Attachment 8 _ CDRLs_1423-1_APS_20260910.docx

DOCX document 50 KB Posted

Attached to
Combined Synopsis/Solicitation for Commercial Items Agile Professional Services ("APS”) Department of the Army
Solicitation number
W900KK-26-R-A023
Issued by

About this file

This is a Contract Data Requirements List (CDRL) document specifying four mandatory data items for the Agile Professional Services (APS) contract under solicitation W900KK-26-R-A023 with the Department of the Army.

The four required deliverables are: (1) A001 – Contractor's Progress and Status Report, submitted monthly beginning 30 calendar days after contract award with subsequent submissions due on the 10th of each month throughout the contract life, delivered via Wide Area Workflow (WAWF) with government review/approval within 5 business days; (2) A002 – Phase-Out Transition Plan, submitted twice with the first submission due 120 calendar days after contract award and the second due 180 days prior to contract end, delivered via dashboard with 7 business day government review periods; (3) A003 – Agile Dashboard (Scientific and Technical Reports), a live dashboard due within 30 days of contract award providing unfettered government access to all data and tools with real-time availability during sprint planning meetings, submitted as needed (ASREQ); and (4) A004 – Agile Management Plan (Scientific and Technical Reports), due 60 days before the end of the ramp-up period, submitted as needed via dashboard. All deliverables require Microsoft 365 compatibility, with graphics and charts compatible with Microsoft 365 applications. Cost reporting must be traced to Contract Line Item Numbers (CLINs), SubLINs, program or Foreign Military Sales (FMS) case levels, with each cost element referencing government-approved JIRA ticket IDs (Epics/Stories/Tasks) to substantiate monthly billing and burn rates. The Phase-Out Transition Plan must include transfer of all licenses to management tools and databases, all data entered into systems, and instructional materials for tool utilization. Distribution statements restrict A001 to U.S. government agencies only, while A002, A003, and A004 are authorized for U.S. government agencies and their contractors, effective September 1, 2026.

View the file

Other files

File Type Posted
Attachment 3 _ 52.212-2 Evaluation—Commercial Products and Commercial Services_20261008.docx DOCX document
Attachment 4.e - WD 2015-4675 REV 30 20260822 KY.pdf PDF
Agile Professional Services (APS) Questions and Answers_20261008.xlsx XLSX spreadsheet
Attachment 1 _ SOO_Agile_Professional_Services_20261001.docx DOCX document
Attachment 2 _ 52.212-1 Instructions to Offerors—Commercial Products and Commercial Services_20261008.docx DOCX document
Attachment 10 _ APS Pricing Workbook_20261008.xlsx XLSX spreadsheet
APS _ Combined Synopsis Solicitation _ 20261008.docx DOCX document
Attachment 5 _ PWS Template Agile professional Services 20261001.docx DOCX document
APS _ Combined Synopsis Solicitation _ 9.21.2026.docx DOCX document
Attachment 1 _ SOO_Agile_Professional_Services_20260908.docx DOCX document
Attachment 4.a _ WD 2015-4377 REV 33 20260820 NC_9.18.2026.pdf PDF
Attachment 4.c _ WD 2015-4603 REV 34 20260820 AL_9.18.2026.pdf PDF
Attachment 4.d _ WD 2015-4631 REV 34 20260812 AL_9.18.2026.pdf PDF
Attachment 4.e _ WD 2015-4719 REV 34 20260812 KY_9.18.2026.pdf PDF
Attachment 4.g _ WD 2015-5237 REV 32 20260812 TX_9.18.2026.pdf PDF
Attachment 6 _ Quality_Assurance_Surveillance_Plan_(QASP)_Proposal_Template_-_APS_20260903.docx DOCX document
APS _ Combined Synopsis Solicitation _ 9.18.2026.docx DOCX document
Attachment 2 _ 52.212-1 Instructions to Offerors—Commercial Products and Commercial Services_9.18.2026.docx DOCX document
Attachment 3 _ 52.212-2 Evaluation—Commercial Products and Commercial Services_9.18.2026.docx DOCX document
Attachment 4.b _ WD 2015-4553 REV 31 20260730 FL_9.18.2026.pdf PDF
Attachment 4.h _ WD 2015-5629 REV 29 20260513 CA_9.18.2026.pdf PDF
Attachment 9 _ DD254 APS HQ Planning Purpose.pdf PDF
Attachment 4.f _ WD 2015-5197 REV 33 20260812 LA_9.18.2026.pdf PDF
Attachment 4.i _ WD 2015-5775 REV 32 20260812 NY_9.18.2026.pdf PDF
Attachment 5 _ PWS Template Agile professional Services 20260917.docx DOCX document
Attachment 7 _ Clauses and Provisions_W900KK26RA023_9.18.2026.pdf PDF
Attachment 10 _ APS Pricing Workbook_9.18.2026.xlsx XLSX spreadsheet
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT DATA REQUIREMENTS LIST

(1 Data Item)

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.

