This document is a Hazardous Materials Summary Report for Building 1825 at Hanscom Air Force Base in Bedford, Massachusetts, prepared by CDW Consultants in March 2024. The comprehensive report details the findings of a hazardous building materials survey conducted to support the planned demolition of the building, which was constructed in 1955 and currently serves as an office for the base's Environmental Department.
The survey identified several hazardous materials, including asbestos-containing materials in floor tiles, mastic, and pipe insulation. Specifically, asbestos was detected in the break room's vinyl floor tiles (4-10% chrysotile), pipe insulation above the ceiling, and various mastic materials. Additional hazardous materials include mercury-containing fluorescent bulbs, electronic ballasts, lead-based paint, tritium exit signs, emergency light batteries, a 1,000-gallon underground fuel oil storage tank, and a pad-mounted transformer. The report provides detailed recommendations for proper handling, removal, and disposal of these materials in compliance with federal, state, and local regulations, with an estimated total abatement cost of approximately $47,915.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
4 California Drive, Suite 301, Framingham, Massachusetts 01701 508-875-2657 www.cdwconsultants.com
FINAL HAZARDOUS MATERIALS SUMMARY REPORT
Base Admin Building
Building 1825
Hanscom Air Force Base
Bedford, Massachusetts
Project: #MXRD220501
Prepared for:
SMMA
1000 Massachusetts Avenue Cambridge, MA 02138
Prepared by:
CDW Consultants
4 California Avenue Framingham, MA 01701
March 2024
CDW Project # 2105.00
Building 1993B
TABLE OF CONTENTS
Page
1.0 INTRODUCTION
2.0 PROJECT UNDERSTANDING
3.0 GENERAL SITE CONDITIONS
4.0 REPORTS REVIEW
5.0 ASBESTOS SURVEY
5.1 Methods
5.2 Findings
5.3 Recommendations
6.0 LEAD-BASED PAINT
6.1 Methods
6.2 Findings
6.3 Recommendations
7.0 POLYCHLORATED BIPHENYLS
7.1 Methods
7.2 Results
8.0 HAZARDOUS MATERIALS SURVEY
8.1 Methods
8.2 Findings
8.3 Recommendations
APPENDICES
Appendix A: Photographs Appendix B: Asbestos Laboratory Analytical Reports
Appendix C: Lead Paint Laboratory Analytical Report Appendix D: PCB Laboratory Analytical Report Appendix E: Cost Estimate
FIGURE HZ-101: Sample Locations
Building 1993B
CDW CONSULTANTS, INC. ii
EXECUTIVE SUMMARY
CDW Consultants, Inc. (CDW) conducted a hazardous building materials (HBM) survey to identify and report the findings of suspect asbestos-containing materials (ACM), lead based paint (LBP), polychlorinated biphenyls (PCBs) and other visible hazardous materials at Building 1825, located at Hanscom Air Force Base, Massachusetts (Site). In November 2023, CDW staff conducted visual inspections for suspect ACM and other hazardous materials. The HBM survey was conducted in support of demolition of twelve selected buildings on Hanscom Air Force Base.
Building 1825, an active occupied building, is a 3,000 square foot building constructed in 1955.
Building 1825 is utilized by the base Environmental Department. The exterior of the building consists of fiberglass over Styrofoam over concrete at the upper side, with a brick facade at the lower portion on a slab foundation. The interior finishes consist of sheetrock walls, carpet, and tile floors with suspended ceiling tiles. The subject property building contains a central cubical area, offices, and meeting room.
CDW’s HBM inspection identified ACM in floor tile and mastic and pipe insulation. Hazardous materials consist of items ranging from batteries for exit signs and emergency lights, fluorescent bulbs and ballasts, refrigerants, a 1,000-gallon #2 fuel oil underground storage tank (UST) and pad mounted transformer.
Building 1825, Base Admin Building Hanscom Air Force Base
CDW Project #2105.0
1.0 INTRODUCTION
CDW Consultants, Inc. (CDW) is pleased to present this report summarizing the findings of the HBM survey of Building 1825, located at Hanscom Air Force Base, Massachusetts (Site). The HBM survey was conducted by CDW in support of the demolition of this building and eleven others on base. In November 2023, Susan Cahalan (Massachusetts Asbestos Inspector #AI60784) and Bryant Dana (Massachusetts Asbestos Inspector #AI901229) conducted an inspection for suspect materials.
An inspection is required by the United States Environmental Protection Agency (USEPA) National Emission Standards for Hazardous Air Pollutants (NESHAP), prior to scheduled building renovations or demolitions. Additionally, the Massachusetts Department of Environmental Protection (MassDEP) regulate ACM associated with renovation, demolition, and asbestos abatement projects.
2.0 PROJECT UNDERSTANDING
The scope of the work was to provide an HBM survey in support of the demolition. The HBM survey consisted of collecting potential hazardous materials samples including ACM, LBP, and PCBs in building materials. The HBM survey also included a contractor to core and sample the roof, along with investigating behind façade for exterior vapor barrier and digging holes at the slab to look for waterproofing.
3.0 GENERAL SITE CONDITIONS
Building 1825 is a 3,000 square foot building constructed in 1955. Building 1825 is utilized as an office building which is occupied by the Environmental Department. The interior finishes consist of vinyl floor tile, carpet, painted sheetrock walls Which contains a main room with cubicles, an office, two bathrooms, a storage room, a break room, and a boiler room. The boiler room is only accessible through an exterior entrance.
The exterior of the building consists of painted fiberglass over Styrofoam over backup concrete at the upper section, and a brick façade at the lower section. Windows and doors are aluminum framed.
There is a wood façade right below a pitched shingled roof. Under the pitched shingle roof is an old tar and gravel roof. There was no vapor barrier found underground on the slab foundation.
The interior of Building 1825 consists of sheetrock walls, with carpet used throughout except for the breakroom, storage, and bathrooms. Vinyl floor tiles are located in the break room, both bathrooms, and the storage closet. Suspended ceiling tiles and cove base moldings trim the bottom of the sheetrock.
4.0 REPORTS REVIEW
No previous hazardous building surveys or abatement reports were available for review.
