About this file

This is a Schedule of Items pricing template for roadway maintenance services across eight ranger districts and units of the Mark Twain National Forest. The contract covers a Base Year (5/1/2026–4/30/2027) plus four option years through 4/30/2031. Contractors must provide unit pricing for surface blading maintenance (single-lane and double-lane roadways measured in miles), culvert installation and replacement (18-inch and 24-inch diameter in both corrugated metal pipe and HDPE materials, measured in linear feet), and crushed aggregate supply in five size classifications (1-inch clean, 1-inch base, 2-inch clean, 2-inch base, and 3-inch to 6-inch clean, measured in tons). The eight service areas are Salem Ranger District, Houston-Rolla Ranger District, Potosi-Fredericktown Ranger District, Poplar Bluff Ranger District, Eleven Point Ranger District, Ava Unit, Cassville Unit, and Willow Springs Unit. Estimated quantities vary by location and service type, ranging from 50 to 150 miles for surface blading and 30 linear feet or units for culvert work and 15 tons for aggregate materials.

The solicitation uses a firm-fixed-price model with Lowest Price Technically Acceptable (LPTA) evaluation methodology. Quantities are estimated and subject to change based on funding availability and bids received; not all line items will necessarily be awarded in each contract year. Contractors must submit unit prices for each service line item across all five contract years to enable government evaluation of pricing consistency and total cost. The award is anticipated to be issued by the Department of Agriculture Forest Service covering multiple counties across Missouri including Barry, Stone, Christian, Taney, Ozark, Douglas, Howell, Oregon, Ripley, Carter, Wayne, Butler, Iron, Madison, St. Francious, St. Genevieve, Bollinger, Washington, Phelps, Texas, Laclede, Pulaski, and Wright.

View the file

Other files for this federal contract opportunity

Other files attached to Roadway Surface Blading/Grading Needed for the Mark Twain National Forest, newest first.
File Type Posted
Amended RFQ 12444526Q0014 (1).pdf PDF
Solicitation Amendment Document.pdf PDF
Attachment D Wage Determination .pdf PDF
Attachment A Experience Questionnaire.pdf PDF
Attachment C Statement of Work 26-30.docx DOCX document
12444526Q0014 Commercial Services RFQ.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCHEDULE OF ITEMS

Task/Subtask Estimated Unit Unit Price Unit Price Unit Price Unit Price Unit Price Description Quantity*

Base Year Option Option Option Option

Year 1 Year 2 Year 3 Year 4

2029 2030

5/1/26-4/30/27 5/1/27-4/30/28 5/1/28-4/30/29 5/1/29-4/30/30 5/1/30-04/30/31

5. MAINTENANCE – SURFACE BLADING and CULVERTS

5.1 - SALEM RANGER DISTRICT

5.1.1. Single Lane

50.0 Mile

5.1.2. Double Lane

100.0 Mile

5.1.3. Installation of CMP Culverts - 18” dia.

L.F.

5.1.4. Replacement of CMP Culverts – 18” dia.

L.F.

5.1.5. Installation of CMP Culverts - 24” dia.

L.F.

5.1.6. Replacement of CMP Culverts – 24” dia.

L.F.

5.1.7. Installation of HDPE Culverts – 18” dia.

L.F.

5.1.8. Installation of HDPE Culverts – 24” dia.

L.F.

5.1.9 Crushed Aggregate – 1” Clean

15 Ton $_______

5.1.10 Crushed Aggregate – 1” Base

Ton

5.1.11 Crushed Aggregate – 2” Clean

Ton

5.1.12 Crushed Aggregate – 2” Base

Ton

5.1.13 Crushed Aggregate – 3” to 6” Clean

Ton

*Quantities are estimated and may change based on bids received.

The award of bid items and quantities awarded on bid items will be determined based on the availability of funds. Quantities are subject to change for the option year period

Not all bid items may be awarded each year.

SCHEDULE OF ITEMS

Task/Subtask Estimated Unit Unit Price Unit Price Unit Price Unit Price Unit Price

Description Quantity*

Base Year Option

5/1/26-4/30/27 5/1/27-4/30/28 5/1/28-4/30/29 5/1/29-4/30/30 5/1/30-4/30/31

5. MAINTENANCE – SURFACE BLADING, CULVERTS and AGGREGATE (cont.)

5.2 - HOUSTON-ROLLA RANGER DISTRICT

5.2.1. Single Lane

50.0 Mile

5.2.2. Double Lane

50.0 Mile

5.2.3. Installation of Culverts - 18” dia.

L.F.

5.2.4. Replacement of Culverts – 18” dia.

L.F.

5.2.5. Installation of Culverts - 24” dia.

L.F.

