The document is a detailed electrical testing and maintenance schedule for the Fargo VA Health Care System, covering multiple buildings and electrical equipment over various dates in April and May 2022. The schedule systematically outlines specific electrical testing activities across different building rooms and equipment groups, including external and internal switchgear inspections, low voltage breaker cycle tests, DLRO (digital low resistance ohmmeter) contact resistance measurements, generator inspections, and transfer switch evaluations. The testing groups are organized chronologically from Group 0 through Group 7, with scheduled and actual test dates meticulously tracked for each electrical system component.
Key equipment tested includes normal power switchgear, main and tie breakers, motor control centers (MCCs), emergency switchboards, critical and life safety branches, and various electrical panels across Buildings 1, 9, 10, 11, 30, 40, 46, and 56. Some notable details include specialized tests like thermal imaging, insulation resistance checks, and specific breaker inspections using equipment like Eaton Magnum with Digitrip and RMS310 trip units. Two items (Fire Pump ATS and Surgery Chiller ATS in Building 46) are marked as "Untestable", indicating potential constraints or limitations in their testing procedures.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C26325B0012 0003.docx | DOCX document | |
| 36C26325B0012 0002.docx | DOCX document | |
| Attachment A - Statement of Work - Revised 6-26-2025.pdf | ||
| Attachment J - 437-25-103 Electrical Testing Questions and Answers Responses.pdf | ||
| Attachment I - Site Visit Sign In Sheets 6-12-2025.pdf | ||
| Attachment H _ 846770 Report _ Hyko Solutions _ Fargo VA _ Signed.pdf | ||
| 36C26325B0012 0001.docx | DOCX document | |
| Attachment D - Bid Drawings - 33 pages.pdf | ||
| 36C26325B0012_1.docx | DOCX document | |
| Attachment G - VAAR 852.219-75 Limitations on Subcontracting-Cert of Compliance_JAN 2023 [DEVIATION] - 2 pages.pdf | ||
| Attachment E - Wage Rate determination - 8 pages.pdf | ||
| Attachment F - Questions Request Form - 1 page.pdf | ||
| Attachment C - Specifications - 438 pages.pdf | ||
| Attachment A - SOW 12 pages.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Building Room Equipment / Test Notes Group Scheduled Actual
1 External T1‐E 0 4/12/2022 4/26/2022
1 External T1‐SHOPS (T38) 0 4/12/2022 4/26/2022
1 External T1‐W 0 4/12/2022 4/26/2022
9 External T9‐W 0 4/12/2022 4/26/2022
9 External T9‐SCAN 0 4/12/2022 4/26/2022
9 External T9‐XRAY 0 4/12/2022 4/26/2022
9 External T9‐E 0 4/12/2022 4/26/2022
11 External T11 0 4/12/2022 4/26/2022
46 External T46‐E 0 4/12/2022 5/12/2022
46 External T46‐W 0 4/12/2022 5/12/2022
46 BC‐79 MCC‐1N1 1 4/26/2022 5/12/2022