5.0 ASBESTOS SURVEY
5.1 Methods
The investigative work for the asbestos survey included conducting a visual inspection of physically accessible areas of the subject areas. Once the visual inspection was completed, the building components were categorized into homogeneous areas. CDW collected bulk samples of different homogeneous suspect materials for asbestos analysis. The bulk samples were delivered under chain of custody to Asbestos Identification Laboratory, Inc. (AIL) located in Woburn, Massachusetts. AIL is a state licensed (#AA000208) and NVLAP-accredited laboratory (lab code #200919-0) for asbestos analysis. Bulk samples were analyzed for asbestos content by polarized light microscopy (PLM) using USEPA Method 600/R-93/116. A positive stop method was used – if one sample in a homogeneous group is positive then additional samples of the same material are not analyzed.
Samples analyzed to contain greater than 1% asbestos are to be treated as ACM as defined by the USEPA and Commonwealth of Massachusetts Department of Environmental Protection (MassDEP).
Photographs are provided in Appendix A. The asbestos analytical report is provided in Appendix B.
5.2 Findings
Findings are listed in the below table.
Sample ID Material Location Asbestos %
1A,B,C White Dotted w/Bubbles Ceiling Tile
Women’s Bathroom ND
2A,B,C White Dotted w/ long Squiggles Ceiling Tile
Cubicle Area (Main Room)
ND
3A,B,C White Dotted w/Short Squiggles Ceiling Tile
Cubicle Area (Main Room)
ND
4A,B,C,D,E,F,G White Dotted Texture Ceiling Tile
Throughout Building (Cubicle Area, Break Room, Hallways, Main Entrance)
ND
5A,B,C 12”x12” Off White Dotted Ceiling Tile
Above Ceiling (Main Room)
ND
6A,B,C Glue Daubs Behind 12’x12’ Ceiling Tile
Above Ceiling )Main Room)
ND
7A,B,C Gray Cove Molding Bathrooms/Break Room ND
8A,B,C Tan Mastic Behind Gray Cove
Bathrooms/Break Room ND
9A,B,C,D,E Blue Cove Molding Throughout Building (By Doors, Hallways, Break Room, Cubicle Area)
ND
10A,B,C,D,E Tan Mastic Behind Blue Cove Molding
Throughout building (By Doors, Hallways, Break Room, Cubicle Area)
ND
11A,B,C Caulk Coating on Pipe
Above Ceiling in Front of Ladies Room
Chrysotile 10%
12A,B,C Glue Under Carpet By Exit Door (Northeast Door)
ND
13A,B,C,D,E,F,G Drywall Throughout Building (By Doors, Hallways, Break Room, Cubicle Area)
ND
14A,B,C,D,E,F,G White Wall Cover Throughout building (By Doors, Hallways, Break Room, Cubicle Area)
ND
15A,B,C Joint Compound Main Entrance Way ND
16A,B,C Gray Sealant on Vents
Boiler Room ND
17A,B,C Mudded Ends on Fiberglass Insulation
Boiler Room ND
18A,B,C Stucco Front Side of Building ND
19A,B,C Gray Mastic Under Stucco
Front Side of Building ND
20A,B,C Gray-Brown Exterior Door Caulk
Main Entrance Door ND
21A,B,C Gray-Brown Exterior Caulk on Top of Brick
Front/Back of Right-Side Building
ND
22A,B,C Black Exterior Window Glaze
Front/Back of South Side of Building
ND
23A,B,C Gray-Brown Exterior Window Caulk
Front/Back of Building, South Side
ND
24A,B,C Gray-Brown Exterior Caulk on top of Brick
Perimeter of Building ND
25A,B,C Exterior Window Caulk
West Side of Building ND
26A,B,C White Vinyl Tile Women’s Bathroom ND
27A,B,C Tan Mastic under White Floor Tile
Women’s Room ND
28A,B,C White Vinyl Floor Tile
Men’s Bathroom ND
29A,B,C Tan Mastic under White Floor Tile
Men’s Room ND
30A,B,C Black Vinyl Floor Tile
(Top Layer) Break Room (Kitchen)
Chrysotile 4%
31A,B,C Black Mastic Under Black Floor Tile
Break Room (Kitchen) Chrysotile 10%
32A,B,C Off White Vinyl Floor Tile
(Bottom Layer) Break Room (Kitchen)
Chrysotile 6%
33A,B,C Brown Mastic Under Off White Vinyl Floor Tile
Break Room (Kitchen) Chrysotile 5%
34A,B,C Sheetrock Attic ND
35A,B,C Joint Compound Attic ND
36A,B,C Wall Cover (Exterior) West Side of Building ND
37A,B,C New Shingle Roof ND
38A,B,C Roof underlayment Roof ND
39A,B,C Old Shingle Roof ND
Roof Core 1A Old Tar/Roof Top layer ND
Roof Core 1B Old Tar/Gravel Roof Middle layer ND
Roof Core 1C Tar Old Roof Top of Deck ND
ND = Not Detected Chrysotile = Asbestos Mineral
Refer to the below table for quantities of ACM and presumed ACM (PACM) from CDW’s survey.
Material Description
Location
Est.
Quantity
Units
Caulk Coating on Pipe at Connections
Above Ceiling in Front of Ladies Room
25 EA
Black VCT Tile (Top Layer) Break Room (Kitchen) 330 SF
Black Mastic Break Room (Kitchen) 330 SF
Off White VCT Tile (Bottom Layer) Break Room (Kitchen)
330 SF
Brown Mastic Break Room (Kitchen) 330 SF
Remnant Pipe Insulation and Fittings (PACM)
Fixed Walls, Unknown Trenches 500 LF
SF = Square Foot LF = Linear Foot
5.3 Recommendations
ACM that will be impacted by renovation or demolition work must be removed before they are disturbed. This work must be conducted in accordance with a project design as prepared by a licensed Asbestos Abatement Project Designer. This report is not intended for use as an abatement design. Prior to disturbance, the ACM identified must be abated by a Commonwealth of Massachusetts-licensed asbestos abatement contractor following all federal, state & local regulations governing asbestos abatement. A copy of the asbestos Waste Shipment record must be received within 35 days of removal from the Site. Asbestos air quality sampling must be conducted under USEPA regulations following asbestos abatement and prior to re-occupancy of the spaces. If additional materials are discovered that have not been sampled, those materials should be considered ACMs until laboratory analysis determines otherwise. During renovation or demolition work, it is possible that additional suspect ACM will be encountered in areas such as subsurface tunnels, behind fixed walls etc. Contractors should be apprised to conduct any such work in a controlled manner.
