Attachment E_EVER Provisional Construction Schedule Flamingo.pdf
PDF 1 MB Posted
- Solicitation number
- 140P1121R0001
About this file
This is a solicitation for an indefinite delivery indefinite quantity contract to provide museum interpretive exhibit fabrication and installation services to National Park Service locations. The contractor shall plan, produce, and install new and replacement exhibits of all sizes, from small temporary displays to major museum exhibitions, in accordance with the terms of the IDIQ contract. The National Park Service National Office will furnish required data, materials, and project information to support exhibit planning and production work. The period of performance is for a one year base period with four one-year options.
View the file
Other files
Show all 34
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Activity ID Activity Name Original Duration
Remaining Duration
Duration % Complete
Early Start Early Finish Late Start Late Finish Total Float
Budgeted Total Cost
Renovation FRenovation Flamingo Visitor Facility - Schedule Update #02 as of 01-Mar-2 359 325 9.47% 01-Mar-20 09-Jun-21 26-Feb-20 07-Jun-21 -2 $7,258,774.00
PROJECT MIPROJECT MILESTONES & SUMMARY 359 325 9.47% 01-Mar-20 09-Jun-21 26-Feb-20 07-Jun-21 -2 $0.00
Project MilestonProject Milestones 513 21 95.91% 01-Mar-20 09-Jun-21 26-Feb-20 07-Jun-21 -2 $0.00 PM-1000 Notice to Proceed (N.T.P.) 0 0 100% 01-Mar-20 26-Feb-20 $0.00 PM-9000 Substantial Completion (T.C.O.) 0 0 0% 19-May-21 17-May-21 -2 $0.00 PM-9900 Final Completion 0 0 0% 09-Jun-21 07-Jun-21 -2 $0.00
Project SummarProject Summary 357 325 8.96% 01-Mar-20 09-Jun-21 26-Feb-20 07-Jun-21 -2 $0.00
Overall Project Overall Project Summary 511 466 8.81% 01-Mar-20 09-Jun-21 26-Feb-20 07-Jun-21 -2 $0.00 PS-1000 Overall Project Duration (N.T.P. to Substantial Completion) 490 445 9.18% 01-Mar-20 19-May-21 26-Feb-20 17-May-21 -2 $0.00 PS-2000 Overall Project Duration (N.T.P. to Final Completion) 511 466 8.81% 01-Mar-20 09-Jun-21 26-Feb-20 07-Jun-21 -2 $0.00
Visitor Center SVisitor Center Summary 271 271 0% 02-Apr-20 26-Apr-21 31-Mar-20 03-May-21 5 $0.00 PM-VC-1000 Demolition Work Summary @ VC 29 29 0% 02-Apr-20 12-May-20 31-Mar-20 08-May-20 -2 $0.00 PS-VC-0000 Complete Demolition @ VC 0 0 0% 12-May-20 08-May-20 -2 $0.00 PS-VC-2000 Structural Work Summary @ VC 74 74 0% 13-May-20 26-Aug-20 11-May-20 24-Aug-20 -2 $0.00 PS-VC-3000 Roofing Work Summary @ VC 42 42 0% 27-Aug-20 26-Oct-20 10-Sep-20 10-Mar-21 93 $0.00 PS-VC-4000 MEPs & Finishes Work Summary @ Upper - VC 168 168 0% 27-Aug-20 26-Apr-21 25-Aug-20 03-May-21 5 $0.00 PS-VC-5000 Exterior Doors & Glazing Work Summary @ VC 34 34 0% 02-Oct-20 18-Nov-20 15-Oct-20 11-Mar-21 77 $0.00 PS-VC-6000 MEP Work Summary @ Roof - VC 23 23 0% 27-Oct-20 30-Nov-20 11-Mar-21 19-Apr-21 98 $0.00 PS-VC-7000 MEPs & Finishes Work Summary @ Lower - VC 76 76 0% 13-Nov-20 04-Mar-21 17-Dec-20 03-May-21 42 $0.00 PM-VC-2000 Complete MEPs @ Lower - VC 0 0 0% 23-Feb-21 03-May-21 49 $0.00 PM-VC-2100 Complete Finishes @ Lower - VC 0 0 0% 04-Mar-21 05-Apr-21 22 $0.00 PM-VC-3000 Complete MEPs @ Upper - VC 0 0 0% 21-Apr-21 03-May-21 8 $0.00 PM-VC-3100 Complete Finishes @ Upper - VC 0 0 0% 26-Apr-21 03-May-21 5 $0.00
Law EnforcemeLaw Enforcement Summary 216 216 0% 13-May-20 19-Mar-21 11-Aug-20 03-May-21 31 $0.00 PS-LE-1000 Demolition Work Summary @ LE 23 23 0% 13-May-20 15-Jun-20 11-Aug-20 11-Sep-20 63 $0.00 PM-LE-1000 Complete Demolition @ LE 0 0 0% 15-Jun-20 11-Sep-20 63 $0.00 PS-LE-2000 Structural Work Summary @ LE 62 62 0% 15-Jun-20 10-Sep-20 14-Sep-20 02-Nov-20 37 $0.00 PS-LE-4000 MEPs & Finishes Work Summary @ Upper - LE 132 132 0% 11-Sep-20 19-Mar-21 03-Nov-20 03-May-21 31 $0.00 PS-LE-3000 Roofing Work Summary @ LE 30 30 0% 02-Oct-20 12-Nov-20 19-Nov-20 10-Mar-21 80 $0.00 PS-LE-7000 MEPs & Finishes Work Summary @ Lower - LE 48 48 0% 10-Nov-20 20-Jan-21 11-Feb-21 03-May-21 73 $0.00 PS-LE-5000 Exterior Doors & Glazing Work Summary @ LE 18 18 0% 13-Nov-20 10-Dec-20 18-Dec-20 21-Apr-21 92 $0.00 PS-LE-6000 MEP Work Summary @ Roof - LE 21 21 0% 13-Nov-20 15-Dec-20 11-Mar-21 03-May-21 97 $0.00 PM-LE-2100 Complete Finishes @ Lower - LE 0 0 0% 18-Jan-21 28-Apr-21 72 $0.00 PM-LE-2000 Complete MEPs @ Lower - LE 0 0 0% 20-Jan-21 03-May-21 73 $0.00 PM-LE-3000 Complete MEPs @ Upper - LE 0 0 0% 03-Mar-21 03-May-21 43 $0.00 PM-LE-3100 Complete Finishes @ Upper - LE 0 0 0% 19-Mar-21 03-May-21 31 $0.00
Walkway SummWalkway Summary 228 225 1.32% 02-Mar-20 19-Jan-21 27-Jan-21 17-May-21 84 $0.00 PS-WK-1000 Demolition Work Summary @ Walkway 60 72 0% 02-Mar-20 10-Jun-20 27-Jan-21 08-Feb-21 168 $0.00 PS-WK-2000 Structural Work Summary @ Walkway 12 12 0% 31-Aug-20 16-Sep-20 09-Feb-21 22-Feb-21 109 $0.00 PS-WK-3000 Roofing Work Summary @ Walkway 17 17 0% 29-Oct-20 20-Nov-20 23-Feb-21 17-Mar-21 79 $0.00 PS-WK-4000 MEPs & Finishes Work Summary @ Walkway 33 33 0% 02-Dec-20 19-Jan-21 25-Mar-21 17-May-21 84 $0.00 PM-WK-1000 Complete MEPs @ Walkway 0 0 0% 30-Dec-20 10-May-21 92 $0.00 PM-WK-1100 Complete Finishes @ Walkway 0 0 0% 19-Jan-21 17-May-21 84 $0.00
Sitework SummSitework Summary 280 287 0% 02-Mar-20 15-Apr-21 07-Dec-20 17-May-21 22 $0.00 PS-WM-1000 Watermain Work Summary @ Walkway 103 125 0% 02-Mar-20 25-Aug-20 07-Dec-20 05-Apr-21 154 $0.00 PM-WM-1000 Watermain Work Complete @ Site 0 0 0% 25-Aug-20 05-Apr-21 154 $0.00 PS-SW-2000 Site Improvement Work Summary @ Walkway 30 30 0% 05-Mar-21 15-Apr-21 06-Apr-21 17-May-21 22 $0.00
S O N D J F M A M J Jul A S O N D J F M A M J J A S 2020 2021
Notice to Proceed (N.T.P.)
