Attachment 5 General Condition Breakdown.docx

DOCX document 13 KB Posted

Attached to
596-21-104 - AJP – Replace Deteriorated Underground Utilities - Water, Sanitary & Storm Drain Distribution (SD)
Solicitation number
36C24925R0003
Issued by

About this file

This is a general conditions breakdown template listing standard construction project overhead and management items, organized into three main categories: Project Management, Bonds and Insurance, and Site Conditions. The Project Management section includes key personnel positions like Superintendent, Safety Manager, Project Manager, and support staff. The Bonds and Insurance section covers Builder's Risk Insurance, General Liability Insurance, and Security/Payment/Performance Bonds. The Site Conditions section details temporary facilities and services including power, water, security, protection measures, and site logistics requirements.

This template is associated with VA solicitation 36C24925R0003, a $5-10 million construction project to replace underground utilities at the Lexington VA Healthcare System. The project is set aside for Service-Disabled Veteran Owned Small Businesses (SDVOSB) and will be awarded using Lowest Price Technically Acceptable (LPTA) criteria under FAR Part 15. The work involves replacing water, sanitary and storm drain distribution systems in an active medical facility environment, requiring special consideration for infection control, noise, and dust mitigation.

View the file

Other files

Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Management:

Superintendent(s)

Safety Manager

CPM Scheduler

Quality Assurance/Quality Control

Project Manager (s)

Project Executive

Field Office Engineer

Field Office Support Staff

Project Expeditor

Assistant Superintendent (s)

Project Manager Subtotal

Bonds and Insurance (excluding any for Subcontractors):

Builder’s Risk Insurance

General Liability Insurance

Security, Payment & Performance Bonds

Bonds and Insurance Subtotal:

Site Conditions:

Temporary Power Consumption (Offices)

Temporary Power Consumption (General Site Use)

Temporary Water and Sewer Consumption

Temporary Water Hookup, Distribution & Meters

Temporary Electrical Hookup, Distribution & Meters

Temporary Telephone & Network System Installation

Temporary Telephone & Internet Consumption Fees

Temporary Fire Protection

Temporary Heating & Cooling

Temporary Fencing

Temporary Covered Walkways

SWPPP Measures

Temporary Entries and Truck Washes

Street Cleaning (by G.C.)

Traffic Control Measures

Temporary Barricades & Signage

Temporary Roads & Walkways (install & maintenance)

Temporary Lighting

Temporary Partitions & Covered Floor Openings

Temporary Toilets/Sanitary Measures

Temporary Laydown (prep and restoration)

Security System/Watchman

Pre-construction Photo Documentation

Progress Photos

Temporary Protection (in place work/adjacent structures)