6.0 LEAD-BASED PAINT
6.1 Methods
CDW performed a visual inspection of painted surfaces. CDW collected samples from different color paints on various types of building component substrates. Samples were submitted to Aerobiology Laboratory Associates Incorporated, A Pace Laboratory, located in Woburn, Massachusetts for analysis via Atomic Absorption Spectrometry (AAS).
6.2 Findings
The results of the laboratory analysis are provided in the below table.
Sample ID Sample Description/Location Lead Concentration
(% Weight)
LBP – 1 White Paint on Pipe Above Ceiling 0.096 LBP – 2 Blue Paint in Mechanical Room 0.055 LBP – 3 Gray Paint on Door Frames <RL LBP - 4 Brown Paint (Exterior) 0.034
The USEPA and US Department of Housing and Urban Development defines LBP as any paint or surface coating that contains lead equal to exceeding one milligram per square centimeter (1.0 mg/cm2) or 0.5% by weight. The OSHA lead-in-construction standard defines lead containing paint (LCP) as a paint or coating containing any detectable level of lead. Three out of the four samples taken contain lead detected above laboratory detection limits. The laboratory analytical report is included in Appendix C.
6.3 Recommendations
Based on the conclusions of this testing, the following recommendations are offered:
• During demolition or renovation, paint materials containing lead should not be sanded, scraped, drilled, or otherwise altered unless proper engineering controls are used to prevent migration of fugitive lead containing dust from the work area. Under OSHA regulations, any demolition or renovation to be performed at a structure where lead in paint and dust is present must be performed in accordance with a worker protection policy, including, but not limited to, appropriate training, medical monitoring, respiratory protection, and other protective equipment.
• In addition to the worker protection requirements stipulated by OSHA, MassDEP and the USEPA regulate the disposal of wastes that are potentially hazardous. Such wastes may include paint chips and residue generated during abatement or repainting work, or whole components, such as wood windows, doors, and trim that are coated with LBP and that are disposed of as the result of renovation or demolition work. To determine the required method for disposing of permeable items coated with LBP, the MassDEP and the USEPA require representative sampling of the debris to determine the quantity of lead that would be expected to leach into the environment if the debris were disposed of in a landfill. The representative sample(s) must be analyzed by the Toxicity Characteristic Leaching Process (TCLP) to determine the proper disposal method.
7.0 POLYCHLORATED BIPHENYLS
7.1 Methods
CDW conducted a visual inspection for suspect PCB containing building materials. Once the suspect
PCB building materials were identified, bulk samples were collected of building materials (caulk, glaze, and paint) for laboratory analysis. The samples were submitted to Pace Analytical Laboratory out of East Longmeadow, Massachusetts for analysis via USEPA Method 8082 with Soxhlet extraction 3540C. A copy of the PCB laboratory report is provided in Appendix D.
7.2 Results
The PCB analytical results are summarized in the below tables.
The table below represents pipe covering and paint.
Sample ID Material/Location Concentration (mg/Kg)
PCB-1 Pipe Covering/ Above Ceiling
4.5
PCB-2 Light Blue Paint/ Mech Room
ND
PCB-3 White Paint/ Above Ceiling Pipe
PCB-4 Blue/Gray Paint/ Doorway ND
The table below represents caulk and glaze.
PCB-1 Brown, Gray Window Caulk/ Front/Rear of Building
ND
PCB-2 Brown-Gray Caulk on Brick/ Back/ Street Side
ND
PCB-3 Brown, Gray Window Caulk/East Side of Building
ND
PCB-4 Brown-Gray Caulk on Brick/ West Side of Building
ND
PCB-5 Exterior Black Window Glaze
ND
PCB-6 Gray-Brown Exterior Caulk on Top of Brick
PCB-7 Exterior Gray-Brown Window Caulk
ND
PCB-8 Exterior Gray-Brown Door Caulk
The analytical results are compared to the USEPA standard of 50 milligrams per kilograms (mg/kg), which is the threshold for bulk product waste, as defined by USEPA 40 CFR § 761.3, and regulated under the Toxic Substances Control Act (TSCA). None of the samples collected had concentrations of PCBs above the TSCA limit of 50 milligrams per kilogram. The pipe covering above the ceiling in front of the ladies’ room, contained PCB concentration <10 mg/kg. Furthermore, for the low level of PCBs less than 10 mg/kg, there are no sources noted such as leaking ballasts or building materials containing PCBs above 50 mg/kg leaching into adjacent materials. Therefore, the building materials are considered “Excluded PCB Product.”
8.0 HAZARDOUS MATERIALS SURVEY
8.1 Methods
OHM Visual Inspection
CDW visually inspected the Site building for universal, special, and hazardous wastes associated with building materials. These included but were not limited to the following:
• Mercury-containing devices (fluorescent light tubes, thermostats, gauges, etc.);
• di (2-ethylhexyl phthalate (DEHP)-containing light ballasts ;
• Chlorofluorocarbon (CFC)-containing equipment (refrigerants, air conditioners/HVAC equipment, water bubblers, etc.)
• Tritium-containing devices (exit signs);
• Lead-Acid batteries (emergency lights, etc.)
8.2 Findings
The visual survey for hazardous materials identified mercury-containing light tubes, electronic light ballasts, lead and tritium batteries, refrigerants, and other hazardous materials. No hazardous materials sampling or analysis was conducted as part of this survey. A list OHMs identified are listed below.
Material Description Location Est.
Units
Fluorescent Bulbs (Mercury) Throughout 40 4’ Tubes
Electronic Ballasts Throughout 40 EA
Exterior Lights Exterior Walls 5 EA
Fluorescent Bulbs Throughout 5 EA
Thermostats (Mercury) Throughout 4 EA
Exit Signs (Tritium) Throughout 3 EA
Emergency Lights (Batteries) Throughout 10 EA
Fire Alarms Throughout 5 EA
Smoke/Heat Detectors (Americium)
Throughout 15 EA
Refrigerants Air Compressor/Air Conditioner
1 EA
1,000-Gallon Fuel Oil UST and Piping
Exterior 1 EA
Pad Mounted Transformer Exterior, Labeled as <50 ppm PCBs
1 EA
EA = Each
8.3 Recommendations
Prior to removal, light tubes, ballasts, tritium batteries, smoke detectors and CFLs will require proper handling, removal, transportation, and off-site recycling/reclamation. Refrigerants and transformer fluid will require handling and disposal in accordance with applicable Military, Federal and State regulations.
