This is a Statement of Work (SOW) for dismantling, demolition, removal, and site restoration services at the Gloria Ford Estate on the Emmett Ranger District, Boise National Forest in Boise County, Idaho (coordinates: 44.0482574, -115.8387632).
The Contractor shall provide all labor, supervision, equipment, tools, transportation, and incidentals necessary to execute full dismantling and demolition of all structures and improvements, including removal of utilities, septic components, vault toilets, tanks, pipelines, foundations, and slabs. The Contractor must identify, handle, remove, and dispose of hazardous materials including asbestos-containing materials, lead-based paint, and miscellaneous hazardous items in compliance with 29 CFR 1926.1101, EPA NESHAP, and RRP Rule requirements. All work shall include waste management and disposal to approved facilities with maintenance of landfill receipts and waste shipment records, backfilling of demolition voids with acceptable materials, rough grading to blend with surrounding terrain, application of approved seed mixtures, and installation of erosion and sediment controls. The Contractor is responsible for site security, equipment protection, pressure washing all equipment before arrival to remove mud and noxious weeds, and maintaining a clean and safe work environment. Explosive demolition is not permitted. The period of performance is 120 calendar days from the Notice to Proceed, beginning July 15, 2026, with work performed during daylight hours unless otherwise approved. All costs for mobilization, traffic control, hazardous materials handling, erosion control, waste disposal, and site restoration are included in the lump sum payment with no separate compensation. Submittals required include work plans (demolition, hazardous materials abatement, environmental controls), traffic control plan, safety and health plan, personnel qualification documentation, pre-demolition photographs or video, demolition schedule, and final disposal documentation. The Government will provide a Phase I ESA report, 2021 Asbestos Survey, 2021 Hazardous Materials Report, and site map with building descriptions.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 260508 Questions and Answers.docx | DOCX document | |
| SF 30 Amendment 0001.pdf | ||
| Attachment 3 - SOW REVISED.pdf | ||
| Attachment 2 - Schedule of Items.xlsx | XLSX spreadsheet | |
| Attachment 8 - Wage Determination 20155503 Boise County.pdf | ||
| Attachment 4 - Site Map.pdf | ||
| Attachment 7 - Hazardous Materials Report.pdf | ||
| Attachment 1 - Solicitation 1240LR260013 BSNF.pdf | ||
| Attachment 2 - Schedule of Items.xlsx | XLSX spreadsheet | |
| Attachment 5 - Environmental Site Assessment.pdf | ||
| Attachment 6 - Asbestos Survey.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Service-Oriented Statement of Work (Hybrid Format) Gloria Ford Estate – Decommissioning Services Dismantling, Demolition, Removal, and Site Restoration
1.0 Scope of Services
The Contractor shall provide all labor, supervision, equipment, tools, transportation, and incidentals necessary to perform dismantling, demolition, removal, and disposal services, including site restoration, at the Gloria Ford Estate on the Emmett Ranger District, Boise National Forest.
Services include:
· Removal and off-site disposal of buildings, structures, foundations, concrete, walkways, debris, furnishings, and associated appurtenances.
· Identification, handling, removal, and disposal of hazardous materials, including asbestos, lead-based paint, and other regulated materials.
· Backfilling of demolition voids, grading, surface restoration, seeding, and final site cleanup.
· Compliance with all applicable federal, state, and local environmental and safety regulations.
All services shall be performed in accordance with applicable environmental regulations, safety standards, and Forest Service requirements.
2.0 Location of Services
Work will be performed at the Gloria Ford Estate, located on the Emmett Ranger District, Boise National Forest, Boise County, Idaho.
Coordinates: 44.0482574, -115.8387632.
3.0 Site Conditions and Access
The Contractor is responsible for becoming familiar with all site conditions before beginning work.
The following conditions apply:
· The worksite will be closed to public access during performance of services; the Contractor is responsible for signage, securing work areas, and public safety.
· The Contractor must provide security for its own equipment and materials.
· All equipment brought onto National Forest land must be clean and free of mud, debris, and noxious weeds; pressure washing is required before arrival.
· No utilities are available on-site.
4.0 Service Requirements
4.1 Dismantling and Demolition Services
The Contractor shall:
· Execute full dismantling and demolition of all structures and improvements.
· Remove utilities, septic components, vault toilets, tanks, pipelines, foundations, slabs, and other constructed items.
· Manage dust, noise, and environmental impacts through appropriate control measures.
· Provide temporary protection of adjacent facilities and natural resources.
Explosive demolition is not permitted.
4.2 Waste Management and Disposal
The Contractor shall:
· Transport all debris, waste, hazardous materials, and demolition byproducts to approved disposal facilities.
· Comply with EPA, state, and county solid waste, hazardous waste, lead-based paint, and asbestos regulations.
· Maintain landfill receipts, waste shipment records, and documentation of final disposal.
4.3 Hazardous Materials Handling
Hazardous materials may include:
· Asbestos-containing drywall texture and joint compound.
· Lead-based paint on interior and exterior surfaces.
· Potentially hazardous miscellaneous materials (e.g., drums, chemicals).
Contractor responsibilities:
· Provide certified personnel and approved work plans for asbestos abatement and lead-based paint handling.
· Conduct all work prior to general demolition, following 29 CFR 1926.1101, EPA NESHAP, and RRP Rule requirements.
· Prepare site-specific Health & Safety Plans for review and approval.
4.4 Site Restoration
The Contractor shall:
· Backfill all voids resulting from demolition with acceptable materials.
· Rough grade the site to blend with surrounding terrain.
· Apply approved seed mixtures to disturbed areas.
· Install erosion and sediment controls before ground disturbance and maintain them throughout the work.
5.0 Submittals
The Contractor shall provide the following for Government review and acceptance:
· Work plans (demolition, hazardous materials abatement, environmental controls).
· Traffic control plan.
· Safety and health plan.
· Qualification documentation for demolition, asbestos, and LBP abatement personnel.
· Asbestos Work Plan and Air Monitoring Plan (if applicable).
· Pre-demolition photographs or video.
· Schedule of demolition services.
· Landfill receipts and waste shipment records following disposal.
6.0 Performance Requirements
The Contractor shall:
· Comply with all federal, state, and local laws and regulations related to demolition, waste disposal, and hazardous materials.
· Perform all services in a manner that protects Forest Service property, public safety, and natural resources.
· Maintain a clean and safe work environment.
· Correct any deficiencies, unsafe conditions, or damages at no additional cost to the Government.
7.0 Government-Furnished Information
The Government will provide:
· Phase I ESA report
· Asbestos Survey (2021)
· Hazardous Materials Report (2021)
· Site map and building descriptions (Appendices referenced in the original document.)
8.0 Period of Performance
· Start Date: July 15, 2026
· Period: 120 calendar days from Notice to Proceed
9.0 Hours of Work
The Contractor shall perform work during daylight hours unless otherwise approved.
10.0 Deliverables
· Work plans (hazardous materials, demolition, traffic control)
· Environmental control plan
· Pre‑demolition condition documentation
· Daily logs or updates as required
· Final site restoration verification
· Disposal documentation (receipts, WSRs)
· Final completion report
11.0 Quality Assurance and Inspection
· Government will conduct inspections throughout performance.
· Deficiencies must be corrected promptly at the Contractor’s expense.
· Work is subject to stop‑work orders if unsafe or non-compliant.
12.0 Payment
All work under this SOW is lump sum unless otherwise identified in the Schedule of Items.
No separate payments will be made for:
· Mobilization
· Traffic control
· Hazardous materials handling
· Erosion control
· Waste disposal
· Site restoration All such activities are incidental to the services covered under this SOW.