Cover Sheet
Instructions
Offeror:
NASA Fire Services Contract (NFSC) Price Proposal Template Instructions:
General Instructions:
1. The price template instructions listed below are provided to assist the Offeror in completing each worksheet tab. Offeror will be responsible for submitting a complete and mathematically accurate file submission to the Government.
| 2. | The Offeror (i.e., prime contractor) shall complete Attachment F2 NFSC Price Proposal, its subcontractors shall complete Attachment F3 NFSC Subcontractor Price Template and return in the native format. Attachment F2 NFSC Price Proposal Template shall represent a fully integrated pricing strategy to include all subcontractor(s)/team members. In addition, the pricing template shall encompass all proposed prices associated with the requirements of the RFP. | NFSC Period of Performance | | | | | | | | | | |
| | NASA Location | Phase In | Base Period | | Option 1 | Option 2 | Option 3 | Option 4 | Option 5 | Option 6 | Contract Total Months |
| | | | GFY 22 | GFY 23 | GFY 24 | GFY 25 | GFY 26 | GFY 27 | GFY 28 | GFY 29 | |
| | | 60 days | 10 months | 1 year | 1 year | 1 year | 1 year | 1 year | 1 year | 1 year | |
| | Ames Research Center (ARC) | 8/1/22 | | 10/1/22 | 10/1/23 | 10/1/24 | 10/1/25 | 10/1/26 | 10/1/27 | 10/1/28 | |
| | | 9/30/22 | | 9/30/23 | 9/30/24 | 9/30/25 | 9/30/26 | 9/30/27 | 9/30/28 | 9/30/29 | |
| 3. | The NFSC contract Period of Performance (POP) table for each location by Government Fiscal Year (GFY) is provided in the table to the right. The potential NFSC POP is 7-years 10-months, which consists of a 2-year base period and 6 one-year option periods. The specific dates are available in the POP table. The Phase-in period for each location shall not exceed 60 days. | | 2 | | 12 | 12 | 12 | 12 | 12 | 12 | 12 | 84 |
| | Kennedy Space Center (KSC) | 8/1/22 | | 10/1/22 | 10/1/23 | 10/1/24 | 10/1/25 | 10/1/26 | 10/1/27 | 10/1/28 | |
| | | 9/30/22 | | 9/30/23 | 9/30/24 | 9/30/25 | 9/30/26 | 9/30/27 | 9/30/28 | 9/30/29 | |
| | | 2 | | 12 | 12 | 12 | 12 | 12 | 12 | 12 | 84 |
| | Stennis Space Center (SSC) | 5/1/25 | | | | 7/1/25 | 10/1/25 | 10/1/26 | 10/1/27 | 10/1/28 | |
| | | 6/30/25 | | | | 9/30/25 | 9/30/26 | 9/30/27 | 9/30/28 | 9/30/29 | |
| 4. | Offerors shall not propose escalation on classification subject to Wage Determinations (i.e., area/prevailing in the locality and collective bargaining agreements) Offerors shall not propose a lower rate than the one provided for each classification subject to wage determinations. | | 2 | | | | 3 | 12 | 12 | 12 | 12 | 51 |
| | Wallops Flight Facility (WFF) | 10/1/21 | 12/1/21 | 10/1/22 | 10/1/23 | 10/1/24 | 10/1/25 | 10/1/26 | 10/1/27 | 10/1/28 | |
| | | 11/30/21 | 9/30/22 | 9/30/23 | 9/30/24 | 9/30/25 | 9/30/26 | 9/30/27 | 9/30/28 | 9/30/29 | |
| | | 2 | 10 | 12 | 12 | 12 | 12 | 12 | 12 | 12 | 94 |
| 5. | This workbook contains a hidden worksheet/tab titled "Drop Down List" that is used for the pull down menus in the workbook. To make sure the pull down menus work properly, please do not modify or alter the table data in the "Drop Down List" tab. | White Sands Test Facility (WSTF) | 8/1/22 | | 10/1/22 | 10/1/23 | 10/1/24 | 10/1/25 | 10/1/26 | 10/1/27 | 10/1/28 | |
| | | 9/30/22 | | 9/30/23 | 9/30/24 | 9/30/25 | 9/30/26 | 9/30/27 | 9/30/28 | 9/30/29 | |
| | | 2 | | 12 | 12 | 12 | 12 | 12 | 12 | 12 | 84 |
6. The Excel workbook provided by the Government contains necessary formulas to accurately summarize the Offeror inputs. If the Offeror changes or adds any formulas, it shall provide narrative support which fully details and explains the changes in their price volume submittal.
7. Reserved
Pricing Template Preparation Instructions by Worksheet Tab:
| To the extent applicable to its proposal, each Offeror shall develop and complete the following worksheet tabs [Summary, Baseline Services, IDIQ Unit Rates, IDIQ Hourly Rates, Phase In, GFY 22 DL, GFY 23 DL ,GFY 24 DL, GFY 25 DL, GFY 26 DL, GFY 27 DL, GFY 28 DL, GFY 29 DL, ODC, Subcontractor, IDIQ Unit Rates, and IDIQ Hourly Rates_BEQ]. Within each worksheet tab there is a table that can be expanded if needed to add more supporting data. Please keep all added data within the table so the summary table will populate all of the proposed information. The pricing template preparation instructions assists the Offeror in developing and completing each worksheet tabs. However, it is the Offeror's responsibility to make sure that each data worksheet tab is filled in correctly and then summarized to create a proposed price. | | Template/Worksheet Tabs | |
| | Cover Sheet | |
| | Instructions | |
| | Summary | |
| | Baseline Services | |
| | IDIQ Unit Rates | |
| | IDIQ Hourly Rates | |
| | Phase In | |
| | Direct Labor | |
| | | GFY 22 DL |
| Summary | | GFY 23 DL |
| 1. | No Offeror input or modification is required for this tab. This tab summarizes the Offerors proposed price by location and Elements of Cost for the base period and option years. The buttons to the right of the summarized pivot tables can be used to filter the specific data by location or Elements of Cost for each GFY. The summarized data that populates the summary table on this tab will be pulled from each of the Green highlighted tabs in this template: [Phase In, GFY 22 DL, GFY 23 DL ,GFY 24 DL, GFY 25 DL, GFY 26 DL, GFY 27 DL, GFY 28 DL, GFY 29 DL, ODC, Subcontractor, and IDIQ Unit Rates_BEQ]. The first Summary tables will pull the Total Hours and Total GFY Dollars Burdened thru Profit and then the second table will separate and pull each location Total GFY Dollars Burdened thru Profit (using SUMIFS formula) from each of the NFSC contract element of cost worksheet tabs [Phase In, GFY 22 DL, GFY 23 DL ,GFY 24 DL, GFY 25 DL, GFY 26 DL, GFY 27 DL, GFY 28 DL, and GFY 29 DL, ODC, Subcontractor, and IDIQ Unit Rates_BEQ] that will result in the Total Price to the Government. For the excel SumIfs formula to work correctly the Offeror will need to select the correct location acronym (ARC, KSC, SSC, WFF, and WSTF). Offerors are advised there is a Government provided note in Summary tab, Cell M15. | | GFY 24 DL |
| | | GFY 25 DL |
| | | GFY 26 DL |
| | | GFY 27 DL |
| | | GFY 28 DL |
| | | GFY 29 DL |
| | ODC | |
| | Subcontractor | |
| | IDIQ Unit Rates | |
| | Drop Down List (hidden tab) | |
| 2. | Baseline Services: |
| No Offeror input or modifications are required for this tab. This tab summarizes the Offeror's proposed Baseline Services and Pre-priced Optional Services total price to the Government by Contract Line Item Number (CLIN) for the base period and option years. The summarized data that populates this tab will be pulled from each of the following Green highlighted tabs (column Z): [GFY 22 DL, GFY 23 DL ,GFY 24 DL, GFY 25 DL, GFY 26 DL, GFY 27 DL, GFY 28 DL, GFY 29 DL]. The Total Price to the Government shall include the Offeror allocate of nonlabor fully burdened dollars (e.g. from ODC, Subcontractor tabs) and will exclude the IDIQ Unit Rates_BEQ, as applicable. The Baseline Services summary will also include GSA Fleet Vehicles, Maintenance and Fuel Baseline Services and Government Directed Travel that will be pulled from the ODC tab. |
| 3. | IDIQ Unit Rates: |
| Offeror’s shall provide the price for each of the IDIQ Unit Rates in Green background shaded cells in this tab. The data needed in this tab consist of base period and option years: IDIQ Unit Rates - Labor Category and Total IDIQ Unit Price to the Government. The price lists for IDIQ Unit Rates shall include all compensation (wages and fringe benefits); Other Direct Cost (ODC) including materials, equipment, vehicles, transportation, subcontractors, certification/recertification, and any other non-labor direct cost); General and Administrative (G&A), overhead, and any other indirect as applicable, and profit unless explicitly instructed to be priced separately. |
| 4. | IDIQ Hourly Rates: |
| No Offeror input or modification are required for this worksheet it is completely formula driven. This tab summarizes the Offeror's proposed Fully Burdened Labor Rate thru Profit for the base period and option years. The summarized data that populates this tab will be pulled from each of the following green highlighted tabs (column L): [GFY 22 DL, GFY 23 DL , GFY 24 DL, GFY 25 DL, GFY 26 DL, GFY 27 DL, GFY 28 DL, and GFY 29 DL] using Vlookup formula after the pricing information is provided. The price list for IDIQ Hourly Rates shall consist of fully-burdened hourly labor rates to be used by the Government in negotiating and ordering additional requirements as needed. IDIQ Hourly Rates shall match the fully burdened labor rates used for the Baseline Services price list (excludes pre-priced options). |
The fringe dollars to be proposed in column J, "Fringe Dollars to be added to Labor Rate," shall account for straight-time, overtime, and double-time hour identified in columns O-Q, "Total Straight Time Hours," "Total Over Time Hours," and "Total Double Time Hours".