46 BC‐79 Switchgear Inspection 1 4/26/2022 5/12/2022
46 BC‐79 DLRO 1 4/26/2022 5/12/2022
1 BE‐99 Normal Power Switchgear 1 4/26/2022 5/26/2022
1 BE‐99 2 Main Breakers (WLS2D320) 1 4/26/2022 5/26/2022
1 BE‐99 1 Tie Breaker (WLS2F320) 1 4/26/2022 5/26/2022
1 BE‐99 Switchgear Inspection 1 4/26/2022 5/26/2022
1 BE‐99 Low Voltage Breaker Cycle & DLRO 1 4/26/2022 5/26/2022
30 External T‐NW 2 4/27/22 or 4/28/22 4/27/2022
40 112B MCC‐1 2 4/27/22 or 4/28/22 4/27/2022
40 112B Switchgear Inspection 2 4/27/22 or 4/28/22 4/27/2022
40 112B DLRO 2 4/27/22 or 4/28/22 4/27/2022
40 212 MCC‐2 2 4/27/22 or 4/28/22 4/27/2022
40 212 Switchgear Inspection 2 4/27/22 or 4/28/22 4/27/2022
40 212 DLRO 2 4/27/22 or 4/28/22 4/27/2022
40 ATS 2 4/27/22 or 4/28/22 4/27/2022
46 BA‐01A Normal Power Switchgear 2 4/27/22 or 4/28/22 4/28/2022
46 BA‐01A Switchgear Inspection 2 4/27/22 or 4/28/22 4/28/2022
46 BA‐01A 26 Low Voltage PCB Amptector 2 4/27/22 or 4/28/22 4/28/2022
46 BA‐01 MCCB‐46 2 4/27/22 or 4/28/22 4/28/2022
46 BA‐01 Switchgear Inspection 2 4/27/22 or 4/28/22 4/28/2022
46 BA‐01 DLRO 2 4/27/22 or 4/28/22 4/28/2022
46 BA‐01A 2 Spare Breakers on the floor 2 4/27/22 or 4/28/22 4/29/2022
46 BA‐01 MCCB‐3 2 4/27/22 or 4/28/22 4/29/2022
46 BA‐01 Switchgear Inspection 2 4/27/22 or 4/28/22 4/29/2022
46 BA‐01 DLRO 2 4/27/22 or 4/28/22 4/29/2022
30 External Switchboard Inspection 2 4/27/22 or 4/28/22 5/12/2022
30 External Switchgear Inspection 2 4/27/22 or 4/28/22 5/12/2022
30 External Low Voltage Breaker Cycle & DLRO 2 4/27/22 or 4/28/22 5/12/2022
30 External Transfer Switch Medium Voltage Disconnect 2 4/27/22 or 4/28/22 5/12/2022
30 External Insulation Resistance 2 4/27/22 or 4/28/22 5/12/2022
30 External DLRO Contacts 2 4/27/22 or 4/28/22 5/12/2022
39 External T39 2 4/27/22 or 4/28/22 5/12/2022
40 111 Normal Power Switchgear 2 4/27/22 or 4/28/22 5/12/2022
40 111 Main Breaker Thermal 2 4/27/22 or 4/28/22 5/12/2022
40 111 DLRO 2 4/27/22 or 4/28/22 5/12/2022
40 111 Switchgear Inspection 2 4/27/22 or 4/28/22 5/12/2022
40 111 Low Voltage Breaker Cycle & DLRO 2 4/27/22 or 4/28/22 5/12/2022
40 External T40 2 4/27/22 or 4/28/22 5/12/2022
13 External T13 3 5/10/22 or 5/11/22 5/10/2022
56 External T56‐1 3 5/10/22 or 5/11/22 5/10/2022
56 External T56‐2 3 5/10/22 or 5/11/22 5/10/2022
56 External T56‐3 3 5/10/22 or 5/11/22 5/10/2022
46 BA‐01 ATS 3 5/10/22 or 5/11/22 5/12/2022
46 BA‐01B Generator Inspection 3 5/10/22 or 5/11/22 5/12/2022
46 BA‐01B Generator Control Switchboard Inspection 3 5/10/22 or 5/11/22 5/12/2022
46 BA‐01B Battery Charger Inspection 3 5/10/22 or 5/11/22 5/12/2022
46 BA‐01B Equipment Branch ATS 3 5/10/22 or 5/11/22 5/12/2022
46 BA‐01B Life Safety Branch ATS 3 5/10/22 or 5/11/22 5/12/2022
46 BA‐01B EE Switchboard 3 5/10/22 or 5/11/22 5/12/2022
46 BA‐01B Switchgear Inspection 3 5/10/22 or 5/11/22 5/12/2022
