Attachment 5 - Past Performance Questionnaire.docx
DOCX document 153 KB Posted
- Attached to
- FBI Crime Scene Management Vehicles - Updated
- Solicitation number
- 15F06726Q0000291
About this file
This is a Past Performance Questionnaire template used by the Federal Bureau of Investigation to evaluate contractor performance on past relevant contracts. The questionnaire is intended for references to complete and submit regarding an offeror's prior experience with similar work, specifically in support of the FBI's procurement of ten Crime Scene Management Vehicles (Solicitation Number 15F06726Q0000291). References must submit completed forms directly to Contracting Specialist Jamie Compton at jlmelzer@fbi.gov and Contracting Officer Maureen Murdock at mmurdock@fbi.gov, with the email subject line formatted to include the solicitation number and evaluated company name.
The questionnaire requires references to provide detailed project identification information including the contractor name, contract or order number, project title, period of performance, and reference contact details. References are then asked to rate the contractor's performance across six evaluation criteria—Quality of Service, Schedule, Cost Control, Business Relations, Management of Key Personnel, and Utilization of Small Business—using a five-point adjectival rating scale (Exceptional, Very Good, Satisfactory, Marginal, or Unsatisfactory, with a Not Applicable option for Cost Control). Each rating category includes detailed definitions to guide consistent evaluation. At minimum, any Marginal or Unsatisfactory ratings must be supported by additional substantiating comments. The questionnaire concludes with an open-ended question asking whether the reference would have reservations about soliciting the contractor for future critical and demanding programs.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FEDERAL BUREAU OF INVESTIGATION
FINANCE AND FACILITIES DIVISION | PROCUREMENT SECTION
PAST PERFORMANCE QUESTIONNAIRE
To Whom It May Concern:
The Federal Bureau of Investigation intends to acquire ten (10) Crime Scene Management Vehicles.
In order to accurately evaluate an Offerors past performance, your assistance is requested in obtaining and verifying its relevant past performance history on the attached Past Performance Rating Form. Please note that the Offeror was directed to submit to you a copy of the Experience Narrative for your contract that it submitted as part of its proposal.
Upon completion of this form, please e-mail it directly to the Contracting Specialist, Jamie Compton at jlmelzer@fbi.gov and Maureen Murdock at mmurdock@fbi.gov
Please make the subject line of the e-mail read 15F06726Q0000291 – Crime Scene Management Vehicles PPQ
– Past Performance Questionnaire – Insert Evaluated Company’s Name.”
The following standards will be used in arriving at the rating:
| Outstanding | The Contractor’s performance exceeded customer expectations and was technically acceptable, providing significant features or benefits. |
| Satisfactory | The Contractor met customer expectations or contract requirements and demonstrated an acceptable understanding of the requirements. |
Unsatisfactory The Contractor’s performance was either marginal or did not meet customer expectations or contract requirements.
Other If the element is not applicable, indicate with “N/A.” If no data has been obtained or additional comments are provided, please note in this column.
PAST PERFORMANCE PROJECT IDENTIFICATON
CONTRACTOR NAME:
CONTRACT or ORDER NUMBER:
| PROJECT TITLE: |
| Click here to enter text. |
| TOTAL PERIOD OF PERFORMANCE, INCLUDING OPTIONS |
| Click here to enter text. |
PAST PERFORMANCE REFERENCE INFORMATION
| NAME: |
| Click here to enter text. |
| TITLE: |
| Click here to enter text. |
| AGENCY or CUSTOMER: |
| Click here to enter text. |
| PHONE: |
| Click here to enter text. |
| Click here to enter text. |
DESCRIPTION OF SERIVICES PROVIDED:
Click here to enter text.
For each of the Six (6) criteria listed below, the rater must choose One (1) Adjectival Rating by checking the box, as applicable. At a minimum, for any rating that is checked Marginal or Unsatisfactory, please submit additional comments to substantiate the rating. If Cost Control is N/A, Please explain why.
1. QUALITY OF SERVICE
| RATING |
| Adjectival Rating |
| Definition |
Exceptional Performance meets contractual requirements and exceeds many to the Government’s benefit. The element being assessed was accomplished with few minor problems for which corrective actions taken by the Contractor were highly effective
Very Good Performance meets contractual requirements and exceeds some to the Government’s benefit. The element being assessed was accomplished with some minor problems for which corrective actions taken by the Contractor were effective
Satisfactory Performance meets contractual requirements. The element being assessed contains some minor problems for which corrective actions taken by the Contractor appear or were satisfactory
Marginal Performance does not meet some contractual requirements. The element being assessed reflects a serious problem for which the Contractor has not yet identified corrective actions.
