Attachment 5 - Schedule of material submittals.pdf

PDF 89 KB Posted

Attached to
Busway Install Building 2265 Federal contract opportunity
Solicitation number
FA301620R0092
Issued by
Department of the Air Force Air Education and Training Command

View the file

Other files for this federal contract opportunity

Other files attached to Busway Install Building 2265, newest first.
File Type Posted
FA301620R0092 Busway Install B2265 Questions_Answers Rev10Sep2020.docx DOCX document
Questions_Answers FA301620R0092 Busway Install B2265.pdf PDF
Attachment 4 - Wage determination TX20200231 Rev28Aug2020.pdf PDF
Amendment 0004 FA301620R00920004.pdf PDF
Attachment 10 - Section L Rev09Sep2020.pdf PDF
Attachment 13 - One Line Diagram_UPS_Room 20.pdf PDF
Attachment 12 - Electrical Riser_Architectural Drawing.pdf PDF
Attachment 1 - Statement of work_rev08Sep2020.pdf PDF
FA301620R00920003.pdf PDF
Attachment 10 - Section L Rev18Aug2020.pdf PDF
Solicitation Amendment 002 FA301620R00920002.pdf PDF
Solicitation Amendment 001 FA301620R00920001.pdf PDF
Attachment 10 - Section L.pdf PDF
Attachment 4 - Wage determination TX20200231.pdf PDF
Attachment 2 - Concept Plans.pdf PDF
Attachment 3 - Weather Data.pdf PDF
FA301620R0092.pdf PDF
Single Source Justification (Brand Name) - Starline Track Busway System -R_Redacted.pdf PDF
Attachment 9 - Construction Cost Estimate Breakdown.xls XLS spreadsheet
Attachment 7 - Lead and asbestos Report.pdf PDF
Attachment 11 - Section M.pdf PDF
Attachment 1 - Statement of work.pdf PDF
Attachment 6 - DD1354.pdf PDF
Attachment 8 - Access Request Form.pdf PDF
Show all 24

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 1 OF 7 PAGES

Busway Install B2265

01 11 00.10 SD-01 Preconstruction Submittals

Salvage Plan

01 14 00 SD-01 Preconstruction Submittals

1.4.1.1 Glist of Contract Personnel

1.4.1.2Installation Access

01 30 00 SD-01 Preconstruction Submittals

1.3 GView Location Map

1.4 GProgress and Completion

Pictures

01 32 01.00 10 SD-01 Preconstruction Submittals

GProject Schedule CPM

01 32 16.00 20 SD-01 Preconstruction Submittals

1.2 GBaseline Construction Schedule

1.2 GBaseline Design Schedule

SD-07 Certificates

1.4Monthly Updates

01 33 00 SD-01 Preconstruction Submittals

1.7 GSubmittal Register

01 33 16.00 10 SD-01 Preconstruction Submittals

1.4.1 GDesign Quality Control Plan

1.4.2.2Initial Design Conference

1.4.2.3Preconstruction Conference

3.4.1 GDCM Procedures

3.7.4 GSubmittal Register

SD-05 Design Data

1.6.1 CDesign and Code Checklists

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P H

C L A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 2 OF 7 PAGES

01 33 16.00 10 2.3 CSustainable Design

3.2.1 RInterim Design Submittals

3.5.6.1.1 GInterior And Exterior Building

Finishes Scheme

3.5.6.2.3 GFurniture, Fixtures & Equipment

3.6.3Conference Documentation

3.7 RFinal Design Submittals

3.8 CDesign Complete Documents

SD-11 Closeout Submittals

3.7.5 GDD Form 1354

01 33 29 SD-01 Preconstruction Submittals

1.5.3.1 GPreliminary High Performance

and Sustainable Building Checklist

1.4.1 GSustainability Action Plan

1.5.3.1 GPreliminary Sustainability

eNotebook

SD-11 Closeout Submittals

1.5.3.1 GFinal High Performance and

Sustainable Building Checklist

1.5.3.1 GFinal Sustainability eNotebook

1.5.3.1 GAmended Final Sustainability

eNotebook

1.5.3.1 GAmended Final High

Performance and Sustainable

Building Checklist

01 35 26 SD-01 Preconstruction Submittals

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 3 OF 7 PAGES

01 35 26 1.6 GAccident Prevention Plan (APP)

SD-06 Test Reports

1.11Notifications and Reports

1.11.2 GAccident Reports

LHE Inspection Reports

SD-07 Certificates

1.5.1.3Crane Operators/Riggers

GStandard Lift Plan

GCritical Lift Plan

GNaval Architecture Analysis

1.7Activity Hazard Analysis (AHA)

1.8.1Confined Space Entry Permit

1.8.1Hot Work Permit

Certificate of Compliance

License Certificates

01 45 00.00 10 SD-01 Preconstruction Submittals

3.2 GContractor Quality Control (CQC)

Plan

3.2.2 GAdditional Requirements for

Design Quality Control (DQC) Plan

SD-05 Design Data

3.2.2Discipline-Specific Checklists

3.8.1Design Quality Control

SD-06 Test Reports

3.8.2Verification Statement

01 57 20 SD-01 Preconstruction Submittals

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 4 OF 7 PAGES

01 57 20 3.11.1.4 GAsbestos Hazard Abatement Plan

GAsbestos Certifications

GAsbestos Transporter License

GAsbestos Medical clearances

(may be reviewed on site)

GAsbestos Training Certificates

GAsbestos TDSHS License as applicable

1.6 GEnvironmental Protection Plan

3.16 GEnvironmental Protection Plan

3.1.7 GFish and Wildlife

1.5.1 GEnvironmental Permits

3.7.2Equipment Inventory

SD-06 Test Reports

GAny Asbestos Inspection reports that have not been provided by the area specific Environmental Office.

Any Asbestos Inspection Reports that were not included in the original assessment or a results to a change in the scope of work.

G Unsigned copy of State

Renovation, Demolition

Notifications 15 days prior; G

GLead Work Plans

GLead Occupant Protection Plan.

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 5 OF 7 PAGES

01 57 20 GTexas Department of State

Health Services Lead Licenses

GLead Notifications

GLead Training Certificates

GLead Based Paint Reports

GLead Inspection reports

SD-03 Product Data

GAsbestos Air Monitoring reports

GLead Air Monitoring reports

SD-04 Samples

GLead OSHA Negative Exposure

Assessment or

GLead Work Plan.

EPA Lead Training

GLead Awareness Training certificates

GOSHA Air Monitoring

GLead Training Certificates

GWaste Disposal Plan, May be included in work plan

GLead Inspection reports

GLead Based Paint Reports

SD-06 Test Reports

3.1.4.1 GAnalytical Results

01 74 19 SD-01 Preconstruction Submittals

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 6 OF 7 PAGES

01 74 19 1.6 GIntegrated Solid Waste

Management Plan

SD-06 Test Reports

Quarterly Reports

Annual Report

SD-11 Closeout Submittals

1.9 SFinal Construction Waste

Diversion Report

01 78 00 SD-03 Product Data

1.4.1Warranty Management Plan

1.4.3Warranty Tags

Spare Parts Data

SD-08 Manufacturer’s Instructions

1.4.1Instructions

SD-10 Operation and Maintenance

Data

3.2 GOperation and Maintenance

Manuals

SD-11 Closeout Submittals

3.1 GAs-Built Drawings

GRecord Drawings

1.4.1As-Built Record of Equipment and Materials

Final Approved Shop Drawings

Construction Contract

Specifications

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 7 OF 7 PAGES

01 78 00 2.1 GCertification of EPA Designated

Items

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR