Performance Standards and Guarantees for Irrigation System Management Services
This document is Attachment C to contract DMS-25/26-032 for Irrigation System Management Services. It establishes the performance standards and measurement criteria that the Contractor must meet on a quarterly basis, with the Facility Manager required to complete and submit the form quarterly to the Contract Manager. The form requires the signatures of both the Facility Manager and Contractor upon completion.
The document specifies four key deliverables with associated performance guarantees and measurement standards: (1) Damage, Leaks, and Malfunctions—the Contractor must immediately report any irrigation system damage, leaks, or malfunctions via email to the DMS Facilities Manager with a 5% invoice deduction for noncompliance; (2) Minor Repairs—the Contractor must repair minor irrigation system components damaged during routine service operations with a 5% invoice deduction for noncompliance; (3) Irrigation Schedule—the Contractor is responsible for irrigation operations and schedule with prior approval required from the DMS Facilities Manager for any deviations, subject to a 10% invoice deduction for noncompliance; and (4) Quarterly Summary Report—the Contractor must submit Attachment B within five business days of the quarterly inspection with a 5% invoice deduction if the report is not timely submitted. Performance is rated on a three-point scale: 1-Good (Performance Acceptable), 2-Fair (Performance Needs Improvement), and 3-Poor (Below Standards/Non-Compliant), with invoice deductions applied for Poor ratings.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment C - Performance Standards and Guarantees
DMS-25/26-032
Irrigation System Management Services
The Facility Manager must complete and submit this form quarterly to the Contract Manager. The Facility Manager and Contractor must sign and date this form after completion.
Deliverable Guarantee Measurement 1 - Good
2 - Fair
3 - Poor
Minimum Result of Noncompliance
Damage, Leaks, Malfunctions
Section 2.2.1: The Contractor shall immediately report via e-mail any irrigation system damage, leaks, or malfunctions to the DMS Facilities Manager and provide information on the Quarterly Summary Report.
Contract Manager will receive monthly acknowledgement of services from Facility Manager (Attachment B - Quarterly Summary Report).
5% will be deducted from Contractor's invoice for site associated with non-compliance.
Minor Repairs
Section 2.2.5: The Contractor shall make any repairs to minor irrigation system components that are damaged or destroyed during routine service operations.
Contract Manager will receive monthly acknowledgement of services from Facility Manager (Attachment B - Quarterly Summary Report).
5% will be deducted from Contractor's invoice for site associated with non-compliance.
Irrigation Schedule
Section 2.1.4: Contractor is responsible for the Irrigation Operations and Schedule. Any deviation requires prior approval from the DMS Facilities Manager.
Contract Manager will receive monthly acknowledgement of services from Facility Manager (Attachment B - Quarterly Summary Report).
10% will be deducted from Contractor's invoice for site associated with non-compliance.
Quarterly Summary Report
Section 2.3: The Contractor shall submit Attachment B - Quarterly Summary Report within five business days of the quarterly inspection.
Contract Manager will receive Attachment B – Quarterly Summary Report with all quantitative and qualitative measurements.
5% will be deducted from Contractor’s invoice if report is not submitted within 5 business days.
Attachment C - Performance Standards and Guarantees
DMS-25/26-032
Irrigation System Management Services
Rating definitions:
1- Good: Performance Acceptable 2- Fair: Performance Needs Improvement (if Contractor fails to correct deficiencies the following month, Contractor will receive a 3 - Poor rating and invoice deductions will apply pursuant to Attachment C - Performance Standards and Guarantees) 3- Poor: Below Standards/Non-Compliant (invoice deductions apply pursuant to Attachment C - Performance Standards and Guarantees)
Facility Manager Contractor
Date Date