Attachment 9 - Tyndall_Design_Wind_Speed_A4C-2_Memo.pdf
PDF 87 KB Posted
- Attached to
- Construct Honor Guard Facility, Tyndall AFB, FL
- Solicitation number
- FA481924R0014
About this file
This document is a memorandum from the Deputy Director of Civil Engineers, DCS/Logistics, Engineering, & Force Protection, providing design guidance for the redevelopment of Tyndall Air Force Base (AFB) in Florida following Hurricane Michael in 2018. The memo establishes the design wind speeds to be used for building infrastructure and facilities at Tyndall AFB, based on Risk Categories III-V, with wind speeds ranging from 165 mph to 203 mph. Additionally, the memo provides guidance on the use of exterior building envelope materials that have a current Miami-Dade Notice of Acceptance and are installed to High-Velocity Hurricane Zone (HVHZ) standards. This is intended to improve facility resiliency and reduce the risk of building envelope compromise and structural failure due to high winds and debris impacts.
The related federal contract opportunity is for the construction of a new Honor Guard Facility at Tyndall AFB, with Solicitation Number FA481924R0014. The purpose of this project is to provide a new facility, parking lot, and storm drainage for the Honor Guard. The contracting agency is the Department of the Air Force, Air Combat Command.
View the file
Other files
Show all 33
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE AIR FORCE
HEADQUARTERS UNITED STATES AIR FORCE
WASHINGTON, DC
MEMORANDUM FOR AFCEC/CL
FROM: HQ USAF/A4C
1260 Air Force Pentagon Washington, DC 20330-1260
SUBJECT: Tyndall AFB Design Wind Speeds and Building Envelope Protection
I am issuing this design guidance to the Air Force Civil Engineer Center (AFCEC) and the Tyndall Project Management Office (PMO) to establish the design wind speed for the redevelopment of Tyndall AFB, Florida, following its destruction by Hurricane Michael in October 2018. This guidance is applicable only to Tyndall AFB and is intended to ensure that the design of infrastructure and facilities is more resilient to future severe weather events.
UFC 3-301-01, Structural Engineering, establishes the wind speed used in structural design for DoD locations and implements the American Society of Civil Engineers Standard 7, Minimum Design Loads for Buildings and Other Structures. The UFC is in revision incorporating the 2016 ASCE 7 updates and minor updates to the Risk Categories (RC) with a projected publication in CY 2019. It is my understanding that while there are no RC V facilities at Tyndall AFB, this category remains available for future facility requirements.
Based upon our AF Structural SME recommendations and in alignment with the SecAF directed Severe Weather Readiness Assessment recommendations, the Tyndall PMO will use the draft 2019 UFC and the following Tyndall design wind speeds based upon Risk Categories III-V:
RC I (mph) RC II (mph) RC III (mph) RC IV (mph) RC V (mph) Tyndall Design Wind Speeds
Not Permitted
Not Permitted
165 170 203
In addition to the wind speeds discussed, I am issuing additional design guidance on opening protection and exterior envelope materials. While we should always use our Unified Facilities Criteria as the basis for all our facilities designs, we will also integrate the best practices from the Florida Building Code (FBC) High-Velocity Hurricane Zone (HVHZ) into this design guidance to further improve facility resiliency at Tyndall.
All exterior building envelope materials such as but not limited to windows, glazing, roofing systems, concrete masonry unit or metal panel walls, and doors shall have a current Miami-Dade Notice of Acceptance (NOA) and installed to HVHZ standards that match the specified wind requirement. The intent is to provide additional protection where the UFC may be less prescriptive to reduce the risk of building envelope compromise and/or structural failure due to high winds and large and small missile, or debris, impacts. Our construction industry partners shall continue to have the option of submitting test results or drawings sealed by a Professional Engineer stating conformance with HVHZ standards in lieu of materials pre-approved by Miami- Dade County. An example for this particular situation might be a custom-engineered submittal for an aircraft hangar door.
Finally, all structural designs shall ensure a continuous wind load transfer from roof framing to foundation, another HVHZ design principle. In many cases our UFCs will already address this: for example, the roof framing will be connected structural steel columns bolted to interior or perimeter footings. Smaller structures that may not have a structural steel frame should be reviewed to ensure the use of straps or other appropriate roof framing to foundation connections through the load bearing walls.
NANCY J. BALKUS, P.E., SES
Deputy Director of Civil Engineers DCS/Logistics, Engineering, & Force Protection