Substantial C
Final Com
Overall Proje Overall Pr
Demolition Work Summary @ VC Complete Demolition @ VC
Structural Work Summary @ VC Roofing Work Summary @ VC
MEPs & Finishe Exterior Doors & Glazing Work Sum
MEP Work Summary @ Roof - VC MEPs & Finishes Wor
Complete MEPs @ Lo Complete Finishes @
Complete MEPs Complete Finis
Demolition Work Summary @ LE Complete Demolition @ LE
Structural Work Summary @ LE MEPs & Finishes W
Roofing Work Summary @ LE MEPs & Finishes Work Sum
Exterior Doors & Glazing Work S MEP Work Summary @ Roof -
Complete Finishes @ Lowe Complete MEPs @ Lower -
Complete MEPs @ Up Complete Finishes @
Demolition Work Summary @ Walkway Structural Work Summary @ Walkway
Roofing Work Summary @ Walkwa MEPs & Finishes Work Sum
Complete MEPs @ Walkway Complete Finishes @ Walk
Watermain Work Summary @ Walkway Watermain Work Complete @ Site
Site Improvemen
Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining Work
Renovation Flamingo Visitor Facility - Schedule Update #02 as of 01-Mar-20 Activity Report - All Activities
Flamingo UP02
Data Date: 01-Mar-20
ATTACHMENT E -- EVER EXHIBIT FABRICATION
Remaining Duration
Duration % Complete
Early Start Early Finish Late Start Late Finish Total Float
Budgeted Total Cost
PM-SW-2000 Complete Site Improvement @ Site 0 0 0% 15-Apr-21 17-May-21 22 $0.00
ENGINEERINENGINEERING & PROCUREMENT 358 324 9.5% 01-Mar-20 08-Jun-21 26-Feb-20 07-Jun-21 -1 $266,112.38
Generatl SubmitGeneratl Submittals 358 324 9.5% 01-Mar-20 08-Jun-21 26-Feb-20 07-Jun-21 -1 $141,112.38
Div 01: General Div 01: General Requirements 358 324 9.5% 01-Mar-20 08-Jun-21 26-Feb-20 07-Jun-21 -1 $141,112.38 Initial PM SubmInitial PM Submittals 55 21 61.82% 01-Mar-20 30-Mar-20 26-Feb-20 27-Mar-20 -2 $134,112.38 Div 01: SubmitDiv 01: Submittals 1 0 100% 01-Mar-20 01-Mar-20 26-Feb-20 27-Mar-20 $97,112.38 S-01-0000 Submit Bond & Insurance (Cost Activity) 1 0 100% 01-Mar-20 01-Mar-20 27-Mar-20 27-Mar-20 $97,112.38 S-01-6000 Submit Site-Specific Safety Plan 1 0 100% 01-Mar-20 01-Mar-20 27-Mar-20 27-Mar-20 $0.00 S-01-6100 Submit Quality Control Plan 1 0 100% 01-Mar-20 01-Mar-20 27-Mar-20 27-Mar-20 $0.00 S-01-2000 Submit IAQ Plan 1 0 100% 01-Mar-20 01-Mar-20 27-Mar-20 27-Mar-20 $0.00 S-01-3000 Submit Waste Management Plan 1 0 100% 01-Mar-20 01-Mar-20 27-Mar-20 27-Mar-20 $0.00 S-01-3200 Submit Recycling Plan 1 0 100% 01-Mar-20 01-Mar-20 27-Mar-20 27-Mar-20 $0.00 S-01-3100 Submit Commissioning Plan 1 0 100% 01-Mar-20 01-Mar-20 26-Feb-20 26-Feb-20 $0.00 S-01-7000 Submit Schedule of Values 1 0 100% 01-Mar-20 01-Mar-20 27-Mar-20 27-Mar-20 $0.00 S-01-8000 Submit Construction Schedule 1 0 100% 01-Mar-20 01-Mar-20 27-Mar-20 27-Mar-20 $0.00 S-01-1000 Submit Environmental Plan 1 0 100% 01-Mar-20 01-Mar-20 27-Mar-20 27-Mar-20 $0.00 S-01-4000 Submit Historic Preservation Treatment Plan 1 0 100% 01-Mar-20 01-Mar-20 18-Mar-20 18-Mar-20 $0.00 S-01-5000 Submit Demolition Plan 1 0 100% 01-Mar-20 01-Mar-20 27-Mar-20 27-Mar-20 $0.00
Div 01: ReviewDiv 01: Reviews & Approvals 76 30 60.53% 01-Mar-20 30-Mar-20 26-Feb-20 27-Mar-20 -4 $37,000.00 R-01-6000 Review/Approven Accident Prevention Plan 30 0 100% 01-Mar-20 01-Mar-20 27-Mar-20 27-Mar-20 $3,000.00 R-01-6100 Review/Approve Quality Control Plan 30 0 100% 01-Mar-20 01-Mar-20 27-Mar-20 27-Mar-20 $3,000.00 R-01-2000 Review/Approve IAQ Plan 30 0 100% 01-Mar-20 01-Mar-20 27-Mar-20 27-Mar-20 $3,000.00 R-01-3000 Review/Approve Waste Management Plan 30 0 100% 01-Mar-20 01-Mar-20 27-Mar-20 27-Mar-20 $3,000.00 R-01-5000 Review/Approve Under An Ace Pollution Prevention Plan 30 0 100% 01-Mar-20 01-Mar-20 27-Mar-20 27-Mar-20 $3,000.00 R-01-3200 Review/Approve Recycling Plan 30 0 100% 01-Mar-20 01-Mar-20 27-Mar-20 27-Mar-20 $0.00 R-01-7000 Review/Approve Schedule of Values 30 0 100% 01-Mar-20 01-Mar-20 27-Mar-20 27-Mar-20 $3,000.00 R-01-8000 Review/Approve Construction Schedule 30 0 100% 01-Mar-20 01-Mar-20 27-Mar-20 27-Mar-20 $5,000.00 R-01-1000 Review/Approve Environmental Plan 30 0 100% 01-Mar-20 01-Mar-20 27-Mar-20 27-Mar-20 $0.00 R-01-4000 Review/Approve Historic Preservation Treatment Plan 30 9 70% 01-Mar-20 09-Mar-20 18-Mar-20 26-Mar-20 17 $6,000.00 R-01-3100 Review/Approve Commissioning Plan 30 30 0% 01-Mar-20 30-Mar-20 26-Feb-20 26-Mar-20 -4 $8,000.00
Project Closing Project Closing Submittals 13 13 0% 20-May-21 08-Jun-21 19-May-21 07-Jun-21 -1 $7,000.00 Div 01: SubmitDiv 01: Submittals 8 8 0% 20-May-21 01-Jun-21 19-May-21 28-May-21 -1 $0.00 S-01-9000 Prepare/Submit As-Builts 8 8 0% 20-May-21 01-Jun-21 19-May-21 28-May-21 -1 $0.00 S-01-9100 Prepare/Submit O&Ms 8 8 0% 20-May-21 01-Jun-21 19-May-21 28-May-21 -1 $0.00 S-01-9200 Prepare/Submit Warranties 5 5 0% 20-May-21 26-May-21 24-May-21 28-May-21 2 $0.00
Div 01: ReviewDiv 01: Reviews & Approvals 8 8 0% 27-May-21 08-Jun-21 01-Jun-21 07-Jun-21 -1 $7,000.00 R-01-9200 Review/Approve Warranties 5 5 0% 27-May-21 03-Jun-21 01-Jun-21 07-Jun-21 2 $2,000.00 R-01-9000 Review/Approve As-Builts 5 5 0% 02-Jun-21 08-Jun-21 01-Jun-21 07-Jun-21 -1 $3,000.00 R-01-9100 Review/Approve O&Ms 5 5 0% 02-Jun-21 08-Jun-21 01-Jun-21 07-Jun-21 -1 $2,000.00
Construction SuConstruction Submittals 246 212 13.82% 01-Mar-20 30-Dec-20 26-Feb-20 06-May-21 90 $125,000.00 S-00-0000 Start of Submittal Preparation 0 0 100% 01-Mar-20 26-Feb-20 $0.00 Div 02: ExistingDiv 02: Existing Conditions 28 0 100% 01-Mar-20 01-Mar-20 25-Mar-20 11-Aug-20 115 $4,000.00 Div 02: SubmittaDiv 02: Submittals 6 0 100% 01-Mar-20 01-Mar-20 25-Mar-20 10-Aug-20 $0.00 S-02-1000 Submit Demolition Plan - Visitor Center 1 0 100% 01-Mar-20 01-Mar-20 25-Mar-20 25-Mar-20 $0.00 S-02-2000 Submit Demolition Plan - Law Enforcement Building 1 0 100% 01-Mar-20 01-Mar-20 10-Aug-20 10-Aug-20 $0.00
Div 02: ReviewsDiv 02: Reviews & Approvals 37 1 97.3% 01-Mar-20 01-Mar-20 25-Mar-20 11-Aug-20 163 $4,000.00 R-02-1000 Review/Approve Demolition Plan - Visitor Center 30 1 96.67% 01-Mar-20 01-Mar-20 25-Mar-20 25-Mar-20 24 $2,500.00 R-02-2000 Review/Approve Demolition Plan - Law Enforcement Building 30 1 96.67% 01-Mar-20 01-Mar-20 10-Aug-20 11-Aug-20 163 $1,500.00
S O N D J F M A M J Jul A S O N D J F M A M J J A S 2020 2021
Complete Site Im
Submit Bond & Insurance (Cost Activity) Submit Site-Specific Safety Plan Submit Quality Control Plan Submit IAQ Plan Submit Waste Management Plan
Submit Recycling Plan Submit Commissioning Plan
Submit Schedule of Values Submit Construction Schedule
Submit Environmental Plan Submit Historic Preservation Treatment Plan Submit Demolition Plan