5.2.6. Replacement of Culverts – 24” dia.

L.F.

5.2.7. Installation of HDPE Culverts – 18” dia.

L.F.

5.2.8. Installation of HDPE Culverts – 24” dia.

L.F.

5.2.9 Crushed Aggregate – 1” Clean

15 Ton $_______

5.1.10 Crushed Aggregate – 1” Base

Ton

5.1.11 Crushed Aggregate – 2” Clean

Ton

5.1.12 Crushed Aggregate – 2” Base

Ton

5.1.13 Crushed Aggregate – 3” to 6” Clean

Ton

*Quantities are estimated and may change based on bids received.

The award of bid items and quantities awarded on bid items will be determined based on the availability of funds. Quantities are subject to change for the option year period Not all bid items may be awarded each year.

SCHEDULE OF ITEMS

Task/Subtask Estimated Unit Unit Price Unit Price Unit Price Unit Price Unit Price

Description Quantity*

Base Year Option

2026 2027 2028 2029

5.3 – POTOSI-FREDERICKTOWN RANGER DISTRICT

5.3.1. Single Lane

50.0 Mile

5.3.2. Double Lane

150.0 Mile

5.3.3. Installation of Culverts - 18” dia.

L.F.

5.3.4. Replacement of Culverts – 18” dia.

L.F.

5.3.5. Installation of Culverts - 24” dia.

L.F.

5.3.6. Replacement of Culverts – 24” dia.

L.F.

5.3.7. Installation of HDPE Culverts – 18” dia.

L.F.

5.3.8. Installation of HDPE Culverts – 24” dia.

L.F.

5.3.9 Crushed Aggregate – 1” Clean

15 Ton $_______

5.1.10 Crushed Aggregate – 1” Base

Ton

5.1.11 Crushed Aggregate – 2” Clean

Ton

5.1.12 Crushed Aggregate – 2” Base

Ton

5.1.13 Crushed Aggregate – 3” to 6” Clean

Ton

*Quantities are estimated and may change based on bids received.

The award of bid items and quantities awarded on bid items will be determined based on the availability of funds. Quantities are subject to change for the option year period Not all bid items may be awarded each year.

SCHEDULE OF ITEMS

Task/Subtask Estimated Unit Unit Price Unit Price Unit Price Unit Price Unit Price

Description Quantity*

Base Year Option

5/1/26-4/30/27 5/1/27-04/30/28 5/1/28-4/30/29 5/1/29-4/30/30 5/1/30-4/30/31

5.4 - POPLAR BLUFF RANGER DISTRICT

5.4.1. Single Lane

50.0 Mile

5.4.2. Double Lane

50.0 Mile

5.4.3. Installation of Culverts - 18” dia.

Each

5.4.4. Replacement of Culverts – 18” dia.

Each

5.4.5. Installation of Culverts - 24” dia.

L.F.

5.4.6. Replacement of Culverts – 24” dia.

L.F.

5.4.7. Installation of HDPE Culverts – 18” dia.

L.F.

5.4.8. Installation of HDPE Culverts – 24” dia.

L.F.

5.4.9 Crushed Aggregate – 1” Clean 15 Ton $_______

5.1.10 Crushed Aggregate – 1” Base

Ton

5.1.11 Crushed Aggregate – 2” Clean

Ton

5.1.12 Crushed Aggregate – 2” Base

Ton

5.1.13 Crushed Aggregate – 3” to 6” Clean

Ton

*Quantities are estimated and may change based on bids received.

The award of bid items and quantities awarded on bid items will be determined based on the availability of funds. Quantities are subject to change for the option year periods.

Not all bid items may be awarded each year.

SCHEDULE OF ITEMS

Task/Subtask Estimated Unit Unit Price Unit Price Unit Price Unit Price Unit Price

Description Quantity*

Base Year Option

2029 2030

5/1/26-4/30/27 5/1/27-4/30/28 5/1/28-4/30/29 5/1/29-4/30/30 5/1/30-4/30/31

5. MAINTENANCE – SURFACE BLADING, CULVERTS and AGGREGATE (cont.)

5.5 - ELEVEN POINT RANGER DISTRICT

5.5.1. Single Lane

50.0 Mile

5.5.2. Double Lane

150.0 Mile

5.5.3. Installation of Culverts - 18” dia.

L.F.

5.5.4. Replacement of Culverts – 18” dia.

L.F.

5.5.5. Installation of Culverts - 24” dia.

L.F.

5.5.6. Replacement of Culverts – 24” dia.

L.F.

5.5.7. Installation of HDPE Culverts – 18” dia.

L.F.

5.5.8. Installation of HDPE Culverts – 24” dia.

L.F.