| 5. | Phase In: |
| Offeror’s shall provide the prices requested in Green background shaded cells in this tab. The pricing data proposed in this tab shall represent the offeror’s Total Price to the Government necessary to perform all phase-in requirements of this RFP. Offeror Phase-In price shall not exceed 60 days for each location (ARC, KSC, SSC, WFF and WSTF). The Offeror may propose $0 for Phase-In; however, the Offeror's shall identify the value of the Phase-In in its pricing narrative. The "Phase-In" tab requires the offeror’s to provide it Total Price to the Government for all proposed phase-in activities. |
| 6. | GFY 22, 23, 24, 25, 26, 27, 28, & 29 DL: |
| The Offeror shall input their proposed pricing data into the Green background shaded cells in each of the Direct Labor worksheet tabs [GFY 22 DL, GFY 23 DL ,GFY 24 DL, GFY 25 DL, GFY 26 DL, GFY 27 DL, GFY 28 DL, and GFY 29 DL]. The data needed in these Direct Labor worksheet tabs consist of each contract year's labor categories (Offeror's Labor Categories cross mapped to the equivalent Government Labor Category), labor types (Exempt, Non-Exempt/Non-Represented, Collective Bargaining Agreement, Wage Determination), Direct Labor Rates (straight time, overtime, double time, fully burdened), labor hours (straight time, overtime, double time, subcontractor, and total hours), and total labor dollars (straight time, overtime, double time, and burdened thru profit) as outlined in the RFP and requirements. Also, required are fringe , indirect and profit dollars being added to labor rates which will provide total fringe, indirect and profit dollars that are calculated in accordance with the Offerors disclosed and or accounting practice. The Offeror will enter their own Labor Categories that are applicable to the Government provided Equivalent Government Labor Category (column B), location (column C), CLIN (column D), PWS (column E), and labor type (column F) from a drop down menu provided on each GFY 22 DL, GFY 23 DL ,GFY 24 DL, GFY 25 DL, GFY 26 DL, GFY 27 DL, GFY 28 DL, and GFY 29 DL tabs. Once the Offeror inputs the Labor Categories in GFY 22 DL tab in column A, then the same data will copy over to the GFY 23 DL ,GFY 24 DL, GFY 25 DL, GFY 26 DL, GFY 27 DL, GFY 28 DL, and GFY 29 DL tabs. The Offeror must ensure each item listed (e.g. location and CLIN) in the drop down menu is selected for the summary table to pull all the data correctly. The Offeror will need to add their own calculation of labor rates and hours to create the "Total Hours (Prime and Sub)" and "Total Labor Dollars Burdened thru Profit" in accordance with their own disclosed and or accounting practice for the applicable labor category. To verify that each Offeror is consistent with the minimum hours for each labor category, as provided by the Government, conditional formatting has been added to the "Total Hours (Prime and Sub)" (column S) of each labor tab. |
(i) Note: Subcontractor labor hours from Attachment F3 NFSC Subcontractor Price Template shall be added to column R on each GFY 22, 23, 24, 25, 26, 27, 28, & 29 DL tab. This is due to the verification of each Offeror Total Hours (Prime and Sub) is consistent with the minimum hours for each labor category, as provided by the Government
(ii) Note: For each labor category, allocate fully burdened nonlabor dollars from the ODC and Subcontractor tabs, as applicable to the Total Labor Dollars Burdened thru Profit (see column Z).
| 7. | ODC |
| Offeror’s shall provide the prices requested in Green background shaded cells in this tab for Other Direct Cost (ODC)/Non-Labor Item(s). The data needed in this tab consist of the summarized dollars for the base period and option years: ODC/Non-labor Items and associated total ODC summarized dollars burdened thru profit. The Offeror will need to add or input their own ODC/Non-labor item names that are applicable to the total ODC dollars burdened thru profit. The proposed ODC/Non-Labor Item(s) could include (not limited to): supplies, materials, equipment, uniforms, training, vehicles, maintenance, fuel, travel, or ODC expenses not classified elsewhere. The Offeror is required to select the applicable location (column B) from a drop down menu provided on the worksheet tab that matches the correct ODC/Non-labor items. Once ODC/Non-labor Items Total Dollars Burdened thru Profit are entered for the whole period of performance then the table will calculate the Total ODC/Non-Labor Dollars (Base + Options). The Summary worksheet tab will pull the Total GFY Dollars Burdened thru Profit and then it will separate and pull each location Total GFY Dollars Burdened thru Profit. In addition to the regular ODC/Non-labor Items pricing for the Contract, the Offeror is required to provide ODC/Non-labor Items that would be needed for each of the locations Pre-priced Options. |
In accordance with the clause at C.25.4 Non-Routine Property Replacement, the Offeror shall apportion a total value of $575,000 to CLIN prices listed in B.2.1 Baseline Services for KSC. This information will be pre-populated in the ODC tab as a line item for KSC as the following: Base period (GFY 2022-2023): $100,00; Option period 1 (GFY 2024): $50,000, Option period 2 (GFY 2025): $50,000, Option period 3 (GFY 2026): $75,000, Option period 4 (GFY 2027): $75,000, Option period 5 (GFY 2028): $100,000, Option period 6 (GFY 2029): $125,000, and Total (base and all option periods): $575,000.
| 8. | Subcontractors: |
| Offeror’s shall provide the prices requested in Green background shaded cells in this tab. The data needed in this tab consist of each potential contract years: Subcontractors hours and associated total subcontractor dollars burdened thru profit. The Offeror will need to add their own calculation to create the total Subcontractors dollars burdened thru profit in accordance with their own disclosed and or accounting practice. Then the Offeror will need to select the applicable location (column B) from a drop down menu provided on the worksheet tab that matches the applicable Subcontractor. The Offeror will need to verify the Total Hours and Total Dollars (Burdened thru Profit) provided by each subcontract member. (e.g. sum of all team members proposed by the Prime to the Government). |
(i) Attachment F3 NFSC Subcontractor Price Template is required for all subcontractors, regardless of dollar value.
(ii) Subcontractor includes any supplier, distributor, vendor, firm or consultant (including parent or affiliate corporations, divisions, business units, or segments), other than the prime contractor, who offers to furnish or furnishes any supplies, materials, equipment, or services of any kind under a prime contract or a subcontract entered into in connection with such prime contract.
