Attachment 6 - Sample Progress Schedule.xlsx
XLSX spreadsheet 24 KB Posted
- Attached to
- Repair Hangar Roof, H40 Amendment 03
- Solicitation number
- FA301620R0045
About this file
This document contains a sample progress schedule template and details for a federal contract solicitation. The sample progress schedule template outlines the planned timeline for key work elements on a project to replace pneumatic controls across multiple facilities, including 13% for site preparation over June and July 2018, 60% for construction from July through October 2018, and contract closeout activities concluding in May 2019.
The related federal contract solicitation is for repair work on Hangar H40's roof and seeks bids in response to Solicitation Number FA301620R0045 issued by the Department of the Air Force Air Education and Training Command. As outlined in the attached solicitation documents, interested vendors should review the provided materials for full project details. No further information is included regarding response dates, award timing, or other contractual requirements.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AF3064
| 1. CONTRACT NO. | 8. PROJECT TITLE: Replace Pneumatic Controls - Multi Facility | 10. APPROVAL RECOMMENDED BY | |||||||||||||
| FA3016-18-C-XXXX | DATE SIGNED | ||||||||||||||
| 3. COMPLETION DATE: | 9. SUBMITTED BY: | ||||||||||||||
| 4. PURCHASE REQUEST NO. | Contractor's Name | DATE SIGNED | CONTRACTOR'S SIGNATURE | 11. APPROVED BY | |||||||||||
| 5. PROJECT NO. TYMX111031 | Contractor's Address | DATE SIGNED | CONTRACTING OFFICER'S SIGNATURE | ||||||||||||
| 6. ACTUAL STARTING DATE: | Contractor's Address | ||||||||||||||
| 7. ACTUAL COMPLETION DATE: | |||||||||||||||
| LINE NO. | WORK ELEMENTS | % | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Jan | Feb | Mar | Apr | May | Jun |
| A | B | C | 2018 | 2018 | 2018 | 2018 | 2018 | 2018 | 2018 | 2018 | 2018 | 2018 | 2018 | 2018 | 2018 |
| 1 | Bonds | 2.00% | 2.00% | ||||||||||||
| 2 | Schematic Drawing | 5.00% | 5.00% | ||||||||||||
| 3 | Site Prep | 13.00% | 13.00% | ||||||||||||
| 4 | Construction | 60.00% | 60.00% | ||||||||||||
| 5 | Cleanup | 15.00% | 15.00% | ||||||||||||
| 6 | Contract Closeout | 5.00% | 5.00% | ||||||||||||
| 7 | |||||||||||||||
| 8 | |||||||||||||||
| 9 | |||||||||||||||
| 10 | |||||||||||||||
| 11 | |||||||||||||||
| 12 | |||||||||||||||
| 13 | |||||||||||||||
| 14 | |||||||||||||||
| 15 | |||||||||||||||
| 16 | |||||||||||||||
| 17 | |||||||||||||||
| 18 | |||||||||||||||
| 19 | |||||||||||||||
| 20 |
| 100.00% | |||||||
| MONTHLY TOTAL: | 7.00% | 73.00% | 15.00% | 5.00% | 100.00% | ||
| ACTUAL PROGRESS: | 7.00% | 80.00% | 95.00% | 100.00% | 100.00% | ||
| Highlighted areas to be completed by the contractor; dates and percentages contained are for format example only |
FA301618R0023 Attachment 6