About this file
This deliverable items list outlines the hardware, software, and documentation required under the Landsat Next Instrument Suite contract. Key deliverables include three Landsat Next Instrument Suite units, interface and operational simulators, a software development facility, witness samples, drill templates, mounting hardware, electrical connectors, printed wiring boards, engineering units, and all associated source code and documentation. Delivery dates range from contract award to six months prior to spacecraft integration. Accompanying test and verification requirements are specified.
The related draft request for proposal seeks responses from interested offerors to provide the Landsat Next Instrument Suite and associated deliverables. Potential offerors should monitor the SAM website for release of the solicitation and any amendments. NASA intends to publicize respondents to facilitate teaming arrangements but will withhold names of offerors requesting anonymity. The solicitation number, agency, and opportunity type are identified.
View the file
Other files for this federal contract opportunity
Show all 50
Landsat Next Instrument Suite (LandIS) Request for Proposal has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LandIS DIL LNEXT-LANDIS-LIST-0004 Revision -ii
Landsat Next Landsat Instrument Suite (LandIS) Deliverable Items List (DIL)
Signature Page
Prepared by:
Electronic Signature in TDMS
12/22/2022 Joy Henegar-leon Date Landsat Next Payload Technical Manager NASA/GSFC, Code 426
Approved by:
Wen-Ting Hsieh Date Landsat Next Payload Manager NASA/Goddard, Code 426
Evan Webb Date Landsat Next Systems Manager NASA/GSFC, Code 599
James Pontius Date Landsat Next Project Manager NASA/GSFC, Code 426 iii
CM Foreword This document is a Landsat Next Project Configuration Management (CM)-controlled document.
Changes to this document require prior approval of the applicable Configuration Control Board (CCB) Chairperson or designee. Proposed changes shall be submitted to the Landsat Next CM Office (CMO), along with supportive material justifying the proposed change. Changes to this document will be made by complete revision.
Questions or comments concerning this document should be addressed to:
NASA/Goddard Space Flight Center Landsat Next Project Office, Code 426 Attention: Configuration Management Office Greenbelt, Maryland 20771 iv
Change History Log
Revision Effective Date Description of Changes
- 12/22/2022 LNEXT-CCR-0013– Initial Release v
List of TBDs/TBRs Hyperlink to TBx Location Summary Ind.
Name/Org.
Due Date vi
Table of Contents CM FOREWORD ..........................................................................................................................III
CHANGE HISTORY LOG .......................................................................................................... IV
LIST OF TBDS/TBRS .................................................................................................................... V
TABLE OF CONTENTS .............................................................................................................. VI
LIST OF FIGURES ...................................................................................................................... VI
LIST OF TABLES ........................................................................................................................ VI
List of Figures No table of contents entries found.
List of Tables No table of contents entries found.
DIL LNEXT-LANDIS-LIST-0004
Deliverable Items List:
A. Hardware:
Item No. Description SOW
Reference Qty Schedule Transportation
Class A-1 Landsat Next
Instrument Suite (LandIS), Including Protective Covers
3.0 3 No Later Than (NLT) Contract Effective Date
(CED)+ 60
months
I
A-2 LandIS Interface Simulator (LIS), Including Harnesses
3.5.14 3 Instrument Critical Design Review (CDR) + 3 Months
II
A-3 LandIS Operational Simulator (LOpS)
3.5.14 6 Instrument Pre- Ship Review (PSR) – 6 months
II
A-4 Software Development and Verification Facility (SDVF)
3.5.8.4 1 At handover to the Government
II
A-5 Spectral Filter Witness Samples
3.5.13.3 Per Instrument
Mission Assurance Requirements
(IMAR)
As Generated II
A-6 Instrument Drill Templates
3.9.2 2 NLT Instrument CDR + 6 months
II
A-7 LandIS Spacecraft Mounting Hardware
3.12.3 3 Sets Plus Spares With Item 1 II
A-8 LandIS Electrical Connectors
3.12.3 3 Sets Plus Spares With Item 1 II
A-9 Printed Wiring Board Coupons
3.3 Per IMAR As Generated II
A-10 Flight Spares 3.10 All At handover to the Government
II
A-11 Engineering Design Units
3.5.15 All At handover to
the Government
II
B. Software:
B-1 The Complete Set of Source
Code, Patch History and Associated Build Scripts to Regenerate the Image
3.5.8.1 1 At handover to the Government
IV