260508 Questions and Answers.docx
DOCX document 21 KB Posted
- Solicitation number
- 1240LR26Q0013
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a Questions and Answers document for Solicitation No. 1240LR26Q0013, a Request for Quotation (RFQ) issued by the U.S. Forest Service for the Boise National Forest Gloria Ford Estate Decommissioning project. The Q&A addresses critical clarifications regarding project scope and contractor responsibilities. Key responses indicate that the government anticipates asbestos-containing material (ACM) abatement to occur prior to decommissioning structures, though no engineer letter confirming condemned status or state variance for in-place demolition has been obtained. Contractors are responsible for providing a qualified third-party hygienist and associated costs as part of their bid. The project requires removal of dead trees and limbs necessary for site clearance, with large woody debris potentially repurposed for erosion control and site rehabilitation. Contractors must install and later decommission a construction entrance off Banks-Lowman Road in coordination with Boise County Road and Bridge Department.
This Total Small Business Set-Aside acquisition utilizes NAICS code 238910 (Site Preparation Contractors) with a small business size standard of $19 million. Amendment 000001, dated May 8, 2026, replaced the Statement of Work in its entirety, posted these Q&As, and extended the quote submission deadline to May 19, 2026 at 5:00 p.m. MDT. Complete quote packages must include a completed Schedule of Items and Technical Approach as separate attachments, with the signed and dated SF 30 form required for compliance consideration. No government-sponsored site visit is planned, though potential bidders may visit at their own convenience.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 2 - Schedule of Items.xlsx | XLSX spreadsheet | |
| SF 30 Amendment 0001.pdf | ||
| Attachment 3 - SOW REVISED.pdf | ||
| Attachment 3 - SOW.docx | DOCX document | |
| Attachment 2 - Schedule of Items.xlsx | XLSX spreadsheet | |
| Attachment 7 - Hazardous Materials Report.pdf | ||
| Attachment 1 - Solicitation 1240LR260013 BSNF.pdf | ||
| Attachment 6 - Asbestos Survey.pdf | ||
| Attachment 4 - Site Map.pdf | ||
| Attachment 5 - Environmental Site Assessment.pdf | ||
| Attachment 8 - Wage Determination 20155503 Boise County.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
| Solicitation No. 1240LR26Q0013 Amendment 000001 | U.S. Forest Service |
| Gloria Ford Estate Decommissioning Boise | National Office |
QUESTIONS AND ANSWERS
May 8, 2026
1) Have the structures officially been classified as condemned? If so, please provide engineer letter.
Structures are uninhabitable. Government is not aware of an engineer letter indicating condemned classification.
2) Has the government received a variance from the state to demo the structures with the asbestos left in place? If so, please provide variance.
Government has not received a variance from the State.
3) For bidding purposes are you requiring us to provide you a bid to abate all ACM prior to Demo? Or Demo structures with ACM in place?
A bid for demo in place is not possible without answers to questions #1 and #2 be “Yes” Government anticipates abatement to occur on prior to decommissioning the structures.
4) Will the government provide 3rd party hygienist or are we to include this cost in our bids?
Government will not be providing 3rd party hygienist.
5) Do you have an address for this project?
See Statement of Work
6) Looking at the site there are a lot of dead trees that are potential fire hazards. Are you wanting those removed?
Contractor needs to remove dead trees and limbs as necessary to perform the site removal and disposal requirements in the SOW. The large woody debris may be used in the site rehabilitation as erosion control and/or organic addition to the site grading/seeding requirements.
7) Are we going to have to put in a construction entrance in?
Yes, the Contractor will likely need to install a construction entrance off the Banks-Lowman Road. Contractor needs to coordinate with Boise County Road and Bridge Department on the ingress and egress requirements of this entrance. The entrance shall be decommissioned after the project is complete.
8) There are a few trees that will need to be removed to clean this site up, is this going to be ok?
Yes