ATTACHMENT A - BASE OFFER PRICE BREAKDOWN FORM.docx

DOCX document 21 KB Posted

Attached to
Z2DA--658-24-102 Replace Building 2 AHUs
Solicitation number
36C24626R0072
Issued by

About this file

This is a Base Offer Price Breakdown Form template for Phase II of a solicitation related to replacing Building 2 Air Handler Units at a Department of Veterans Affairs facility (VISN 6). The form is designed for contractors to submit detailed pricing for the project identified as RFP Number TBD and Project No. 658-24-102.

The pricing template requires offerors to break down costs across 27 construction and building system divisions using the MasterFormat classification system, including General Requirements, Existing Conditions, Concrete, Masonry, Metals, Wood and Plastic, Thermal & Moisture Protection, Doors and Windows, Finishes, Specialties, Equipment, Furnishings, Special Construction, Conveying Equipment, Fire Suppression, Plumbing, HVAC, Integrated Automation, Electrical, Communications, Electronic Safety & Security, Earthwork, Exterior Improvements, Utilities, Transportation, and Electrical Power Generation. For each division, contractors must provide separate line items for Labor, Material, and Total Cost. The form includes subtotal calculations for all divisions, followed by a section for Overhead/Profit and Insurance Bond percentages, with designated spaces for contractors to enter their overhead percentage, profit percentage, and insurance bond percentage, culminating in a final Total Base Proposal Item Price. This is a blank template and does not contain specific pricing information or response deadlines.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PHASE II - SOLICITATION ATTACHMENT A

BASE PROPOSAL ITEM PRICE BREAKDOWN FORM

RFP NUMBER: TBD

PROJECT NO./TITLE: 658-24-102, Replace Building 2 Air Handler Units

OFFEROR:

ITEM
DESCRIPTION
Labor
Material
Total Cost
Division 1
General Requirements
Division 2
Existing Conditions
Division 3
Concrete
Division 4
Masonry
Division 5
Metals
Division 6
Wood and Plastic
Division 7
Thermal & Moisture Protect
Division 8
Doors and Windows
Division 9
Finishes
Division 10
Specialties
Division 11
Equipment
Division 12
Furnishings
Division 13
Special Construction
Division 14
Conveying Equipment
Division 21
Fire Suppression
Division 22
Plumbing
Division 23
HVAC
Division 25
Integrated Automation
Division 26
Electrical
Division 27
Communications
Division 28
Electronic Safety & Security
Division 31
Earthwork
Division 32
Exterior Improvements
Division 33
Utilities
Division 34
Transportation
Division 48
Electrical Power Generation

Divisions Subtotal:

Overhead/Profit and Insurance

Bond (___%)

Overhead (___%)

Profit (___%)

Subtotal:

TOTAL BASE PROPOSAL ITEM PRICE