Review/Approven Accident Prevention Plan Review/Approve Quality Control Plan
Review/Approve IAQ Plan Review/Approve Waste Management Plan Review/Approve Under An Ace Pollution Prevention Plan
Review/Approve Recycling Plan Review/Approve Schedule of Values Review/Approve Construction Schedule Review/Approve Environmental Plan
Review/Approve Historic Preservation Treatment Plan Review/Approve Commissioning Plan
Prepare/Su Prepare/Su
Prepare/Su
Review/Ap Review/Ap Review/Ap
Start of Submittal Preparation
Submit Demolition Plan - Visitor Center Submit Demolition Plan - Law Enforcement Building
Review/Approve Demolition Plan - Visitor Center Review/Approve Demolition Plan - Law Enforcement Building
Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining Work
Renovation Flamingo Visitor Facility - Schedule Update #02 as of 01-Mar-20
Activity Report - All Activities
Flamingo UP02
Remaining Duration
Duration % Complete
Early Start Early Finish Late Start Late Finish Total Float
Budgeted Total Cost
Div 03: ConcretDiv 03: Concrete 23 0 100% 01-Mar-20 01-Mar-20 15-May-20 15-May-20 $4,000.00 Div 03: SubmittaDiv 03: Submittals 1 0 100% 01-Mar-20 01-Mar-20 15-May-20 15-May-20 $0.00 S-03-2000 Submit Reinforcement 1 0 100% 01-Mar-20 01-Mar-20 15-May-20 15-May-20 $0.00 S-03-1000 Submit Concrete 1 0 100% 01-Mar-20 01-Mar-20 15-May-20 15-May-20 $0.00
Div 03: ReviewsDiv 03: Reviews & Approvals 30 0 100% 01-Mar-20 01-Mar-20 15-May-20 15-May-20 $4,000.00 R-03-2000 Review/Approve Reinforcement 30 0 100% 01-Mar-20 01-Mar-20 15-May-20 15-May-20 $2,000.00 R-03-1000 Review/Approve Concrete 30 0 100% 01-Mar-20 01-Mar-20 15-May-20 15-May-20 $2,000.00
Div 04: MasonryDiv 04: Masonry 23 0 100% 01-Mar-20 01-Mar-20 28-May-20 28-May-20 63 $2,000.00 Div 04: SubmittaDiv 04: Submittals 1 0 100% 01-Mar-20 01-Mar-20 28-May-20 28-May-20 $0.00 S-04-1000 Submit Masonry 1 0 100% 01-Mar-20 01-Mar-20 28-May-20 28-May-20 $0.00
Div 04:Reviews Div 04:Reviews & Approvals 30 1 96.67% 01-Mar-20 01-Mar-20 28-May-20 28-May-20 88 $2,000.00 R-04-1000 Review/Approve Masonry 30 1 96.67% 01-Mar-20 01-Mar-20 28-May-20 28-May-20 88 $2,000.00
Div 05: MetalsDiv 05: Metals 93 93 0% 10-Mar-20 20-Jul-20 20-Mar-20 23-Mar-21 171 $7,500.00 Div 05: SubmittaDiv 05: Submittals 21 21 0% 10-Mar-20 07-Apr-20 20-Mar-20 08-Jan-21 191 $0.00 S-05-1000 Submit Structural Steel 1 1 0% 10-Mar-20 10-Mar-20 20-Mar-20 20-Mar-20 8 $0.00 S-05-3000 Submit Composite Steel Deck 1 1 0% 10-Mar-20 10-Mar-20 10-Apr-20 10-Apr-20 23 $0.00 S-05-2000 Submit Metal Guardrails/Handrails 1 1 0% 24-Mar-20 24-Mar-20 18-Dec-20 18-Dec-20 188 $0.00 S-05-4000 Submit Stainless Steel Mesh 1 1 0% 07-Apr-20 07-Apr-20 08-Jan-21 08-Jan-21 191 $0.00 S-05-5000 Submit Suspended Metalwork Rails & Blades 1 1 0% 07-Apr-20 07-Apr-20 25-Sep-20 25-Sep-20 120 $0.00
Div 05: ReviewsDiv 05: Reviews & Approvals 58 58 0% 11-Mar-20 07-May-20 22-Mar-20 09-Feb-21 278 $7,500.00 R-05-1000 Review/Approve Structural Steel 30 30 0% 11-Mar-20 09-Apr-20 22-Mar-20 20-Apr-20 11 $1,500.00 R-05-3000 Review/Approve Composite Steel Deck 30 30 0% 11-Mar-20 09-Apr-20 11-Apr-20 10-May-20 31 $1,500.00 R-05-2000 Review/Approve Metal Guardrails/Handrails 30 30 0% 25-Mar-20 23-Apr-20 21-Dec-20 19-Jan-21 271 $1,500.00 R-05-4000 Review/Approve Stainless Steel Mesh 30 30 0% 08-Apr-20 07-May-20 11-Jan-21 09-Feb-21 278 $1,500.00 R-05-5000 Review/Approve Suspended Metalwork Rails & Blades 30 30 0% 08-Apr-20 07-May-20 28-Sep-20 27-Oct-20 173 $1,500.00
Div 05: FabricatDiv 05: Fabrication & Delivery 70 70 0% 10-Apr-20 20-Jul-20 21-Apr-20 23-Mar-21 171 $0.00 F-05-1000 FAD Structural Steel Columns/Beams 40 40 0% 10-Apr-20 05-Jun-20 21-Apr-20 16-Jun-20 7 $0.00 F-05-1100 FAD Structural Steel Roof Joists 60 60 0% 10-Apr-20 06-Jul-20 04-May-20 28-Jul-20 16 $0.00 F-05-1200 FAD Structural Steel Plates 30 30 0% 10-Apr-20 21-May-20 22-May-20 06-Jul-20 30 $0.00 F-05-3000 FAD Composite Steel Deck 20 20 0% 10-Apr-20 07-May-20 11-May-20 08-Jun-20 21 $0.00 F-05-2000 FAD Metal Guardrails/Handrails 40 40 0% 24-Apr-20 19-Jun-20 20-Jan-21 16-Mar-21 186 $0.00 F-05-4000 FAD Stainless Steel Mesh 30 30 0% 08-May-20 19-Jun-20 10-Feb-21 23-Mar-21 191 $0.00 F-05-5000 FAD Suspended Metalwork Rails & Blades 50 50 0% 08-May-20 20-Jul-20 28-Oct-20 11-Jan-21 120 $0.00
Div 06: Wood, PDiv 06: Wood, Plastics, and Composites 103 103 0% 07-Apr-20 31-Aug-20 27-Oct-20 31-Mar-21 147 $5,000.00 Div 06: SubmittaDiv 06: Submittals 11 11 0% 07-Apr-20 21-Apr-20 27-Oct-20 18-Dec-20 168 $0.00 S-06-1000 Submit Restroom Countertops 1 1 0% 07-Apr-20 07-Apr-20 18-Dec-20 18-Dec-20 178 $0.00 S-06-2000 Submit Millwork at Bookstore 1 1 0% 07-Apr-20 07-Apr-20 27-Oct-20 27-Oct-20 142 $0.00 S-06-5000 Submit Solid Surface Laminate 1 1 0% 07-Apr-20 07-Apr-20 28-Oct-20 28-Oct-20 143 $0.00 S-06-4000 Submit Millwork at Gallery 1 1 0% 07-Apr-20 07-Apr-20 05-Nov-20 05-Nov-20 149 $0.00 S-06-3000 Submit Kitchen/Corridor Cabinets & Countertops 1 1 0% 21-Apr-20 21-Apr-20 11-Dec-20 11-Dec-20 163 $0.00
Div 06: ReviewsDiv 06: Reviews & Approvals 44 44 0% 08-Apr-20 21-May-20 28-Oct-20 17-Jan-21 241 $5,000.00 R-06-1000 Review/Approve Restroom Countertops 30 30 0% 08-Apr-20 07-May-20 19-Dec-20 17-Jan-21 255 $1,000.00 R-06-2000 Review/Approve Millwork at Bookstore 30 30 0% 08-Apr-20 07-May-20 28-Oct-20 26-Nov-20 203 $1,000.00 R-06-5000 Review/Approve Solid Surface Laminate 30 30 0% 08-Apr-20 07-May-20 29-Oct-20 27-Nov-20 204 $1,000.00 R-06-4000 Review/Approve Millwork at Gallery 30 30 0% 08-Apr-20 07-May-20 06-Nov-20 05-Dec-20 212 $1,000.00 R-06-3000 Review/Approve Kitchen/Corridor Cabinets & Countertops 30 30 0% 22-Apr-20 21-May-20 13-Dec-20 11-Jan-21 235 $1,000.00
Div 06: FabricatDiv 06: Fabrication & Delivery 80 80 0% 08-May-20 31-Aug-20 12-Jan-21 31-Mar-21 147 $0.00 F-06-1000 FAD Restroom Countertops 40 40 0% 08-May-20 06-Jul-20 18-Jan-21 12-Mar-21 174 $0.00
S O N D J F M A M J Jul A S O N D J F M A M J J A S 2020 2021
Submit Reinforcement Submit Concrete
Review/Approve Reinforcement Review/Approve Concrete
Submit Masonry
Review/Approve Masonry
Submit Structural Steel Submit Composite Steel Deck
Submit Metal Guardrails/Handrails Submit Stainless Steel Mesh Submit Suspended Metalwork Rails & Blades
Review/Approve Structural Steel Review/Approve Composite Steel Deck
Review/Approve Metal Guardrails/Handrails Review/Approve Stainless Steel Mesh Review/Approve Suspended Metalwork Rails & Blades
FAD Structural Steel Columns/Beams FAD Structural Steel Roof Joists
FAD Structural Steel Plates FAD Composite Steel Deck
