About this file

This is a Price Component Confirmation Table document detailing how various electricity cost components should be treated across four Independent System Operator (ISO) regions: PJM, ERCOT, ISONE, and CAISO. The document breaks down which costs should be included in bid prices versus passed through, and whether components require individual line item billing.

For all regions, core components like Energy Commodity Costs, Ancillary Services, Scheduling, and Balancing/Congestion Costs are fixed and included in bid prices. An Enel X Inc. Fee of $0.0007 per kWh is consistently required across all regions. The table specifies a minimum +/- 20% Annual Bandwidth requirement based on aggregated usage for each pricing group. Region-specific variations exist in how certain components are treated - for example, Capacity Costs are treated as Economic Price Adjustment in PJM but are pass-through costs in ISONE. Most taxes are treated as pass-through costs requiring individual line item billing across all regions. The document supports GSA solicitation 47PA0825R0002 for retail electric supply, with technical proposals due by March 7, 2025.

View the file

Other files

File Type Posted
Amendment 0015_Solicitation 47PA0825R002 Exhibit 1 ISONE and CAISO Accounts.xlsx XLSX spreadsheet
Amendment 0015 Solicitation 47PA0825R0002.pdf PDF
Amendment 0015 Block and Index Calculator Spreadsheet - Block (Shaped Hedge) Index - Sample Calculations 8.5.2025.xls XLS spreadsheet
Amendment 0014_Solicitation 47PA0825R002 Exhibit 1 ISONE and CAISO Accounts.xlsx XLSX spreadsheet
Amendment 0014 Block and Index Calculator Spreadsheet - Block (Shaped Hedge) Index - Sample Calculations 7.29.2025.xls XLS spreadsheet
Amendment 0014 Solicitation 47PA0825R0002.pdf PDF
Amendment 0013_Solicitation 47PA0825R002 Exhibit 1 ISONE and CAISO Accounts (1).xlsx XLSX spreadsheet
Amendment 0013 Solicitation 47PA0825R0002.pdf PDF
Amendment 0012 Solicitation 47PA0825R0002.pdf PDF
Amendment 0012_Solicitation 47PA0825R002 Exhibit 1 ISONE and CAISO Accounts.xlsx XLSX spreadsheet
Amendment 0011 ATTACHMENT 3_ Price Component Confirmation Table.xlsx XLSX spreadsheet
Amendment 0012_Solicitation 47PA0825R0002 Block and Index Calculator Spreadsheet - Block (Shaped Hedge) Index - Sample Calculations.xls XLS spreadsheet
Amendment 0011_ Solicitation 47PA0825R0002.pdf PDF
Amendment 0011_Solicitation 47PA0825R0002 Exhibit 1 ISONE and CAISO Accounts.xlsx XLSX spreadsheet
Amendment 0010 ATTACHMENT 3_ Price Component Confirmation Table.xlsx XLSX spreadsheet
Amendment 0010_Solicitation 47PA0825R002 Exhibit 1 ISONE and CAISO Accounts.xlsx XLSX spreadsheet
Amendment 0010_Solicitation 47PA0825R0002.pdf PDF
Amendment 0009_Solicitation 47PA0825R0002.pdf PDF
Amendment 0009_Solicitation 47PA0825R0002 Exhibit 1 PJM and ERCOT Accounts.xlsx XLSX spreadsheet
Amendment 0008_Solicitation 47PA0825R0002.pdf PDF
Amendment 0007_Solicitation 47PA0825R002 FInal Exhibit 1 PJM and ERCOT Accounts.xlsx XLSX spreadsheet
Amendment 0007_Solicitation 47PA0825R0002.pdf PDF
Amendment 0006 Solicitation 47PA0825R0002 FY25 Streamlined Electric Buy.pdf PDF
Amendment 0006_Solicitation 47PA0825R002 FInal Exhibit 1 PJM and ERCOT Accounts.xlsx XLSX spreadsheet
Amendment 0005_Solicitation 47PA0825R002 FInal Exhibit 1 PJM and ERCOT Accounts.xlsx XLSX spreadsheet
Amendment 0005 Solicitation 47PA0825R0002 FY25 Streamlined Electric Buy.pdf PDF
Amendment 0004 Solicitation 47PA0825R0002 FInal Exhibit 1 PJM and ERCOT Accounts.xlsx XLSX spreadsheet
Amendment 0004 Solicitation 47PA0825R002 FInal Exhibit 1 PJM and ERCOT Accounts.xlsx XLSX spreadsheet
Amendment 0004_Solicitation 47PA0825R0002 FY25 Streamlined Electric Buy.pdf PDF
9. Amendment 0003_Solicitation 47PA0825R002 FInal Exhibit 1 PJM & ERCOT Accounts.xlsx XLSX spreadsheet
3. Q & A 47PA0825R0002 FY25 Solicitation.pdf PDF
2. Amendment 0003_ Summary of Changes.pdf PDF
5. Amendment 0003_ Solicitation FY25 Streamlined Electric Buy.pdf PDF
9. Amendment 0003_ Solicitation 47PA0825R002 FInal Exhibit 1 PJM & ERCOT Accounts.xlsx XLSX spreadsheet
1. Amendment 0003_Standard Form 30.pdf PDF
5. Amendment 0003_Solicitation FY25 Streamlined Electric Buy.pdf PDF
4. Amendment 0003_1449 Form.pdf PDF
7. Amendment 0003_ATTACHMENT 12 Pre-Proposal Call Schedule.pdf PDF
8. Amendment 0003_ATTACHMENT 13 Preliminary Exhibit 1 .xlsx XLSX spreadsheet
3. Amendment 0003_Q & A.pdf PDF
2. Amendment 0003_Summary of Changes.pdf PDF
6. Amendment 0003_ ATTACHMENT 3_ PRICE COMPONENT CONFIRMATION TABLE.xlsx XLSX spreadsheet
Solicitation Amendment 47PA0825R0002_0002.pdf PDF
Amendment 0001_Solicitation 47PA0825R0002.pdf PDF
Attachment 13 Preliminary Exhibit 1.xlsx XLSX spreadsheet
FY25 GSA Streamlined Retail Electric Solicitation.pdf PDF
Show all 46

