ATTACHMENT B - Brainerd Multi-Specialty Activation Project Timelines.xlsx
XLSX spreadsheet 15 KB Posted
- Attached to
- Q702--Brainerd Multi-Specialty Clinic IOT&A
- Solicitation number
- 36C77625Q0137
About this file
The file is a detailed timeline and CLIN (Contract Line Item Number) spreadsheet for the Brainerd Multi-Specialty Clinic Improvement, Oversight, Transition, and Activation (IOT&A) project. The contract spans three years from June 2025 to May 2028, with a base year and two option years, covering comprehensive project management, interior design, space planning, transition planning, and project staffing services. Base year CLINs include PM support, interior design, concept of operations, and acquisition planning, while optional tasks include acquisition package development, warehousing management, personnel file relocation, activation services, and staff training.
The project is for the Department of Veterans Affairs, specifically expanding the Brainerd, Minnesota Community-Based Outpatient Clinic (CBOC) from 25,319 to 41,052 net usable square feet. The new facility will provide 230 parking spaces and enhance medical services including mental health, rehabilitation, and audiology. The solicitation (36C77625Q0137) is managed by the VA Technology Acquisition Center in Austin, with the overall goal of improving healthcare access and comprehensive care for Veterans in the region. The contract includes cost-reimbursable travel and other direct costs provisions across its base and option years.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Timeline
| Brainerd, MN Multi-Specialty IOT&A | ||||||||||||||||||||||||||||||||||||||||
| 06/25 | 07/25 | 08/25 | 09/25 | 10/25 | 11/25 | 12/25 | 01/26 | 02/26 | 03/26 | 04/26 | 05/26 | 06/26 | 07/26 | 08/26 | 09/26 | 10/26 | 11/26 | 12/26 | 01/27 | 02/27 | 03/27 | 04/27 | 05/27 | 06/27 | 07/27 | 08/27 | 09/27 | 10/27 | 11/27 | 12/27 | 01/28 | 02/28 | 03/28 | 04/28 | 05/28 | |||||
| Task Number | CLIN | Task Order Title | Period of Performance | Lease Award | BOD | FPD | ||||||||||||||||||||||||||||||||||
| PWS 16.1 | Base | CLIN 0001 | PM Support Base Year | 06/01/2025 - 05/31/2026 | ||||||||||||||||||||||||||||||||||||
| PWS 16.1 | Option Year | CLIN 1001 | PM Support Option Year 1 | 06/01/2026 - 05/31/2027 | ||||||||||||||||||||||||||||||||||||
| PWS 16.1 | Option Year | CLIN 2001 | PM Support Option Year 2 | 06/01/2027 - 05/31/2028 | ||||||||||||||||||||||||||||||||||||
| PWS 16.2 | Base | CLIN 0002 | Interior Design, FF&E and Space Planning Services | 06/01/2025 - 05/31/2026 | ||||||||||||||||||||||||||||||||||||
| PWS 16.3 | Base | CLIN 0003 | Concept of Operations, Transition Planning and Project Staffing Planning | 06/01/2025 - 05/31/2026 | ||||||||||||||||||||||||||||||||||||
| PWS 16.4 | Base | CLIN 0004 | Acquisition Planning Services | 06/01/2025 - 05/31/2026 | ||||||||||||||||||||||||||||||||||||
| PWS 17.1 | Optional Task | CLIN 0007 | Acquisition Packages Development | 01/26/2027 - 08/25/2027 | ||||||||||||||||||||||||||||||||||||
| PWS 17.2 | Optional Task | CLIN 0008 | Warehousing and Warehousing Management Services | 07/26/2027 - 02/25/2028 | ||||||||||||||||||||||||||||||||||||
| PWS 17.3 | Optional Task | CLIN 0009 | Relocation of Reuse and Personnel Files | 10/26/2027 - 04/25/2028 | ||||||||||||||||||||||||||||||||||||
| PWS 17.4 | Optional Task | CLIN 0010 | Activation Services and Post Occupancy Support | 10/26/2027 - 05/31/2028 | ||||||||||||||||||||||||||||||||||||
| PWS 17.5 | Optional Task | CLIN 0011 | Staff Training and Orientation | 10/26/2027 - 04/25/2028 |
CLINs
| Period | CLIN NO. | TASK | Est. PoP | FY | Duration |
| Base | 0001 | Comprehensive PM Support | 06/01/2025 - 05/31/2026 | 25 | 12 MO |
| Base | 0002 | Comprehensive Interior Design, FF&E and Space Planning | 06/01/2025 - 05/31/2026 | 25 | 12 MO |
| Base | 0003 | Concept of Operations (CONOPS), Transition Planning and Project Staffing Planning | 06/01/2025 - 05/31/2026 | 25 | 12 MO |
| Base | 0004 | Acqusition Planning Services | 06/01/2025 - 05/31/2026 | 25 | 12 MO |
| Base | 0005 | Cost Reiumbursable Travel | 06/01/2025 - 05/31/2026 | 25 | 12 MO |
| Base | 0006 | Other Direct Costs-Cost Reimbursable | 06/01/2025 - 05/31/2026 | 25 | 12 MO |
| Optional Task 1 | 0007 | Acquisition Packages Development | 01/26/2027 - 08/25/2027 | 27 | 7 MO |
| Optional Task 2 | 0008 | Warehousing and Warehousing Management Services | 07/26/2027 - 02/25/2028 | 27 | 7 MO |
| Optional Task 3 | 0009 | Relocation of Reuse and Personnel Files | 10/26/2027 - 04/25/2028 | 28 | 6 MO |
| Optional Task 4 | 0010 | Activation Services and Post Occupancy Support | 10/26/2027 - 05/31/2028 | 28 | 7 MO |
| Optional Task 5 | 0011 | Staff Training and Orientation | 10/26/2027 - 04/25/2028 | 28 | 6 MO |
| Option Year 1 | 1001 | Comprehensive PM Support | 06/01/2026 - 05/31/2027 | 26 | 12 MO |
| Option Year 1 | 1005 | Cost Reiumursable Travel | 06/01/2026 - 05/31/2027 | 26 | 12 MO |
| Option Year 1 | 1006 | Other Direct Costs-Cost Reimbursable | 06/01/2026 - 05/31/2027 | 26 | 12 MO |
| Option Year 2 | 2001 | Comprehensive PM Support | 06/01/2027 - 05/31/2028 | 27 | 12 MO |
| Option Year 2 | 2005 | Cost Reiumursable Travel | 06/01/2027 - 05/31/2028 | 27 | 12 MO |
| Option Year 2 | 2006 | Other Direct Costs-Cost Reimbursable | 06/01/2027 - 05/31/2028 | 27 | 12 MO |