FAD Metal Guardrails/Handrails FAD Stainless Steel Mesh
FAD Suspended Metalwork Rails & Blades
Submit Restroom Countertops Submit Millwork at Bookstore Submit Solid Surface Laminate Submit Millwork at Gallery
Submit Kitchen/Corridor Cabinets & Countertops
Review/Approve Restroom Countertops Review/Approve Millwork at Bookstore Review/Approve Solid Surface Laminate Review/Approve Millwork at Gallery
Review/Approve Kitchen/Corridor Cabinets & Countertops
FAD Restroom Countertops
Remaining Level of Effort Actual Level of Effort Actual Work
Remaining Duration
Duration % Complete
Early Start Early Finish Late Start Late Finish Total Float
Budgeted Total Cost
F-06-3000 FAD Kitchen/Corridor Cabinets & Countertops 50 50 0% 22-May-20 03-Aug-20 12-Jan-21 22-Mar-21 160 $0.00 F-06-2000 FAD Millwork at Bookstore 40 40 0% 07-Jul-20 31-Aug-20 26-Jan-21 22-Mar-21 140 $0.00 F-06-5000 FAD Solid Surface Laminate 40 40 0% 07-Jul-20 31-Aug-20 27-Jan-21 23-Mar-21 141 $0.00 F-06-4000 FAD Millwork at Gallery 40 40 0% 07-Jul-20 31-Aug-20 04-Feb-21 31-Mar-21 147 $0.00
Div 07: ThermalDiv 07: Thermal and Moisture Protection 88 88 0% 17-Mar-20 20-Jul-20 15-May-20 15-Feb-21 145 $6,000.00 Div 07: SubmittaDiv 07: Submittals 6 6 0% 17-Mar-20 24-Mar-20 15-May-20 16-Oct-20 145 $0.00 S-07-1000 Submit Roofing Material 1 1 0% 17-Mar-20 17-Mar-20 15-May-20 15-May-20 43 $0.00 S-07-2000 Submit Wall Insulation 1 1 0% 24-Mar-20 24-Mar-20 04-Sep-20 04-Sep-20 116 $0.00 S-07-3000 Submit Wall Panels (Trespa) 1 1 0% 24-Mar-20 24-Mar-20 16-Oct-20 16-Oct-20 145 $0.00
Div 07: ReviewsDiv 07: Reviews & Approvals 37 37 0% 18-Mar-20 23-Apr-20 17-May-20 17-Nov-20 208 $6,000.00 R-07-1000 Review/Approve Roofing Material 30 30 0% 18-Mar-20 16-Apr-20 17-May-20 15-Jun-20 60 $0.00 R-07-2000 Review/Approve Wall Insulation 30 30 0% 25-Mar-20 23-Apr-20 05-Sep-20 04-Oct-20 164 $3,000.00 R-07-3000 Review/Approve Wall Panels (Trespa) 30 30 0% 25-Mar-20 23-Apr-20 19-Oct-20 17-Nov-20 208 $3,000.00
Div 07: FabricatDiv 07: Fabrication & Delivery 65 65 0% 17-Apr-20 20-Jul-20 16-Jun-20 15-Feb-21 145 $0.00 F-07-1000 FAD Roofing Material 60 60 0% 17-Apr-20 13-Jul-20 16-Jun-20 09-Sep-20 41 $0.00 F-07-2000 FAD Wall Insulation 20 20 0% 24-Apr-20 21-May-20 05-Oct-20 30-Oct-20 113 $0.00 F-07-3000 FAD Wall Panels (Trespa) 60 60 0% 24-Apr-20 20-Jul-20 18-Nov-20 15-Feb-21 145 $0.00
Div 08: OpeningDiv 08: Openings 103 103 0% 10-Mar-20 03-Aug-20 12-Jun-20 28-Apr-21 187 $12,000.00 Div 08: SubmittaDiv 08: Submittals 21 21 0% 10-Mar-20 07-Apr-20 12-Jun-20 01-Feb-21 207 $0.00 S-08-1000 Submit Exterior Windows & Storefronts 1 1 0% 10-Mar-20 10-Mar-20 12-Jun-20 12-Jun-20 67 $0.00 S-08-2000 Submit Exterior Storefront Doors 1 1 0% 10-Mar-20 10-Mar-20 07-Aug-20 07-Aug-20 106 $0.00 S-08-1100 Prepare Window Mock-up 5 5 0% 11-Mar-20 17-Mar-20 15-Jun-20 19-Jun-20 67 $0.00 S-08-3000 Submit Interior Doors 1 1 0% 24-Mar-20 24-Mar-20 04-Jan-21 04-Jan-21 197 $0.00 S-08-4000 Submit Door Hardware 1 1 0% 07-Apr-20 07-Apr-20 18-Dec-20 18-Dec-20 178 $0.00 S-08-5000 Submit Automatic Door Operation Push Buttons 1 1 0% 07-Apr-20 07-Apr-20 01-Feb-21 01-Feb-21 207 $0.00 S-08-6000 Submit Glass Railings 1 1 0% 07-Apr-20 07-Apr-20 30-Oct-20 30-Oct-20 145 $0.00 S-08-7000 Submit Interior Glazing 1 1 0% 07-Apr-20 07-Apr-20 16-Oct-20 16-Oct-20 135 $0.00
Div 08: ReviewsDiv 08: Reviews & Approvals 58 58 0% 11-Mar-20 07-May-20 22-Jun-20 03-Mar-21 300 $12,000.00 R-08-1000 Review/Approve Exterior Windows & Storefronts 30 30 0% 11-Mar-20 09-Apr-20 22-Jun-20 21-Jul-20 103 $2,000.00 R-08-2000 Review/Approve Exterior Storefront Doors 30 30 0% 11-Mar-20 09-Apr-20 09-Aug-20 07-Sep-20 151 $2,000.00 R-08-1100 Review/Approve Window Mock-up 30 30 0% 18-Mar-20 16-Apr-20 22-Jun-20 21-Jul-20 96 $2,000.00 R-08-3000 Review/Approve Interior Doors 30 30 0% 25-Mar-20 23-Apr-20 05-Jan-21 03-Feb-21 286 $0.00 R-08-4000 Review/Approve Door Hardware 30 30 0% 08-Apr-20 07-May-20 21-Dec-20 19-Jan-21 257 $1,000.00 R-08-5000 Review/Approve Automatic Door Operation Push Buttons 30 30 0% 08-Apr-20 07-May-20 02-Feb-21 03-Mar-21 300 $2,000.00 R-08-6000 Review/Approve Glass Railings 30 30 0% 08-Apr-20 07-May-20 01-Nov-20 30-Nov-20 207 $2,000.00 R-08-7000 Review/Approve Interior Glazing 30 30 0% 08-Apr-20 07-May-20 18-Oct-20 16-Nov-20 193 $1,000.00
Div 08: FabricatDiv 08: Fabrication & Delivery 80 80 0% 10-Apr-20 03-Aug-20 22-Jul-20 28-Apr-21 187 $0.00 F-08-2000 FAD Exterior Storefront Doors 60 60 0% 10-Apr-20 06-Jul-20 08-Sep-20 02-Dec-20 104 $0.00 F-08-1000 FAD Exterior Windows & Storefronts 60 60 0% 17-Apr-20 13-Jul-20 22-Jul-20 14-Oct-20 66 $0.00 F-08-3000 FAD Interior Doors 40 40 0% 24-Apr-20 19-Jun-20 04-Feb-21 31-Mar-21 197 $0.00 F-08-4000 FAD Door Hardware 40 40 0% 08-May-20 06-Jul-20 20-Jan-21 16-Mar-21 176 $0.00 F-08-5000 FAD Automatic Door Operation Push Buttons 40 40 0% 08-May-20 06-Jul-20 04-Mar-21 28-Apr-21 207 $0.00 F-08-6000 FAD Glass Railings 50 50 0% 08-May-20 20-Jul-20 01-Dec-20 10-Feb-21 142 $0.00 F-08-7000 FAD Interior Glazing 60 60 0% 08-May-20 03-Aug-20 17-Nov-20 12-Feb-21 134 $0.00
Div 09: FinishesDiv 09: Finishes 83 83 0% 07-Apr-20 03-Aug-20 25-Aug-20 22-Apr-21 183 $19,500.00 Div 09: SubmittaDiv 09: Submittals 1 1 0% 07-Apr-20 07-Apr-20 25-Aug-20 29-Jan-21 206 $0.00 S-09-1000 Submit Drywall 1 1 0% 07-Apr-20 07-Apr-20 18-Sep-20 18-Sep-20 115 $0.00 S-09-2000 Submit Epoxy Concrete Coating/Coating/Resinous Flooring 1 1 0% 07-Apr-20 07-Apr-20 22-Jan-21 22-Jan-21 201 $0.00
S O N D J F M A M J Jul A S O N D J F M A M J J A S 2020 2021
FAD Kitchen/Corridor Cabinets & Countertops FAD Millwork at Bookstore FAD Solid Surface Laminate FAD Millwork at Gallery
Submit Roofing Material Submit Wall Insulation Submit Wall Panels (Trespa)
Review/Approve Roofing Material Review/Approve Wall Insulation Review/Approve Wall Panels (Trespa)
FAD Roofing Material FAD Wall Insulation
FAD Wall Panels (Trespa)
Submit Exterior Windows & Storefronts Submit Exterior Storefront Doors Prepare Window Mock-up Submit Interior Doors
Submit Door Hardware Submit Automatic Door Operation Push Buttons Submit Glass Railings Submit Interior Glazing
Review/Approve Exterior Windows & Storefronts Review/Approve Exterior Storefront Doors Review/Approve Window Mock-up Review/Approve Interior Doors
Review/Approve Door Hardware Review/Approve Automatic Door Operation Push Buttons Review/Approve Glass Railings Review/Approve Interior Glazing
FAD Exterior Storefront Doors FAD Exterior Windows & Storefronts
FAD Interior Doors FAD Door Hardware FAD Automatic Door Operation Push Buttons
