materials change sources or types. The Contractor shall provide cementitious materials meeting the requirements of the applicable specification, and as modified herein. Provide mill certificates and test results conducted within six-months of the submittal date as part of the concrete mixture qualification submittal. Provide a single manufacturer of cementitious material for each type of cement and supplementary cementing materials supplied to the project.
Provide portland cement conforming to ASTM C150/C150M, Type II, low alkali with tri-calcium aluminates(C3A) content less than 10 percent and a maximum cement-alkali content of 0.80 percent Na2Oe (sodium oxide equivalent). Type III cement shall be used only with concurrence of the agency's Subject Matter Expert in Concrete Materials. When HVFA mixtures are specified, they should be blended with Type II portland cement. HVFA is required instead of using Type V cement in high-sulfate areas. Low alkali cement may be required if the proposed aggregates are found to be expansive. ASTM C150/C150M cements shall be combined with supplementary cementing materials in the concrete mixture.
- Apply a polyurethane coating system in conformance with MPI ASM, No. 72, MPI ASM, No. 77, and MPI ASM, No. 101. Apply a prime coat with a dry-film thickness of not less than 0.05 millimeter 2 mils. Finish coats are polyurethane-based material as specified.
- Mooring devices shall be cast in ductile iron 80-55-06 conforming to ASTM A436, unless otherwise indicated. The device shall be as shown in the contract drawings. Submit certificates of compliance on the devices stating that the mooring devices meet the specified requirements.
- Grounding rods, unless otherwise indicated, shall conform to UL 467 and shall be made of copper-clad steel. The rods shall be not less than 19 mm 3/4 inch in diameter and not less than 3 m 10 feet long. The copper cladding shall conform to the applicable requirements of ASTM B371/B371M, Copper Alloy UNS No's. c 69400, c 69430, c 69440 or c 69450. The copper cladding shall be not less than 0.25 mm 0.010 inches thick at any point and shall comply with adherence requirements and the banding requirements of UL 467. Submit certificates of compliance stating that the grounding rods meet the specified requirements. Rods shall be provided with a closed eye or shepherd's hook bend having an inside diameter of not less than 32 mm 1-1/4 inches. The rods shall be pointed.
- Reinforcing steel shall conform to ASTM A615/A615M Grade 40 or 60 for #4 tie bars and Grade 60 for #6 vertical bars. Steel shall be welded into cages in accordance with AWS D1.4/D1.4M and inserted securely in the piers, in position and alignment, as shown, prior to concrete placement. Submit certificates of compliance stating that the reinforcing steel meets the specified requirements.
4.) GENERAL REQUIREMENTS AND PROCEDURES:
All workmanship shall meet the standards specified herein and shall be accomplished in conformance with approved and accepted standards of the industry; equipment manufacturers, federal standards; and applicable building and safety codes.
i. All work is to be accomplished in accordance with NAVSTA and NAVFAC safety instructions and guidelines.
ii. Contractor shall comply with the latest version of EM 385-1-1 (including interim changes) that is in effect on the date of the request for proposal.
iii. Contractor shall comply with the latest version of NAVFAC P-307 (including interim changes) that is in effect on the date of the request for proposal.
iv. Contractors shall perform work in accordance with the latest version of UFC (Unified Facilities Code) and UFGS (Unified Facilities Guideline Specifications) in general and specifically with the latest version of
. UFGS 02 41 00 Demolition & Deconstruction
. UFGS 03 31 29 Marine Concrete with Service Life Modeling
. UFGS 03 31 30 Marine Concrete
. UFGS 05 05 23.16 Structural welding
. UFGS 06 13 33 Pier Timberwork
. UFGS 09 96 00 High Performance Coatings
. UFGS 09 97 13.27 Coating of steel waterfront structures, Zero VOC, Splash Zone Coating
. UFSC 09 97 13.27 Exterior coating of steel structure
. UFGS 26 05 00 Common Work Results For Electrical
. UFGS 26 56 00 Lighting Poles And Standards
. UFC 3-440-05N Tropical Engineering
(Including interim changes) that is in effect on the date of the request for proposal.
v. All work shall be free of missing components and of defects which would prevent it from functioning as originally intended and or designed.
vi. Contractor shall site-verify all dimensions and measurements identified in Statement of Work prior to providing proposal.
vii. All trash shall become the property of the contractor and disposed of per base instructions to landfill or removed from island. No material is to be left on the job site when crews are not actively working the job.
viii. During and at completion of work, debris shall not be allowed to spread unnecessarily into adjacent areas nor accumulate in work area itself. All such debris, excess material and parts shall be cleaned up and removed at the completion of the job and at the end of each day or the beginning and end of each working shift that work is in progress.
ix. All work shall be coordinated thru Public Works Department to include Facilities Maintenance Director, Environmental and NSGB Fire Department.
x. All products used shall be delivered to construction site in new unopened condition and all products shall be available as the assigned lay-down area prior to start of construction. All products shall be inspected to verify that the shelf life has not expired.
xi. Contractor shall provide a toilet portable chemical for the duration of the job. The toilet portable chemical shall be serviced at least weekly or as necessary to maintain sanitary conditions as determined by the contracting officer or designated representative (COR) at the expense of the contractor.
xii. The contractor shall have all utilities located prior to commencing work. The contractor shall be responsible for all utility locates during the duration of the contract.
Any damaged caused to utilities shall be the responsibility of the contractor to repair to a like new condition as defined by the contracting officer’s representative (COR).
xiii. The contractor shall request utility outages at a minimum of 15 days through contracting officer or their designated representative (COR).
xiv. Hot work permits and Fire Watch personnel will be required if any cutting, grinding, welding, etc. are to take place. Refer to EM 385-1-1 for requirements.