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PJM

PJM PRICE COMPONENT CONFIRMATION TABLE
Price ComponentTreatmentInclude In Bid Prices?Requires Individual Line Item Billing?Notes
Energy Commodity CostsFixedYesNo - Included in Bid Price
Minimum of +/- 20 % Annual Bandwidth Based on the Aggregated Usage of Each Pricing GroupFixedYesNo - Included in Bid Price
Ancillary Services and other ISO Costs (Including but not limited to OATT Tariff, Operating Reserves, ISO Administrative Fees, Public Service Commission and/or Public Utility Commission fees)FixedYesNo - Included in Bid Price
SchedulingFixedYesNo - Included in Bid Price
Balancing and Congestion CostsFixedYesNo - Included in Bid Price
Line Losses including Distribution Losses to the End-use MeterFixedYesNo - Included in Bid Price
State Renewable Portfolio Standards (RPS) Compliance Costs (other than ORECs) for States where the Supplier is Responsible (not the utility)FixedYesNo - Included in Bid PriceOffers are instructed to include known costs at time of award, any future changes after the date of award will be handled under Section A.14 Electric Regulatory Changes
Transmission Loss Credits (TLCs)FixedYesNo - Included in Bid Price
Ohio Commercial Activity Tax (Only for accounts in Ohio)No - Included in Bid Price
Enel X Inc. Fee of $.0007 per kWhFixedYesNo - Included in Bid Price
Renewable Energy Certificates (RECs) that Comply with Section A.12 of this Solicitation (as applicable)FixedYesNo - Included in Bid Price
Capacity (ICAP & UCAP)Economic Price AdjustmentNoNo
Transmission Costs (including Network Integration Transmission Service [NITS], Regional Transmission Expansion Planning [RTEP], Financial Transmission Right [FTR], Transmission Reallocation Costs [TEAC], and Transmission Enhancement [TEC])Economic Price AdjustmentNoNo
Auction Revenue Rights (ARRs)Economic Price AdjustmentNoNo
Reliability Must Run (RMR)Economic Price AdjustmentNoNo
FERC Order 745 and FERC 494 / EL05-121-009 Compliance CostsEconomic Price AdjustmentNoNo
Offshore Wind RECs (ORECs)Economic Price AdjustmentNoNo
Applicable Taxes (other than OH Commercial Activity Tax)Pass-Through at CostNoYes