B. EXHIBIT

C. CATEGORY

TDP

TM

OTHER

MGMT

D. SYSTEM/ITEM

Agile Professional Services

E. CONTRACT/PR NO.

TBD

F. CONTRACTOR

1. DATA ITEM NO.

A001

2. TITLE OF THE DATA ITEM

CONTRACTOR’S PROGRESS AND STATUS REPORT

3. SUBTITLE

4. AUTHORITY

(Data Acquisition Document No.)

DI-MGMT-81928

5. CONTRACT REFERENCE

PWS xxxx

6. REQUIRING OFFICE

SFAE-STR-CPE

17. PRICE GROUP

18.

ESTIMATED TOTAL PRICE

7. DD 250 REQ

DD

8. APP CODE

N/A

9.

DIST STATEMENT REQUIRED

B

10. FREQUENCY

MNTHLY

12.

DATE OF FIRST SUBMISSION

SEE BLOCK 16

11. AS OF DATE

N/A

13.

DATE OF SUBSEQUENT SUBMISSION

SEE BLOCK 16

14.

DISTRIBUTION

a. ADDRESSEE

b. COPIES

Draft

Final Reg Repro

SEE BLOCK 16

16. REMARKS

1. BLOCK 7: THE CONTRACTOR SHALL INITIATE A ZERO COST RECEIVING

REPORT IN WIDE AREA WORKFLOW (WAWF) TO THE TECHNICAL OFFICE

RESPONSIBLE FOR THE REVIEW/APPROVAL OF THE DATA ITEM

2. BLOCK 9: DISTRIBUTION STATEMENT B. DISTRIBUTION AUTHORIZED

TO U.S. GOVERNMENT AGENCIES ONLY DUE TO ADMINISTRATIVE USE

EFFECTIVE 1 SEPTEMBER 2026. OTHER REQUESTS FOR THIS DOCUMENT

SHALL BE REFERRED TO U.S. ARMY CAPABILITY PROGRAM EXECUTIVE

SIMULATION, TRAINING, TEST & THREAT (CPE-ST3).

3. BLOCK 12: SHALL BE DUE 30 CALENDAR DAYS AFTER CONTRACT AWARD.

4. BLOCK 13: SUBSEQUENT SUBMISSION SHALL BE DUE ON THE 10TH OF

EVERY MONTH THROUGH OUT THE LIFE OF THE CONTRACT.

5. BLOCK 14: DELIVERABLES SHALL BE DELIVERED VIA WAWF IN

ACCORDANCE WITH CONTRACT CLAUSES SET FORTH IN SECTION G,

CONTRACT ADMINISTRATION DATA. IN THE EVENT THAT DOCUMENTATION

CANNOT BE PROVIDED VIA WAWF (DUE TO FILE SIZE OR CONTENT TYPE),

THEN A COVER PAGE SHALL BE SUBMITTED VIA WAWF AND THE

DELIVERABLE SHALL BE ELECTRONICALLY MAILED OR DELIVERED VIA

DOD SAFE (https://safe.apps.mil/) TO THE COR. IN ADDITION, PROOF OF

FILE SUBMITTAL VIA E-MAIL OR SAFE SHALL BE INCLUDED WITH THE

DOCUMENT COVER PAGE. SUBMITTAL SHALL BE IN MICROSOFT 365. ALL

GRAPHICS, FIGURES, CHARTS, AND TABLES SHALL BE COMPATIBLE WITH

MICROSOFT 365.

6. THE GOVERNMENT WILL HAVE 5 BUSINESS DAYS FOR REVIEW,

ACCEPTANCE OR REJECTION OF THE SUBMISSION.

7. CONTRACTOR SHALL HAVE 5 BUSINESS DAYS TO INCORPORATE

GOVERNMENT COMMENTS

8. COSTS SHALL BE REPORTED AND TRACED TO THE CLIN, SLIN, PROGRAM

OR FMS CASE LEVEL. EACH REPORTED COST ELEMENT REPRESENTING

AGILE SERVICE EXECUTION SHALL REFERENCE CORRESPONDING

GOVERNMENT-APPROVED JIRA TICKET IDS (EPICS/STORIES/TASKS) TO

SUBSTANTIATE MONTHLY BILLING AND BURN RATES.