Limitations
The conclusions are limited to the information available at the time of the field survey and the scope of services, as defined. No subsurface soil or groundwater sampling and analysis was performed. Where access to portions of the Site or to structures on the site was unavailable or limited, CDW renders no opinion as to the presence of hazardous material or the presence of indirect evidence related to hazardous material in that portion of the site or structure. This report cannot be solely relied upon for renovation or demolition. The sampling performed forms the basis for conclusions expressed and areas inaccessible for testing limits those conclusions. No other conclusions, interpretations or recommendations are contained or implied in this report other than those expressed. While CDW followed industry standards during the inspection, we do not warrant that all suspect hazardous building materials were identified in or on the buildings and shall not be held liable related to future abatement costs related to hazardous materials that are either not discovered or not appropriately characterized. This is due in part to inherent problems with every building inspection, such as, but not limited to:
• Seemingly homogeneous materials that are not in fact homogeneous;
• Seemingly representative locations that are not in fact representative;
• Layered materials that are not uniformly present or are isolated;
• Materials that are present and accessible but were not considered to be hazardous,
• Materials that are present in an isolated and limited quantity; and
• Material that is present in locations that are unsafe or otherwise difficult to access.
Client acknowledges that CDW's inspection is limited, and all hazardous materials may only become apparent during the course of future renovation or demolition. During the course of future renovation/demolition work, it is likely that additional hazardous materials or materials suspected of being hazardous will be identified. Such materials should be assumed to be hazardous unless appropriate evaluation or sampling and analysis demonstrate otherwise. No other use of this report is warranted without the written consent of CDW Consultants, Inc.
CDW appreciates the opportunity to provide our services to you on this project.
Very truly yours, CDW CONSULTANTS, INC.
Susan Cahalan, PG, ISSP-SA Associate/Senior Environmental Geologist
Bryant Dana Environmental Scientist
FIGURE
210 sqft
294 sqft
133 sqft
1154 sqft
214 sqft
330 sqft
25 sf
12 sf 77 sf
23 sf
64 sf
14 sf
1 2 7 8 9 103 4 5 6
A
B
C
D
E
F
G
STATUS
SI
ZE
SU
BM
IT
TE
D B
Y:
C H
EC
KE
D B
Y:
D R
AW
N
B Y:
D
ES
IG
N
ED
B
Y:
IS
SU
E
D
AT
E:
SO
LI
C
IT
AT
IO
N N
O
C O
N
TR
AC
T
N O
D
EP
AR
TM
EN
T
O F
TH
E
AI
R
F O
R C
E
AI
R F
O R
C E
M
AT
ER
IA
L C
O M
M
AN
D th A
IR
B
AS
E
G R
O U
P/ C
E
BA
SE
C
IV
IL
E N
G
IN
EE
R
IN
G
D
IV
IS
IO
N
D
ES
IG
N
F
IR
M
ST
R
EE
T
AD
D R
ES
S
C
IT
Y, S
TA
TE
, Z
IP
M
AR
K D
ES
C
R
IP
TI
O
N D
AT
E
66 AIR
TH
ASE GROUP
B
SHEET IDENTIFICATION
H
AN
SC
O
M A
FB
, M
A
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
AN
SI
-D
XX
XX
XX
XX
XX
XX
XX
XX
XX
O
PT
IO
N
AL
F
IE
LD
XX
XX
XX
O
PT
IO
N
AL
F
IE
LD
XX
XX
XX
M
AY
AD
D R
ES
S
PROPERTY OF THE U.S. AIR FORCE: FOR OFFICIAL USE ONLY
FL
O
O R
H
AZ
M
AT
F
LO
O
R P
LA
N
HZ-101
B 1825
0 2' 4' 8'
SCALE:14"=1'-0"
R
ED
R
AW
N
APPENDIX A
This is the exterior of the main entrance to building 1825. Sample 20A,B,C (Ext Door Caulk) is marked with a red arrow. Sample 21A,B,C (Ext Caulk on top of Brick) is marked with a blue arrow.
This photo is a close up of the window caulk on the exterior windows. Sample 23A,B,C (Ext Window
Caulk) is highlighted in this photo with a red arrow.
This photo shows the entrance to the boiler room. Within this photo sample 21A,B,C (Ext Caulk on top of brick) is shown and represented with a red arrow.
This photo shows the right side of the main cubicle area. Multiple samples are shown within this photo.
Samples 9/10 A,B,C,D,E (Blue Cove Molding/Tan Mastic) are marked with a red arrow. Sample 4A-G
(White Dotted Texture Ceiling Tile) is marked with a blue arrow. Sample 3A,B,C (White Dotted w/ short squiggles Ceiling Tile) is marked with a light blue arrow.
This is above the panel ceiling on the interior of the building in the main cubicle area. Sample 11A,B,C
(Caulk Coating on Pipe Above Ceiling in Front of Ladies Room) was positive, 10% Chrysotile marked with a red arrow.
This is the break room/kitchen of the building. In this room there is a fridge and stove used by the employees. Sample 30/31/32/33A,B,C were all taken in this room marked with a red arrow. All the samples came back positive for ACM. Sample 30C (Black VCT Tile), 4% Chrysotile. Sample 31C (Black
Mastic), 10% Chrysotile. Sample 32C (Off White VCT Tile), 6% Chrysotile. 33C (Brown Mastic), 5%
Chrysotile.
This photo was taken in the boiler room. Samples 17A,B,C (TSI MUD ENDS) are shown and marked with a red arrow.
APPENDIX B
Asbestos Identification Laboratory.
165 New Boston St., Ste 227
Woburn, MA 01801 781-932-9600
Web: www.asbestosidentificationlab.com Email:
mikemanning@asbestosidentificationlab.com
Batch: 107455
Dear Alan Sundquist, Thank you Alan Sundquist for your business.