FAD Glass Railings FAD Interior Glazing
Submit Drywall Submit Epoxy Concrete Coating/Coating/Resinous Flooring
Remaining Level of Effort Actual Level of Effort Actual Work
Remaining Duration
Duration % Complete
Early Start Early Finish Late Start Late Finish Total Float
Budgeted Total Cost
S-09-7400 Submit Terrazzo 1 1 0% 07-Apr-20 07-Apr-20 23-Oct-20 23-Oct-20 140 $0.00 S-09-4000 Submit Acoustical Fiber Glass Panels 1 1 0% 07-Apr-20 07-Apr-20 30-Oct-20 30-Oct-20 145 $0.00 S-09-5000 Submit Metal Ceiling Panels 1 1 0% 07-Apr-20 07-Apr-20 11-Sep-20 11-Sep-20 110 $0.00 S-09-6000 Submit Acoustical Ceiling 1 1 0% 07-Apr-20 07-Apr-20 04-Dec-20 04-Dec-20 168 $0.00 S-09-7000 Submit Vinyl Tiles 1 1 0% 07-Apr-20 07-Apr-20 31-Dec-20 31-Dec-20 186 $0.00 S-09-7100 Submit Wood & Rubber Wall Base 1 1 0% 07-Apr-20 07-Apr-20 29-Dec-20 29-Dec-20 184 $0.00 S-09-7200 Submit Carpet 1 1 0% 07-Apr-20 07-Apr-20 26-Jan-21 26-Jan-21 203 $0.00 S-09-7300 Submit Porcelain Tiles 1 1 0% 07-Apr-20 07-Apr-20 15-Jan-21 15-Jan-21 196 $0.00 S-09-8000 Submit Acoustical Suspended Panels 1 1 0% 07-Apr-20 07-Apr-20 25-Aug-20 25-Aug-20 98 $0.00 S-09-9000 Submit Stain Slat Walls 1 1 0% 07-Apr-20 07-Apr-20 22-Dec-20 22-Dec-20 180 $0.00 S-09-3000 Submit Paint 1 1 0% 07-Apr-20 07-Apr-20 29-Jan-21 29-Jan-21 206 $0.00
Div 09: ReviewsDiv 09: Reviews & Approvals 30 30 0% 08-Apr-20 07-May-20 26-Aug-20 01-Mar-21 298 $19,500.00 R-09-1000 Review/Approve Drywall 30 30 0% 08-Apr-20 07-May-20 20-Sep-20 19-Oct-20 165 $1,500.00 R-09-2000 Review/Approve Epoxy Concrete Coating/Coating/Resinous Flooring 30 30 0% 08-Apr-20 07-May-20 25-Jan-21 23-Feb-21 292 $1,500.00 R-09-7400 Review/Approve Terrazzo 30 30 0% 08-Apr-20 07-May-20 25-Oct-20 23-Nov-20 200 $1,500.00 R-09-4000 Review/Approve Acoustical Fiber Glass Panels 30 30 0% 08-Apr-20 07-May-20 01-Nov-20 30-Nov-20 207 $1,500.00 R-09-5000 Review/Approve Metal Ceiling Panels 30 30 0% 08-Apr-20 07-May-20 14-Sep-20 13-Oct-20 159 $1,500.00 R-09-6000 Review/Approve Acoustical Ceiling 30 30 0% 08-Apr-20 07-May-20 06-Dec-20 04-Jan-21 242 $1,500.00 R-09-7000 Review/Approve Vinyl Tiles 30 30 0% 08-Apr-20 07-May-20 03-Jan-21 01-Feb-21 270 $1,500.00 R-09-7100 Review/Approve Wood & Rubber Wall Base 30 30 0% 08-Apr-20 07-May-20 30-Dec-20 28-Jan-21 266 $1,500.00 R-09-7200 Review/Approve Carpet 30 30 0% 08-Apr-20 07-May-20 27-Jan-21 25-Feb-21 294 $1,500.00 R-09-7300 Review/Approve Porcelain Tiles 30 30 0% 08-Apr-20 07-May-20 16-Jan-21 14-Feb-21 283 $1,500.00 R-09-8000 Review/Approve Acoustical Suspended Panels 30 30 0% 08-Apr-20 07-May-20 26-Aug-20 24-Sep-20 140 $1,500.00 R-09-9000 Review/Approve Stain Slat Walls 30 30 0% 08-Apr-20 07-May-20 23-Dec-20 21-Jan-21 259 $1,500.00 R-09-3000 Review/Approve Paint 30 30 0% 08-Apr-20 07-May-20 31-Jan-21 01-Mar-21 298 $1,500.00
Div 09: FabricatDiv 09: Fabrication & Delivery 60 60 0% 08-May-20 03-Aug-20 25-Sep-20 22-Apr-21 183 $0.00 F-09-1000 FAD Drywall 10 10 0% 08-May-20 21-May-20 20-Oct-20 02-Nov-20 114 $0.00 F-09-2000 FAD Epoxy Concrete Coating/Resinous Flooring 20 20 0% 08-May-20 05-Jun-20 24-Feb-21 23-Mar-21 201 $0.00 F-09-7400 FAD Terrazzo 50 50 0% 08-May-20 20-Jul-20 24-Nov-20 05-Feb-21 139 $0.00 F-09-4000 FAD Acoustical Fiber Glass Panels 50 50 0% 08-May-20 20-Jul-20 01-Dec-20 10-Feb-21 142 $0.00 F-09-5000 FAD Metal Ceiling Panels 50 50 0% 08-May-20 20-Jul-20 14-Oct-20 24-Dec-20 110 $0.00 F-09-6000 FAD Acoustical Ceiling 40 40 0% 08-May-20 06-Jul-20 05-Jan-21 01-Mar-21 165 $0.00 F-09-7000 FAD Vinyl Tiles 40 40 0% 08-May-20 06-Jul-20 02-Feb-21 29-Mar-21 185 $0.00 F-09-7100 FAD Wood & Rubber Wall Base 40 40 0% 08-May-20 06-Jul-20 29-Jan-21 25-Mar-21 183 $0.00 F-09-7200 FAD Carpet 40 40 0% 08-May-20 06-Jul-20 26-Feb-21 22-Apr-21 203 $0.00 F-09-7300 FAD Porcelain Tiles 40 40 0% 08-May-20 06-Jul-20 15-Feb-21 09-Apr-21 194 $0.00 F-09-8000 FAD Acoustical Suspended Panels 60 60 0% 08-May-20 03-Aug-20 25-Sep-20 21-Dec-20 97 $0.00 F-09-9000 FAD Stain Slat Walls 60 60 0% 08-May-20 03-Aug-20 22-Jan-21 15-Apr-21 178 $0.00
Div 10: SpecialtDiv 10: Specialties 83 83 0% 07-Apr-20 03-Aug-20 20-Nov-20 26-Apr-21 185 $10,500.00 Div 10: SubmittaDiv 10: Submittals 1 1 0% 07-Apr-20 07-Apr-20 20-Nov-20 29-Jan-21 206 $0.00 S-10-1000 Submit Toilet Vanities 1 1 0% 07-Apr-20 07-Apr-20 04-Jan-21 04-Jan-21 187 $0.00 S-10-2000 Submit Toilet Partitions 1 1 0% 07-Apr-20 07-Apr-20 20-Nov-20 20-Nov-20 160 $0.00 S-10-3000 Submit Toilet Accessories 1 1 0% 07-Apr-20 07-Apr-20 25-Nov-20 25-Nov-20 163 $0.00 S-10-4000 Submit Interior Signage 1 1 0% 07-Apr-20 07-Apr-20 31-Dec-20 31-Dec-20 186 $0.00 S-10-5000 Submit Lockers 1 1 0% 07-Apr-20 07-Apr-20 08-Jan-21 08-Jan-21 191 $0.00 S-10-6000 Submit Operable Partitions 1 1 0% 07-Apr-20 07-Apr-20 29-Jan-21 29-Jan-21 206 $0.00 S-10-6010 Submit Exterior Signage 1 1 0% 07-Apr-20 07-Apr-20 31-Dec-20 31-Dec-20 186 $0.00
Div 10: ReviewsDiv 10: Reviews & Approvals 30 30 0% 08-Apr-20 07-May-20 23-Nov-20 01-Mar-21 298 $10,500.00
S O N D J F M A M J Jul A S O N D J F M A M J J A S 2020 2021
Submit Terrazzo Submit Acoustical Fiber Glass Panels Submit Metal Ceiling Panels Submit Acoustical Ceiling Submit Vinyl Tiles Submit Wood & Rubber Wall Base Submit Carpet Submit Porcelain Tiles Submit Acoustical Suspended Panels Submit Stain Slat Walls Submit Paint
Review/Approve Drywall Review/Approve Epoxy Concrete Coating/Coating/Resinous Review/Approve Terrazzo Review/Approve Acoustical Fiber Glass Panels Review/Approve Metal Ceiling Panels Review/Approve Acoustical Ceiling Review/Approve Vinyl Tiles Review/Approve Wood & Rubber Wall Base Review/Approve Carpet Review/Approve Porcelain Tiles Review/Approve Acoustical Suspended Panels Review/Approve Stain Slat Walls Review/Approve Paint
FAD Drywall FAD Epoxy Concrete Coating/Resinous Flooring
FAD Terrazzo FAD Acoustical Fiber Glass Panels FAD Metal Ceiling Panels
FAD Acoustical Ceiling FAD Vinyl Tiles FAD Wood & Rubber Wall Base FAD Carpet FAD Porcelain Tiles
FAD Acoustical Suspended Panels FAD Stain Slat Walls
Submit Toilet Vanities Submit Toilet Partitions Submit Toilet Accessories Submit Interior Signage Submit Lockers Submit Operable Partitions Submit Exterior Signage
Remaining Level of Effort Actual Level of Effort Actual Work
Remaining Duration
Duration % Complete
Early Start Early Finish Late Start Late Finish Total Float
Budgeted Total Cost
