This is a Statement of Work (SOW) for drilling and installing a new potable water well system at Sherman Homes Vacation Cabins in Kettle Falls, Washington, located within Lake Roosevelt National Recreation Area (LARO).
The base contract scope requires the contractor to furnish all labor, materials, supervision, equipment, permits, testing, and related services to drill one potable water well (Well #1) to an estimated depth of 200-400 feet, including well casing installation, pressure grouting of the annular space, well development, submersible pump installation (0.5 HP), electrical service installation from an existing source approximately 200 linear feet to the wellhead, well disinfection, potable water testing, startup and operational verification, site restoration, and submission of as-built documentation. The work must comply with Northeast Tri County Health District regulations, Federal Safe Drinking Water Act requirements, National Electrical Code (NEC), OSHA 29 CFR 1926, EPA potable water standards, and National Park Service operational and environmental requirements. An optional second well (Well #2) with identical technical specifications may be awarded contingent upon successful performance of Well #1 and Government funding availability. All work must be completed within 60 calendar days from issuance of Notice to Proceed and include mobilization, permitting, drilling operations, electrical installation, pump installation, testing, disinfection, startup, site restoration, and final documentation. The contractor must obtain all required permits including well drilling, environmental, electrical, and utility clearances. Final acceptance occurs upon successful potable water laboratory testing (including total coliform, E. coli, nitrates/nitrites, and inorganic constituents), verification of operational systems, completion of startup testing, submission of all required documentation, approval of as-built drawings, completion of site restoration, and final Government inspection approval. If initial testing fails, the contractor must re-disinfect and repeat testing at no additional Government cost.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation (RFQ) No. 140P8326Q0046 Attachment 4 - SOW
STATEMENT OF WORK (SOW)
Drill and Install New Potable Water Well
Sherman Homes Vacation Cabins
Sherman Homes Spur Rd Kettle Falls, WA 99141 Lake Roosevelt National Recreation Area (LARO)
PART 1 – GENERAL INFORMATION
1.1 Project Title
Drilling and Installation of New Potable Water Well(s) – Sherman Homes Vacation Cabins
1.2 Project Location
Sherman Homes Vacation Cabins Sherman Homes Spur Rd Kettle Falls, WA 99141
1.3 Background
In the early 1950’s the NPS established a goal of encouraging recreational use of Lake Roosevelt National Recreation Area by authorizing leases for summer vacation cabin sites. Today eight private cabins exist at Sherman Homes with no access to potable well water.
Upon successful installation and acceptance of the new well system, potable well water will be available for these cabins in the future.
PART 2 – GENERAL
ITEM 1 – DESCRIPTION OF WORK
2.1 Objective
The Contractor shall furnish all labor, supervision, materials, tools, equipment, transportation, permits, testing, utilities, environmental protection measures, and incidentals necessary to complete the drilling, construction, testing, disinfection, electrical connection, startup, and commissioning of a new potable water well system identified as Well #1 within the project area.
The Contractor shall also provide pricing for one Optional Item for drilling and construction of a second potable water well identified as Well #2. Award of Well #2 shall be contingent upon the performance results of Well #1 and the availability of Government funding at the time of award.
All technical requirements and specifications applicable to Well #1 shall apply equally to Well #2, if the Option is exercised by the Government.
The work includes drilling and constructing a potable water well estimated between approximately 200 and 400 feet in depth, installation of a submersible pump system, electrical service installation, well development, potable water testing, disinfection, startup, restoration, and final commissioning.
All work shall comply with:
• Northeast Tri County Health District regulations
• Federal Safe Drinking Water Act requirements
• National Electrical Code (NEC)
• OSHA 29 CFR 1926
• EPA potable water standards
• State and local environmental regulations
• National Park Service operational and environmental requirements
2.2 Work Covered by Contract Documents
The Contractor shall provide all labor, materials, supervision, equipment, permits, transportation, testing, and incidentals necessary to complete the following:
Base – Well #1
• Mobilization and demobilization of drilling equipment and support vehicles
• Site access coordination and temporary site protection
• Utility locates and excavation coordination
• Drilling of one potable water well
• Installation of well casing and sanitary seal
• Pressure grouting of annular space
• Well development and cleaning
• Installation of sanitary well cap
• Installation of pitless adapter
• Furnishing and installation of one submersible well pump
• Electrical installation from existing source to wellhead
• Startup and operational testing
• Potable water testing and laboratory analysis
• Site restoration and cleanup
• Preparation of as-built documentation
Option #1 – Well #2
Provide all labor, materials, supervision, testing, and incidental work necessary to complete a second potable water well installation at the location identified on project drawings as Well #2.