Michael Manning Owner/Director
Asbestos Identification Laboratory has completed the analysis of the samples from your office for the above referenced project.
The Analysis Method is BULK PLM ANALYSIS, EPA/600/R-93/116The information and analysis contained in this report have been generated using the EPA /600/R-93/116 Method for the Determination of Asbestos in Bulk Building Materials. Materials or products that contain more than 1% of any kind or combination of asbestos are considered an asbestos containing building material as determined by the EPA. This Polarized Light Microscope (PLM) technique may be performed either by visual estimation or point counting. Point counting provides a determination of the area percentage of asbestos in a sample. If the asbestos is estimated to be less than 10% by visual estimation of friable material, the determination may be repeated using the point counting technique. The results of the point counting supersede visual PLM results. Results in this report only relate to the items tested. This report may not be used by the customer to claim product endorsement by NVLAP or any other U.S.
Government Agency.
Alan Sundquist CDW Consultants, Inc.
6 Huron Drive Natick, MA 01760
Project Information
#2105
Hanscom (Building #1825)
Method: BULK PLM ANALYSIS, EPA/600/R-93/116
• NVLAP Lab Code: 200919-0
• Massachusetts Certification License: AA000208
• State of Connecticut, Department of Public Health Approved Environmental Laboratory Registration Number: PH-0142
• State of Maine, Department of Environmental Protection Asbestos Analytical Laboratory License Number: LB-0078(Bulk) LA-0087(Air)
• State of Rhode Island and Providence Plantations. Department of Health Certification: AAL-121
• State of Vermont, Department of Health Environmental Health License AL934461
Laboratory results represent the analysis of samples as submitted by the customer. Information regarding sample location, description, area, volume, etc., was provided by the customer. Information provided by the customer can affect the validity of results. Asbestos Identification Laboratory is not responsible for sample collection activities or analytical method limitations.
Unless notified in writing to return samples, Asbestos Identification Laboratory discards customer samples after 30 days.
Samples containing subsamples or layers will be analyzed separately when applicable. Reports are kept at Asbestos Identification Laboratory for three years. All customer information will be maintained in confidentiality. This report shall not be reproduced, except in full, without the written consent of Asbestos Identification Laboratory.
Alan Sundquist CDW Consultants, Inc.
6 Huron Drive Natick, MA 01760
Project Information
#2105
Hanscom (Building #1825)
Method: BULK PLM ANALYSIS, EPA/600/R-93/116
Asbestos %Material Color Non-Asbestos %LocationFieldID
LabID tan Fiberglass 40
Mineral Wool 10 Cellulose 40 Non-Fibrous 101175491
1A Womens BathroomWhite Dotted w/ Bubbles
CT
None Detected tan Fiberglass 40 Mineral Wool 10 Cellulose 40 Non-Fibrous 101175492
1B Womens BathroomWhite Dotted w/ Bubbles
CT
None Detected tan Fiberglass 40 Mineral Wool 10 Cellulose 40 Non-Fibrous 101175493
1C Womens BathroomWhite Dotted w/ Bubbles
CT
None Detected tan Fiberglass 30 Cellulose 55 Non-Fibrous 151175494
2A Cubicle Area (Main Room)White Dotted w/ Long Squiggles CT
None Detected tan Fiberglass 30 Cellulose 55 Non-Fibrous 151175495
2B Cubicle Area (Main Room)White Dotted w/ Long Squiggles CT
None Detected tan Fiberglass 30 Cellulose 55 Non-Fibrous 151175496
2C Cubicle Area (Main Room)White Dotted w/ Long Squiggles CT
None Detected tan Fiberglass 30 Cellulose 55 Non-Fibrous 151175497
3A Cubicle Area (Main Room)White Dotted w/ Short Squiggles CT
None Detected tan Fiberglass 30 Cellulose 55 Non-Fibrous 151175498
3B Cubicle Area (Main Room)White Dotted w/ Short Squiggles CT
None Detected tan Fiberglass 30 Cellulose 55 Non-Fibrous 151175499
3C Cubicle Area (Main Room)White Dotted w/ Short Squiggles CT
None Detected gray Fiberglass 35 Mineral Wool 10 Cellulose 45 Non-Fibrous 101175500
4A Throughout Building (Cubicle Area, Break Room, Hallways, Main Entrance)
White Dotted Texture CT None Detected gray Fiberglass 35 Mineral Wool 10 Cellulose 45 Non-Fibrous 101175501
4B Throughout Building (Cubicle Area, Break Room, Hallways, Main Entrance)
White Dotted Texture CT None Detected gray Fiberglass 35 Mineral Wool 10 Cellulose 45 Non-Fibrous 101175502
4C Throughout Building (Cubicle Area, Break Room, Hallways, Main Entrance)
White Dotted Texture CT None Detected gray Fiberglass 35 Mineral Wool 10 Cellulose 45 Non-Fibrous 101175503
4D Throughout Building (Cubicle Area, Break Room, Hallways, Main Entrance)
White Dotted Texture CT None Detected
Sampled: Received: November 17, 2023November 15, 2023 Analyzed:November 09, 2023
Analyzed by: 107455Batch:
Monday 20 November 2023
6 Huron Drive Natick, MA 01760
Project Information
#2105
Hanscom (Building #1825)
Method: BULK PLM ANALYSIS, EPA/600/R-93/116
Asbestos %Material Color Non-Asbestos %LocationFieldID
LabID gray Fiberglass 35