ERCOT

ERCOT PRICE COMPONENT CONFIRMATION TABLE
Price ComponentTreatmentInclude in Bid Price?Requires Individual Line Item Billing?Notes
Energy Commodity CostsFixedYesNo - Included in Bid Price
Ancillary services (Including but not limited to Congestion Revenue Rights (CRR), Firm Fuel Supply Service and Reg Up, Reg Down, Responsive Reserve, Non-Spin, RUC Clawback Payment and RUC Decommitment Charge, RUC Make Whole Uplift Charge, ERCOT Contingency Reserve Service Charge (ECRS) )FixedYesNo - Included in Bid Price
SchedulingFixedYesNo - Included in Bid Price
Balancing and Congestion Costs (Including Basis Costs and Nodal Congestion)FixedYesNo - Included in Bid Price
Fuel CostsFixedYesNo - Included in Bid Price
Independent System Operator (ISO) / Qualified Scheduling entity (QSE) Admin Charges and FeesFixedYesNo - Included in Bid Price
Line Losses including Distribution Losses to the End-use MeterFixedYesNo - Included in Bid Price
Operating Reserve Demand Curve (ORDC / RT Imbalance costsFixedYesNo - Included in Bid Price
TX Renewable Portfolio Standards (RPS) Compliance CostsFixedYesNo - Included in Bid PriceOffers are instructed to include known costs at time of award, any future changes after the date of award will be handled under Section A.14 Electric Regulatory Changes
Reliability Unit Commitment (RUC ) Capacity Short Charge CostsFixedYesNo - Included in Bid Price
Reliability Must Run (RMR)FixedYesNo - Included in Bid Price
Auction Revenue Rights (ARRs)FixedYesNo - Included in Bid Price
Minimum of +/- 20 % Annual Bandwidth Based on the Aggregated Usage of Each Pricing GroupFixedYesNo - Included in Bid Price
Enel X Inc. Fee of $.0007 per kWhFixedYesNo - Included in Bid Price
Renewable Energy Certificates (RECs) that Comply with Section A.12 of this Solicitation (as applicable)FixedYesNo - Included in Bid Price
Market Securitization DefaultPass-through at costNoNo
Market Securitization UpliftPass-through at costNoNo
Bridging Solution Option (Phase II Market Redesign)Pass-through at costNoNoOffers are instructed to include known costs at time of award, any future changes after the date of award will be handled under Section A.14 Electric Regulatory Changes
ERCOT Emergency Pricing Program (PUCT Rule Section 25.509 and Project No. 54585)Pass-through at costNoNoOffers are instructed to include known costs at time of award, any future changes after the date of award will be handled under Section A.14 Electric Regulatory Changes
Applicable Taxes (Including but not limited to TX Gross Receipts Tax (GRT) and TX Public Utility Commission Gross Receipts Assessment tax (PUCA))Pass-through at costNoYes
Applicable excise taxes and TDSP charges (Including but not limited to Transmission Cost Recovery Factor, Distribution Cost Recovery Factor, Distribution System Charge, Metering Charge and Customer Charge)Pass-through at costNoBill Per TDSP Requirements