46 BA‐01B Low Voltage Breaker Cycle & DLRO 3 5/10/22 or 5/11/22 5/12/2022
46 BA‐01B Critical Branch Switchboard 3 5/10/22 or 5/11/22 5/12/2022
46 BA‐01B Switchgear Inspection 3 5/10/22 or 5/11/22 5/12/2022
46 BA‐01B Low Voltage Breaker Cycle & DLRO 3 5/10/22 or 5/11/22 5/12/2022
46 BA‐01B Equipment Branch EBE‐2 3 5/10/22 or 5/11/22 5/12/2022
46 BA‐01B Switchgear Inspection 3 5/10/22 or 5/11/22 5/12/2022
46 BA‐01B Low Voltage Breaker Cycle & DLRO 3 5/10/22 or 5/11/22 5/12/2022
46 BA‐01 ATS 3 5/10/22 or 5/11/22 5/12/2022
46 2D‐12 MCC‐EB462C1 3 5/10/22 or 5/11/22 5/12/2022
46 2D‐12 Switchgear Inspection 3 5/10/22 or 5/11/22 5/12/2022
46 2D‐12 DLRO 3 5/10/22 or 5/11/22 5/12/2022
46 4C‐27 MCC‐ES464C1 3 5/10/22 or 5/11/22 5/12/2022
46 4C‐27 Switchgear Inspection 3 5/10/22 or 5/11/22 5/12/2022
46 4C‐27 DLRO 3 5/10/22 or 5/11/22 5/12/2022
46 BA‐01A Emergency Panel EBE 3 5/10/22 or 5/11/22 5/24/2022
46 BA‐01A Switchgear Inspection 3 5/10/22 or 5/11/22 5/24/2022
46 BA‐01A Low Voltage Breaker Cycle & DLRO 3 5/10/22 or 5/11/22 5/24/2022
46 BC‐79 MCCEB‐1 3 5/10/22 or 5/11/22 5/25/2022
46 BC‐79 Switchgear Inspection 3 5/10/22 or 5/11/22 5/25/2022
46 BC‐79 DLRO 3 5/10/22 or 5/11/22 5/25/2022
56 Normal Power Switchgear 3 5/10/22 or 5/11/22 5/25/2022
56 Switchgear Inspection 3 5/10/22 or 5/11/22 5/25/2022
56 2 Main Breakers 3 5/10/22 or 5/11/22 5/25/2022
56 1 Tie Breaker 3 5/10/22 or 5/11/22 5/25/2022
56 Low Voltage Breaker Cycle & DLRO 3 5/10/22 or 5/11/22 5/25/2022
56 26kV Loop 3 5/10/22 or 5/11/22 5/27/2022
56 4 Sectionalizing Switches 3 5/10/22 or 5/11/22 5/27/2022
56 1 Low Voltage Disconnect ACCH‐4 3 5/10/22 or 5/11/22 5/27/2022
9 BA‐10 Normal Power Switchgear 4 5/12/2022 5/12/2022
9 BA‐10 2 Main Breakers (EATON Magnum w/ Digitrip) 4 5/12/2022 5/12/2022
9 BA‐10 1 Tie Breaker (EATON Magnum w/ Digitrip) 4 5/12/2022 5/12/2022
9 BA‐10 Switchgear Inspection 4 5/12/2022 5/12/2022
9 BA‐10 Low Voltage Breaker Cycle & DLRO 4 5/12/2022 5/12/2022
9 BA‐10 4 Low Voltage Breakers w/ RMS310 Trip Units 4 5/12/2022 5/12/2022
9 BA‐10 X‐Ray Panel 4 5/12/2022 5/12/2022
9 BA‐10 Switchgear Inspection 4 5/12/2022 5/12/2022
9 BA‐10 Low Voltage Breaker Cycle & DLRO 4 5/12/2022 5/12/2022
9 BA‐10 MCC‐3B Breaker 4 5/12/2022 5/24/2022
9 BA‐10 Inspect DLRO Contact Resistance 4 5/12/2022 5/26/2022
9 BA‐10 Manual Transfer Switch EB90N3 4 5/12/2022 5/26/2022
1 BE‐99 Critical Branch Switchboard 5 5/17/2022 5/25/2022
1 BE‐99 Switchgear Inspection 5 5/17/2022 5/25/2022
1 BE‐99 Low Voltage Breaker Cycle & DLRO 5 5/17/2022 5/25/2022
1 BE‐98 Emergency Switchboard EBE‐1 5 5/17/2022 5/25/2022
1 BE‐98 1 Generator Main Breaker w/ ETU 745 5 5/17/2022 5/25/2022
1 BE‐98 3 Breakers w/ Disperado 555 Trip Units 5 5/17/2022 5/25/2022
1 BE‐98 Generator Inspection 5 5/17/2022 5/26/2022