The Government reserves the right to award or decline the Option Item based upon project budget and successful completion and performance of Well #1.
2.3 Existing Conditions
The Contractor shall verify all site conditions prior to beginning work. Existing subsurface conditions, groundwater elevations, and geological formations may vary from anticipated conditions.
Submission of a proposal constitutes acknowledgment that the Contractor has visited the site or otherwise become familiar with all existing conditions affecting the work.
2.4 Period of Performance
All work shall be completed within 60 calendar days from issuance of Notice to Proceed.
The Period of Performance includes:
• Mobilization
• Permitting
• Drilling
• Well construction
• Electrical installation
• Pump installation
• Testing
• Disinfection
• Startup
• Site restoration
• Final documentation
ITEM 3 – PERMITS AND REGULATORY
REQUIREMENTS
3.1 Permits
The Contractor shall obtain all permits, licenses, and inspections necessary to perform the work.
This includes, but is not limited to:
• Well drilling permits
• Environmental permits
• Electrical permits
• Utility clearances
• Inspection approvals
Permit costs shall be included in the overall cost of the Contractor’s proposal.
3.2 Regulatory Compliance
All work shall comply with:
• Northeast Tri County Health District well regulations
• OSHA 29 CFR 1926
• National Electrical Code (NFPA 70)
• EPA potable water requirements
• State groundwater protection regulations
• Federal environmental regulations
• National Park Service resource protection requirements
ITEM 4 – CONTRACTOR USE OF PREMISES
4.1 Site Protection
The Contractor shall protect:
• Existing vegetation
• Utilities
• Adjacent structures
• Roads and parking areas
• Cultural and natural resources
• Existing drainage systems
Disturbance shall be limited to approved work areas only.
4.2 Access and Staging
The Contractor shall coordinate staging, equipment access, and drilling operations with the NPS Project Manager.
Temporary access routes shall be restored upon completion.
4.3 Daily Cleanup
The Contractor shall maintain a clean worksite at all times and remove debris daily.
No waste materials shall be buried onsite.
ITEM 5 – WELL DRILLING AND CONSTRUCTION
5.1 Mobilization
The Contractor shall mobilize drilling rigs, compressors, support equipment, generators, water trucks, and all necessary support personnel.
5.2 Drilling Operations
The Contractor shall:
1. Verify drilling location with the NPS Project Manager prior to drilling.
2. Drill a potable water well to an estimated depth between 200 and 400 feet.
3. Final well depth shall be determined based on:
o Water yield o Geologic conditions o Water quality o Direction from the NPS Project Manager
4. Provide minimum 8-inch borehole diameter unless otherwise approved.
5. Maintain borehole stability throughout drilling operations.
6. Prevent contamination of groundwater during drilling.
5.3 Well Casing Installation
The Contractor shall:
• Install casing in accordance with Northeast Tri County Health District standards.
• Install casing plumb and aligned.
• Use approved casing materials suitable for potable water use.
• Seal casing to prevent surface water infiltration.
5.4 Grouting
• Pressure grout the annular space from bottom to surface.
• Utilize approved bentonite or cementitious grout materials.
• Prevent voids within grout column.
• Provide grout certification documentation.
5.5 Well Development
The Contractor shall develop the well utilizing approved surging, pumping, airlifting, or jetting methods until:
• Water is visually clear
• Sand content is minimized
• Stabilized yield is achieved
The Contractor shall remove drilling debris and sediment from the well.