000000 INTERNAL#_x000D_

ISONE

ISONE PRICE COMPONENT CONFIRMATION TABLE
Price ComponentTreatmentInclude in Bid Price?Requires Individual Line Item Billing?Notes
Block Energy Commodity CostsFixedYesNo - Included in Bid Price
Ancillary Services and other ISO Costs (Including but not limited to OATT Tariff, Operating Reserves, ISO Administrative Fees, Public Service Commission and/or Public Utility Commission fees)FixedYesNo - Included in Bid Price
Transmission Loss Credits (TLCs)FixedYesNo - Included in Bid Price
Auction Revenue Rights (ARRs)FixedYesNo - Included in Bid Price
Reliability Must Run (RMR)FixedYesNo - Included in Bid Price
SchedulingFixedYesNo - Included in Bid Price
Balancing and Congestion CostsFixedYesNo - Included in Bid Price
Enel X Inc. Fee of $.0007 per kWhFixedYesNo - Included in Bid Price
Renewable Energy Certificates (RECs) that Comply with Section A.12 of this Solicitation (as applicable)FixedYesNo - Included in Bid Price
Minimum of +/- 20 % Annual Bandwidth Based on the Aggregated Usage of Each Pricing GroupFixedYesNo - Included in Bid Price
State Mandated Renewable Portfolio Standards (RPS) and Alternate Energy Portfolio Standard (AEPS) Compliance CostsPass-through at costNoNoOffers are instructed to include known costs at time of award, any future changes after the date of award will be handled under Section A.14 Electric Regulatory Changes
Capacity Costs (ICAP )Pass-through at costNoNo
Line Losses including Distribution Losses to the End-use MeterPass-through at costNoNo
FERC Order 745 and FERC 494 / EL05-121-009 Compliance CostsPass-through at costNoNo
Fuel Security Costs (Mystic Cost of Service, Inventoried Energy Program Energy Security Improvements)Pass-through at costNoNo
Locational Forward ReservesPass-through at costNoNo
Locational Price DifferentialsPass-through at costNoNo
Regional Transmission RightsPass-through at costNoNo
Financial Transmission Rights (FTR)Pass-through at costNoNo
Fuel CostsPass-through at costNoNo
Marginal Loss Credits (MLCs)Pass-through at costNoNo
Applicable TaxesPass-through at costNoYes

CAISO

CAISO PRICE COMPONENT CONFIRMATION TABLE
Price ComponentTreatmentInclude in Bid Price?Requires Individual Line Item Billing?Notes
Energy Commodity CostsFixedYesNo - Included in Bid Price
Minimum of +/- 20 % Annual Bandwidth Based on the Aggregated Usage of Each Pricing GroupFixedYesNo - Included in Bid Price
Ancillary Services and other ISO Costs (Including but not limited to OATT Tariff, Operating Reserves, ISO Administrative Fees, Public Service Commission and/or Public Utility Commission fees)FixedYesNo - Included in Bid Price
Balancing and Congestion Costs (Including Congestion Basis Costs)FixedYesNo - Included in Bid Price
Line Losses including Distribution Losses to the End-use MeterFixedYesNo - Included in Bid Price
Enel X Inc. Fee of $.0007 per kWhFixedYesNo - Included in Bid Price
Renewable Energy Certificates (RECs) that Comply with Section A.12 of this Solicitation (as applicable)FixedYesNo - Included in Bid Price
Marginal Loss Credits (MLCs)FixedYesNo - Included in Bid Price
Transmission Loss Credits (TLCs)FixedYesNo - Included in Bid Price
CA Renewable Portfolio Standards (RPS) Compliance CostsFixedYesNo - Included in Bid PriceOffers are instructed to include known costs at time of award, any future changes after the date of award will be handled under Section A.14 Electric Regulatory Changes
SchedulingFixedYesNo - Included in Bid Price
Resource Adequacy (RA)FixedYesNo - Included in Bid Price
Financial Transmission Rights (FTR)FixedYesNo - Included in Bid Price
Reliability Must Run (RMR)FixedYesNo - Included in Bid Price
Auction Revenue Rights (ARRs)FixedYesNo - Included in Bid Price
FERC Order 745 and FERC 494 / EL05-121-009 Compliance CostsFixedYesNo - Included in Bid Price
State Energy Resource ChargeFixedYesNo - Included in Bid Price
Applicable TaxesPass-through at costNoYes

000000 INTERNAL#_x000D_