5.5.9 Crushed Aggregate – 1” Clean

15 Ton $_______

5.1.10 Crushed Aggregate – 1” Base

Ton $________ $_______

5.1.11 Crushed Aggregate – 2” Clean

Ton

5.1.12 Crushed Aggregate – 2” Base

Ton

5.1.13 Crushed Aggregate – 3” to 6” Clean

Ton

*Quantities are estimated and may change based on bids received.

The award of bid items and quantities awarded on bid items will be determined based on the availability of funds. Quantities are subject to change for the option year period Not all bid items may be awarded each year.

SCHEDULE OF ITEMS

Task/Subtask Estimated Unit Unit Price Unit Price Unit Price Unit Price Unit Price

Description Quantity*

Base Year Option

5.6 - AVA UNIT

5.6.1. Single Lane

50.0 Mile

5.6.2. Double Lane

100.0 Mile

5.6.3. Installation of Culverts - 18” dia.

L.F.

5.6.4. Replacement of Culverts – 18” dia.

L.F.

5.6.5. Installation of Culverts - 24” dia.

L.F.

5.6.6. Replacement of Culverts – 24” dia.

L.F.

5.6.7. Installation of HDPE Culverts – 18” dia.

L.F.

5.6.8. Installation of HDPE Culverts – 24” dia.

L.F.

5.6.9 Crushed Aggregate – 1” Clean

15 Ton $_______

5.1.10 Crushed Aggregate – 1” Base

Ton

5.1.11 Crushed Aggregate – 2” Clean

Ton

5.1.12 Crushed Aggregate – 2” Base

Ton

5.1.13 Crushed Aggregate – 3” to 6” Clean

Ton

*Quantities are estimated and may change based on bids received.

The award of bid items and quantities awarded on bid items will be determined based on the availability of funds. Quantities are subject to change for the option year period Not all bid items may be awarded each year.

SCHEDULE OF ITEMS

Task/Subtask Estimated Unit Unit Price Unit Price Unit Price Unit Price Unit Price

Description Quantity*

Base Year Option

2028 2029 2030

5.7 - CASSVILLE UNIT

5.7.1. Single Lane

50.0 Mile

5.7.2. Double Lane

50.0 Mile

5.7.3. Installation of Culverts - 18” dia.

L.F.

5.7.4. Replacement of Culverts – 18” dia.

L.F.

5.7.5. Installation of Culverts - 24” dia.

L.F.

5.7.6. Replacement of Culverts – 24” dia.

L.F.

5.7.7. Installation of HDPE Culverts – 18” dia.

L.F.

5.7.8. Installation of HDPE Culverts – 24” dia.

L.F.

5.7.9 Crushed Aggregate – 1” Clean

15 Ton $_______

5.1.10 Crushed Aggregate – 1” Base

Ton

5.1.11 Crushed Aggregate – 2” Clean

Ton

5.1.12 Crushed Aggregate – 2” Base

Ton

5.1.13 Crushed Aggregate – 3” to 6” Clean

Ton

*Quantities are estimated and may change based on bids received.

The award of bid items and quantities awarded on bid items will be determined based on the availability of funds. Quantities are subject to change for the option year period Not all bid items may be awarded each year.

SCHEDULE OF ITEMS

Task/Subtask Estimated Unit Unit Price Unit Price Unit Price Unit Price Unit Price

Description Quantity*

Base Year Option

5/1/26-4/30/27 5/1/27-4/30/28 5/1/28-4/30/29 5/1/29-4/30/29 5/1/30-4/30/31

5.8 - WILLOW SPRINGS UNIT

5.8.1. Single Lane

50.0 Mile

5.8.2. Double Lane

75.0 Mile

5.8.3. Installation of Culverts - 18” dia.

L.F.

5.8.4. Replacement of Culverts – 18” dia.

L.F.

5.8.5. Installation of Culverts - 24” dia.

L.F.

5.8.6. Replacement of Culverts – 24” dia.

L.F.

5.8.7. Installation of HDPE Culverts – 18” dia.

L.F.

5.8.8. Installation of HDPE Culverts – 24” dia.

L.F.

5.8.9 Crushed Aggregate – 1” Clean

15 Ton $_______

5.1.10 Crushed Aggregate – 1” Base

Ton

5.1.11 Crushed Aggregate – 2” Clean

Ton

5.1.12 Crushed Aggregate – 2” Base

Ton

5.1.13 Crushed Aggregate – 3” to 6” Clean

Ton

*Quantities are estimated and may change based on bids received.

The award of bid items and quantities awarded on bid items will be determined based on the availability of funds. Quantities are subject to change for the option year periods.

Not all bid items may be awarded each year.

File details come from the government source that posted it. Updated .