5.6 Sanitary Completion
The Contractor shall install:
• Sanitary well cap
• Lead-free pitless adapter
• Vermin-proof seals
• Surface protection measures
ITEM 6 – PUMP INSTALLATION
6.1 Submersible Pump
The Contractor shall furnish and install one:
• 0.5 HP submersible pump
• Stainless steel or approved steel-alloy construction
• Potable water rated components
6.2 Pump Appurtenances
The Contractor shall provide:
• Drop pipe
• Electrical cable
• Check valve
• Torque arrestor
• Safety rope
• Pitless adapter connection
• Pump controls
6.3 Pump Setting
The Contractor shall set the pump at the proper operational depth based on:
• Static water level
• Pumping water level
• Well yield
• Manufacturer requirements
6.4 Startup and Verification
• Verify pump operation
• Verify amperage draw
• Verify pressure and flow
• Test all controls
• Confirm leak-free operation
ITEM 7 – ELECTRICAL INSTALLATION
7.1 General Requirements
Electrical work shall be performed by a licensed electrician.
All work shall comply with NEC requirements.
7.2 Electrical Scope
The Contractor shall:
• Install underground conduit from electrical source to wellhead o Distance is approximately 200 linear feet
• Install conductors properly sized for pump load
• Install appropriately sized breaker
• Install NEMA-rated disconnect at wellhead
• Provide grounding and bonding
• Protect conductors from physical damage
7.3 Electrical Startup
• Energize system
• Verify voltage
• Verify phase and rotation if applicable
• Test disconnect operation
• Confirm proper pump startup
ITEM 8 – TESTING AND DISINFECTION
8.1 Well Disinfection
The Contractor shall disinfect the completed well system in accordance with AWWA standards and applicable health district requirements.
8.2 Yield and Drawdown Testing
The Contractor shall perform:
• Pumping tests
• Drawdown monitoring
• Recovery monitoring
• Yield verification
Testing duration shall comply with health district requirements.
8.3 Potable Water Testing
The Contractor shall provide certified laboratory testing including:
• Total coliform
• E. coli
• Nitrates/nitrites
• Required inorganic constituents
• Additional parameters required by regulatory agencies
Certified test results shall be submitted to the Government.
8.4 Failed Testing
If initial testing fails:
• Contractor shall re-disinfect the well
• Contractor shall repeat testing
• Additional corrective actions shall be performed at no additional cost to the Government
ITEM 9 – SUBMITTALS
The Contractor shall submit:
• Driller’s license
• Insurance certificates
• Site-specific safety plan
• Drilling procedures
• Well completion report
• Grout certifications
• Pump specifications
• Electrical inspection approvals
• Certified potable water laboratory results
• As-built drawings
• Operation and Maintenance manuals
• Warranty documentation
ITEM 10 – SAFETY REQUIREMENTS
• Comply with OSHA 29 CFR 1926
• Maintain a site-specific safety plan
• Utilize proper excavation and drilling safety procedures
• Maintain safe traffic and pedestrian controls
• Secure drilling areas daily
• Prevent fuel and fluid spills
• Protect park resources and adjacent facilities
All employees shall wear appropriate PPE including:
• Hard hats
• Safety glasses
• High visibility clothing
• Gloves
• Steel-toe boots
• Hearing protection
ITEM 11 – SITE RESTORATION
The Contractor shall restore all disturbed areas including:
• Grading disturbed soils
• Replacing displaced aggregate
• Restoring drainage patterns
• Removing drilling fluids and debris
• Removing temporary access materials
• Seeding disturbed areas if directed
The site shall be returned to preconstruction condition or better.