R-10-1000 Review/Approve Toilet Vanities 30 30 0% 08-Apr-20 07-May-20 05-Jan-21 03-Feb-21 272 $1,500.00 R-10-2000 Review/Approve Toilet Partitions 30 30 0% 08-Apr-20 07-May-20 23-Nov-20 22-Dec-20 229 $1,500.00 R-10-3000 Review/Approve Toilet Accessories 30 30 0% 08-Apr-20 07-May-20 28-Nov-20 27-Dec-20 234 $1,500.00 R-10-4000 Review/Approve Interior Signage 30 30 0% 08-Apr-20 07-May-20 04-Jan-21 02-Feb-21 271 $1,500.00 R-10-5000 Review/Approve Lockers 30 30 0% 08-Apr-20 07-May-20 11-Jan-21 09-Feb-21 278 $1,500.00 R-10-6000 Review/Approve Operable Partitions 30 30 0% 08-Apr-20 07-May-20 31-Jan-21 01-Mar-21 298 $1,500.00 R-10-6010 Review/Approve Exterior Signage 30 30 0% 08-Apr-20 07-May-20 02-Jan-21 31-Jan-21 269 $1,500.00
Div 10: FabricatDiv 10: Fabrication & Delivery 60 60 0% 08-May-20 03-Aug-20 23-Dec-20 26-Apr-21 185 $0.00 F-10-1000 FAD Toilet Vanities 30 30 0% 08-May-20 19-Jun-20 04-Feb-21 17-Mar-21 187 $0.00 F-10-2000 FAD Toilet Partitions 60 60 0% 08-May-20 03-Aug-20 23-Dec-20 18-Mar-21 158 $0.00 F-10-3000 FAD Toilet Accessories 60 60 0% 08-May-20 03-Aug-20 28-Dec-20 22-Mar-21 160 $0.00 F-10-4000 FAD Interior Signage 40 40 0% 08-May-20 06-Jul-20 03-Feb-21 30-Mar-21 186 $0.00 F-10-5000 FAD Lockers 40 40 0% 08-May-20 06-Jul-20 10-Feb-21 06-Apr-21 191 $0.00 F-10-6000 FAD Operable Partitions 40 40 0% 08-May-20 06-Jul-20 02-Mar-21 26-Apr-21 205 $0.00 F-10-6010 FAD Exterior Signage 40 40 0% 08-May-20 06-Jul-20 01-Feb-21 26-Mar-21 184 $0.00
Div 11: EquipmDiv 11: Equipment 53 53 0% 21-Apr-20 06-Jul-20 26-Jan-21 30-Apr-21 209 $4,000.00 Div 11: SubmittaDiv 11: Submittals 1 1 0% 21-Apr-20 21-Apr-20 26-Jan-21 19-Feb-21 211 $0.00 S-11-1000 Submit Office Equiment 1 1 0% 21-Apr-20 21-Apr-20 19-Feb-21 19-Feb-21 211 $0.00 S-11-2000 Submit Kitchen Appliances 1 1 0% 21-Apr-20 21-Apr-20 26-Jan-21 26-Jan-21 193 $0.00
Div 11: ReviewsDiv 11: Reviews & Approvals 30 30 0% 22-Apr-20 21-May-20 27-Jan-21 21-Mar-21 304 $4,000.00 R-11-1000 Review/Approve Office Equiment 30 30 0% 22-Apr-20 21-May-20 20-Feb-21 21-Mar-21 304 $2,000.00 R-11-2000 Review/Approve Kitchen Appliances 30 30 0% 22-Apr-20 21-May-20 27-Jan-21 25-Feb-21 280 $2,000.00
Div 11: FabricatDiv 11: Fabrication & Delivery 30 30 0% 22-May-20 06-Jul-20 26-Feb-21 30-Apr-21 209 $0.00 F-11-1000 FAD Office Equiment 30 30 0% 22-May-20 06-Jul-20 22-Mar-21 30-Apr-21 209 $0.00 F-11-2000 FAD Kitchen Appliances 30 30 0% 22-May-20 06-Jul-20 26-Feb-21 08-Apr-21 193 $0.00
Div 12: FurnishDiv 12: Furnishings 94 99 0% 01-Mar-20 20-Jul-20 12-Jan-21 06-May-21 203 $7,500.00 Div 12: SubmittaDiv 12: Submittals 11 1 90.91% 01-Mar-20 07-Apr-20 12-Jan-21 25-Feb-21 225 $0.00 S-12-2000 Submit Window Shades 1 0 100% 01-Mar-20 01-Mar-20 25-Feb-21 25-Feb-21 $0.00 S-12-1000 Submit Merchandize Fixtures & Shelving 1 1 0% 07-Apr-20 07-Apr-20 15-Jan-21 15-Jan-21 196 $0.00 S-12-3000 Submit FF&E's 1 1 0% 07-Apr-20 07-Apr-20 12-Jan-21 12-Jan-21 193 $0.00 S-12-4000 Submit Foll UP Floor Mats 1 1 0% 07-Apr-20 07-Apr-20 19-Feb-21 19-Feb-21 221 $0.00 S-12-4010 Submit Benches 1 1 0% 07-Apr-20 07-Apr-20 09-Feb-21 09-Feb-21 213 $0.00
Div 12: ReviewsDiv 12: Reviews & Approvals 44 68 0% 01-Mar-20 07-May-20 13-Jan-21 21-Mar-21 318 $7,500.00 R-12-2000 Review/Approve Window Shades 30 8 75% 01-Mar-20 08-Mar-20 25-Feb-21 04-Mar-21 362 $1,500.00 R-12-1000 Review/Approve Merchandize Fixtures & Shelving 30 30 0% 08-Apr-20 07-May-20 17-Jan-21 15-Feb-21 284 $1,500.00 R-12-3000 Review/Approve FF&E's 30 30 0% 08-Apr-20 07-May-20 13-Jan-21 11-Feb-21 280 $1,500.00 R-12-4000 Review/Approve Foll UP Floor Mats 30 30 0% 08-Apr-20 07-May-20 20-Feb-21 21-Mar-21 318 $1,500.00 R-12-4010 Review/Approve Benches 30 30 0% 08-Apr-20 07-May-20 10-Feb-21 11-Mar-21 308 $1,500.00
Div 12: FabricatDiv 12: Fabrication & Delivery 94 94 0% 09-Mar-20 20-Jul-20 12-Feb-21 06-May-21 203 $0.00 F-12-2000 FAD Window Shades 40 40 0% 09-Mar-20 01-May-20 05-Mar-21 29-Apr-21 252 $0.00 F-12-1000 FAD Merchandize Fixtures & Shelving 40 40 0% 08-May-20 06-Jul-20 16-Feb-21 12-Apr-21 195 $0.00 F-12-3000 FAD FF&E's 50 50 0% 08-May-20 20-Jul-20 12-Feb-21 22-Apr-21 193 $0.00 F-12-4000 FAD Foll UP Floor Mats 30 30 0% 08-May-20 19-Jun-20 22-Mar-21 30-Apr-21 219 $0.00 F-12-4010 FAD Benches 40 40 0% 08-May-20 06-Jul-20 12-Mar-21 06-May-21 213 $0.00
Div 14: ConveyiDiv 14: Conveying Equipment 93 93 0% 24-Mar-20 03-Aug-20 16-Oct-20 25-Feb-21 143 $3,000.00 Div 14: SubmittaDiv 14: Submittals 1 1 0% 24-Mar-20 24-Mar-20 16-Oct-20 16-Oct-20 145 $0.00 S-14-1000 Submit Elevator 1 1 0% 24-Mar-20 24-Mar-20 16-Oct-20 16-Oct-20 145 $0.00
Div 14: ReviewsDiv 14: Reviews & Approvals 30 30 0% 25-Mar-20 23-Apr-20 17-Oct-20 15-Nov-20 206 $3,000.00
S O N D J F M A M J Jul A S O N D J F M A M J J A S 2020 2021
Review/Approve Toilet Vanities Review/Approve Toilet Partitions Review/Approve Toilet Accessories Review/Approve Interior Signage Review/Approve Lockers Review/Approve Operable Partitions Review/Approve Exterior Signage
FAD Toilet Vanities FAD Toilet Partitions FAD Toilet Accessories
FAD Interior Signage FAD Lockers FAD Operable Partitions FAD Exterior Signage
Submit Office Equiment Submit Kitchen Appliances
Review/Approve Office Equiment Review/Approve Kitchen Appliances
FAD Office Equiment FAD Kitchen Appliances
Submit Window Shades Submit Merchandize Fixtures & Shelving Submit FF&E's Submit Foll UP Floor Mats Submit Benches
Review/Approve Window Shades Review/Approve Merchandize Fixtures & Shelving Review/Approve FF&E's Review/Approve Foll UP Floor Mats Review/Approve Benches
FAD Window Shades FAD Merchandize Fixtures & Shelving
FAD FF&E's FAD Foll UP Floor Mats
FAD Benches
Submit Elevator
Remaining Level of Effort Actual Level of Effort Actual Work
Remaining Duration
Duration % Complete
Early Start Early Finish Late Start Late Finish Total Float
Budgeted Total Cost
R-14-1000 Review/Approve Elevator 30 30 0% 25-Mar-20 23-Apr-20 17-Oct-20 15-Nov-20 206 $3,000.00 Div 14: FabricatDiv 14: Fabrication & Delivery 70 70 0% 24-Apr-20 03-Aug-20 16-Nov-20 25-Feb-21 143 $0.00 F-14-1000 FAD Elevator 70 70 0% 24-Apr-20 03-Aug-20 16-Nov-20 25-Feb-21 143 $0.00
Div 21: Fire SupDiv 21: Fire Suppression 73 73 0% 17-Mar-20 26-Jun-20 17-Nov-20 01-Mar-21 170 $3,000.00 Div 21: SubmittaDiv 21: Submittals 1 1 0% 17-Mar-20 17-Mar-20 17-Nov-20 17-Nov-20 172 $0.00 S-21-1000 Submit FP Sprinkler Heads 1 1 0% 17-Mar-20 17-Mar-20 17-Nov-20 17-Nov-20 172 $0.00
Div 21: ReviewsDiv 21: Reviews & Approvals 30 30 0% 18-Mar-20 16-Apr-20 18-Nov-20 17-Dec-20 245 $3,000.00 R-21-1000 Review/Approve FP Sprinkler Heads 30 30 0% 18-Mar-20 16-Apr-20 18-Nov-20 17-Dec-20 245 $3,000.00
