Attachment 5 General Condition Breakdown.docx

DOCX document 13 KB Posted

Attached to
Z2DA--626-25-101 - Upgrade Critical Environments I
Solicitation number
36C24926R0049
Issued by

About this file

This is a General Condition Breakdown document that outlines the cost categories and line items typically required for construction project management and site preparation activities.

The document is organized into three primary cost categories: Project Management, Bonds and Insurance, and Site Conditions. The Project Management section identifies staffing requirements including superintendent(s), safety manager, CPM scheduler, quality assurance/quality control personnel, project manager(s), project executive, field office engineer, field office support staff, project expeditor, and assistant superintendent(s). The Bonds and Insurance section specifies builder's risk insurance, general liability insurance, and security, payment, and performance bonds. The Site Conditions section encompasses temporary infrastructure and support systems including power consumption, water and sewer services, electrical and telephone installations, fire protection, heating and cooling, fencing, covered walkways, stormwater pollution prevention plan (SWPPP) measures, traffic control, temporary barricades and signage, roads and walkways, lighting, partitions, sanitary facilities, laydown areas, security systems, and photographic documentation. This breakdown serves as a cost estimation template for general contracting work on the Department of Veterans Affairs' Upgrade Critical Environments I project (Z2DA--626-25-101), a pre-solicitation opportunity within Veterans Integrated Service Network 9.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Management:

Superintendent(s)

Safety Manager

CPM Scheduler

Quality Assurance/Quality Control

Project Manager (s)

Project Executive

Field Office Engineer

Field Office Support Staff

Project Expeditor

Assistant Superintendent (s)

Project Manager Subtotal

Bonds and Insurance (excluding any for Subcontractors):

Builder’s Risk Insurance

General Liability Insurance

Security, Payment & Performance Bonds

Bonds and Insurance Subtotal:

Site Conditions:

Temporary Power Consumption (Offices)

Temporary Power Consumption (General Site Use)

Temporary Water and Sewer Consumption

Temporary Water Hookup, Distribution & Meters

Temporary Electrical Hookup, Distribution & Meters

Temporary Telephone & Network System Installation

Temporary Telephone & Internet Consumption Fees

Temporary Fire Protection

Temporary Heating & Cooling

Temporary Fencing

Temporary Covered Walkways

SWPPP Measures

Temporary Entries and Truck Washes

Street Cleaning (by G.C.)

Traffic Control Measures

Temporary Barricades & Signage

Temporary Roads & Walkways (install & maintenance)

Temporary Lighting

Temporary Partitions & Covered Floor Openings

Temporary Toilets/Sanitary Measures

Temporary Laydown (prep and restoration)

Security System/Watchman

Pre-construction Photo Documentation

Progress Photos

Temporary Protection (in place work/adjacent structures)