ITEM 12 – ACCEPTANCE
Final acceptance shall occur upon:
• Successful potable water laboratory testing
• Verification of operational well system
• Completion of startup testing
• Submission of all required documentation
• Approval of as-built drawings
• Completion of site restoration
• Final inspection approval by the Government
PART 3 – EXECUTION
Phase 1 – Mobilization and Site Preparation
• Coordinate access and staging with NPS
• Verify utility locations
• Install erosion and sediment controls
• Protect adjacent resources
• Mobilize drilling equipment
Phase 2 – Drilling Operations
• Drill borehole to required depth
• Monitor geological formations
• Protect groundwater from contamination
• Maintain drilling logs
• Stabilize borehole throughout operations
Phase 3 – Well Construction
• Install casing
• Pressure grout annular space
• Install sanitary completion components
• Develop well until clear and sand-free
Phase 4 – Pump and Electrical Installation
• Install pump assembly
• Install conduit and wiring
• Install disconnect and controls
• Perform electrical testing
Phase 5 – Testing and Disinfection
• Disinfect system
• Conduct yield testing
• Conduct drawdown testing
• Obtain certified potable laboratory testing
Phase 6 – Startup and Restoration
• Verify system operation
• Restore disturbed areas
• Remove debris and temporary facilities
• Submit closeout documentation
• Participate in final inspection
| STATEMENT OF WORK (SOW) |
| Drill and Install New Potable Water Well |
| Sherman Homes Vacation Cabins |
| PART 1 – GENERAL INFORMATION |
| 1.1 Project Title |
| 1.2 Project Location |
| 1.3 Background |
| PART 2 – GENERAL |
| ITEM 1 – DESCRIPTION OF WORK |
| 2.1 Objective |
| The Contractor shall furnish all labor, supervision, materials, tools, equipment, transportation, permits, testing, utilities, environmental protection measures, and incidentals necessary to complete the drilling, construction, testing, disinfection, ... |
| The Contractor shall also provide pricing for one Optional Item for drilling and construction of a second potable water well identified as Well #2. Award of Well #2 shall be contingent upon the performance results of Well #1 and the availability of Go... |
| The work includes drilling and constructing a potable water well estimated between approximately 200 and 400 feet in depth, installation of a submersible pump system, electrical service installation, well development, potable water testing, disinfecti... |
| All work shall comply with: |
| Northeast Tri County Health District regulations |
| Federal Safe Drinking Water Act requirements |
| National Electrical Code (NEC) |
| OSHA 29 CFR 1926 |
| EPA potable water standards |
| State and local environmental regulations |
| National Park Service operational and environmental requirements |
| 2.2 Work Covered by Contract Documents |
| The Contractor shall provide all labor, materials, supervision, equipment, permits, transportation, testing, and incidentals necessary to complete the following: |
| Base – Well #1 |
| Mobilization and demobilization of drilling equipment and support vehicles |
| Site access coordination and temporary site protection |
| Utility locates and excavation coordination |
| Drilling of one potable water well |
| Installation of well casing and sanitary seal |
| Pressure grouting of annular space |
| Well development and cleaning |
| Installation of sanitary well cap |
| Installation of pitless adapter |
| Furnishing and installation of one submersible well pump |
| Electrical installation from existing source to wellhead |
| Startup and operational testing |
| Potable water testing and laboratory analysis |
| Site restoration and cleanup |
| Preparation of as-built documentation |
| Option #1 – Well #2 |
| Provide all labor, materials, supervision, testing, and incidental work necessary to complete a second potable water well installation at the location identified on project drawings as Well #2. |
| The Government reserves the right to award or decline the Option Item based upon project budget and successful completion and performance of Well #1. |
| 2.3 Existing Conditions |
| The Contractor shall verify all site conditions prior to beginning work. Existing subsurface conditions, groundwater elevations, and geological formations may vary from anticipated conditions. |
| Submission of a proposal constitutes acknowledgment that the Contractor has visited the site or otherwise become familiar with all existing conditions affecting the work. |
| 2.4 Period of Performance |