1 BE‐99 Equipment Branch 5 5/17/2022 5/31/2022
1 BE‐99 Switchgear Inspection 5 5/17/2022 5/31/2022
1 BE‐99 Low Voltage Breaker Cycle & DLRO 5 5/17/2022 5/31/2022
1 BE‐99 Life Safety Branch 5 5/17/2022 5/31/2022
1 BE‐99 Switchgear Inspection 5 5/17/2022 5/31/2022
1 BE‐99 Low Voltage Breaker Cycle & DLRO 5 5/17/2022 5/31/2022
1 BE‐99 Critical Branch ATS 5 5/17/2022 5/31/2022
1 BE‐99 Equipment Branch ATS 5 5/17/2022 5/31/2022
1 BE‐99 Life Safety Branch ATS 5 5/17/2022 5/31/2022
1 BE‐98 Battery Charger Inspection 5 5/17/2022 5/31/2022
9 BB‐34 Manual Transfer Switch MTS‐1 6 5/18/22 or 5/19/22 5/24/2022
9 BB‐34 Manual Transfer Switch MTS‐2 6 5/18/22 or 5/19/22 5/24/2022
9 BB‐34 Manual Transfer Switch MTS‐3 6 5/18/22 or 5/19/22 5/24/2022
9 BA‐10 Equipment Branch EB1 6 5/18/22 or 5/19/22 6/2/2022
9 BA‐10 Switchgear Inspection 6 5/18/22 or 5/19/22 6/2/2022
9 BA‐10 Low Voltage Breaker Cycle & DLRO 6 5/18/22 or 5/19/22 6/2/2022
9 BA‐10 1 Low Voltage Breaker w/ RMS310 Trip Unit 6 5/18/22 or 5/19/22 6/2/2022
9 BA‐10 Critical Branch Switchboard 6 5/18/22 or 5/19/22 6/2/2022
9 BA‐10 Switchgear Inspection 6 5/18/22 or 5/19/22 6/2/2022
9 BA‐10 Low Voltage Breaker Cycle & DLRO 6 5/18/22 or 5/19/22 6/2/2022
9 BA‐10 Equipment Branch EB2 6 5/18/22 or 5/19/22 6/2/2022
9 BA‐10 Switchgear Inspection 6 5/18/22 or 5/19/22 6/2/2022
9 BA‐10 Low Voltage Breaker Cycle & DLRO 6 5/18/22 or 5/19/22 6/2/2022
9 BA‐10 2 Low Voltage Breakers w/ RMS310 Trip Units 6 5/18/22 or 5/19/22 6/2/2022
9 BA‐10 Life Safety Branch 6 5/18/22 or 5/19/22 6/2/2022
9 BA‐10 Switchgear Inspection 6 5/18/22 or 5/19/22 6/2/2022
9 BA‐10 Low Voltage Breaker Cycle & DLRO 6 5/18/22 or 5/19/22 6/2/2022
9 BA‐10 Critical Branch ATS 6 5/18/22 or 5/19/22 6/2/2022
9 BA‐10 Equipment Branch EB1 ATS 6 5/18/22 or 5/19/22 6/2/2022
9 BA‐10 Equipment Branch EB2 ATS 6 5/18/22 or 5/19/22 6/2/2022
9 BA‐10 Life Safety Branch ATS 6 5/18/22 or 5/19/22 6/2/2022
9 BA‐07A Generator Inspection 6 5/18/22 or 5/19/22 6/2/2022
9 BA‐07A Battery Charger Inspection 6 5/18/22 or 5/19/22 6/2/2022
9 BA‐07A Emergency Switchboard 6 5/18/22 or 5/19/22 6/2/2022
9 BA‐07A Switchgear Inspection 6 5/18/22 or 5/19/22 6/2/2022
9 BA‐07A Low Voltage Breaker Cycle & DLRO 6 5/18/22 or 5/19/22 6/2/2022
9 BA‐07A Main Breaker w/ RMS310 Trip Unit 6 5/18/22 or 5/19/22 6/2/2022
9 BA‐07A Manual Transfer Switch EB90N1 6 5/18/22 or 5/19/22 6/2/2022
10 External T10 7 4/30/2022 5/14/2022
11 Generator Inspection 7 4/30/2022 5/14/2022
11 Disconnect Switch 7 4/30/2022 5/14/2022
11 DLRO 7 4/30/2022 5/14/2022
11 Battery Charger Inspection 7 4/30/2022 5/14/2022
Protective Relays 7 4/30/2022 5/14/2022
Medium Voltage Disconnects 7 4/30/2022 5/14/2022
5 4160 MV Disconnects Feeders 1‐4 and Cap Bank 7 4/30/2022 5/14/2022
46 BA‐01A Fire Pump ATS Untestable
46 BA‐01A Surgery Chiller ATS Untestable