ALL CDRLS SUBMITTED AFTER 4:00PM EST ON FRIDAY WILL BE

CONSIDERED SUBMITTED ON THE NEXT GOVERNMENT WORK DAY.

15. TOTAL

G. PREPARED BY

H. DATE

I. APPROVED BY

J. DATE

DD FORM 1423-1, FEB 2001

PREVIOUS EDITION MAY BE USED.

Page 1 of 4 Pages

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

TM

MGMT

E. CONTRACT/PR NO.

A002

2. TITLE OF THE DATA ITEM

Phase-Out Transition Plan

3. SUBTITLE

4. AUTHORITY

(Data Acquisition Document No.)

DI-MGMT-81945A

5. CONTRACT REFERENCE

PWS xxx

8. APP CODE

N/A

9.

DIST STATEMENT REQUIRED

C

10. FREQUENCY

2TIME

12.

DATE OF FIRST SUBMISSION

SEE BLOCK 16

11. AS OF DATE

N/A

13.

DATE OF SUBSEQUENT SUBMISSION

SEE BLOCK 16

Reg

1. BLOCK 7: THE CONTRACTOR SHALL INITIATE A ZERO COST RECEIVING

REPORT IN WIDE AREA WORKFLOW (WAWF) TO THE TECHNICAL OFFICE

RESPONSIBLE FOR THE REVIEW/APPROVAL OF THE DATA ITEM PER BLOCK 6

2. BLOCK 9: DISTRIBUTION STATEMENT C. DISTRIBUTION AUTHORIZED

TO U.S. GOVERNMENT AGENCIES AND THEIR CONTRACTORS ONLY DUE TO

ADMINISTRATIVE USE EFFECTIVE 1 SEPTEMBER 2026. OTHER REQUESTS

FOR THIS DOCUMENT SHALL BE REFERRED TO U.S. ARMY CAPABILITY

PROGRAM EXECUTIVE SIMULATION, TRAINING, TEST & THREAT (CPE-ST3).

3. BLOCK 12: THE 1ST TRANSISITION PLAN SHALL BE DUE 120 CALENDAR

DAYS AFTER THE CONTRACT.

4. BLOCK 13: THE SUBSEQUENT SUBMISSION SHALL BE DUE 180 DAYS

PRIOR TO THE CONTRACT ENDS.

5. THE GOVERNMENT WILL HAVE 7 BUSINESS DAYS FOR REVIEW,

ACCEPTANCE OR REJECTION OF THE SUBMISSION.

6. THE CONTRACTOR SHALL HAVE 7 BUSINESS DAYS TO INCORPORATE

GOVERNMENT COMMENTS.

6. BLOCK 14: DELIVERABLES SHALL BE DELIVERED VIA THE DASHBOARD.

ALL CDRLS SUBMITTED AFTER 4:00PM EST ON FRIDAY WILL BE

CONSIDERED SUBMITTED ON THE NEXT GOVERNMENT BUSINESS.

7. THE CONTRACTOR SHALL INCLUDE THE FOLLOWING AS PART OF THE TRANSITION:

- ALL LICENSES TO THE MANAGEMENT TOOLS AND DATABASES

- ALL DATA ENTERED INTO THE TOOLS AND DATABASES

- INSTRUCTIONAL MATERIALS NEEDED TO UTILIZE THE TOOLS THE

CONTRACTOR SHALL TRANSITION

15. TOTAL

Page 2 of 4 Pages

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

TM

MISC

E. CONTRACT/PR NO.

A003

2. TITLE OF THE DATA ITEM

Scientific and Technical Reports

3. SUBTITLE

AGILE DASHBOARD

4. AUTHORITY

(Data Acquisition Document No.)

DI-MISC-80711A

5. CONTRACT REFERENCE

PWS xxx

8. APP CODE

N/A

9.

DIST STATEMENT REQUIRED

C

10. FREQUENCY

ASREQ

12.

DATE OF FIRST SUBMISSION

SEE BLK 16

11. AS OF DATE

N/A

13.