Mineral Wool 10 Cellulose 45 Non-Fibrous 101175504
4E Throughout Building (Cubicle Area, Break Room, Hallways, Main Entrance)
White Dotted Texture CT None Detected gray Fiberglass 35 Mineral Wool 10 Cellulose 45 Non-Fibrous 101175505
4F Throughout Building (Cubicle Area, Break Room, Hallways, Main Entrance)
White Dotted Texture CT None Detected gray Fiberglass 35 Mineral Wool 10 Cellulose 45 Non-Fibrous 101175506
4G Throughout Building (Cubicle Area, Break Room, Hallways, Main Entrance)
White Dotted Texture CT None Detected tan Cellulose 95 Non-Fibrous 5
1175507
5A Above Ceiling (Main Room)12"x12" Off White Dotted
CT
None Detected tan Cellulose 95 Non-Fibrous 5
1175508
5B Above Ceiling (Main Room)12"x12" Off White Dotted
CT
None Detected tan Cellulose 95 Non-Fibrous 5
1175509
5C Above Ceiling (Main Room)12"x12" Off White Dotted
CT
None Detected brown Non-Fibrous 100
1175510
6A Above Ceiling (Main Room)Glue Daubs Behind 12"x12" CT
None Detected brown Non-Fibrous 100
1175511
6B Above Ceiling (Main Room)Glue Daubs Behind 12"x12" CT
None Detected brown Non-Fibrous 100
1175512
6C Above Ceiling (Main Room)Glue Daubs Behind 12"x12" CT
None Detected gray Non-Fibrous 100
1175513
7A Bathrooms/Break RoomGray Cove Molding None Detected gray Non-Fibrous 100
1175514
7B Bathrooms/Break RoomGray Cove Molding None Detected gray Non-Fibrous 100
1175515
7C Bathrooms/Break RoomGray Cove Molding None Detected tan Non-Fibrous 100
1175516
8A Bathrooms/Break RoomTan Mastic Behind Gray Cove
None Detected tan Non-Fibrous 100
1175517
8B Bathrooms/Break RoomTan Mastic Behind Gray Cove
None Detected tan Non-Fibrous 100
1175518
8C Bathrooms/Break RoomTan Mastic Behind Gray Cove
None Detected
Sampled: Received: November 17, 2023November 15, 2023 Analyzed:November 09, 2023
Analyzed by: 107455Batch:
6 Huron Drive Natick, MA 01760
Project Information
#2105
Hanscom (Building #1825)
Method: BULK PLM ANALYSIS, EPA/600/R-93/116
Asbestos %Material Color Non-Asbestos %LocationFieldID
LabID blue Non-Fibrous 100
1175519
9A Throughout Building (By Doors, Hallways, Break Room, Cubicle Area)
Blue Cove Molding None Detected blue Non-Fibrous 100
1175520
9B Throughout Building (By Doors, Hallways, Break Room, Cubicle Area)
Blue Cove Molding None Detected blue Non-Fibrous 100
1175521
9C Throughout Building (By Doors, Hallways, Break Room, Cubicle Area)
Blue Cove Molding None Detected blue Non-Fibrous 100
1175522
9D Throughout Building (By Doors, Hallways, Break Room, Cubicle Area)
Blue Cove Molding None Detected blue Non-Fibrous 100
1175523
9E Throughout Building (By Doors, Hallways, Break Room, Cubicle Area)
Blue Cove Molding None Detected tan Non-Fibrous 100
1175524
10A Throughout Building (By Doors, Hallways, Break Room, Cubicle Area)
Tan Mastic Behind Blue Cove
None Detected tan Non-Fibrous 100
1175525
10B Throughout Building (By Doors, Hallways, Break Room, Cubicle Area)
Tan Mastic Behind Blue Cove
None Detected tan Non-Fibrous 100
1175526
10C Throughout Building (By Doors, Hallways, Break Room, Cubicle Area)
Tan Mastic Behind Blue Cove
None Detected tan Non-Fibrous 100
1175527
10D Throughout Building (By Doors, Hallways, Break Room, Cubicle Area)
Tan Mastic Behind Blue Cove
None Detected tan Non-Fibrous 100
1175528
10E Throughout Building (By Doors, Hallways, Break Room, Cubicle Area)
Tan Mastic Behind Blue Cove
None Detected
Detected Chrysotile 10 multi Non-Fibrous 90
1175529
11A Above Ceiling in Front of Ladies Room
Caulk Coating on Pipe
1175530
11B Above Ceiling in Front of Ladies Room
Caulk Coating on Pipe Not Analyzed
1175531
11C Above Ceiling in Front of Ladies Room
Caulk Coating on Pipe Not Analyzed multi Non-Fibrous 100
1175532
12A by Exit Door (Northeast Door)
Glue under Carpet None Detected multi Non-Fibrous 100
1175533
12B by Exit Door (Northeast Door)
Glue under Carpet None Detected multi Non-Fibrous 100
1175534
12C by Exit Door (Northeast Door)
Glue under Carpet None Detected
Sampled: Received: November 17, 2023November 15, 2023 Analyzed:November 09, 2023
Analyzed by: 107455Batch:
6 Huron Drive Natick, MA 01760
Project Information
#2105
Hanscom (Building #1825)
Method: BULK PLM ANALYSIS, EPA/600/R-93/116
Asbestos %Material Color Non-Asbestos %LocationFieldID
LabID gray Cellulose 10
Non-Fibrous 90 1175535
13A Throughout Building (by Doors, Offices, Break Room, Cubicle Area)
Drywall None Detected gray Cellulose 10 Non-Fibrous 90
1175536
13B Throughout Building (by Doors, Offices, Break Room, Cubicle Area)
Drywall None Detected gray Cellulose 10 Non-Fibrous 90
1175537
13C Throughout Building (by Doors, Offices, Break Room, Cubicle Area)
Drywall None Detected gray Cellulose 10 Non-Fibrous 90
1175538
13D Throughout Building (by Doors, Offices, Break Room, Cubicle Area)
Drywall None Detected gray Cellulose 10 Non-Fibrous 90
1175539
13E Throughout Building (by Doors, Offices, Break Room, Cubicle Area)
Drywall None Detected gray Cellulose 10 Non-Fibrous 90
1175540
13F Throughout Building (by Doors, Offices, Break Room, Cubicle Area)
Drywall None Detected gray Cellulose 10 Non-Fibrous 90
1175541
13G Throughout Building (by Doors, Offices, Break Room, Cubicle Area)