Unsatisfactory Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The element being assessed contains a serious problem(s) for which the Contractor’s corrective actions appear or were ineffective.
ADDITIONAL COMMENTS:
Click here to enter text.
2. SCHEDULE
| RATING |
| Adjectival Rating |
| Definition |
Performance meets contractual requirements and exceeds many to the Government’s benefit. The element being assessed was accomplished with few minor problems for which corrective actions taken by the Contractor were highly effective
Performance meets contractual requirements and exceeds some to the Government’s benefit. The element being assessed was accomplished with some minor problems for which corrective actions taken by the Contractor were effective
Performance meets contractual requirements. The element being assessed contains some minor problems for which corrective actions taken by the Contractor appear or were satisfactory
Performance does not meet some contractual requirements. The element being assessed reflects a serious problem for which the Contractor has not yet identified corrective actions.
Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The element being assessed contains a serious problem(s) for which the Contractor’s corrective actions appear or were ineffective.
Click here to enter text.
3. COST CONTROL
| RATING |
| Adjectival Rating |
| Definition |
Performance meets contractual requirements and exceeds many to the Government’s benefit. The element being assessed was accomplished with few minor problems for which corrective actions taken by the Contractor were highly effective
Performance meets contractual requirements and exceeds some to the Government’s benefit. The element being assessed was accomplished with some minor problems for which corrective actions taken by the Contractor were effective
Performance meets contractual requirements. The element being assessed contains some minor problems for which corrective actions taken by the Contractor appear or were satisfactory
Performance does not meet some contractual requirements. The element being assessed reflects a serious problem for which the Contractor has not yet identified corrective actions.
Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The element being assessed contains a serious problem(s) for which the Contractor’s corrective actions appear or were ineffective.
Not Applicable
Click here to enter text.
4. BUSINESS RELATIONS
| RATING |
| Adjectival Rating |
| Definition |
Performance meets contractual requirements and exceeds many to the Government’s benefit. The element being assessed was accomplished with few minor problems for which corrective actions taken by the Contractor were highly effective
Performance meets contractual requirements and exceeds some to the Government’s benefit. The element being assessed was accomplished with some minor problems for which corrective actions taken by the Contractor were effective
Performance meets contractual requirements. The element being assessed contains some minor problems for which corrective actions taken by the Contractor appear or were satisfactory
Performance does not meet some contractual requirements. The element being assessed reflects a serious problem for which the Contractor has not yet identified corrective actions.
Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The element being assessed contains a serious problem(s) for which the Contractor’s corrective actions appear or were ineffective.
Click here to enter text.
5. MANAGEMENT OF KEY PERSONNEL
| RATING |
| Adjectival Rating |
| Definition |
Performance meets contractual requirements and exceeds many to the Government’s benefit. The element being assessed was accomplished with few minor problems for which corrective actions taken by the Contractor were highly effective
Performance meets contractual requirements and exceeds some to the Government’s benefit. The element being assessed was accomplished with some minor problems for which corrective actions taken by the Contractor were effective
Performance meets contractual requirements. The element being assessed contains some minor problems for which corrective actions taken by the Contractor appear or were satisfactory
Performance does not meet some contractual requirements. The element being assessed reflects a serious problem for which the Contractor has not yet identified corrective actions.
Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The element being assessed contains a serious problem(s) for which the Contractor’s corrective actions appear or were ineffective.
Click here to enter text.
6. UTILIZATION OF SMALL BUSINESS
| RATING |
| Adjectival Rating |
| Definition |
Performance meets contractual requirements and exceeds many to the Government’s benefit. The element being assessed was accomplished with few minor problems for which corrective actions taken by the Contractor were highly effective
Performance meets contractual requirements and exceeds some to the Government’s benefit. The element being assessed was accomplished with some minor problems for which corrective actions taken by the Contractor were effective
Performance meets contractual requirements. The element being assessed contains some minor problems for which corrective actions taken by the Contractor appear or were satisfactory
Performance does not meet some contractual requirements. The element being assessed reflects a serious problem for which the Contractor has not yet identified corrective actions.
Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The element being assessed contains a serious problem(s) for which the Contractor’s corrective actions appear or were ineffective.
Click here to enter text.
Overall would you have any reservations about soliciting this contractor in the future or having them perform one of your critical and demanding programs? Why or why not?