(iii) Subcontractor may submit Attachment F3 NFSC Subcontractor Price Template as part of the Prime's proposal submittal to the Government or directly to the Government in accordance with provision F.4 Addendum to FAR 52.212-1 Offerors-Commercial Items: Tailored Paragraphs.
| 9. | IDIQ Unit Rates_BEQ: |
| No Offeror input or modifications are required for this tab. This tab summarizes the Offeror's proposed IDIQ Unit Rates_BEQ prices by Contract Line Item Number (CLIN) for the base period and option years. The summarized data that populates this tab will be pulled from the following Green highlighted tab: IDIQ Unit Rates. Within this tab, the price list for IDIQ Unit Rates (all CLINs, base period and all option periods, and all sites) will be multiplied by the Government-provided best-estimated quantities (BEQs) that will calculate the IDIQ Unit Rates_BEQ total price to the Government (Based on unit price for each item identified in Column A multiplied by the Govt' provided BEQ found in Column D). BEQ’s are the same for each year of contract performance (base period and all option periods). Offerors shall not change the BEQ values in the IDIQ Unit Rates_BEQ tab. BEQs are for evaluation purposes only and do not represent a limit or guarantee of future work nor do they represent an obligation, commitment, or amount to be ordered by the Government. Because of the uncertainties involved, there will be no stated minimum or maximum quantities for each CLIN specified in the IDIQ Unit Rates price list, and no future adjustment to the resulting price list, increase or decrease, will be made as a result of ordering above or below the BEQs. |
Summary NASA Fire Services Contract (NFSC) Price Proposal Template - Phase In - Dollars Burdened thru Profit
| | Total Summary | |
| | Elements of Cost | Phase In (60 days) |
| (Fully Burdened) | Base Period-Year 1 | | |
Total Price to the Government (GFY 22) Base Period-Year 2 Total Price to the Government (GFY 23) Option 1 Total Price to the Government (GFY 24) Option 2 Total Price to the Government (GFY 25) Option 3 Total Price to the Government (GFY 26) Option 4 Total Price to the Government (GFY 27) Option 5 Total Price to the Government (GFY 28) Option 6 Total Price to the Government
| (GFY 29) | Total Price to the Government (GFY 22-29) | Total Evaluated Price (Phase-In + GFY 22-29) | | | | | | | | | | | |
| | Gov't Minimum Hours | | 65,998 | 555,660 | 555,660 | 647,100 | 630,020 | 630,020 | 630,020 | 630,020 | 4,344,498 | |
| | Total Proposed Hours | | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
| | Direct Labor | | | | | | | | | | | |
| (unburdened) | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | | |
| | DL Fringe Benefits | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| | DL Indirect/Profit | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| | ODC/Non-Labor | | | | | | | | | | | |
| (Fully Burdened) | | $ 50,000 | $ 50,000 | $ 50,000 | $ 50,000 | $ 75,000 | $ 75,000 | $ 100,000 | $ 125,000 | $ 575,000 | $ 575,000 | | |
| | Subcontractor | | | | | | | | | | | |
| (Fully Burdened) | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | | |
| | IDIQ (by BEQ) | | | | | | | | | | | |
| (Fully Burdened) | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | | |
| | Total | $ - 0 | $ 50,000 | $ 50,000 | $ 50,000 | $ 50,000 | $ 75,000 | $ 75,000 | $ 100,000 | $ 125,000 | $ 575,000 | $ 575,000 |
| | Total Evaluated Price | | | | | | | | | | | |
| (Allocated) | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | Note: Cell L13 and L54 must equal Cell L15 | |
| | | | | | | | | | | | $ 575,000 | $ 575,000 |
| NASA Location and Element of Cost Summary - The Offeror will need to make sure that the NASA Location is selected from the drop down menu for the summary table to pull all the data correctly. | | | | | | | | | | | | |
| NASA Location | Elements of Cost | Phase In (60 days) | | | | | | | | | | |
| (Fully Burdened) | Base Period-Year 1 | | | | | | | | | | | | |
Total Price to the Government (GFY 22) Base Period-Year 2 Total Price to the Government (GFY 23) Option 1 Total Price to the Government (GFY 24) Option 2 Total Price to the Government (GFY 25) Option 3 Total Price to the Government (GFY 26) Option 4 Total Price to the Government (GFY 27) Option 5 Total Price to the Government (GFY 28) Option 6 Dollars Burdened thru Profit
| (GFY 29) | Total Hours and Total Price to the Government (GFY 22-29) | Total Evaluated Price (Phase-In + GFY 22-29) | | | | | | | | | | | |
| KSC | Total Hours | | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
| KSC | Direct Labor | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| KSC | ODC/Non-Labor | | $ 50,000 | $ 50,000 | $ 50,000 | $ 50,000 | $ 75,000 | $ 75,000 | $ 100,000 | $ 125,000 | $ 575,000 | |
| KSC | Subcontractor | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| KSC | IDIQ (by BEQ) | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| KSC | Total (per Location) | $ - 0 | $ 50,000 | $ 50,000 | $ 50,000 | $ 50,000 | $ 75,000 | $ 75,000 | $ 100,000 | $ 125,000 | $ 575,000 | $ 575,000 |
| WFF | Total Hours | | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
| WFF | Direct Labor | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| WFF | ODC/Non-Labor | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| WFF | Subcontractor | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| WFF | IDIQ (by BEQ) | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| WFF | Total (per Location) | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| ARC | Total Hours | | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
| ARC | Direct Labor | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| ARC | ODC/Non-Labor | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| ARC | Subcontractor | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| ARC | IDIQ (by BEQ) | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| ARC | Total (per Location) | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| SSC | Total Hours | | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
| SSC | Direct Labor | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| SSC | ODC/Non-Labor | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| SSC | Subcontractor | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| SSC | IDIQ (by BEQ) | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| SSC | Total (per Location) | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| WSTF | Total Hours | | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
