Attachment 8 - AF66 Submittal schedule.xlsx
XLSX spreadsheet 30 KB Posted
- Attached to
- Repair Sewer Manholes Beale AFB
- Solicitation number
- FA468624F0005
About this file
This document outlines a submittal schedule for a federal contract to repair sewer manholes at Beale Air Force Base in California. The contractor must provide design documents, plans, specifications, test results and other submittals on a rolling basis between the notice to proceed date and final acceptance inspection. Key submittals and deadlines include 95% design documents due 35 days after NTP, reinforced steel drawings and concrete mix designs due 45 days after NTP, mechanical, electrical and plumbing component data due 14 to 45 days after NTP, and as-built drawings and test results due within 7 days of final acceptance inspection. The purpose of the repair work is to replace or reseal manhole grade rings, frames and covers, raise frames 6 inches above ground, install plugs, seal around pipes and benches, and address inflow and infiltration issues across the air base. The solicitation was issued by the Department of the Air Force Air Combat Command.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Submittal 1
| SCHEDULE OF MATERIAL SUBMITTALS | PROJECT NUMBER | PROJECT NAME | SOLICITATION /CONTRACT NUMBER | |||||||||||||||||||
| WT11790270 | Repair Sewer Manholes, (Address I&I). | TBD | ||||||||||||||||||||
| TO BE COMPLETED BY PROJECT ENGINEER | TO BE COMPLETED BY CONTRACT ADMINISTRATOR | |||||||||||||||||||||
| LINE NUMBER | Note: 3 copies required per submittal. Government will retain all submittals. Provide an electronic copy for each submittal. | CERTIF. OF COMPLIANCE | SHOP DRAWINGS | COLOR SELECTION | MANUFATURUR'S RECOMMENDATION | CATALOG DATA | O&M RECOMMENDATIONS | CALCULATIONS | WARRANTY | DRAWINGS | REPORT | TEST RESULTS | REQUIRED SUBMISSION DATE | DATE TO CONTRACTING | DATE TO CIVIL ENGINEERING | RETURN SUSPENSE DATE | SUBMITTAL NUMBERS | APPROVED | DISAPPROVED | CONTRACTOR SUBMITTAL | FINAL APPROVAL | |
| GENERAL | ||||||||||||||||||||||
| Project Specific Form 66 | X | NTP + 3 | ||||||||||||||||||||
| Construction Schedule | X | NTP + 7 | ||||||||||||||||||||
| TCN Schedule (electronic required, hard copy optional) | NTP + 7 | |||||||||||||||||||||
| Contractor's Health, Safety, and Environment Plan | NTP + 7 | |||||||||||||||||||||
| Contractor's QA/QC Plan | NTP + 7 | |||||||||||||||||||||
| Copy of Engineering License(s) of person or consultancy responsible for design | Design | |||||||||||||||||||||
| DESIGN | ||||||||||||||||||||||
| All submissions to be provided in hard copy and electronically unless noted otherwise. 65%, 95%, and 100% Design Documents to include: | NTP + 21 (65%) NTP + 35 (95%) NTP + 45 (100%) | |||||||||||||||||||||
| Roof Drain Storm Sewer Tie In | NTP+45 | |||||||||||||||||||||
| Wind Loading Diagrams for Roof | NTP+45 | PE STAMP REQ'D | ||||||||||||||||||||
| Structural Connection Details for Shear Walls | NTP+45 | PE STAMP REQ'D | ||||||||||||||||||||
| Structural Connection Details for Framing | NTP+45 | PE STAMP REQ'D | ||||||||||||||||||||
| Structural Connection Details for Blast Resistant Doors & Windows | NTP+45 | PE STAMP REQ'D | ||||||||||||||||||||
| HVAC Calculations | NTP+45 | |||||||||||||||||||||
| Sprinkler Layout | NTP+45 | FPE or NICET Tech stamp req'd | ||||||||||||||||||||
| Fire Alarm Layout | NTP+45 | FPE or NICET Tech stamp req'd | ||||||||||||||||||||
| Communications Layout | NTP+45 | |||||||||||||||||||||
| Technical Specifications | X | NTP+7 | ||||||||||||||||||||
| DEMOLITION/ASBESTOS | ||||||||||||||||||||||
| Demolition Plan | X | NTP+45 | ||||||||||||||||||||
| Asbestoes Plan | NTP+45 | |||||||||||||||||||||
| CIVIL | ||||||||||||||||||||||
| Soil Gradations for each type of soil used | Install -7 | |||||||||||||||||||||
| Moisture-Density curve for each type of soil used | Install -7 | |||||||||||||||||||||
| Nuclear Densometer Calibration | Install -7 | |||||||||||||||||||||
| Soil Compaction Test Results for Utilities, Facilities & Pavement | Install+7 | |||||||||||||||||||||
| Storm Pipe | Design+14 | |||||||||||||||||||||
| ARCHITECTURAL | ||||||||||||||||||||||
| Blast Resistant Doors and Frames | NTP+45 | |||||||||||||||||||||
| Door Hardware | NTP+45 | Hardware Schedule | ||||||||||||||||||||
| Gypsum Board-Type X | NTP+45 | |||||||||||||||||||||
| Gypsum Board-Type X-Mold Resistant | NTP+45 | |||||||||||||||||||||
| Wood Paneling | NTP+45 | |||||||||||||||||||||