DATE OF SUBSEQUENT SUBMISSION

N/A

Reg

SEE BLK 16

1. BLOCK 7: THE CONTRACTOR SHALL SUBMIT THE DATA ITEM TO THE

OFFICE RESPONSIBLE FOR THE REVIEW/APPROVAL OF THE DATA ITEM PER BLOCK 6

2. BLOCK 9: DISTRIBUTION STATEMENT C. DISTRIBUTION AUTHORIZED

TO U.S. GOVERNMENT AGENCIES AND THEIR CONTRACTORS ONLY DUE TO

ADMINISTRATIVE USE EFFECTIVE 1 SEPTEMBER 2026. OTHER REQUESTS

FOR THIS DOCUMENT SHALL BE REFERRED TO U.S. ARMY CAPABILITY

PROGRAM EXECUTIVE SIMULATION, TRAINING, TEST & THREAT (CPE-ST3).

3. BLOCK 12: THE CONTRACTOR SHALL SUBMIT THE AGILE DASHBOARD IN

A LIVE DASHBOARD WITHIN 30 DAYS AFTER CONTRACT AWARD.

4. THE GOVERNMENT WILL HAVE 7 CALENDAR DAYS FOR REVIEW,

ACCEPTANCE OR REJECTION OF THE SUBMISSION. THE CONTRACTOR

SHALL PROVIDE THE GOVERNMENT WITH UNFETTERED ACCESS TO THE DATA AND TOOLS.

5. THE CONTRACTOR SHALL HAVE 7 CALENDAR DAYS TO INCORPORATE

GOVERNMENT COMMENTS INTO THE AGILE DASHBOARD. AT SPRINT

PLANNING MEETINGS, THE CONTRACTOR SHALL PROVIDE REAL TIME

ACCESS TO THE TOOL. THE CONTRACTOR SHALL ALSO PROVIDE THE

GOVERNMENT ACCESS AT ANY TIME AND/OR AS REQUESTED TO THE TOOLS,

DASHBOARD, AND DATA.

6. BLOCK 14: ALL DATA SHALL BE AVAILABLE VIA THE DASHBOARD.

7. THE DASHBOARD SHALL:

[CONTRACTOR FILLS IN]

15. TOTAL

01-SEP-2026

Page 3 of 4 Pages

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

TM

MISC

E. CONTRACT/PR NO.

A004

2. TITLE OF THE DATA ITEM

Scientific and Technical Reports

3. SUBTITLE

Agile Management Plan

4. AUTHORITY

(Data Acquisition Document No.)

DI-MISC-80711A

5. CONTRACT REFERENCE

PWS xxxx

8. APP CODE

N/A

9.

DIST STATEMENT REQUIRED

C

10. FREQUENCY

ASREQ

12.

DATE OF FIRST SUBMISSION

SEE BLOCK 16

11. AS OF DATE

N/A

13.

DATE OF SUBSEQUENT SUBMISSION

N/A

Reg

1. BLOCK 7: THE CONTRACTOR SHALL SUBMIT THE DATA ITEM TO THE

OFFICE RESPONSIBLE FOR THE REVIEW/APPROVAL OF THE DATA ITEM PER BLOCK 6

2. BLOCK 9: DISTRIBUTION STATEMENT C. DISTRIBUTION AUTHORIZED

TO U.S. GOVERNMENT AGENCIES AND THEIR CONTRACTORS ONLY DUE TO

ADMINISTRATIVE USE EFFECTIVE 1 SEPTEMBER 2026. OTHER REQUESTS

FOR THIS DOCUMENT SHALL BE REFERRED TO U.S. ARMY CAPABILITY

PROGRAM EXECUTIVE SIMULATION, TRAINING, TEST & THREAT (CPE-ST3).

3. BLOCK 12: THE CONTRACTOR SHALL SUBMIT THE AGILE MANAGEMENT

PLAN WITHIN 60 DAYS BEFORE THE END OF THE RAMP-UP PERIOD.

4. THE GOVERNMENT WILL HAVE 7 CALENDAR DAYS FOR REVIEW,

ACCEPTANCE OR REJECTION OF THE SUBMISSION.

5. THE CONTRACTOR SHALL HAVE 7 CALENDAR DAYS TO INCORPORATE

GOVERNMENT COMMENTS INTO THE AGILE MANAGEMENT PLAN

6. BLOCK 14: ALL DATA SHALL BE AVAILABLE VIA THE DASHBOARD.

7. THE AGILE MANAGEMENT PLAN SHALL INCLUDE:

[CONTRACTOR FILLS IN]

15. TOTAL

PREVIOUS EDITION MAY BE USED.

Page 4 of 4 Pages image1.png image2.png image3.png