| WSTF | Direct Labor | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| WSTF | ODC/Non-Labor | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| WSTF | Subcontractor | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| WSTF | IDIQ (by BEQ) | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| WSTF | Total (per Location) | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total | Total Hours | | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
| Total | Direct Labor | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| Total | ODC/Non-Labor | $ - 0 | $ 50,000 | $ 50,000 | $ 50,000 | $ 50,000 | $ 75,000 | $ 75,000 | $ 100,000 | $ 125,000 | $ 575,000 | |
| Total | Subcontractor | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| Total | IDIQ (by BEQ) | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| Total Price (GFY) | | $ - 0 | $ 50,000 | $ 50,000 | $ 50,000 | $ 50,000 | $ 75,000 | $ 75,000 | $ 100,000 | $ 125,000 | $ 575,000 | $ 575,000 |
| | | | | | | | | | | | $ - 0 | $ - 0 |
Baseline Services
| LOCATION | CLIN | DESCRIPTION | CONTRACT CLIN TYPE | CONTRACT PERIOD | Date Start | Date End | Total Price to the Government |
| KSC | K001.0 | Program Management | Baseline Services | Base Period | 12/1/21 | 9/30/23 | $ - 0 |
| KSC | K002.0 | Fire Services | Baseline Services | Base Period | 10/1/22 | 9/30/23 | $ - 0 |
| KSC | K002.1 | Fire Station #2 Two Additional Firefighter/Lieutenants Pre-priced Option | Pre-priced Optional Services | Base Period | 10/1/22 | 9/30/23 | $ - 0 |
| KSC | K002.2 | Fire Station #3 Pre-priced Option | Pre-priced Optional Services | Base Period | 10/1/22 | 9/30/23 | $ - 0 |
| KSC | K003.0 | GSA Fleet Vehicles, Maintenance and Fuel | Baseline Services | Base Period | 10/1/22 | 9/30/23 | $ - 0 |
| KSC | K004.0 | Government Directed Travel | Baseline Services | Base Period | 10/1/22 | 9/30/23 | $ - 0 |
| KSC | K101.0 | Program Management | Baseline Services | Option Year 1 | 10/1/23 | 9/30/24 | $ - 0 |
| KSC | K102.0 | Fire Services | Baseline Services | Option Year 1 | 10/1/23 | 9/30/24 | $ - 0 |
| KSC | K102.1 | Fire Station #2 Two Additional Firefighter/Lieutenants Pre-priced Option | Pre-priced Optional Services | Option Year 1 | 10/1/23 | 9/30/24 | $ - 0 |
| KSC | K102.2 | Fire Station #3 Pre-priced Option | Pre-priced Optional Services | Option Year 1 | 10/1/23 | 9/30/24 | $ - 0 |
| KSC | K103.0 | GSA Fleet Vehicles, Maintenance and Fuel | Baseline Services | Option Year 1 | 10/1/23 | 9/30/24 | $ - 0 |
| KSC | K104.0 | Government Directed Travel | Baseline Services | Option Year 1 | 10/1/23 | 9/30/24 | $ - 0 |
| KSC | K201.0 | Program Management | Baseline Services | Option Year 2 | 10/1/24 | 9/30/25 | $ - 0 |
| KSC | K202.0 | Fire Services | Baseline Services | Option Year 2 | 10/1/24 | 9/30/25 | $ - 0 |
| KSC | K202.1 | Fire Station #2 Two Additional Firefighter/Lieutenants Pre-priced Option | Pre-priced Optional Services | Option Year 2 | 10/1/24 | 9/30/25 | $ - 0 |
| KSC | K202.2 | Fire Station #3 Pre-priced Option | Pre-priced Optional Services | Option Year 2 | 10/1/24 | 9/30/25 | $ - 0 |
| KSC | K203.0 | GSA Fleet Vehicles, Maintenance and Fuel | Baseline Services | Option Year 2 | 10/1/24 | 9/30/25 | $ - 0 |
| KSC | K204.0 | Government Directed Travel | Baseline Services | Option Year 2 | 10/1/24 | 9/30/25 | $ - 0 |
| KSC | K301.0 | Program Management | Baseline Services | Option Year 3 | 10/1/25 | 9/30/26 | $ - 0 |
| KSC | K302.0 | Fire Services | Baseline Services | Option Year 3 | 10/1/25 | 9/30/26 | $ - 0 |
| KSC | K302.1 | Fire Station #2 Two Additional Firefighter/Lieutenants Pre-priced Option | Pre-priced Optional Services | Option Year 3 | 10/1/25 | 9/30/26 | $ - 0 |
| KSC | K302.2 | Fire Station #3 Pre-priced Option | Pre-priced Optional Services | Option Year 3 | 10/1/25 | 9/30/26 | $ - 0 |
| KSC | K303.0 | GSA Fleet Vehicles, Maintenance and Fuel | Baseline Services | Option Year 3 | 10/1/25 | 9/30/26 | $ - 0 |
| KSC | K304.0 | Government Directed Travel | Baseline Services | Option Year 3 | 10/1/25 | 9/30/26 | $ - 0 |
| KSC | K401.0 | Program Management | Baseline Services | Option Year 4 | 10/1/26 | 9/30/27 | $ - 0 |
| KSC | K402.0 | Fire Services | Baseline Services | Option Year 4 | 10/1/26 | 9/30/27 | $ - 0 |
| KSC | K402.1 | Fire Station #2 Two Additional Firefighter/Lieutenants Pre-priced Option | Pre-priced Optional Services | Option Year 4 | 10/1/26 | 9/30/27 | $ - 0 |
| KSC | K402.2 | Fire Station #3 Pre-priced Option | Pre-priced Optional Services | Option Year 4 | 10/1/26 | 9/30/27 | $ - 0 |
| KSC | K403.0 | GSA Fleet Vehicles, Maintenance and Fuel | Baseline Services | Option Year 4 | 10/1/26 | 9/30/27 | $ - 0 |
| KSC | K404.0 | Government Directed Travel | Baseline Services | Option Year 4 | 10/1/26 | 9/30/27 | $ - 0 |
| KSC | K501.0 | Program Management | Baseline Services | Option Year 5 | 10/1/27 | 9/30/28 | $ - 0 |
| KSC | K502.0 | Fire Services | Baseline Services | Option Year 5 | 10/1/27 | 9/30/28 | $ - 0 |
| KSC | K502.1 | Fire Station #2 Two Additional Firefighter/Lieutenants Pre-priced Option | Pre-priced Optional Services | Option Year 5 | 10/1/27 | 9/30/28 | $ - 0 |
| KSC | K502.2 | Fire Station #3 Pre-priced Option | Pre-priced Optional Services | Option Year 5 | 10/1/27 | 9/30/28 | $ - 0 |
| KSC | K503.0 | GSA Fleet Vehicles, Maintenance and Fuel | Baseline Services | Option Year 5 | 10/1/27 | 9/30/28 | $ - 0 |
| KSC | K504.0 | Government Directed Travel | Baseline Services | Option Year 5 | 10/1/27 | 9/30/28 | $ - 0 |
| KSC | K601.0 | Program Management | Baseline Services | Option Year 6 | 10/1/28 | 9/30/29 | $ - 0 |
| KSC | K602.0 | Fire Services | Baseline Services | Option Year 6 | 10/1/28 | 9/30/29 | $ - 0 |
| KSC | K602.1 | Fire Station #2 Two Additional Firefighter/Lieutenants Pre-priced Option | Pre-priced Optional Services | Option Year 6 | 10/1/28 | 9/30/29 | $ - 0 |
| KSC | K602.2 | Fire Station #3 Pre-priced Option | Pre-priced Optional Services | Option Year 6 | 10/1/28 | 9/30/29 | $ - 0 |
| KSC | K603.0 | GSA Fleet Vehicles, Maintenance and Fuel | Baseline Services | Option Year 6 | 10/1/28 | 9/30/29 | $ - 0 |
| KSC | K604.0 | Government Directed Travel | Baseline Services | Option Year 6 | 10/1/28 | 9/30/29 | $ - 0 |
| LOCATION | CLIN | DESCRIPTION | CONTRACT CLIN TYPE | CONTRACT PERIOD | Date Start | Date End | Total Price to the Government |
| WFF | W001.0 | Program Management | Baseline Services | Base Period | 12/1/21 | 9/30/23 | $ - 0 |
| WFF | W002.0 | Fire Services | Baseline Services | Base Period | 12/1/21 | 9/30/23 | $ - 0 |
| WFF | W002.1 | Station #26-2 24hrs Ops Prepriced Option | Pre-priced Optional Services | Base Period | 12/1/21 | 9/30/23 | $ - 0 |
| WFF | W002.2 | One Deputy Fire Chief Pre-priced Option | Pre-priced Optional Services | Base Period | 12/1/21 | 9/30/23 | $ - 0 |
| WFF | W002.3 | Assistant Chief of Fire Prevention Pre-priced Option | Pre-priced Optional Services | Base Period | 12/1/21 | 9/30/23 | $ - 0 |
| WFF | W003.0 | GSA Fleet Vehicles, Maintenance and Fuel | Baseline Services | Base Period | 12/1/21 | 9/30/23 | $ - 0 |
| WFF | W004.0 | Government Directed Travel | Baseline Services | Base Period | 12/1/21 | 9/30/23 | $ - 0 |
| WFF | W101.0 | Program Management | Baseline Services | Option Year 1 | 10/1/23 | 9/30/24 | $ - 0 |
| WFF | W102.0 | Fire Services | Baseline Services | Option Year 1 | 10/1/23 | 9/30/24 | $ - 0 |
| WFF | W102.1 | Station #26-2 24hrs Ops Prepriced Option | Pre-priced Optional Services | Option Year 1 | 10/1/23 | 9/30/24 | $ - 0 |
| WFF | W102.2 | One Deputy Fire Chief Pre-priced Option | Pre-priced Optional Services | Option Year 1 | 10/1/23 | 9/30/24 | $ - 0 |
| WFF | W102.3 | Assistant Chief of Fire Prevention Pre-priced Option | Pre-priced Optional Services | Option Year 1 | 10/1/23 | 9/30/24 | $ - 0 |
| WFF | W103.0 | GSA Fleet Vehicles, Maintenance and Fuel | Baseline Services | Option Year 1 | 10/1/23 | 9/30/24 | $ - 0 |
| WFF | W104.0 | Government Directed Travel | Baseline Services | Option Year 1 | 10/1/23 | 9/30/24 | $ - 0 |
| WFF | W201.0 | Program Management | Baseline Services | Option Year 2 | 10/1/24 | 9/30/25 | $ - 0 |
| WFF | W202.0 | Fire Services | Baseline Services | Option Year 2 | 10/1/24 | 9/30/25 | $ - 0 |
| WFF | W202.1 | Station #26-2 24hrs Ops Prepriced Option | Pre-priced Optional Services | Option Year 2 | 10/1/24 | 9/30/25 | $ - 0 |
| WFF | W202.2 | One Deputy Fire Chief Pre-priced Option | Pre-priced Optional Services | Option Year 2 | 10/1/24 | 9/30/25 | $ - 0 |
| WFF | W202.3 | Assistant Chief of Fire Prevention Pre-priced Option | Pre-priced Optional Services | Option Year 2 | 10/1/24 | 9/30/25 | $ - 0 |
| WFF | W203.0 | GSA Fleet Vehicles, Maintenance and Fuel | Baseline Services | Option Year 2 | 10/1/24 | 9/30/25 | $ - 0 |
| WFF | W204.0 | Government Directed Travel | Baseline Services | Option Year 2 | 10/1/24 | 9/30/25 | $ - 0 |
| WFF | W301.0 | Program Management | Baseline Services | Option Year 3 | 10/1/25 | 9/30/26 | $ - 0 |
| WFF | W302.0 | Fire Services | Baseline Services | Option Year 3 | 10/1/25 | 9/30/26 | $ - 0 |
| WFF | W302.1 | Station #26-2 24hrs Ops Prepriced Option | Pre-priced Optional Services | Option Year 3 | 10/1/25 | 9/30/26 | $ - 0 |
| WFF | W302.2 | One Deputy Fire Chief Pre-priced Option | Pre-priced Optional Services | Option Year 3 | 10/1/25 | 9/30/26 | $ - 0 |
| WFF | W302.3 | Assistant Chief of Fire Prevention Pre-priced Option | Pre-priced Optional Services | Option Year 3 | 10/1/25 | 9/30/26 | $ - 0 |
| WFF | W303.0 | GSA Fleet Vehicles, Maintenance and Fuel | Baseline Services | Option Year 3 | 10/1/25 | 9/30/26 | $ - 0 |
| WFF | W304.0 | Government Directed Travel | Baseline Services | Option Year 3 | 10/1/25 | 9/30/26 | $ - 0 |
| WFF | W401.0 | Program Management | Baseline Services | Option Year 4 | 10/1/26 | 9/30/27 | $ - 0 |
| WFF | W402.0 | Fire Services | Baseline Services | Option Year 4 | 10/1/26 | 9/30/27 | $ - 0 |
| WFF | W402.1 | Station #26-2 24hrs Ops Prepriced Option | Pre-priced Optional Services | Option Year 4 | 10/1/26 | 9/30/27 | $ - 0 |
| WFF | W402.2 | One Deputy Fire Chief Pre-priced Option | Pre-priced Optional Services | Option Year 4 | 10/1/26 | 9/30/27 | $ - 0 |
| WFF | W402.3 | Assistant Chief of Fire Prevention Pre-priced Option | Pre-priced Optional Services | Option Year 4 | 10/1/26 | 9/30/27 | $ - 0 |
| WFF | W403.0 | GSA Fleet Vehicles, Maintenance and Fuel | Baseline Services | Option Year 4 | 10/1/26 | 9/30/27 | $ - 0 |
| WFF | W404.0 | Government Directed Travel | Baseline Services | Option Year 4 | 10/1/26 | 9/30/27 | $ - 0 |
| WFF | W501.0 | Program Management | Baseline Services | Option Year 5 | 10/1/27 | 9/30/28 | $ - 0 |
| WFF | W502.0 | Fire Services | Baseline Services | Option Year 5 | 10/1/27 | 9/30/28 | $ - 0 |
| WFF | W502.1 | Station #26-2 24hrs Ops Prepriced Option | Pre-priced Optional Services | Option Year 5 | 10/1/27 | 9/30/28 | $ - 0 |
| WFF | W502.2 | One Deputy Fire Chief Pre-priced Option | Pre-priced Optional Services | Option Year 5 | 10/1/27 | 9/30/28 | $ - 0 |
| WFF | W502.3 | Assistant Chief of Fire Prevention Pre-priced Option | Pre-priced Optional Services | Option Year 5 | 10/1/27 | 9/30/28 | $ - 0 |
| WFF | W503.0 | GSA Fleet Vehicles, Maintenance and Fuel | Baseline Services | Option Year 5 | 10/1/27 | 9/30/28 | $ - 0 |
| WFF | W504.0 | Government Directed Travel | Baseline Services | Option Year 5 | 10/1/27 | 9/30/28 | $ - 0 |
| WFF | W601.0 | Program Management | Baseline Services | Option Year 6 | 10/1/28 | 9/30/29 | $ - 0 |
| WFF | W602.0 | Fire Services | Baseline Services | Option Year 6 | 10/1/28 | 9/30/29 | $ - 0 |
| WFF | W602.1 | Station #26-2 24hrs Ops Prepriced Option | Pre-priced Optional Services | Option Year 6 | 10/1/28 | 9/30/29 | $ - 0 |
| WFF | W602.2 | One Deputy Fire Chief Pre-priced Option | Pre-priced Optional Services | Option Year 6 | 10/1/28 | 9/30/29 | $ - 0 |
| WFF | W602.3 | Assistant Chief of Fire Prevention Pre-priced Option | Pre-priced Optional Services | Option Year 6 | 10/1/28 | 9/30/29 | $ - 0 |
| WFF | W603.0 | GSA Fleet Vehicles, Maintenance and Fuel | Baseline Services | Option Year 6 | 10/1/28 | 9/30/29 | $ - 0 |
| WFF | W604.0 | Government Directed Travel | Baseline Services | Option Year 6 | 10/1/28 | 9/30/29 | $ - 0 |
| LOCATION | CLIN | DESCRIPTION | CONTRACT CLIN TYPE | CONTRACT PERIOD | Date Start | Date End | Total Price to the Government |
| ARC | A001.0 | Program Management | Baseline Services | Base Period | 10/1/22 | 9/30/23 | $ - 0 |
| ARC | A002.0 | Fire Services - Structural | Baseline Services | Base Period | 10/1/22 | 9/30/23 | $ - 0 |
| ARC | A002.1 | Six Additional Firefighter/Paramedic Pre-priced Option | Pre-priced Optional Services | Base Period | 10/1/22 | 9/30/23 | $ - 0 |
| ARC | A002.2 | Six Additional Firefighter/EMT Pre-priced Option | Pre-priced Optional Services | Base Period | 10/1/22 | 9/30/23 | $ - 0 |
| ARC | A002.3 | Battallion Chief of Training/Safety Pre-priced Option | Pre-priced Optional Services | Base Period | 10/1/22 | 9/30/23 | $ - 0 |
| ARC | A003.0 | Fire Services - Aircraft Rescue and Firefighting (ARFF) | Baseline Services | Base Period | 10/1/22 | 9/30/23 | $ - 0 |
| ARC | A004.0 | GSA Fleet Vehicles, Maintenance and Fuel | Baseline Services | Base Period | 10/1/22 | 9/30/23 | $ - 0 |
| ARC | A005.0 | Government Directed Travel | Baseline Services | Base Period | 10/1/22 | 9/30/23 | $ - 0 |
| ARC | A101.0 | Program Management | Baseline Services | Option Year 1 | 10/1/23 | 9/30/24 | $ - 0 |
| ARC | A102.0 | Fire Services - Structural | Baseline Services | Option Year 1 | 10/1/23 | 9/30/24 | $ - 0 |