| Wood Chair Rails | NTP+45 | |||||||||||||||||||||
| Wood Ceiling Cloud | NTP+45 | |||||||||||||||||||||
| Sheet Vinyl Flooring | NTP+45 | |||||||||||||||||||||
| Rubber Base | NTP+45 | |||||||||||||||||||||
| Ceiling Tiles | NTP+45 | |||||||||||||||||||||
| Blast Resistant Window | NTP+45 | |||||||||||||||||||||
| Glazing | NTP+45 | |||||||||||||||||||||
| Solid Surface Countertops | NTP+45 | |||||||||||||||||||||
| Kitchen Cabinets | NTP+45 | |||||||||||||||||||||
| Garbage Disposal | NTP+45 | |||||||||||||||||||||
| Interior Paint | NTP+45 | |||||||||||||||||||||
| Exterior Paint | NTP+45 | |||||||||||||||||||||
| Roofing System | NTP+45 | |||||||||||||||||||||
| Roofing Insulation | NTP+45 | |||||||||||||||||||||
| Roof Drains | NTP+45 | |||||||||||||||||||||
| Scuppers | NTP+45 | |||||||||||||||||||||
| Coping | NTP+45 | |||||||||||||||||||||
| Flashing | NTP+45 | |||||||||||||||||||||
| STRUCTURAL | ||||||||||||||||||||||
| Reinforcing Steel Drawings | NTP+45 | |||||||||||||||||||||
| Concrete Mix Design | NTP+45 | |||||||||||||||||||||
| Concrete Curing Compounds, Admixtures, Joint Sealants, Expansion Joints | X | X | X | X | X | NTP+45 | ||||||||||||||||
| Concrete Field Test Results | X | NTP+45 | ||||||||||||||||||||
| Reinforcing Steel Mill Certifications | NTP+45 | |||||||||||||||||||||
| Slump Test results & Concrete Truck Tickets (per truck) | Test + 3 | |||||||||||||||||||||
| 7-Day Concrete Compressive Strength Test | Test + 3 | |||||||||||||||||||||
| 28-Day Concrete Compressive Strength Test | Test + 3 | |||||||||||||||||||||
| Blast Resistant Window Attachment | Design + 14 | |||||||||||||||||||||
| MECHANICAL | ||||||||||||||||||||||
| HVAC Balancing | Design+14 | |||||||||||||||||||||
| Registers | Design+14 | |||||||||||||||||||||
| Dampers | Design+14 | |||||||||||||||||||||
| Ductwork | Design+14 | |||||||||||||||||||||
| Sprinkler Heads | NTP+14 | |||||||||||||||||||||
| Ductwork Pressure Drops Before Removal | NTP+14 | |||||||||||||||||||||
| Ductwork Pressure Drops After Installation | NTP+14 | |||||||||||||||||||||
| Ductwork | NTP+14 | |||||||||||||||||||||
| Controls | Design+14 | |||||||||||||||||||||
| Piping | Design+14 | |||||||||||||||||||||
| Heaters | Design+14 | |||||||||||||||||||||
| Valves | Design+14 | |||||||||||||||||||||
| Pumps | Design+14 | |||||||||||||||||||||
| Thermal Insulation | Design+14 | |||||||||||||||||||||
| Instrumentation | Design+14 | |||||||||||||||||||||
| PLUMBING | ||||||||||||||||||||||
| Plumbing Fixtures | NTP+45 | |||||||||||||||||||||
| Piping for Water | NTP+45 | |||||||||||||||||||||
| Garbage Disposal | X | NTP+45 | ||||||||||||||||||||
| Waste and Vent | X | NTP+45 | ||||||||||||||||||||
| INTERIOR ELECTRICAL | ||||||||||||||||||||||
| Cables(electrical,comm,fire alarm) | NTP+45 | |||||||||||||||||||||
| Switches | NTP+45 | |||||||||||||||||||||
| Receptacles | NTP+45 | |||||||||||||||||||||
| Panels | NTP+45 | |||||||||||||||||||||
| Breakers | NTP+45 | |||||||||||||||||||||
| Conduits | NTP+45 | |||||||||||||||||||||
| Lighting Fixtures | NTP+45 | |||||||||||||||||||||
| Lighting UPS units (if req'd) | NTP+45 | |||||||||||||||||||||
| Communication System Outlets(incl jacks) | NTP+45 | |||||||||||||||||||||
| Communications patch panels | NTP+45 | |||||||||||||||||||||
| PA Speakers | NTP+45 | |||||||||||||||||||||
| Fire Alarm Devices (All) | NTP+45 | |||||||||||||||||||||
| Occupancy Sensors | NTP+45 | |||||||||||||||||||||
| Power Packs | NTP+45 | |||||||||||||||||||||
| EXTERIOR ELECTRICAL | ||||||||||||||||||||||
| Conduits | NTP+14 | |||||||||||||||||||||
| Transformer | NTP+14 | |||||||||||||||||||||
| Meter | NTP+14 | |||||||||||||||||||||
| Cables(med & low voltage) | NTP+14 | |||||||||||||||||||||
| Switches | NTP+14 | |||||||||||||||||||||
| Contactors | NTP+14 | |||||||||||||||||||||
| Panels | NTP+14 | |||||||||||||||||||||
| Breakers | NTP+14 | |||||||||||||||||||||
| Controller | NTP+14 | |||||||||||||||||||||
| Junction Cabinet | NTP+14 | |||||||||||||||||||||
| Heating Mat | NTP+14 | |||||||||||||||||||||
| CLOSEOUT | ||||||||||||||||||||||
| O&M maint data and maint manuals & Manufacturer's Warranty for Communications Equipment | Install + 4 | |||||||||||||||||||||
| Factory and Field Test Certificates, Logs and Test Results | X | Before Acceptance | ||||||||||||||||||||
| Inspection Logbook | X | Before Acceptance | ||||||||||||||||||||
| As Builts (electronic in AutoCAD and hard copies on Mylar) | Final + 7 |