This is a Memorandum from the U.S. Army Corps of Engineers, Fort Bliss Directorate of Public Works (DPW), establishing requirements for the delivery of final as-built drawings. The memorandum, dated March 29, 2016, is directed to Shahrukh Shahzada, P.E., Resident Engineer, and identifies Lorenzo Molina as the point of contact for the Construction Branch, DPW.
The deliverables required include: two CDs containing AutoCAD files saved in 2015 AutoCAD version format with both CAD and PDF drawings; one set of mylar hard copies with 3 mil minimum thickness; and all external reference files bound to respective drawings and provided electronically in a separate folder. All drawings must be stamped "Final As-built Drawings" with completion dates in the bottom right corner, incorporate all construction modifications electronically with no red-line corrections permitted, and contain accurate dimensions, coordinates, utility line depth information, piping and ducting sizes, and underground utility depths. Drawings must include all required disciplines (general, civil, architectural, landscaping, irrigation, plumbing, mechanical, electrical, fire protection, and others) and be coherently organized rather than divided into fast-track or non-fast-track packages. Civil drawings and maps must use viable coordinate systems, specifically Texas State Plane Central FIPS 4203 NAD 1983 or GCS 1984 UTM 13N if provided by Master Planning. All survey points, brass caps, and turning points must include pertinent information on the drawings. These requirements also apply to internal engineering projects and PRIDE initiatives.
View the file
Other files
Show all 43
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
March 29, 2016
Lorenzo Molina (915)569-5520 Lorenzo.m.molina.civ@mail.mil
The following are the requirements for turning over as-built drawings to the Fort Bliss DPW Master Planning division.
1. 1 set of Autocad DWG files. (2CDs)
2. 1 set of PDF files. (2CDs)
3. 1 set of mylar hard copies.
4. The above must contain all the required disciplines for a complete and viable product, i.e. general, civil, architectural, landscaping, irrigation, plumbing, mechanical, electrical, fire and etc.
5. The drawings shall be stamped 'as-built' in the bottom right hand corner underneath the title block.
6. All modifications and RFI's shall be incorporated into the drawings and no drawings shall be marked up (or in other words "Red lined").
7. All external reference (XRef) files shall be included.
8. All external reference (XRef) files shall bound to make each drawing sheet.
9. Any maps including all civil drawings must be in a viable coordinate system. If the initial maps are received from Master Planning they will be in Texas State Plane Central FIPS 4203 NAD 1983 or GCS 1984 UTM 13N.
10. All drawings will have accurate dimensions.
11. All piping and ducting will have accurate sizes.
12. All underground utilities will have accurate depths listed.
13. All drawings sets shall be coherently organized not divided into fast track/non fast track or any other incomprehensible package.
14. All turning points, brass caps, survey points, etc will have their pertinent information listed on the drawings.
15 Internal engineering projects and PRIDE should follow these requirements also.