| ARC | A102.1 | Six Additional Firefighter/Paramedic Pre-priced Option | Pre-priced Optional Services | Option Year 1 | 10/1/23 | 9/30/24 | $ - 0 |
| ARC | A102.2 | Six Additional Firefighter/EMT Pre-priced Option | Pre-priced Optional Services | Option Year 1 | 10/1/23 | 9/30/24 | $ - 0 |
| ARC | A102.3 | Battallion Chief of Training/Safety Pre-priced Option | Pre-priced Optional Services | Option Year 1 | 10/1/23 | 9/30/24 | $ - 0 |
| ARC | A103.0 | Fire Services - Aircraft Rescue and Firefighting (ARFF) | Baseline Services | Option Year 1 | 10/1/23 | 9/30/24 | $ - 0 |
| ARC | A104.0 | GSA Fleet Vehicles, Maintenance and Fuel | Baseline Services | Option Year 1 | 10/1/23 | 9/30/24 | $ - 0 |
| ARC | A105.0 | Government Directed Travel | Baseline Services | Option Year 1 | 10/1/23 | 9/30/24 | $ - 0 |
| ARC | A201.0 | Program Management | Baseline Services | Option Year 2 | 10/1/24 | 9/30/25 | $ - 0 |
| ARC | A202.0 | Fire Services - Structural | Baseline Services | Option Year 2 | 10/1/24 | 9/30/25 | $ - 0 |
| ARC | A202.1 | Six Additional Firefighter/Paramedic Pre-priced Option | Pre-priced Optional Services | Option Year 2 | 10/1/24 | 9/30/25 | $ - 0 |
| ARC | A202.2 | Six Additional Firefighter/EMT Pre-priced Option | Pre-priced Optional Services | Option Year 2 | 10/1/24 | 9/30/25 | $ - 0 |
| ARC | A202.3 | Battallion Chief of Training/Safety Pre-priced Option | Pre-priced Optional Services | Option Year 2 | 10/1/24 | 9/30/25 | $ - 0 |
| ARC | A203.0 | Fire Services - Aircraft Rescue and Firefighting (ARFF) | Baseline Services | Option Year 2 | 10/1/24 | 9/30/25 | $ - 0 |
| ARC | A204.0 | GSA Fleet Vehicles, Maintenance and Fuel | Baseline Services | Option Year 2 | 10/1/24 | 9/30/25 | $ - 0 |
| ARC | A205.0 | Government Directed Travel | Baseline Services | Option Year 2 | 10/1/24 | 9/30/25 | $ - 0 |
| ARC | A301.0 | Program Management | Baseline Services | Option Year 3 | 10/1/25 | 9/30/26 | $ - 0 |
| ARC | A302.0 | Fire Services - Structural | Baseline Services | Option Year 3 | 10/1/25 | 9/30/26 | $ - 0 |
| ARC | A302.1 | Six Additional Firefighter/Paramedic Pre-priced Option | Pre-priced Optional Services | Option Year 3 | 10/1/25 | 9/30/26 | $ - 0 |
| ARC | A302.2 | Six Additional Firefighter/EMT Pre-priced Option | Pre-priced Optional Services | Option Year 3 | 10/1/25 | 9/30/26 | $ - 0 |
| ARC | A302.3 | Battallion Chief of Training/Safety Pre-priced Option | Pre-priced Optional Services | Option Year 3 | 10/1/25 | 9/30/26 | $ - 0 |
| ARC | A303.0 | Fire Services - Aircraft Rescue and Firefighting (ARFF) | Baseline Services | Option Year 3 | 10/1/25 | 9/30/26 | $ - 0 |
| ARC | A304.0 | GSA Fleet Vehicles, Maintenance and Fuel | Baseline Services | Option Year 3 | 10/1/25 | 9/30/26 | $ - 0 |
| ARC | A305.0 | Government Directed Travel | Baseline Services | Option Year 3 | 10/1/25 | 9/30/26 | $ - 0 |
| ARC | A401.0 | Program Management | Baseline Services | Option Year 4 | 10/1/26 | 9/30/27 | $ - 0 |
| ARC | A402.0 | Fire Services - Structural | Baseline Services | Option Year 4 | 10/1/26 | 9/30/27 | $ - 0 |
| ARC | A402.1 | Six Additional Firefighter/Paramedic Pre-priced Option | Pre-priced Optional Services | Option Year 4 | 10/1/26 | 9/30/27 | $ - 0 |
| ARC | A402.2 | Six Additional Firefighter/EMT Pre-priced Option | Pre-priced Optional Services | Option Year 4 | 10/1/26 | 9/30/27 | $ - 0 |
| ARC | A402.3 | Battallion Chief of Training/Safety Pre-priced Option | Pre-priced Optional Services | Option Year 4 | 10/1/26 | 9/30/27 | $ - 0 |
| ARC | A403.0 | Fire Services - Aircraft Rescue and Firefighting (ARFF) | Baseline Services | Option Year 4 | 10/1/26 | 9/30/27 | $ - 0 |
| ARC | A404.0 | GSA Fleet Vehicles, Maintenance and Fuel | Baseline Services | Option Year 4 | 10/1/26 | 9/30/27 | $ - 0 |
| ARC | A405.0 | Government Directed Travel | Baseline Services | Option Year 4 | 10/1/26 | 9/30/27 | $ - 0 |
| ARC | A501.0 | Program Management | Baseline Services | Option Year 5 | 10/1/27 | 9/30/28 | $ - 0 |
| ARC | A502.0 | Fire Services - Structural | Baseline Services | Option Year 5 | 10/1/27 | 9/30/28 | $ - 0 |
| ARC | A502.1 | Six Additional Firefighter/Paramedic Pre-priced Option | Pre-priced Optional Services | Option Year 5 | 10/1/27 | 9/30/28 | $ - 0 |
| ARC | A502.2 | Six Additional Firefighter/EMT Pre-priced Option | Pre-priced Optional Services | Option Year 5 | 10/1/27 | 9/30/28 | $ - 0 |
| ARC | A502.3 | Battallion Chief of Training/Safety Pre-priced Option | Pre-priced Optional Services | Option Year 5 | 10/1/27 | 9/30/28 | $ - 0 |
| ARC | A503.0 | Fire Services - Aircraft Rescue and Firefighting (ARFF) | Baseline Services | Option Year 5 | 10/1/27 | 9/30/28 | $ - 0 |
| ARC | A504.0 | GSA Fleet Vehicles, Maintenance and Fuel | Baseline Services | Option Year 5 | 10/1/27 | 9/30/28 | $ - 0 |
| ARC | A505.0 | Government Directed Travel | Baseline Services | Option Year 5 | 10/1/27 | 9/30/28 | $ - 0 |
| ARC | A601.0 | Program Management | Baseline Services | Option Year 6 | 10/1/28 | 9/30/29 | $ - 0 |
| ARC | A602.0 | Fire Services - Structural | Baseline Services | Option Year 6 | 10/1/28 | 9/30/29 | $ - 0 |
| ARC | A602.1 | Six Additional Firefighter/Paramedic Pre-priced Option | Pre-priced Optional Services | Option Year 6 | 10/1/28 | 9/30/29 | $ - 0 |
| ARC | A602.2 | Six Additional Firefighter/EMT Pre-priced Option | Pre-priced Optional Services | Option Year 6 | 10/1/28 | 9/30/29 | $ - 0 |
| ARC | A602.3 | Battallion Chief of Training/Safety Pre-priced Option | Pre-priced Optional Services | Option Year 6 | 10/1/28 | 9/30/29 | $ - 0 |
| ARC | A603.0 | Fire Services - Aircraft Rescue and Firefighting (ARFF) | Baseline Services | Option Year 6 | 10/1/28 | 9/30/29 | $ - 0 |
| ARC | A604.0 | GSA Fleet Vehicles, Maintenance and Fuel | Baseline Services | Option Year 6 | 10/1/28 | 9/30/29 | $ - 0 |
| ARC | A605.0 | Government Directed Travel | Baseline Services | Option Year 6 | 10/1/28 | 9/30/29 | $ - 0 |
| LOCATION | CLIN | DESCRIPTION | CONTRACT CLIN TYPE | CONTRACT PERIOD | Date Start | Date End | Total Price to the Government |
| SSC | S201.0 | Program Management | Baseline Services | Option Year 2 | 7/1/25 | 9/30/25 | $ - 0 |
| SSC | S202.0 | Fire Services | Baseline Services | Option Year 2 | 7/1/25 | 9/30/25 | $ - 0 |
| SSC | S202.1 | Firefighter/EMT Pre-priced Option | Pre-priced Optional Services | Option Year 2 | 7/1/25 | 9/30/25 | $ - 0 |
| SSC | S202.2 | Firefighter Pre-priced Option | Pre-priced Optional Services | Option Year 2 | 7/1/25 | 9/30/25 | $ - 0 |
| SSC | S202.3 | Firefighter/Paramedic Pre-priced Option | Pre-priced Optional Services | Option Year 2 | 7/1/25 | 9/30/25 | $ - 0 |
| SSC | S202.4 | Fire Inspector Pre-priced Option | Pre-priced Optional Services | Option Year 2 | 7/1/25 | 9/30/25 | $ - 0 |
| SSC | S202.5 | Fire Protection Specialist Pre-priced Option | Pre-priced Optional Services | Option Year 2 | 7/1/25 | 9/30/25 | $ - 0 |
| SSC | S203.0 | GSA Fleet Vehicles, Maintenance and Fuel | Baseline Services | Option Year 2 | 7/1/25 | 9/30/25 | $ - 0 |
| SSC | S204.0 | Government Directed Travel | Baseline Services | Option Year 2 | 7/1/25 | 9/30/25 | $ - 0 |
| SSC | S301.0 | Program Management | Baseline Services | Option Year 3 | 10/1/25 | 9/30/26 | $ - 0 |
| SSC | S302.0 | Fire Services | Baseline Services | Option Year 3 | 10/1/25 | 9/30/26 | $ - 0 |
| SSC | S302.1 | Firefighter/EMT Pre-priced Option | Pre-priced Optional Services | Option Year 3 | 10/1/25 | 9/30/26 | $ - 0 |
| SSC | S302.2 | Firefighter Pre-priced Option | Pre-priced Optional Services | Option Year 3 | 10/1/25 | 9/30/26 | $ - 0 |
| SSC | S302.3 | Firefighter/Paramedic Pre-priced Option | Pre-priced Optional Services | Option Year 3 | 10/1/25 | 9/30/26 | $ - 0 |
| SSC | S302.4 | Fire Inspector Pre-priced Option | Pre-priced Optional Services | Option Year 3 | 10/1/25 | 9/30/26 | $ - 0 |
| SSC | S302.5 | Fire Protection Specialist Pre-priced Option | Pre-priced Optional Services | Option Year 3 | 10/1/25 | 9/30/26 | $ - 0 |
| SSC | S303.0 | GSA Fleet Vehicles, Maintenance and Fuel | Baseline Services | Option Year 3 | 10/1/25 | 9/30/26 | $ - 0 |
| SSC | S304.0 | Government Directed Travel | Baseline Services | Option Year 3 | 10/1/25 | 9/30/26 | $ - 0 |
| SSC | S401.0 | Program Management | Baseline Services | Option Year 4 | 10/1/26 | 9/30/27 | $ - 0 |
| SSC | S402.0 | Fire Services | Baseline Services | Option Year 4 | 10/1/26 | 9/30/27 | $ - 0 |
| SSC | S402.1 | Firefighter/EMT Pre-priced Option | Pre-priced Optional Services | Option Year 4 | 10/1/26 | 9/30/27 | $ - 0 |
| SSC | S402.2 | Firefighter Pre-priced Option | Pre-priced Optional Services | Option Year 4 | 10/1/26 | 9/30/27 | $ - 0 |
| SSC | S402.3 | Firefighter/Paramedic Pre-priced Option | Pre-priced Optional Services | Option Year 4 | 10/1/26 | 9/30/27 | $ - 0 |
| SSC | S402.4 | Fire Inspector Pre-priced Option | Pre-priced Optional Services | Option Year 4 | 10/1/26 | 9/30/27 | $ - 0 |
| SSC | S402.5 | Fire Protection Specialist Pre-priced Option | Pre-priced Optional Services | Option Year 4 | 10/1/26 | 9/30/27 | $ - 0 |
| SSC | S403.0 | GSA Fleet Vehicles, Maintenance and Fuel | Baseline Services | Option Year 4 | 10/1/26 | 9/30/27 | $ - 0 |
| SSC | S404.0 | Government Directed Travel | Baseline Services | Option Year 4 | 10/1/26 | 9/30/27 | $ - 0 |
| SSC | S501.0 | Program Management | Baseline Services | Option Year 5 | 10/1/27 | 9/30/28 | $ - 0 |
| SSC | S502.0 | Fire Services | Baseline Services | Option Year 5 | 10/1/27 | 9/30/28 | $ - 0 |
| SSC | S502.1 | Firefighter/EMT Pre-priced Option | Pre-priced Optional Services | Option Year 5 | 10/1/27 | 9/30/28 | $ - 0 |
| SSC | S502.2 | Firefighter Pre-priced Option | Pre-priced Optional Services | Option Year 5 | 10/1/27 | 9/30/28 | $ - 0 |
| SSC | S502.3 | Firefighter/Paramedic Pre-priced Option | Pre-priced Optional Services | Option Year 5 | 10/1/27 | 9/30/28 | $ - 0 |
| SSC | S502.4 | Fire Inspector Pre-priced Option | Pre-priced Optional Services | Option Year 5 | 10/1/27 | 9/30/28 | $ - 0 |
| SSC | S502.5 | Fire Protection Specialist Pre-priced Option | Pre-priced Optional Services | Option Year 5 | 10/1/27 | 9/30/28 | $ - 0 |
| SSC | S503.0 | GSA Fleet Vehicles, Maintenance and Fuel | Baseline Services | Option Year 5 | 10/1/27 | 9/30/28 | $ - 0 |
| SSC | S504.0 | Government Directed Travel | Baseline Services | Option Year 5 | 10/1/27 | 9/30/28 | $ - 0 |
| SSC | S601.0 | Program Management | Baseline Services | Option Year 6 | 10/1/28 | 9/30/29 | $ - 0 |
| SSC | S602.0 | Fire Services | Baseline Services | Option Year 6 | 10/1/28 | 9/30/29 | $ - 0 |
| SSC | S602.1 | Firefighter/EMT Pre-priced Option | Pre-priced Optional Services | Option Year 6 | 10/1/28 | 9/30/29 | $ - 0 |
| SSC | S602.2 | Firefighter Pre-priced Option | Pre-priced Optional Services | Option Year 6 | 10/1/28 | 9/30/29 | $ - 0 |
| SSC | S602.3 | Firefighter/Paramedic Pre-priced Option | Pre-priced Optional Services | Option Year 6 | 10/1/28 | 9/30/29 | $ - 0 |
| SSC | S602.4 | Fire Inspector Pre-priced Option | Pre-priced Optional Services | Option Year 6 | 10/1/28 | 9/30/29 | $ - 0 |
| SSC | S602.5 | Fire Protection Specialist Pre-priced Option | Pre-priced Optional Services | Option Year 6 | 10/1/28 | 9/30/29 | $ - 0 |
| SSC | S603.0 | GSA Fleet Vehicles, Maintenance and Fuel | Baseline Services | Option Year 6 | 10/1/28 | 9/30/29 | $ - 0 |
| SSC | S604.0 | Government Directed Travel | Baseline Services | Option Year 6 | 10/1/28 | 9/30/29 | $ - 0 |
| LOCATION | CLIN | DESCRIPTION | CONTRACT CLIN TYPE | CONTRACT PERIOD | Date Start | Date End | Total Price to the Government |
| WSTF | G001.0 | Program Management | Baseline Services | Base Period | 10/1/22 | 9/30/23 | $ - 0 |
| WSTF | G002.0 | Fire Services | Baseline Services | Base Period | 10/1/22 | 9/30/23 | $ - 0 |
| WSTF | G002.1 | Three Additional Firefighter Pre-priced Option | Pre-priced Optional Services | Base Period | 10/1/22 | 9/30/23 | $ - 0 |
| WSTF | G003.0 | GSA Fleet Vehicles, Maintenance and Fuel | Baseline Services | Base Period | 10/1/22 | 9/30/23 | $ - 0 |
| WSTF | G004.0 | Government Directed Travel | Baseline Services | Base Period | 10/1/22 | 9/30/23 | $ - 0 |
| WSTF | G101.0 | Program Management | Baseline Services | Option Year 1 | 10/1/23 | 9/30/24 | $ - 0 |
| WSTF | G102.0 | Fire Services | Baseline Services | Option Year 1 | 10/1/23 | 9/30/24 | $ - 0 |
| WSTF | G102.1 | Three Additional Firefighter Pre-priced Option | Pre-priced Optional Services | Option Year 1 | 10/1/23 | 9/30/24 | $ - 0 |
| WSTF | G103.0 | GSA Fleet Vehicles, Maintenance and Fuel | Baseline Services | Option Year 1 | 10/1/23 | 9/30/24 | $ - 0 |
| WSTF | G104.0 | Government Directed Travel | Baseline Services | Option Year 1 | 10/1/23 | 9/30/24 | $ - 0 |
| WSTF | G201.0 | Program Management | Baseline Services | Option Year 2 | 10/1/24 | 9/30/25 | $ - 0 |
| WSTF | G202.0 | Fire Services | Baseline Services | Option Year 2 | 10/1/24 | 9/30/25 | $ - 0 |
| WSTF | G202.1 | Three Additional Firefighter Pre-priced Option | Pre-priced Optional Services | Option Year 2 | 10/1/24 | 9/30/25 | $ - 0 |
| WSTF | G203.0 | GSA Fleet Vehicles, Maintenance and Fuel | Baseline Services | Option Year 2 | 10/1/24 | 9/30/25 | $ - 0 |
| WSTF | G204.0 | Government Directed Travel | Baseline Services | Option Year 2 | 10/1/24 | 9/30/25 | $ - 0 |
| WSTF | G301.0 | Program Management | Baseline Services | Option Year 3 | 10/1/25 | 9/30/26 | $ - 0 |