Drywall None Detected white Non-Fibrous 100
1175542
14A Throughout Building (by Doors, Offices, Break Room, Cubicle Area)
White Wall Cover None Detected white Non-Fibrous 100
1175543
14B Throughout Building (by Doors, Offices, Break Room, Cubicle Area)
White Wall Cover None Detected white Non-Fibrous 100
1175544
14C Throughout Building (by Doors, Offices, Break Room, Cubicle Area)
White Wall Cover None Detected white Non-Fibrous 100
1175545
14D Throughout Building (by Doors, Offices, Break Room, Cubicle Area)
White Wall Cover None Detected white Non-Fibrous 100
1175546
14E Throughout Building (by Doors, Offices, Break Room, Cubicle Area)
White Wall Cover None Detected white Non-Fibrous 100
1175547
14F Throughout Building (by Doors, Offices, Break Room, Cubicle Area)
White Wall Cover None Detected white Non-Fibrous 100
1175548
14G Throughout Building (by Doors, Offices, Break Room, Cubicle Area)
White Wall Cover None Detected white Non-Fibrous 100
1175549
15A Main Entrance WayJoint Compound None Detected white Non-Fibrous 100
1175550
15B Main Entrance WayJoint Compound None Detected
Sampled: Received: November 17, 2023November 15, 2023 Analyzed:November 09, 2023
Analyzed by: 107455Batch:
6 Huron Drive Natick, MA 01760
Project Information
#2105
Hanscom (Building #1825)
Method: BULK PLM ANALYSIS, EPA/600/R-93/116
Asbestos %Material Color Non-Asbestos %LocationFieldID
LabID white Non-Fibrous 100
1175551
15C Main Entrance WayJoint Compound None Detected gray Non-Fibrous 100
1175552
16A Boiler RoomGray Sealant on Vents None Detected gray Non-Fibrous 100
1175553
16B Boiler RoomGray Sealant on Vents None Detected gray Non-Fibrous 100
1175554
16C Boiler RoomGray Sealant on Vents None Detected multi Fiberglass 30 Non-Fibrous 70
1175555
17A Boiler RoomTSI MUD ENDS None Detected multi Fiberglass 30 Non-Fibrous 70
1175556
17B Boiler RoomTSI MUD ENDS None Detected multi Fiberglass 30 Non-Fibrous 70
1175557
17C Boiler RoomTSI MUD ENDS None Detected gray Non-Fibrous 100
1175558
18A Front Side of BuildingStucco None Detected gray Non-Fibrous 100
1175559
18B Front Side of BuildingStucco None Detected gray Non-Fibrous 100
1175560
18C Front Side of BuildingStucco None Detected gray Non-Fibrous 100
1175561
19A Front Side of BuildingGray Mastic None Detected gray Non-Fibrous 100
1175562
19B Front Side of BuildingGray Mastic None Detected gray Non-Fibrous 100
1175563
19C Front Side of BuildingGray Mastic None Detected black Non-Fibrous 100
1175564
20A Main Entrance DoorExt Door Caulk None Detected black Non-Fibrous 100
1175565
20B Main Entrance DoorExt Door Caulk None Detected black Non-Fibrous 100
1175566
20C Main Entrance DoorExt Door Caulk None Detected brown Non-Fibrous 100
1175567
21A Front/Back of Right Side Building
Ext Caulk on top of Brick None Detected
Sampled: Received: November 17, 2023November 15, 2023 Analyzed:November 09, 2023
Analyzed by: 107455Batch:
6 Huron Drive Natick, MA 01760
Project Information
#2105
Hanscom (Building #1825)
Method: BULK PLM ANALYSIS, EPA/600/R-93/116
Asbestos %Material Color Non-Asbestos %LocationFieldID
LabID brown Non-Fibrous 100
1175568
21B Front/Back of Right Side Building
Ext Caulk on top of Brick None Detected brown Non-Fibrous 100
1175569
21C Front/Back of Right Side Building
Ext Caulk on top of Brick None Detected black Non-Fibrous 100
1175570
22A Front/Back of BuildingExt Window Glaze None Detected black Non-Fibrous 100
1175571
22B Front/Back of BuildingExt Window Glaze None Detected black Non-Fibrous 100
1175572
22C Front/Back of BuildingExt Window Glaze None Detected gray Non-Fibrous 100
1175573
23A Front/Back of Building, Right Side
Ext Window Caulk None Detected gray Non-Fibrous 100
1175574
23B Front/Back of Building, Right Side
Ext Window Caulk None Detected gray Non-Fibrous 100
1175575
23C Front/Back of Building, Right Side
Ext Window Caulk None Detected brown Non-Fibrous 100
1175576
24A Left Side of BuildingExt Caulk on top of Brick None Detected brown Non-Fibrous 100
1175577
24B Left Side of BuildingExt Caulk on top of Brick None Detected brown Non-Fibrous 100
1175578
24C Left Side of BuildingExt Caulk on top of Brick None Detected brown Non-Fibrous 100
1175579
25A Left Side of BuildingExt Window Caulk None Detected brown Non-Fibrous 100
1175580
25B Left Side of BuildingExt Window Caulk None Detected brown Non-Fibrous 100
1175581
25C Left Side of BuildingExt Window Caulk None Detected white Non-Fibrous 100
1175582
26A Womens BathroomWhite VCT Tile None Detected white Non-Fibrous 100
1175583
26B Womens BathroomWhite VCT Tile None Detected white Non-Fibrous 100
1175584
26C Womens BathroomWhite VCT Tile None Detected
Sampled: Received: November 17, 2023November 15, 2023 Analyzed:November 09, 2023
Analyzed by: 107455Batch:
6 Huron Drive Natick, MA 01760
Project Information
#2105
Hanscom (Building #1825)
Method: BULK PLM ANALYSIS, EPA/600/R-93/116
Asbestos %Material Color Non-Asbestos %LocationFieldID
LabID tan Non-Fibrous 100
1175585
27A Womens RoomTan Mastic under White
VCT
None Detected tan Non-Fibrous 100
1175586
27B Womens RoomTan Mastic under White
VCT
None Detected tan Non-Fibrous 100
1175587