INSTALLATION:
Install all system components and appurtenances in accordance with manufacturer's printed instructions, UFGS, NEC, IEEE C2, NFPA 70, and all other applicable standards as indicated.
Provide all necessary interconnections, services, and adjustments required for a complete and operational system.
CONTRACTOR DAMAGE:
Contractor must immediately notify the Contracting Officer of damage. Contractor is to repair any damages to like new conditions as determined by the contracting officer or their designated representative, at no additional cost to the government. Promptly repair indicated utility lines or systems damaged during site preparation and construction.
FIELD QUALITY CONTROL: NOT USED
ACCEPTANCE TESTS:
Perform acceptance testing in accordance with manufacture instruction and applicable codes such as UFGS. Provide personnel, equipment, instrumentation, and supplies necessary to perform required testing. Notification of any planned testing shall be given to the Contracting Officer at least 10 days working days prior to any test unless specified. Testing shall not proceed until after the Contractor has received written Contracting Officer's approval of the test plans as specified. The Owners or its representatives and Contract Officer Representatives (COR) shall be present at all tests.
Test plans shall define the tests required by applicable specifications, regulation, code, or instruction, to ensure that the system meets technical, operational, and performance specifications. The test plans shall define milestones for the tests, equipment, personnel, facilities, and supplies required. The test plans shall identify the capabilities and functions to be tested. Provide test reports in booklet form showing all field tests performed, upon completion and testing of the installed system. Measurements shall be tabulated on a pair by pair or strand by strand basis.
Contractor shall submit calibration/certification for all testing equipment for use on the project. Certification must be submitted to the Contracting Officer for approval before use on the project.
5.) INSPECTION AND APPROVAL:
All material and workmanship shall be subject to inspection and approval of the Contracting Officer.
Contractor shall provide Site Safety Health Officer (SSHO).
i. The SSHO shall be a full-time responsibility. The SSHO shall report to a senior project (or corporate) official.
ii. The SSHO(s), as a minimum, must have completed the 30-hour OSHA Construction Safety Class or an equivalent, applicable to the work to be performed and given by qualified instructors. The SSHO is also required to have
(5) years of construction industry safety experience or three (3) years if he possesses a Certified Safety Professional (CSP) or safety and health degree.
iii. The SSHO shall be responsible for managing, implementing and enforcing the Contractor’s Safety and Health Program in accordance with the accepted APP.
iv. The SSHO (or a Designated Representative, as identified in the APP/AHA and as deemed appropriate/equivalent to SSHO by the GDA) shall be on-site at all times when work is being performed
6.) GENERAL ADMINISTRATIVE REQUIREMENTS:
A. SUBMITTALS:
The following items shall be provided within 15 days of project award. Government review will occur 21 days after receipt.
Submittals shall be provided electronically with at least one follow-up paper copy for record purposes.
i. Schedule of Work to include cost loading
ii. List of Proposed Subcontractors
iii. Health and Safety Plan specific
iv. Quality Control Plan specific
v. Accident Prevention Plan specific to Task Order
vi. Qualifications of SSHO and Alternates for approval
vii. Product Data listed in paragraph 3- Technical requirements and specifications. PWD construction manager or construction ET shall review submitted items for approval.
viii. Task Specific AHAs for features of work
ix. Project site layout and other specific plans as specified in SOW
B. REPORTS
The following items shall be provided daily.
i. Production Reports
ii. QC Reports
iii. Safety report
C. END OF CONTRACT DOCUMENTATION
The following items shall be provided at the end of contract:
i. Workmanship Warranty
ii. Manufacturer’s Materials Warranties
iii. New equipment operations & maintenance manual (O&M)
D. DAILY DOCUMENTATION
The following items shall be provided daily.
i. Production Reports
ii. QC Reports
iii. Safety Reports
7.) EXAMINATION OF PREMISES:
The contractor shall verify all field conditions, dimensions, quantities, current conditions and all work necessary to complete the job in accordance with the base contract. The Contractor can check with Engineering Office, Public Works Department at Building M207 for copies of current condition drawings, if they exist. For more information call the Engineering Aid office at ext. 5677, during regular working hours
8.) ENVIRONMENTAL CONSIDERATIONS:
All Construction sites are required to adhere to the following specifications in regards to environmental considerations: 01 57 19 Temporary Environmental Controls and 01 57 19.01 20 Supplemental Temporary Environmental Controls.
The Contractor must avoid disturbing any hazardous materials to the fullest extent possible while being able to accomplish the work.
ASBESTOS ABATEMENT – Not Used
LEAD-BASED PAINT ABATEMENT – Not used
SWPPP – Not used
COMMENCEMENT, EXECUTION AND COMPLETION OF WORK:
The Contractor shall complete work within the timeline define in the base JOC contract 120 calendar days or as directed by the Contracting Officer. The Contractor is required to execute the work diligently and all workmanship shall be of the highest quality.
9.) MINOR MATERIALS AND WORK:
Minor materials and work not specifically mentioned herein but necessary for the proper completion of the specified work shall be furnished without additional cost to the Government.
10.) POINTS OF CONTACT:
i. Design Manager: Elijah Goodson
Email: Elijah.goodson@navy.mil Phone: 904-542-4183
ii. Contract Specialist -
Email: Phone:
iii. Construction Manager -
Email: Phone:
iv. d. Engineering Technician -
Email: Phone:
11.) ESTIMATED COST RANGE:
Less than 25,000$
“Submission of a bid proposal by contractors constitutes acknowledgement and acceptant of all items indicated in this
Statement of Work. Contractor agrees to entire scope of work as written unless specifically removed or changed in his proposal.”
Add all drawing or pictures to this section that are applicable to the contract.