| All work shall be completed within 60 calendar days from issuance of Notice to Proceed. |
| The Period of Performance includes: |
| Mobilization |
| Permitting |
| Drilling |
| Well construction |
| Electrical installation |
| Pump installation |
| Testing |
| Disinfection |
| Startup |
| Site restoration |
| Final documentation |
| ITEM 3 – PERMITS AND REGULATORY REQUIREMENTS |
| 3.1 Permits |
| The Contractor shall obtain all permits, licenses, and inspections necessary to perform the work. |
| This includes, but is not limited to: |
| Well drilling permits |
| Environmental permits |
| Electrical permits |
| Utility clearances |
| Inspection approvals |
| Permit costs shall be included in the overall cost of the Contractor’s proposal. |
| 3.2 Regulatory Compliance |
| All work shall comply with: |
| Northeast Tri County Health District well regulations |
| OSHA 29 CFR 1926 |
| National Electrical Code (NFPA 70) |
| EPA potable water requirements |
| State groundwater protection regulations |
| Federal environmental regulations |
| National Park Service resource protection requirements |
| ITEM 4 – CONTRACTOR USE OF PREMISES |
| 4.1 Site Protection |
| The Contractor shall protect: |
| Existing vegetation |
| Utilities |
| Adjacent structures |
| Roads and parking areas |
| Cultural and natural resources |
| Existing drainage systems |
| Disturbance shall be limited to approved work areas only. |
| 4.2 Access and Staging |
| The Contractor shall coordinate staging, equipment access, and drilling operations with the NPS Project Manager. |
| Temporary access routes shall be restored upon completion. |
| 4.3 Daily Cleanup |
| The Contractor shall maintain a clean worksite at all times and remove debris daily. |
| No waste materials shall be buried onsite. |
| ITEM 5 – WELL DRILLING AND CONSTRUCTION |
| 5.1 Mobilization |
| The Contractor shall mobilize drilling rigs, compressors, support equipment, generators, water trucks, and all necessary support personnel. |
| 5.2 Drilling Operations |
| The Contractor shall: |
| 1. Verify drilling location with the NPS Project Manager prior to drilling. |
| 2. Drill a potable water well to an estimated depth between 200 and 400 feet. |
| 3. Final well depth shall be determined based on: |
| o Water yield |
| o Geologic conditions |
| o Water quality |
| o Direction from the NPS Project Manager |
| 4. Provide minimum 8-inch borehole diameter unless otherwise approved. |
| 5. Maintain borehole stability throughout drilling operations. |
| 6. Prevent contamination of groundwater during drilling. |
| 5.3 Well Casing Installation |
| The Contractor shall: |
| Install casing in accordance with Northeast Tri County Health District standards. |
| Install casing plumb and aligned. |
| Use approved casing materials suitable for potable water use. |
| Seal casing to prevent surface water infiltration. |
| 5.4 Grouting |
| The Contractor shall: |
| Pressure grout the annular space from bottom to surface. |
| Utilize approved bentonite or cementitious grout materials. |
| Prevent voids within grout column. |
| Provide grout certification documentation. |
| 5.5 Well Development |
| The Contractor shall develop the well utilizing approved surging, pumping, airlifting, or jetting methods until: |
| Water is visually clear |
| Sand content is minimized |
| Stabilized yield is achieved |
| The Contractor shall remove drilling debris and sediment from the well. |
| 5.6 Sanitary Completion |
| The Contractor shall install: |
| Sanitary well cap |
| Lead-free pitless adapter |
| Vermin-proof seals |
| Surface protection measures |
| ITEM 6 – PUMP INSTALLATION |
| 6.1 Submersible Pump |
| The Contractor shall furnish and install one: |
| 0.5 HP submersible pump |
| Stainless steel or approved steel-alloy construction |
| Potable water rated components |
| 6.2 Pump Appurtenances |
| The Contractor shall provide: |
| Drop pipe |
| Electrical cable |
| Check valve |
| Torque arrestor |
| Safety rope |
| Pitless adapter connection |
| Pump controls |
| 6.3 Pump Setting |
| The Contractor shall set the pump at the proper operational depth based on: |
| Static water level |
| Pumping water level |
| Well yield |
| Manufacturer requirements |
| 6.4 Startup and Verification |
| The Contractor shall: |
| Verify pump operation |
| Verify amperage draw |
| Verify pressure and flow |
| Test all controls |
| Confirm leak-free operation |
| ITEM 7 – ELECTRICAL INSTALLATION |
| 7.1 General Requirements |
| Electrical work shall be performed by a licensed electrician. |