Div 21: FabricatDiv 21: Fabrication & Delivery 50 50 0% 17-Apr-20 26-Jun-20 18-Dec-20 01-Mar-21 170 $0.00 F-21-1000 FAD FP Sprinkler Heads 50 50 0% 17-Apr-20 26-Jun-20 18-Dec-20 01-Mar-21 170 $0.00
Div 22: PlumbinDiv 22: Plumbing 73 73 0% 07-Apr-20 20-Jul-20 04-Dec-20 20-Apr-21 191 $6,000.00 Div 22: SubmittaDiv 22: Submittals 1 1 0% 07-Apr-20 07-Apr-20 04-Dec-20 08-Jan-21 191 $0.00 S-22-1000 Submit Plumbing Fixtures 1 1 0% 07-Apr-20 07-Apr-20 04-Dec-20 04-Dec-20 168 $0.00 S-22-2000 Submit Drinking Fountains (EWC) 1 1 0% 07-Apr-20 07-Apr-20 08-Jan-21 08-Jan-21 191 $0.00 S-22-3000 Submit Water Heaters (WH-1 & WH-2)) 1 1 0% 07-Apr-20 07-Apr-20 24-Dec-20 24-Dec-20 182 $0.00
Div 22: ReviewsDiv 22: Reviews & Approvals 30 30 0% 08-Apr-20 07-May-20 07-Dec-20 09-Feb-21 278 $6,000.00 R-22-1000 Review/Approve Plumbing Fixtures 30 30 0% 08-Apr-20 07-May-20 07-Dec-20 05-Jan-21 243 $2,000.00 R-22-2000 Review/Approve Drinking Fountains (EWC) 30 30 0% 08-Apr-20 07-May-20 11-Jan-21 09-Feb-21 278 $2,000.00 R-22-3000 Review/Approve Water Heaters (WH-1 & WH-2)) 30 30 0% 08-Apr-20 07-May-20 27-Dec-20 25-Jan-21 263 $2,000.00
Div 22: FabricatDiv 22: Fabrication & Delivery 50 50 0% 08-May-20 20-Jul-20 06-Jan-21 20-Apr-21 191 $0.00 F-22-1000 FAD Plumbing Fixtures 50 50 0% 08-May-20 20-Jul-20 06-Jan-21 16-Mar-21 166 $0.00 F-22-2000 FAD Drinking Fountains 50 50 0% 08-May-20 20-Jul-20 10-Feb-21 20-Apr-21 191 $0.00 F-22-3000 FAD Water Heaters (WH-1 & WH-2)) 40 40 0% 08-May-20 06-Jul-20 26-Jan-21 22-Mar-21 180 $0.00
Div 23: HVACDiv 23: HVAC 103 103 0% 17-Mar-20 10-Aug-20 15-Sep-20 31-Mar-21 162 $8,000.00 Div 23: SubmittaDiv 23: Submittals 6 6 0% 17-Mar-20 24-Mar-20 15-Sep-20 04-Jan-21 197 $0.00 S-23-1000 Submit Mech Packaged Units (OSA-V & OSA-L) 1 1 0% 17-Mar-20 17-Mar-20 13-Oct-20 13-Oct-20 147 $0.00 S-23-3000 Submit HVAC Grilles & Diffusers 1 1 0% 24-Mar-20 24-Mar-20 20-Nov-20 20-Nov-20 170 $0.00 S-23-2000 Submit HVAC Controls 1 1 0% 24-Mar-20 24-Mar-20 04-Jan-21 04-Jan-21 197 $0.00 S-23-4000 Submit Mech Air Curtains (ACs) 1 1 0% 24-Mar-20 24-Mar-20 16-Oct-20 16-Oct-20 145 $0.00 S-23-5000 Submit Mech VRF's 1 1 0% 24-Mar-20 24-Mar-20 15-Sep-20 15-Sep-20 122 $0.00 S-23-6000 Submit Exhaust Fan ( EF-L1) 1 1 0% 24-Mar-20 24-Mar-20 18-Dec-20 18-Dec-20 188 $0.00
Div 23: ReviewsDiv 23: Reviews & Approvals 37 37 0% 18-Mar-20 23-Apr-20 16-Sep-20 03-Feb-21 286 $8,000.00 R-23-1000 Review/Approve Mech Packaged Unit (OSA-V & OSA-L) 30 30 0% 18-Mar-20 16-Apr-20 14-Oct-20 12-Nov-20 210 $0.00 R-23-3000 Review/Approve HVAC Grilles & Diffusers 30 30 0% 25-Mar-20 23-Apr-20 22-Nov-20 21-Dec-20 242 $2,000.00 R-23-2000 Review/Approve HVAC Controls 30 30 0% 25-Mar-20 23-Apr-20 05-Jan-21 03-Feb-21 286 $2,000.00 R-23-4000 Review/Approve Mech Air Curtains (ACs) 30 30 0% 25-Mar-20 23-Apr-20 18-Oct-20 16-Nov-20 207 $2,000.00 R-23-5000 Review/Approve Mech VRF's 30 30 0% 25-Mar-20 23-Apr-20 16-Sep-20 15-Oct-20 175 $2,000.00 R-23-6000 Review/Approve Exhaust Fan ( EF-L1) 30 30 0% 25-Mar-20 23-Apr-20 21-Dec-20 19-Jan-21 271 $0.00
Div 23: FabricatDiv 23: Fabrication & Delivery 80 80 0% 17-Apr-20 10-Aug-20 16-Oct-20 31-Mar-21 162 $0.00 F-23-1000 FAD Mech Packaged Unit (OSA-V & OSA-L) 80 80 0% 17-Apr-20 10-Aug-20 13-Nov-20 10-Mar-21 147 $0.00 F-23-3000 FAD HVAC Grilles & Diffusers 40 40 0% 24-Apr-20 19-Jun-20 22-Dec-20 17-Feb-21 167 $0.00 F-23-2000 FAD HVAC Controls 40 40 0% 24-Apr-20 19-Jun-20 04-Feb-21 31-Mar-21 197 $0.00 F-23-4000 FAD Mech Air Curtains (ACs) 60 60 0% 24-Apr-20 20-Jul-20 17-Nov-20 12-Feb-21 144 $0.00 F-23-5000 FAD Mech VRF's 60 60 0% 24-Apr-20 20-Jul-20 16-Oct-20 13-Jan-21 122 $0.00 F-23-6000 FAD Exhaust Fan ( EF-L1) 50 50 0% 24-Apr-20 06-Jul-20 20-Jan-21 30-Mar-21 186 $0.00
Div 26: ElectricaDiv 26: Electrical 83 79 4.82% 01-Mar-20 19-Jun-20 28-Dec-20 21-Apr-21 212 $9,000.00 Div 26: SubmittaDiv 26: Submittals 6 1 83.33% 01-Mar-20 24-Mar-20 28-Dec-20 18-Mar-21 249 $0.00 S-26-3000 Submit Electrical Panels 1 0 100% 01-Mar-20 01-Mar-20 08-Jan-21 08-Jan-21 $0.00
S O N D J F M A M J Jul A S O N D J F M A M J J A S 2020 2021
Review/Approve Elevator
FAD Elevator
Submit FP Sprinkler Heads
Review/Approve FP Sprinkler Heads
FAD FP Sprinkler Heads
Submit Plumbing Fixtures Submit Drinking Fountains (EWC) Submit Water Heaters (WH-1 & WH-2))
Review/Approve Plumbing Fixtures Review/Approve Drinking Fountains (EWC) Review/Approve Water Heaters (WH-1 & WH-2))
FAD Plumbing Fixtures FAD Drinking Fountains
FAD Water Heaters (WH-1 & WH-2))
Submit Mech Packaged Units (OSA-V & OSA-L) Submit HVAC Grilles & Diffusers Submit HVAC Controls Submit Mech Air Curtains (ACs) Submit Mech VRF's Submit Exhaust Fan ( EF-L1)
Review/Approve Mech Packaged Unit (OSA-V & OSA-L) Review/Approve HVAC Grilles & Diffusers Review/Approve HVAC Controls Review/Approve Mech Air Curtains (ACs) Review/Approve Mech VRF's Review/Approve Exhaust Fan ( EF-L1)
FAD Mech Packaged Unit (OSA-V & OSA-L) FAD HVAC Grilles & Diffusers FAD HVAC Controls
FAD Mech Air Curtains (ACs) FAD Mech VRF's
FAD Exhaust Fan ( EF-L1)
Submit Electrical Panels
Remaining Level of Effort Actual Level of Effort Actual Work
Remaining Duration
Duration % Complete
Early Start Early Finish Late Start Late Finish Total Float
Budgeted Total Cost
S-26-1000 Submit Interior Light Fixtures 1 0 100% 01-Mar-20 01-Mar-20 28-Dec-20 28-Dec-20 $0.00 S-28-4000 Submit Exterior Light Fixtures 1 0 100% 01-Mar-20 01-Mar-20 18-Mar-21 18-Mar-21 $0.00 S-26-2000 Submit Lightning Protection 1 1 0% 24-Mar-20 24-Mar-20 08-Jan-21 08-Jan-21 201 $0.00
Div 26: ReviewsDiv 26: Reviews & Approvals 37 30 18.92% 01-Mar-20 23-Apr-20 28-Dec-20 18-Mar-21 328 $9,000.00 R-26-3000 Review/Approve Electrical Panels 30 0 100% 01-Mar-20 01-Mar-20 08-Jan-21 08-Jan-21 $0.00 R-26-1000 Review/Approve Interior Light Fixtures 30 0 100% 01-Mar-20 01-Mar-20 28-Dec-20 28-Dec-20 $3,000.00 R-28-4000 Review/Approve Exterior Light Fixtures 30 0 100% 01-Mar-20 01-Mar-20 18-Mar-21 18-Mar-21 $3,000.00 R-26-2000 Review/Approve Lightning Protection 30 30 0% 25-Mar-20 23-Apr-20 10-Jan-21 08-Feb-21 291 $3,000.00
Div 26: FabricatDiv 26: Fabrication & Delivery 60 79 0% 02-Mar-20 19-Jun-20 28-Dec-20 21-Apr-21 212 $0.00 F-26-1000 FAD Interior Light Fixtures 50 25 50% 02-Mar-20 03-Apr-20 28-Dec-20 01-Feb-21 209 $0.00 F-26-3000 FAD Electrical Panels 60 40 33.33% 02-Mar-20 24-Apr-20 08-Jan-21 04-Mar-21 217 $0.00 F-28-4000 FAD Exterior Light Fixtures 50 25 50% 02-Mar-20 03-Apr-20 18-Mar-21 21-Apr-21 266 $0.00 F-26-2000 FAD Lightning Protection 40 40 0% 24-Apr-20 19-Jun-20 09-Feb-21 05-Apr-21 200 $0.00
