This document is a Statement of Work (SOW) for the demolition of Buildings 1825 and 1839 at Hanscom Air Force Base in Massachusetts. The scope of work includes comprehensive demolition activities such as hazardous materials abatement, complete removal of buildings including foundations and subsurface elements, utility disconnection, and site restoration. Specific tasks involve removing water pipes, sewer lines, electrical infrastructure, hydrants, manholes, and a geothermal well, with all demolition waste to be properly disposed of off-base.

The project requires detailed site restoration, including patching damaged asphalt pavements, ensuring proper grading to prevent water ponding, installing vertical granite curbs and concrete sidewalks, providing clean fill to meet specified grades, and applying 6 inches of topsoil with seeding in disturbed areas. Additional requirements include salvaging specified building components and disposing of all construction debris in compliance with applicable laws and regulations. The work is to be executed in accordance with project plans and industry standards, focusing on complete site clearance and preparation for future use.

View the file

Other files

Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MXRD

Statement of Work

1. SCOPE OF WORK

The following items of work are included in this task order more detailed information.

1.1 Demolish B1825 and B1839 – work includes the removal and proper disposal of all hazardous materials and complete removal of the building and all subsurface foundations.

1.1.1 Hazardous Materials Abatement

Abatement and proper disposal of hazardous materials

1.1.2 Facility Demolition

Remove the facility in its entirety to include all building elements below grade. All demolition waste shall be properly disposed of off base.

1.2 Site Demolition

1.2.1 Remove all pavements and curbing within the limits of work as shown on project plans. This work is to include the section of driveway along building and the parking area at the front of the building.

1.2.2 Removal of Geothermal Well

1.2.3 Loam and seed areas where pavement was removed.

1.3 Utility Demolition – Remove all utilities providing service to B1825 within the limits of work as shown on project plans. Unless otherwise specified all utilities shall be cut and capped in accordance with industry standards.

1.3.1 Water, Sewer and Storm Drainage: Excavate, stockpile and remove & properly dispose of up to 6” of base material. Backfill with appropriate material to grade.

Water:

1.3.1.1 Remove 6-inch ductile iron pipe.

1.3.1.1.2 Pipe shall be removed to the water main and properly capped.

1.3.1.2 Remove water gate valves within limits of work.

1.3.1.3 Remove hydrants and associated piping within limits of work.

Sewer:

1.3.2.4 Remove 6” clay pipe to nearest manhole as noted on plan.

1.3.2.5 Remove sewer manholes within limits of work.

1.3.2 Electrical

1.3.3.1 De-energize the connection at MH-9G-4E.

1.3.3.2 Remove Transformer, located west side of building 1825, drain and remove fluids including PCBs, and pull wires back to Manhole MH-9G-4E. Demolish the conduit in

MXRD

Statement of Work this area.

1.4 Site Restoration – Patch all asphalt pavements damaged as a result of demolition or as shown on the project plans. Ensure proper grading so that there is no ponding of water. Install vertical granite curb and concrete sidewalks as shown. Provide sufficient clean fill to meet the grades and elevations shown. Provide 6” of topsoil and seed all disturbed areas within the limits of work.

1.1.1. Abatement and proper disposal of hazardous materials

1.1.2. Complete demolition of Building 1825 and Building 1839 to include foundations and footings

1.1.3. Removal of utilities serving Building 1825 and Building 1839 as shown on the project plans

1.1.4. Removal of Geothermal Well

1.1.5. Removal of site improvements as noted on the project plans

1.1.6. Restoration of the site as shown on the project plans

1.1.7. Salvage of building components as indicated in Section 5.2

1.1.8. All construction debris shall be properly disposed of off base in accordance with all applicable laws and regulations

END OF DOCUMENT