Attachment 6_Past Performance Questionnaire.docx
DOCX document 40 KB Posted
- Attached to
- 844 CG SYSTEMS ENGINEERING and TECHNICAL ASSISTANCE (SETA) Follow-On Federal contract opportunity
- Solicitation number
- FA701424R0005
About this file
This document is a past performance questionnaire template for a federal contractor. It requests information about a contractor's past performance on a referenced contract to assess experience providing technical expertise in areas such as analytic support, facility-related control systems and data analytics, strategic assessment, and strategic communication. Specifically, it asks the respondent to rate the contractor's performance on over a dozen criteria using a standardized rating scale. It also collects details about the contract such as number of staff provided, type of technical expertise, and whether any cure notices were issued. The questionnaire is to be completed and returned for a solicitation from the Department of the Air Force for 844 CG Systems Engineering and Technical Assistance follow-on services.
View the file
Other files for this federal contract opportunity
Show all 28
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
For Official Use Only When completed, this document is Source Selection Information IAW FAR 2.101 and 3.104.
Past Performance Questionnaire Section 1: Contract Identification
A. Contractor (Company/Division):
B. Contractor Cage Code:
C. Contract Number:
D. Contract Type (e.g., FFP, FPIF, CPIF, CPFF, etc.):
E. Program Title:
F. Brief Program Description:
G. Program Phase (e.g., Engineering & Manufacturing Development (EMD)):
H. Period of Performance
I. Contract Dollar Value
1. Original maximum contract dollar value (assuming all options exercised): $
2. Current maximum contract dollar value (assuming all options exercised): $
3. Reasons for difference between original and current contract dollar value (if applicable):
J. Description of work performed:
K. Was this a competitively awarded contract? ☐ Yes ☐ No
L. Contractor’s Role: ☐ Prime Contractor ☐ Subcontractor ☐ Key Personnel
Note: If offeror holds or has held other contracts with your agency/organization in the last three (3) years, please complete separate Past Performance Questionnaire forms for those contracts as well.
Section 2: Customer or Agency Identification
A. Customer or agency name:
B. Customer or agency description (if applicable):
C. Geographic description of work performed under this contract (i.e., local, nationwide, worldwide, other Commands):
Section 3: Respondent Identification
A. Respondent’s name:
B. Respondent’s title:
C. Respondent’s phone/fax number/e-mail address:
D. Length of time (number of years/months) respondent worked on subject contract and description of responsibility/position/role:
E. Other suggested points of contact:
Section 4: Performance Information
In the table below, indicate your rating for the contractor’s performance by placing an “X” in the appropriate block to the right of each question. Provide supporting information for each response in the space provided. Attach additional pages if more space is needed. The performance rating scale is defined as follows:
Code Performance Rating
E EXCEPTIONAL – Performance meets contractual requirements and exceeds many requirements to the Government’s benefit. The contractual performance being assessed was accomplished with few minor problems for which corrective actions taken by the contractor were highly effective.
V VERY GOOD – Performance meets contractual requirements and exceeds some requirements to the Government’s benefit. The contractual performance being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.
S SATISFACTORY – Performance meets contractual requirements. The contractual performance being assessed contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.
M MARGINAL – Performance does not meet some contractual requirements. The contractual performance being assessed reflects a serious problem for which the contractor has not yet identified corrective actions or the contractor’s proposed actions appear only marginally effective or were not fully implemented.
U UNSATISFACTORY – Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance being assessed contains serious problem(s) for which the contractor’s corrective actions appear or were ineffective.
N/A NOT APPLICABLE – Unable to provide a rating. Contract did not include performance for this aspect, performance was not observed, or information was not available. Do not know.
| The Contractor: |
| E |
| V |
| S |
| M |
| U |
| N/A |
1. Provided experienced managers and supervisors with the technical and administrative abilities needed to meet contract requirements.
SUPPORTING INFORMATION:
2. Demonstrated the ability to hire, maintain, and replace, if necessary, qualified personnel during the contract period.
3. Delegated authority to project managers and supervisors commensurate with contract requirements.
4. Home office participated in solving significant local problems.
5. Provided effective quality control and/or inspection procedures to meet contract requirements.
6. Corrected deficiencies in a timely manner.
7. Provided timely resolution of contract discrepancies.
8. Identified problems as they occurred.
9. Suggested alternative approaches to problems.
10. Displayed initiative to solve problems.
11. Met established project schedules.
12. Was responsive to contract changes.
13. Provided adequate project supervision.
14. Cooperated with Government personnel after award.
15. How would you rate the contractor's overall performance on this contract?
16. How many Full Time Equivalent (FTE) positions did the contractor provide on this contract?
Please provide answer below:
17. What type of technical expertise was provided on this contract?
Please provide answer below:
18. Did the contractor provide technical expertise in the area of analytic support?
EXPLANATION:
☐ Yes ☐ No
19. Did the contractor provide technical expertise in the area of Facility Related Control Systems and Facility Data Analytics?
☐ Yes
20. Did the contractor provide technical expertise in the area of strategic assessment?
☐ Yes
21. Did the contractor provide technical expertise in the area of strategic communication?
☐ Yes
22. Was the contractor ever issued a cure or show cause notice under the referenced contract? If yes, explain.
☐ Yes
23. Would you award another contract to this contractor? If not, explain.
☐ Yes
Additional remarks:
[click and pick the date]
Respondent’s Signature Date
Thank you for your prompt response and assistance!
Please return this completed questionnaire to:
For Official Use Only Page 6 of 6
File details come from the government source that posted it. Updated .