Attachment_B_-_Required_Submittal_Register.docx
DOCX document 39 KB Posted
- Solicitation number
- 41016
- Issued by
- Sacramento County, San Francisco City, California
About this file
This is a Required Submittal Register for the SMF Pedestrian Walkway Riparian Public Art Installation Project issued by the Sacramento County Department of Airports under CUPCCAA Informal Bid, Contract No. 41016, with anticipated execution in November 2026. The project involves furnishing all necessary labor, materials, equipment, and work required to complete a riparian public art installation at Sacramento International Airport's pedestrian walkway. The document establishes eleven minimum project-specific submittal requirements that contractors must provide throughout the contract lifecycle, from initial planning through final acceptance. Key submittals include a baseline Critical Path Method schedule due within 15 calendar days after Notice to Proceed (NTP-1), a Schedule of Values, an Installation Work Plan, rigging and equipment qualification packages, safety plans, equipment loading verification, artwork receiving and custody logs, readiness verification documentation, daily reports during field work, record documentation and installation certification, and waste logs. All initial submissions require twenty working days for County review with fifteen working days allowed for resubmittals, and submittals must be completed before dependent field activities commence. The contract timeline includes two Notice to Proceed phases, with NTP-2 marking authorization for equipment movement and installation work to begin.
The document does not specify pricing terms, contract value, or funding sources within the submittal register itself. No set-asides are identified in this file. The contractor bears responsibility for all safety, qualifications, loading, protection, and performance requirements throughout the project, with County review serving as an administrative requirement that does not authorize field mobilization or relieve contractor obligations. Artist coordination and participation are integrated into the project requirements, with daily reports and record documentation required to verify the quality and integrity of the riparian art installation. The contract maintains a fixed thirty-calendar-day contract time regardless of working-day review periods, and all submissions must be made electronically with field-dependent information revised following authorized site access.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SMF Pedestrian Walkway Riparian Public Art Installation Project Attachment B Attachment B
Sacramento County Department of Airports SMF Pedestrian Walkway Riparian Public Art Installation Project
ATTACHMENT B
REQUIRED SUBMITTAL REGISTER
CUPCCAA Informal Bid | Contract No. 41016 | November 2026 Administration and review This Attachment identifies the minimum Project-specific and payment-administration submittals for the Riparian installation and supplements Special Provisions Sections 5-8, 7-5, 8-1, 11-3 and 12-1 and the applicable SCS. It does not limit other submittals required by the Contract, permits, law, equipment manufacturers or final County Risk Management requirements.
Submit electronically. Unless a longer period is specified, allow twenty (20) Working Days for initial County review and fifteen (15) Working Days for resubmittal review under Section 5-8.01. A listed due date does not shorten a review period. Submit early enough for required corrections and completed review before the dependent activity.
Complete planning and review for initial field activities under NTP-1 before NTP-2. County-approved limited Site access and any field-dependent verification or revision shall follow Sections 5-8.01 and 7-1. Prepare initial submissions using available County-furnished information, identify missing inputs, and promptly revise field-dependent information after authorized access. Do not certify inaccessible conditions as verified.
County-furnished approved artwork drawings, final registration and placement information, available applicable permanent-design, route, joint-cover and loading information, and permit approvals are furnished inputs rather than Contractor-authored submittals. The Contractor shall review this information for its operations and identify material missing or conflicting information. SD-03 is reference-only. Submit actual manufacturer equipment data and proposed loads and protection information; additional engineering is required only under Section 5-7.02 and is not an automatic separate-study requirement.
Review of a submission does not authorize field mobilization, artwork receipt, equipment movement or installation. The applicable NTP-2 or separate express written authorization and activity prerequisites remain required. No dependent Work shall begin before required review and authorization. County review does not approve Contractor means and methods or relieve its safety, qualifications, loading, protection or performance responsibilities.
Working-Day review periods are administrative requirements. They do not establish an installation-day or tuning-day limit and do not change the thirty (30) Calendar Day Contract Time.
County coordination and field dependent items Before NTP-2, document the status of required RFIs, field verification, submissions and reviews, together with availability of the artwork, compatible hardware, final registration, released supporting grid, loading information, access/staging, Artist participation and permit authorization. If a field-dependent item remains, identify its responsible party, required action, review period and effect on the sequence under Section 7-1(D). Delay responsibility remains governed by Section 7-15.
The Contractor shall submit records of initial tuning and review for each area and document onsite handback of remaining components as part of Items 7 and 10. Artist review does not replace County inspection or acceptance and does not authorize an extra-cost or time change.