| WSTF | G302.0 | Fire Services | Baseline Services | Option Year 3 | 10/1/25 | 9/30/26 | $ - 0 |
| WSTF | G302.1 | Three Additional Firefighter Pre-priced Option | Pre-priced Optional Services | Option Year 3 | 10/1/25 | 9/30/26 | $ - 0 |
| WSTF | G303.0 | GSA Fleet Vehicles, Maintenance and Fuel | Baseline Services | Option Year 3 | 10/1/25 | 9/30/26 | $ - 0 |
| WSTF | G304.0 | Government Directed Travel | Baseline Services | Option Year 3 | 10/1/25 | 9/30/26 | $ - 0 |
| WSTF | G401.0 | Program Management | Baseline Services | Option Year 4 | 10/1/26 | 9/30/27 | $ - 0 |
| WSTF | G402.0 | Fire Services | Baseline Services | Option Year 4 | 10/1/26 | 9/30/27 | $ - 0 |
| WSTF | G402.1 | Three Additional Firefighter Pre-priced Option | Pre-priced Optional Services | Option Year 4 | 10/1/26 | 9/30/27 | $ - 0 |
| WSTF | G403.0 | GSA Fleet Vehicles, Maintenance and Fuel | Baseline Services | Option Year 4 | 10/1/26 | 9/30/27 | $ - 0 |
| WSTF | G404.0 | Government Directed Travel | Baseline Services | Option Year 4 | 10/1/26 | 9/30/27 | $ - 0 |
| WSTF | G501.0 | Program Management | Baseline Services | Option Year 5 | 10/1/27 | 9/30/28 | $ - 0 |
| WSTF | G502.0 | Fire Services | Baseline Services | Option Year 5 | 10/1/27 | 9/30/28 | $ - 0 |
| WSTF | G502.1 | Three Additional Firefighter Pre-priced Option | Pre-priced Optional Services | Option Year 5 | 10/1/27 | 9/30/28 | $ - 0 |
| WSTF | G503.0 | GSA Fleet Vehicles, Maintenance and Fuel | Baseline Services | Option Year 5 | 10/1/27 | 9/30/28 | $ - 0 |
| WSTF | G504.0 | Government Directed Travel | Baseline Services | Option Year 5 | 10/1/27 | 9/30/28 | $ - 0 |
| WSTF | G601.0 | Program Management | Baseline Services | Option Year 6 | 10/1/28 | 9/30/29 | $ - 0 |
| WSTF | G602.0 | Fire Services | Baseline Services | Option Year 6 | 10/1/28 | 9/30/29 | $ - 0 |
| WSTF | G602.1 | Three Additional Firefighter Pre-priced Option | Pre-priced Optional Services | Option Year 6 | 10/1/28 | 9/30/29 | $ - 0 |
| WSTF | G603.0 | GSA Fleet Vehicles, Maintenance and Fuel | Baseline Services | Option Year 6 | 10/1/28 | 9/30/29 | $ - 0 |
| WSTF | G604.0 | Government Directed Travel | Baseline Services | Option Year 6 | 10/1/28 | 9/30/29 | $ - 0 |
IDIQ Unit Rates IDIQ Unit Rates NASA Location CLIN # Base Period- Year 1 Total Price to the Government (GFY 22) Base Period- Year 2 Total Price to the Government (GFY 23) Option 1 Total Price to the Government (GFY 24) Option 2 Total Price to the Government (GFY 25) Option 3 Total Price to the Government (GFY 26) Option 4 Total Price to the Government (GFY 27) Option 5 Total Price to the Government (GFY 28) Option 6 Total Price to the Government
(GFY 29)
| KSC - Firefighter/Officer (Lt) One 8-hr shift (any shift) | KSC | K005.1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| KSC - Firefighter/Officer (Lt) One 4-hr shift (any shift) | KSC | K005.2 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| KSC - Firefighter/Officer (Lt) One 1-hr shift (any shift) | KSC | K005.3 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| KSC - Firefighter/Driver One 8-hr shift (any shift) | KSC | K005.4 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| KSC - Firefighter/Driver One 4-hr shift (any shift) | KSC | K005.5 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| KSC - Firefighter/Driver One 1-hr shift (any shift) | KSC | K005.6 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| KSC - Firefighter One 8-hr shift (any shift) | KSC | K005.7 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| KSC - Firefighter One 4-hr shift (any shift) | KSC | K005.8 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| KSC - Firefighter One 1-hr shift (any shift) | KSC | K005.9 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| KSC - Paramedic One 8-hr shift (any shift) | KSC | K005.10 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| KSC - Paramedic One 4-hr shift (any shift) | KSC | K005.11 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| KSC - Paramedic One 1-hr shift (any shift) | KSC | K005.12 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| KSC - Fire Inspector One 8-hr shift (any shift) | KSC | K005.13 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| KSC - Fire Inspector One 4-hr shift (any shift) | KSC | K005.14 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| KSC - Fire Protection One 4-hr shift (any shift) | KSC | K005.15 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| KSC - Fire Protection One 8-hr shift (any shift) | KSC | K005.16 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| KSC - Reserved | KSC | K005.17 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
IDIQ Unit Rates NASA Location CLIN # Base Period-Year 1 Total Price to the Government (GFY 22) Base Period-Year 2 Total Price to the Government (GFY 23) Option 1 Total Price to the Government (GFY 24) Option 2 Total Price to the Government (GFY 25) Option 3 Total Price to the Government (GFY 26) Option 4 Total Price to the Government (GFY 27) Option 5 Total Price to the Government (GFY 28) Option 6 Total Price to the Government
(GFY 29)
| WFF - Firefighter/Officer (Lieutenant) One 8-hr shift (any shift) | WFF | W010.1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| WFF - Firefighter/Officer (Lieutenant) One 4-hr shift (any shift) | WFF | W010.2 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| WFF - Firefighter/Officer (Lieutenant) One 1-hr shift (any shift) | WFF | W010.3 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| WFF - Firefighter/Officer (Captain) One 8-hr shift (any shift) | WFF | W010.4 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| WFF - Firefighter/Officer (Captain) One 4-hr shift (any shift) | WFF | W010.5 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| WFF - Firefighter/Officer (Captain) One 1-hr shift (any shift) | WFF | W010.6 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| WFF - Fire Chief One 8-hr shift (any shift) | WFF | W010.7 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| WFF - Fire Chief One 4-hr shift (any shift) | WFF | W010.8 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| WFF - Fire Chief One 1-hr shift (any shift) | WFF | W010.9 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| WFF - Firefighter One 8-hr shift (any shift) | WFF | W010.10 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| WFF - Firefighter One 4-hr shift (any shift) | WFF | W010.11 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| WFF - Firefighter One 1-hr shift (any shift) | WFF | W010.12 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
This is the start of the file's text. The full file is on GovTribe.