Attachment B - As-built Requirements.pdf

PDF 229 KB Posted

Attached to
New Fort Bliss Paving IDIQ Contract
Solicitation number
W911SG27BA002
Issued by

About this file

This is a Memorandum from the U.S. Army Corps of Engineers, Fort Bliss Directorate of Public Works (DPW), establishing requirements for the delivery of final as-built drawings. The memorandum, dated March 29, 2016, is directed to Shahrukh Shahzada, P.E., Resident Engineer, and identifies Lorenzo Molina as the point of contact for the Construction Branch, DPW.

The deliverables required include: two CDs containing AutoCAD files saved in 2015 AutoCAD version format with both CAD and PDF drawings; one set of mylar hard copies with 3 mil minimum thickness; and all external reference files bound to respective drawings and provided electronically in a separate folder. All drawings must be stamped "Final As-built Drawings" with completion dates in the bottom right corner, incorporate all construction modifications electronically with no red-line corrections permitted, and contain accurate dimensions, coordinates, utility line depth information, piping and ducting sizes, and underground utility depths. Drawings must include all required disciplines (general, civil, architectural, landscaping, irrigation, plumbing, mechanical, electrical, fire protection, and others) and be coherently organized rather than divided into fast-track or non-fast-track packages. Civil drawings and maps must use viable coordinate systems, specifically Texas State Plane Central FIPS 4203 NAD 1983 or GCS 1984 UTM 13N if provided by Master Planning. All survey points, brass caps, and turning points must include pertinent information on the drawings. These requirements also apply to internal engineering projects and PRIDE initiatives.

View the file

Other files

File Type Posted
Wage Determination NM20260035 (Dona Ana Highway) Eff. May 18 2026.pdf PDF
Attachment K - Site Clearance and Line Marking Permit.pdf PDF
Attachment A - The Army Radiation Permit ARP.pdf PDF
Statement of Work W911SG27BA002.pdf PDF
Attachment D - Contractor Requirements Document.pdf PDF
Attachment N - UFGS 05 52 00 Metal Railings.pdf PDF
Attachment N - UFGS 03 30 00 Cast-in-Place Concrete.pdf PDF
Attachment N - UFGS 32 01 17.61 Sealing Cracks in Asphalt Paving.pdf PDF
Attachment I - iWATCH Training for Contractors.pdf PDF
Attachment N - UFGS 32 01 19.61 Sealing Cracks in Asphalt Paving.pdf PDF
Attachment H - Fire Prevention Construction Guide 2025.pdf PDF
Attachment N - UFGS 32 12 13 Bituminous Tack and Prime Coats.pdf PDF
Attachment L - NMDOT Spec.pdf PDF
Attachment N - UFGS 32 01 11.51 Rubber and Paint Removal -Airfield.pdf PDF
Attachment N - UFGS 10 14 53 Traffic Signage.pdf PDF
Attachment F - DPW-RFI Template Blank Form.pdf PDF
Attachment E - DD1354 Form.pdf PDF
Attachment N - UFGS 32 12 15.13 Asphalt Paving for Airfields.pdf PDF
Attachment N - UFGS 32 93 00 Exterior Improvements Plants (1).pdf PDF
Attachment N - UFGS 31 00 00 Earthwork.pdf PDF
Attachment N - UFGS 34 71 13.16 Vehicle Crash Barriers.pdf PDF
Attachment N - UFGS 26 00 00 Electrical.pdf PDF
Attachment N - UFGS 32 01 13.62 Asphalt Surface Treatment.pdf PDF
Attachment N - UFGS 32 16 19 Concrete Curbs Gutters and Sidewalks.pdf PDF
Attachment J - SF 1413 Statement and Acknowledgement for Subcontractors.pdf PDF
Attachment N - UFGS 32 13 13.06 Portland Cement Concrete Pavement for Roads.pdf PDF
Attachment N - UFGS 02 41 00 Demolition.pdf PDF
Attachment N - UFGS 32 31 13 Chain Link Fences and gates.pdf PDF
Attachment N - UFGS 32 84 23 Underground Sprinkler Systems.pdf PDF
Attachment N - UFGS 32 01 16.75 Heater Scarifying of Asphalt Paving.pdf PDF
Attachment C - Construction and Demolition Sample Report.pdf PDF
Attachment N - UFGS 32 17 23 Pavement Markings.pdf PDF
Attachment G - DPW SUBMITTAL FORM V.1.pdf PDF
Attachment N - UFGS 32 12 16 Hot-Mix Asphalt HMA for Roads.pdf PDF
Wage Determination TX20260293 (El Paso Highway) Eff. May 18 2026.pdf PDF
Attachment N - UFGS 33 40 00 Storm Drainage Utilities.pdf PDF
Attachment N - UFGS 32 11 20 Base Course.pdf PDF
Wage Determination NM20260036 (Multiple NM Highway) Eff. May 18 2026.pdf PDF
Attachment N - UFGS 03 45 33 Precast Structural Concrete.pdf PDF
Attachment N - UFGS 31 11 00 Clearing and Grubbing.pdf PDF
Attachment L - TXDOT Spec.pdf PDF
Attachment N - UFGS 32 01 16.71 Cold Milling Asphalt Paving.pdf PDF
Attachment N - UFGS 32 11 33.13 Cement Stabilized Soil (1).pdf PDF
Show all 43

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

March 29, 2016

Lorenzo Molina (915)569-5520 Lorenzo.m.molina.civ@mail.mil

The following are the requirements for turning over as-built drawings to the Fort Bliss DPW Master Planning division.

1. 1 set of Autocad DWG files. (2CDs)

2. 1 set of PDF files. (2CDs)

3. 1 set of mylar hard copies.

4. The above must contain all the required disciplines for a complete and viable product, i.e. general, civil, architectural, landscaping, irrigation, plumbing, mechanical, electrical, fire and etc.

5. The drawings shall be stamped 'as-built' in the bottom right hand corner underneath the title block.

6. All modifications and RFI's shall be incorporated into the drawings and no drawings shall be marked up (or in other words "Red lined").

7. All external reference (XRef) files shall be included.

8. All external reference (XRef) files shall bound to make each drawing sheet.

9. Any maps including all civil drawings must be in a viable coordinate system. If the initial maps are received from Master Planning they will be in Texas State Plane Central FIPS 4203 NAD 1983 or GCS 1984 UTM 13N.

10. All drawings will have accurate dimensions.

11. All piping and ducting will have accurate sizes.

12. All underground utilities will have accurate depths listed.

13. All drawings sets shall be coherently organized not divided into fast track/non fast track or any other incomprehensible package.

14. All turning points, brass caps, survey points, etc will have their pertinent information listed on the drawings.

15 Internal engineering projects and PRIDE should follow these requirements also.