The following minimum Project-specific submittals are required:
| No. |
| Submittal |
| Minimum Content |
| Due |
| 1 |
| Baseline CPM Schedule and Updates |
| NTP-1 planning/reviews, limited Site access, County-controlled NTP-2, delivery/receiving/custody, equipment/protection, rondelle installation, Artist coordination and initial tuning, inspections/corrections, Substantial Completion and subsequent closeout. |
| Baseline within 15 Calendar Days after NTP-1. Updated schedule within 7 Calendar Days after County advance notice of anticipated NTP-2. Present current schedule at preconstruction conference. Other updates under SP Section 7-5. |
| 2 |
| Schedule of Values |
| Activity breakdown corresponding to the baseline schedule and totaling the Contract Price, including the single lump-sum installation item; comply with SP Section 8-1 and applicable payment requirements. |
| Submit sufficiently early for County approval before acceptance of the first Progress Payment request. |
| 3 |
| Installation Work Plan |
| Sequence and direct workforce/supervision; two-team baseline or reviewed alternative; glass receiving, handling and registration control; supplied hardware/attachment procedures; access/staging; Artist participation and initial tuning; protection, inspection, cleanup and closeout. |
| Initial plan within 30 Calendar Days after NTP-1. Final plan at least 20 Working Days before first dependent field activity; complete review before that activity. |
| 4 |
| Rigging, lift, equipment and qualification package |
| Actual movable scaffolds, scissor lift and other equipment; capacities/configurations, assembly/inspection and operating procedures; applicable rigging/lift points and load controls; Contractor-employee operator/rigger/spotter qualifications; communications, exclusion zones, fall/rescue procedures, Artist access; required temporary engineering. |
| At least 20 Working Days before first affected field activity. Final equipment-specific credentials and required review shall be complete before use. |
| 5 |
| IIPP, CSWP, CSSP and applicable task-specific safety plans |
| Required safety documents covering fragile glass and fragments, overhead and elevated work, dropped objects, access-equipment/scaffold movement, equipment operations, rigging where used, loading, fall protection/rescue, public separation and airport/emergency coordination. |
| IIPP, CSWP and CSSP at least 20 Working Days before field mobilization; each applicable TSSP at least 20 Working Days before the affected high-hazard activity. Complete necessary field revisions before the task. |
| 6 |
| Equipment Loading and Protection Verification |
| Actual manufacturer equipment data, models, loaded weights and wheel/caster/point loads; proposed travel, operating and staging configurations; personnel, materials and concurrent loads; routes, load distribution where needed, and floor, finish, joint and threshold protection. Verify compatibility with available applicable information and observable conditions. SD-03 is reference-only. Include signed/sealed calculations only when required under Section 5-7.02; no automatic separate structural study. |
| At least 20 Working Days before equipment delivery/movement. Complete field-dependent revisions, County review, applicable engineering acceptance and activity authorization before movement/use. |
| 7 |
| Artwork receiving, inventory and custody log |
| Delivery/crates/counts/component identifiers and supplied registration/type/length data, hardware, condition photos, damaged packaging, shortages/breakage, custody transfer date and representatives, corrective direction and updates. |
| At authorized receipt and updated as required. Receipt/staging before NTP-2 requires separate express written County authorization. |
| 8 |
| Artwork and Interface Readiness Verification |
| Completed and released permanent grid/mesh and attachments; level/access/elevations/clearances; supplied artwork-side rod/clip/connector compatibility; registration/placement/orientation information; route/staging/finish observations; photos and discrepancies. No unauthorized drilling, permanent-support alteration or rod contact with adjacent elements. |
| Initial available-information package at least 20 Working Days before first affected activity. Update after authorized Site access; resolve discrepancies and complete required review before affected equipment movement or installation, under Sections 5-8.01 and 7-1. |
| 9 |
| Daily Reports |
| Direct workforce, supervision, activities/areas, equipment, deliveries/inventory/breakage, safety, controlled zones, Artist coordination/tuning, inspections, RFIs/changed conditions, delays, progress and photos. |
| Daily during field Work following NTP-2 or other express written field authorization. |
| 10 |
| Record documentation, installation certification, closeout and warranty package |
| Marked record drawings and native registration data; installed component and attachment information; approved deviations; initial area tuning/Artist review records; damage/replacements; full-resolution photos; inspection/permit records; installation certification; corrections/cleanup/demobilization; warranty; spare-component handback; County/Artist-supplied care information. No Contractor-authored conservation program. |
| Proposed index and available installation/care information during NTP-1. Maintain records during Work and update record drawings at least weekly and promptly after adjustments. Current records with Substantial Completion request; complete package before final inspection/Field Acceptance; correct deficiencies before Final Acceptance. |
| 11 |
| Waste Log and Supporting Documentation |
| Applicable County waste log, weight tickets and recycling/disposal records; identify County-retained crates and the assigned crate/packing-material handoff separately from Contractor-disposed waste. |
| Maintain during Work; final documents for County approval before final inspection, Field Acceptance, Final Acceptance or final payment, as applicable under Section 5-8.01. |
| Contract No. 41016 |
| CUPCCAA Informal Bid |
| Page 1 of 1 |