27C Womens RoomTan Mastic under White
VCT
None Detected white Non-Fibrous 100
1175588
28A Mens BathroomWhite VCT Tile None Detected white Non-Fibrous 100
1175589
28B Mens BathroomWhite VCT Tile None Detected white Non-Fibrous 100
1175590
28C Mens BathroomWhite VCT Tile None Detected tan Non-Fibrous 100
1175591
29A Mens RoomTan Mastic under White
VCT
None Detected tan Non-Fibrous 100
1175592
29B Mens RoomTan Mastic under White
VCT
None Detected tan Non-Fibrous 100
1175593
29C Mens RoomTan Mastic under White
VCT
None Detected
Detected Chrysotile 4 black Non-Fibrous 96
1175594
30A (Top Layer) Break Room (Kitchen)
Black VCT Tile
1175595
30B (Top Layer) Break Room (Kitchen)
Black VCT Tile Not Analyzed
1175596
30C (Top Layer) Break Room (Kitchen)
Black VCT Tile Not Analyzed
Detected Chrysotile 10 black Non-Fibrous 90
1175597
31A Break Room (Kitchen)Black Mastic
1175598
31B Break Room (Kitchen)Black Mastic Not Analyzed
1175599
31C Break Room (Kitchen)Black Mastic Not Analyzed
Detected Chrysotile 6 tan Non-Fibrous 94
1175600
32A (Bottom Layer) Break Room (Kitchen)
Off White VCT Tile
1175601
32B (Bottom Layer) Break Room (Kitchen)
Off White VCT Tile Not Analyzed
Sampled: Received: November 17, 2023November 15, 2023 Analyzed:November 09, 2023
Analyzed by: 107455Batch:
6 Huron Drive Natick, MA 01760
Project Information
#2105
Hanscom (Building #1825)
Method: BULK PLM ANALYSIS, EPA/600/R-93/116
Asbestos %Material Color Non-Asbestos %LocationFieldID
LabID
1175602
32C (Bottom Layer) Break Room (Kitchen)
Off White VCT Tile Not Analyzed
Detected Chrysotile 5 black Non-Fibrous 95
1175603
33A Break Room (Kitchen)Brown Mastic
1175604
33B Break Room (Kitchen)Brown Mastic Not Analyzed
1175605
33C Break Room (Kitchen)Brown Mastic Not Analyzed gray Cellulose 10 Non-Fibrous 90
1175606
34A AtticSheetrock None Detected gray Cellulose 10 Non-Fibrous 90
1175607
34B AtticSheetrock None Detected gray Cellulose 10 Non-Fibrous 90
1175608
34C AtticSheetrock None Detected white Non-Fibrous 100
1175609
35A AtticJoint Compound None Detected white Non-Fibrous 100
1175610
35B AtticJoint Compound None Detected white Non-Fibrous 100
1175611
35C AtticJoint Compound None Detected multi Non-Fibrous 100
1175612
36A Right Side of BuildingWall Cover (Exterior) None Detected multi Non-Fibrous 100
1175613
36B Right Side of BuildingWall Cover (Exterior) None Detected multi Non-Fibrous 100
1175614
36C Right Side of BuildingWall Cover (Exterior) None Detected black Fiberglass 35 Non-Fibrous 65
1175615
37A RoofNew Shingle None Detected black Fiberglass 35 Non-Fibrous 65
1175616
37B RoofNew Shingle None Detected black Fiberglass 35 Non-Fibrous 65
1175617
37C RoofNew Shingle None Detected black Cellulose 80 Non-Fibrous 20
1175618
38A RoofRoof Underlayment None Detected
Sampled: Received: November 17, 2023November 15, 2023 Analyzed:November 09, 2023
Analyzed by: 107455Batch:
6 Huron Drive Natick, MA 01760
Project Information
#2105
Hanscom (Building #1825)
Method: BULK PLM ANALYSIS, EPA/600/R-93/116
Asbestos %Material Color Non-Asbestos %LocationFieldID
LabID black Cellulose 80
Non-Fibrous 20 1175619
38B RoofRoof Underlayment None Detected black Cellulose 80 Non-Fibrous 20
1175620
38C RoofRoof Underlayment None Detected black Fiberglass 35 Non-Fibrous 65
1175621
39A RoofOld Shingle None Detected black Fiberglass 35 Non-Fibrous 65
1175622
39B RoofOld Shingle None Detected black Fiberglass 35 Non-Fibrous 65
1175623
39C RoofOld Shingle None Detected black Cellulose 60 Non-Fibrous 40
1175624
Roof Core 1A Top LayerOld Tar/Roof None Detected tan Non-Fibrous 100
1175625
Roof Core 1B Middle LayerOld Tar/Gravel Roof None Detected black Cellulose 60 Non-Fibrous 40
1175626
Roof Core 1C Top of DeckTar Old Roof None Detected
Sampled: Received: November 17, 2023November 15, 2023 Analyzed:November 09, 2023
Analyzed by: 107455Batch:
APPENDIX C
APPENDIX D
APPENDIX E
Material
Description
Location
Est.
Units
Unit Cost
Total Cost
Caulk Coating on Pipe at
Connections
Above Ceiling in Front of Ladies
Room
25 EA $50 $1,250
Black Vinyl Floor Tile
(Top Layer) Break Room (Kitchen)
330 SF $6 $1,980
Black Mastic Break Room (Kitchen)
330 SF $6 $1,980
Off White Vinyl Floor Tile
(Bottom Layer) Break Room
(Kitchen)
330 SF $6 $1,980
Brown Mastic Break Room (Kitchen)
330 SF $6 $1,980
Remnant Pipe Insulation and
Fittings
(PACM)
Fixed Walls, Unknown Trenches
500 LF $20 $10,000
Total $19,170
Location Est.
Quantity
Units Unit Cost Total
Fluorescent Bulbs (Mercury)
Throughout 40 (4’ Tubes)
EA $1 $40
Electronic Ballasts Throughout 40 EA $25 $1,000
Exterior Lights Exterior Walls 5 EA $25 $125
Fluorescent Bulbs Throughout 5 EA $1 $5
Thermostats (Mercury)
Throughout 4 EA $25 $100
Exit Signs (Tritium)
Throughout 3 EA $25 $75
Location Est.
Quantity
Units Unit Cost Total
Emergency Lights (Batteries)
Throughout 10 EA $25 $250
Fire Alarms Throughout 5 EA $25 $125
Smoke/Heat Detectors (Americium)
Throughout 15 EA $35 $525
Refrigerants Air Compressor/Air Conditioner
1 EA $1,500 $1,500
1,000-Gallon Fuel Oil UST and Piping
Exterior 1 EA $20,000 $20,000
Pad Mounted Transformer
Exterior, Labeled as <50 ppm PCBs
1 EA $5,000 $5,000
Total $28,745