Div 28: ElectricaDiv 28: Electrical Safety and Security 83 83 0% 07-Apr-20 03-Aug-20 11-Dec-20 15-Apr-21 178 $6,000.00 Div 28: SubmittaDiv 28: Submittals 1 1 0% 07-Apr-20 07-Apr-20 11-Dec-20 05-Jan-21 188 $0.00 S-28-2000 Submit Fire Alarm Devices 1 1 0% 07-Apr-20 07-Apr-20 05-Jan-21 05-Jan-21 188 $0.00 S-28-1000 Submit Fire Alarm Control Panel 1 1 0% 07-Apr-20 07-Apr-20 11-Dec-20 11-Dec-20 173 $0.00 S-28-3000 Submit Exterior Security & Low Voltage Devices 1 1 0% 07-Apr-20 07-Apr-20 24-Dec-20 24-Dec-20 182 $0.00
Div 28: ReviewsDiv 28: Reviews & Approvals 30 30 0% 08-Apr-20 07-May-20 12-Dec-20 04-Feb-21 273 $6,000.00 R-28-2000 Review/Approve Fire Alarm Devices 30 30 0% 08-Apr-20 07-May-20 06-Jan-21 04-Feb-21 273 $2,000.00 R-28-1000 Review/Approve Fire Alarm Control Panel 30 30 0% 08-Apr-20 07-May-20 12-Dec-20 10-Jan-21 248 $2,000.00 R-28-3000 Review/Approve Exterior Security & Low Voltage Devices 30 30 0% 08-Apr-20 07-May-20 28-Dec-20 26-Jan-21 264 $2,000.00
Div 28: FabricatDiv 28: Fabrication & Delivery 60 60 0% 08-May-20 03-Aug-20 11-Jan-21 15-Apr-21 178 $0.00 F-28-2000 FAD Fire Alarm Devices 50 50 0% 08-May-20 20-Jul-20 05-Feb-21 15-Apr-21 188 $0.00 F-28-1000 FAD Fire Alarm Control Panel 60 60 0% 08-May-20 03-Aug-20 11-Jan-21 02-Apr-21 169 $0.00 F-28-3000 FAD Exterior Security & Low Voltage Devices 40 40 0% 08-May-20 06-Jul-20 27-Jan-21 23-Mar-21 181 $0.00
Div 31: EarthwoDiv 31: Earthwork 43 10 76.74% 01-Mar-20 13-Mar-20 27-Apr-20 08-May-20 40 $2,000.00 Div 31: SubmittaDiv 31: Submittals 1 0 100% 01-Mar-20 01-Mar-20 27-Apr-20 27-Apr-20 $0.00 S-31-1000 Submit Helical Piles 1 0 100% 01-Mar-20 01-Mar-20 27-Apr-20 27-Apr-20 $0.00
Div 31: ReviewsDiv 31: Reviews & Approvals 30 0 100% 01-Mar-20 01-Mar-20 27-Apr-20 27-Apr-20 $2,000.00 R-31-1000 Review/Approve Helical Piles 30 0 100% 01-Mar-20 01-Mar-20 27-Apr-20 27-Apr-20 $2,000.00
Div 31: FabricatDiv 31: Fabrication & Delivery 20 10 50% 02-Mar-20 13-Mar-20 27-Apr-20 08-May-20 40 $0.00 F-31-1000 FAD Helical Piles 20 10 50% 02-Mar-20 13-Mar-20 27-Apr-20 08-May-20 40 $0.00
Div 32: ExteriorDiv 32: Exterior Improvements 186 186 0% 07-Apr-20 30-Dec-20 08-Mar-21 04-May-21 88 $2,000.00 Div 32: SubmittaDiv 32: Submittals 165 165 0% 07-Apr-20 30-Nov-20 08-Mar-21 12-Mar-21 72 $0.00 S-32-1000 Submit Wheel Stops 1 1 0% 07-Apr-20 07-Apr-20 12-Mar-21 12-Mar-21 236 $0.00 S-32-2000 Prepare Sidewalk Mock-up 5 5 0% 20-Nov-20 30-Nov-20 08-Mar-21 12-Mar-21 72 $0.00
Div 32: ReviewsDiv 32: Reviews & Approvals 267 267 0% 08-Apr-20 30-Dec-20 14-Mar-21 13-Apr-21 104 $2,000.00 R-32-1000 Review/Approve Wheel Stops 30 30 0% 08-Apr-20 07-May-20 15-Mar-21 13-Apr-21 341 $1,000.00 R-32-2000 Review/Approve Sidewalk Mock-up 30 30 0% 01-Dec-20 30-Dec-20 14-Mar-21 12-Apr-21 103 $1,000.00
Div 32: FabricatDiv 32: Fabrication & Delivery 15 15 0% 08-May-20 29-May-20 14-Apr-21 04-May-21 236 $0.00 F-32-1000 FAD Wheel Stops 15 15 0% 08-May-20 29-May-20 14-Apr-21 04-May-21 236 $0.00
Div 33: UtilitiesDiv 33: Utilities 43 43 0% 02-Mar-20 29-Apr-20 09-Oct-20 01-Mar-21 211 $4,000.00 Div 33: SubmittaDiv 33: Submittals 1 1 0% 02-Mar-20 02-Mar-20 09-Oct-20 08-Jan-21 217 $0.00 S-33-1000 Submit Watermain 1 1 0% 02-Mar-20 02-Mar-20 09-Oct-20 09-Oct-20 156 $0.00 S-33-2000 Submit Water Plant Pumps 1 1 0% 02-Mar-20 02-Mar-20 08-Jan-21 08-Jan-21 217 $0.00
Div 33: ReviewsDiv 33: Reviews & Approvals 30 30 0% 03-Mar-20 01-Apr-20 10-Oct-20 08-Feb-21 313 $4,000.00 R-33-1000 Review/Approve Watermain 30 30 0% 03-Mar-20 01-Apr-20 10-Oct-20 08-Nov-20 221 $2,000.00
S O N D J F M A M J Jul A S O N D J F M A M J J A S 2020 2021
Submit Interior Light Fixtures Submit Exterior Light Fixtures
Submit Lightning Protection
Review/Approve Electrical Panels Review/Approve Interior Light Fixtures Review/Approve Exterior Light Fixtures
Review/Approve Lightning Protection
FAD Interior Light Fixtures FAD Electrical Panels
FAD Exterior Light Fixtures FAD Lightning Protection
Submit Fire Alarm Devices Submit Fire Alarm Control Panel Submit Exterior Security & Low Voltage Devices
Review/Approve Fire Alarm Devices Review/Approve Fire Alarm Control Panel Review/Approve Exterior Security & Low Voltage Devices
FAD Fire Alarm Devices FAD Fire Alarm Control Panel
FAD Exterior Security & Low Voltage Devices
Submit Helical Piles
Review/Approve Helical Piles
FAD Helical Piles
Submit Wheel Stops Prepare Sidewalk Mock-up
Review/Approve Wheel Stops Review/Approve Sidewalk Mo
FAD Wheel Stops
Submit Watermain Submit Water Plant Pumps
Review/Approve Watermain
Remaining Level of Effort Actual Level of Effort Actual Work
Remaining Duration
Duration % Complete
Early Start Early Finish Late Start Late Finish Total Float
Budgeted Total Cost
R-33-2000 Review/Approve Water Plant Pumps 30 30 0% 03-Mar-20 01-Apr-20 10-Jan-21 08-Feb-21 313 $2,000.00 Div 33: FabricatDiv 33: Fabrication & Delivery 20 20 0% 02-Apr-20 29-Apr-20 09-Nov-20 01-Mar-21 211 $0.00 F-33-1000 FAD Watermain Piping, Tees & PRV's 20 20 0% 02-Apr-20 29-Apr-20 09-Nov-20 08-Dec-20 154 $0.00 F-33-200 FAD Water Plant Pumps 15 15 0% 02-Apr-20 22-Apr-20 09-Feb-21 01-Mar-21 216 $0.00
CONSTRUCTCONSTRUCTION 359 325 9.47% 01-Mar-20 09-Jun-21 24-Mar-20 07-Jun-21 -2 $6,992,661.62
Mobilization & SMobilization & Start-up 35 3 91.43% 01-Mar-20 30-Mar-20 24-Mar-20 27-Mar-20 -2 $19,000.00 C-MOB-1200 Install Contractoring Officer Temporary Office & Furniture 5 0 100% 01-Mar-20 01-Mar-20 27-Mar-20 27-Mar-20 $2,000.00 C-MOB-1400 Install Contractor Temporary Office & Furniture 5 0 100% 01-Mar-20 01-Mar-20 27-Mar-20 27-Mar-20 $2,000.00 C-MOB-1000 Capture Existing Conditions Images 1 0 100% 01-Mar-20 01-Mar-20 27-Mar-20 27-Mar-20 $1,000.00 C-MOB-1100 Install Temporary Fence/Gate & Saftey Barriers 5 0 100% 01-Mar-20 01-Mar-20 24-Mar-20 24-Mar-20 $2,000.00 C-MOB-1800 Install Temporary Signage 2 0 100% 01-Mar-20 01-Mar-20 27-Mar-20 27-Mar-20 $1,000.00 C-MOB-1900 Install Erosion Control 5 0 100% 04-Mar-20 04-Mar-20 27-Mar-20 27-Mar-20 $3,500.00 C-MOB-1500 Install Temporary Portable Toilets 2 0 100% 01-Mar-20 01-Mar-20 27-Mar-20 27-Mar-20 $1,000.00 C-MOB-1700 Install Temporary Utilities 5 0 100% 01-Mar-20 01-Mar-20 27-Mar-20 27-Mar-20 $3,000.00 C-MOB-1600 Install Temp Fire Protection & Fire Extinguishers 4 0 100% 01-Mar-20 01-Mar-20 27-Mar-20 27-Mar-20 $1,000.00 C-MOB-9000 Complete Mobilization 0 0 100% 30-Mar-20 27-Mar-20 $0.00 C-MOB-1300 Install Temp Protection of Plants & Trees 4 3 25% 02-Mar-20 04-Mar-20 24-Mar-20 26-Mar-20 16 $2,500.00
SiteworkSitework 280 266 5% 31-Mar-20 15-Apr-21 07-Dec-20 17-May-21 22 $1,011,466.00
WatermainWatermain 118 104 11.