Attachment 6_Rev 00_Workplan Outline Requirements.pdf
PDF 96 KB Posted
- Attached to
- West Point Renovations Construction & Repairs
- Solicitation number
- PANHES-26-P-0000-029922
About this file
This is a Work Plan Outline template document for the Facilities Repair and Renewal (FRR) Program issued by the Corps of Engineers. The document provides mandatory formatting and content requirements for Designer of Record (DOR) contractors to follow when developing work plans for small and minor projects. Work plans must be submitted electronically in engineering-quality format with sequential page numbering, a Table of Contents containing acronyms and abbreviations, and proper section and paragraph numbering using decimal designations. The title sheet must include project name, contractor information, contract number, Task Order number, project number, plan date, and version status, with signature by the Corporate Quality Management representative.
The work plan must contain nine sections addressing: project introduction with contract details and site description; project management structure and personnel responsibilities including Program Manager, Project Manager, Superintendent, Health and Safety Officer, and Contractor Quality Control Officer; physical security and visitor control procedures; detailed work description with sequence, equipment, and permits; hazardous material removal procedures if applicable; utility disconnect and cap coordination; demolition means and methods with waste management plans; site restoration specifications if applicable; and references. The document must include nine appendices in specified order: Statement of Work and Modifications, Site Maps, Quality Control Plan with personnel resumes, Environmental Protection Plan (if applicable), Storm Water Pollution Prevention Plan (if applicable), Project Schedule, Accident Prevention Plan, and Existing Condition Photographs. Sections not applicable to a specific project must be marked "Not required for this project" while maintaining placeholder space. Any revisions require a dated summary page with all changes highlighted in yellow and bolded text.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 6 - DID_FRR-21-001_Rev 00 Workplan Outline Requirements
Title: Work Plan Outline
Revision No. 000
Applicable Forms:
DATE: 17 APR 2026
Use/Relationship: Designer of Record (DOR) /Contractor shall use this outline to develop the Work Plan. The Work Plan will be used to describe the goals, methods, procedures, and personnel used in small and minor projects awarded by the Facilities Repair and Renewal Program.
Requirements:
1. Work Plans shall be submitted in electronic format as directed in each Task Order. Pages shall be sequentially numbered. Data and drawings shall be of engineering quality with sufficient detail to show interrelations of major features as applicable. All attachments and appendices shall be identified and referenced in the text of the plan and conveyed within the Table of Contents. The Table of Contents shall contain a list of Acronyms or Abbreviations used within the document. The plan shall be legible and suitable for reproduction, in both digital and print format.
The Work Plan shall be separated by Sections and numbered sequentially. Within each Section, the paragraphs shall be numbered sequentially starting with the Section number and using a decimal system, with each Section and paragraph having a unique decimal designation.
Within each Section, any figures, tables, and charts shall also be numbered sequentially starting with the respective Section number.
A title sheet will be provided on the front of the Work Plan which includes the name of the project (site), contractor's name and address, the Corps of Engineers’ contract number, Task Order number (if applicable), and project number, the date of the plan, and the title of the plan.
The contractor’s name/logo shall not dominate the title sheet. The Corporate Quality Management representative shall sign the title sheet. The version of the work plan (i.e., draft, final, etc.) shall be clearly identified on the title sheet.
When revisions to the work plan are required, a dated summary page listing all revised pages shall be submitted with each revision. This summary page shall be identified as such and placed directly behind the title page. All revisions to the Work Plan shall be highlighted in yellow and the text bolded to match the information shown in the summary changes page.
2. Work Plan Outline - Sections, or appendices not used for a specific project shall be marked:
“Not required for this project.” However, the correct section or appendices placeholder shall be left within the document for reference.
Section 1 - Introduction. At a minimum the following information shall be included:
a. Project Title (Contract No., Delivery Order No., etc.) A copy of the actual award PWS and any Modification will be shown in Appendix A – Statement of Work
b. General Information deemed appropriate by the contractor.
c. Site(s) Location and description(s)
Section 2 - Project Management Plan
a. Organization Chart (Home Office and Field) for this project
b. Personnel – Duties and Responsibilities
c. Program Manager (Home Office)
d. Project Manager (Home Office)
e. Project Manager/Superintendent (Project Site)
f. Health and Safety Officer (Home or Project Site)
g. Contractor Quality Control Officer (Home or Project Site)
h. Project Management Team – Contact Information
i. Resumes for Superintendent/SSHO/CQC and alternates with appropriate training certifications
Section 3 - Physical Security and Visitor Control
a. Installation access requirements for personnel
b. Approved gates/routes
c. Vetting of all employees for background checks
Section 4 - Description of the Work
a. Brief detailed sequence of work and work processes; including overall plan and detail drawings as applicable
b. Equipment and subcontractors
c. Permits required (if applicable) with NLT dates
Section 5 - Hazardous and Potentially Hazardous Material Removal
a. . If applicable, list by Building/Structure Number and indicate Subcontractors, disposal facilities and locations, Asbestos Containing Materials (ACM) / Other Regulated Materials (ORM) quantities to be abated, NOI permit, certifications, etc. Provide brief description of expected means and methods to be employed.
Section 6 - Utility Disconnect, Cut, and Cap
Briefly list coordination and responsibility for the following actions (as applicable):
a. Electricity
b. Water
c. Sanitary Sewer
d. Natural Gas, Propane, or other Heating Fuels
e. Communications/Fire Alarm Systems
f. Cut and Cap plans and drawings
Section 7 - Demolition Activities
a. Provide brief description of expected means and methods to be employed
b. Provide brief Waste Management and Diversion Plan to include (at a minimum): Recycle facilities and locations, anticipated quantities by type of materials, haul routes, etc.
Section 8 - Site Restoration (if Applicable)
a. Provide brief description of expected means and methods to be employed
b. Materials: seed/sod, equipment, water requirements, etc. Finished condition of sites
Section 9 - References
Appendices. The work plan shall contain the following documents in the order shown as appendices:
Appendix A – Statement of Work and Modifications as Awarded with initial bid cost at NTP
Appendix B - Site Maps
Appendix C - Quality Control Plan Quality Control Personnel Resume(s) Letter Appointing CQC Personnel for this Project
Appendix D - Environmental Protection Plan (if Applicable)
Appendix E - Storm Water Pollution Prevention Plan (SWPPP) (if Applicable)
Appendix F - Project Schedule (as required per Division 01 Specifications)
Appendix G - Accident Prevention Plan
Appendix H - Existing Condition Project Photographs
| Requirements: |
| Section 2 - Project Management Plan |
| Section 3 - Physical Security and Visitor Control |
| Section 4 - Description of the Work |
| Section 5 - Hazardous and Potentially Hazardous Material Removal |
| Section 6 - Utility Disconnect, Cut, and Cap |
| Section 7 - Demolition Activities |
| Section 9 - References |