| All work shall comply with NEC requirements. |
| 7.2 Electrical Scope |
| The Contractor shall: |
| Install underground conduit from electrical source to wellhead |
| o Distance is approximately 200 linear feet |
| Install conductors properly sized for pump load |
| Install appropriately sized breaker |
| Install NEMA-rated disconnect at wellhead |
| Provide grounding and bonding |
| Protect conductors from physical damage |
| 7.3 Electrical Startup |
| The Contractor shall: |
| Energize system |
| Verify voltage |
| Verify phase and rotation if applicable |
| Test disconnect operation |
| Confirm proper pump startup |
| ITEM 8 – TESTING AND DISINFECTION |
| 8.1 Well Disinfection |
| The Contractor shall disinfect the completed well system in accordance with AWWA standards and applicable health district requirements. |
| 8.2 Yield and Drawdown Testing |
| The Contractor shall perform: |
| Pumping tests |
| Drawdown monitoring |
| Recovery monitoring |
| Yield verification |
| Testing duration shall comply with health district requirements. |
| 8.3 Potable Water Testing |
| The Contractor shall provide certified laboratory testing including: |
| Total coliform |
| E. coli |
| Nitrates/nitrites |
| Required inorganic constituents |
| Additional parameters required by regulatory agencies |
| Certified test results shall be submitted to the Government. |
| 8.4 Failed Testing |
| If initial testing fails: |
| Contractor shall re-disinfect the well |
| Contractor shall repeat testing |
| Additional corrective actions shall be performed at no additional cost to the Government |
| ITEM 9 – SUBMITTALS |
| The Contractor shall submit: |
| Driller’s license |
| Insurance certificates |
| Site-specific safety plan |
| Drilling procedures |
| Well completion report |
| Grout certifications |
| Pump specifications |
| Electrical inspection approvals |
| Certified potable water laboratory results |
| As-built drawings |
| Operation and Maintenance manuals |
| Warranty documentation |
| ITEM 10 – SAFETY REQUIREMENTS |
| The Contractor shall: |
| Comply with OSHA 29 CFR 1926 |
| Maintain a site-specific safety plan |
| Utilize proper excavation and drilling safety procedures |
| Maintain safe traffic and pedestrian controls |
| Secure drilling areas daily |
| Prevent fuel and fluid spills |
| Protect park resources and adjacent facilities |
| All employees shall wear appropriate PPE including: |
| Hard hats |
| Safety glasses |
| High visibility clothing |
| Gloves |
| Steel-toe boots |
| Hearing protection |
| ITEM 11 – SITE RESTORATION |
| The Contractor shall restore all disturbed areas including: |
| Grading disturbed soils |
| Replacing displaced aggregate |
| Restoring drainage patterns |
| Removing drilling fluids and debris |
| Removing temporary access materials |
| Seeding disturbed areas if directed |
| The site shall be returned to preconstruction condition or better. |
| ITEM 12 – ACCEPTANCE |
| Final acceptance shall occur upon: |
| Successful potable water laboratory testing |
| Verification of operational well system |
| Completion of startup testing |
| Submission of all required documentation |
| Approval of as-built drawings |
| Completion of site restoration |
| Final inspection approval by the Government |
| PART 3 – EXECUTION |
| Phase 1 – Mobilization and Site Preparation |
| Coordinate access and staging with NPS |
| Verify utility locations |
| Install erosion and sediment controls |
| Protect adjacent resources |
| Mobilize drilling equipment |
| Phase 2 – Drilling Operations |
| Drill borehole to required depth |
| Monitor geological formations |
| Protect groundwater from contamination |
| Maintain drilling logs |
| Stabilize borehole throughout operations |
| Phase 3 – Well Construction |
| Install casing |
| Pressure grout annular space |
| Install sanitary completion components |
| Develop well until clear and sand-free |
| Phase 4 – Pump and Electrical Installation |
| Install pump assembly |
| Install conduit and wiring |
| Install disconnect and controls |
| Perform electrical testing |
| Phase 5 – Testing and Disinfection |
| Disinfect system |
| Conduct yield testing |
| Conduct drawdown testing |
| Obtain certified potable laboratory testing |
| Phase 6 – Startup and Restoration |
| Verify system operation |
| Restore disturbed areas |
| Remove debris and temporary facilities |
| Submit closeout documentation |
| Participate in final inspection |
File details come from the government source that posted it. Updated .