This file is an Amendment 0010 Attachment containing Price Component Confirmation Tables for multiple electricity markets (PJM, ERCOT, ISONE, and CAISO). The document details specific pricing components for electricity supply, indicating which costs are fixed, included in bid prices, or subject to pass-through adjustments. Key pricing components include energy commodity costs, ancillary services, scheduling, balancing and congestion costs, line losses, renewable portfolio standards compliance, and various administrative fees.
The associated federal contract opportunity is a GSA Streamlined Retail Electric Solicitation (Solicitation Number: 47PA0825R0002) for electricity supply. GSA intends to award multiple contracts for electricity commodity supply to delivery points, with contract terms up to 60 months. The solicitation requires technical proposals to be submitted by 3:00 p.m. EST on March 7, 2025, with potential contract awards occurring at different times throughout the fiscal year. Offerors must be licensed to provide retail electric supply in applicable states, and the procurement will involve pricing groups as specified in the preliminary exhibit.
View the file
Other files
Show all 46
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PJM
| PJM PRICE COMPONENT CONFIRMATION TABLE | ||||
| Price Component | Treatment | Include In Bid Prices? | Requires Individual Line Item Billing? | Notes |
| Energy Commodity Costs | Fixed | Yes | No - Included in Bid Price | |
| Minimum of +/- 20 % Annual Bandwidth Based on the Aggregated Usage of Each Pricing Group | Fixed | Yes | No - Included in Bid Price | |
| Ancillary Services and other ISO Costs (Including but not limited to OATT Tariff, Operating Reserves, ISO Administrative Fees, Public Service Commission and/or Public Utility Commission fees, Reactive Services, Black Start, Reactive Supply and Voltage Control) | Fixed | Yes | No - Included in Bid Price | |
| Scheduling | Fixed | Yes | No - Included in Bid Price | |
| Balancing and Congestion Costs | Fixed | Yes | No - Included in Bid Price | |
| Line Losses including Distribution Losses to the End-use Meter | Fixed | Yes | No - Included in Bid Price | |
| State Renewable Portfolio Standards (RPS) Compliance Costs (other than ORECs) for States where the Supplier is Responsible (not the utility) | Fixed | Yes | No - Included in Bid Price | Offers are instructed to include known costs at time of award, any future changes after the date of award will be handled under Section A.14 Electric Regulatory Changes |
| Transmission Loss Credits (TLCs) | Fixed | Yes | No - Included in Bid Price | |
| Ohio Commercial Activity Tax (Only for accounts in Ohio) | No - Included in Bid Price | |||
| Enel X Inc. Fee of $.0007 per kWh | Fixed | Yes | No - Included in Bid Price | |
| Renewable Energy Certificates (RECs) that Comply with Section A.12 of this Solicitation (as applicable) | Fixed | Yes | No - Included in Bid Price | |
| Capacity (ICAP & UCAP) | Economic Price Adjustment | No | No | |
| Transmission Costs (including Network Integration Transmission Service [NITS], Regional Transmission Expansion Planning [RTEP], Financial Transmission Right [FTR], Transmission Reallocation Costs [TEAC], and Transmission Enhancement [TEC]) | Economic Price Adjustment | No | No | |
| Auction Revenue Rights (ARRs) | Economic Price Adjustment | No | No | |
| Reliability Must Run (RMR) | Economic Price Adjustment | No | No | |
| FERC Order 745 and FERC 494 / EL05-121-009 Compliance Costs | Economic Price Adjustment | No | No | |
| Offshore Wind RECs (ORECs) | Economic Price Adjustment | No | No | |
| Applicable Taxes (other than OH Commercial Activity Tax) | Pass-Through at Cost | No | Yes |
ID#AAABjl8ETGA (2025-05-13 13:46:23) Enel to update all four price component tables in this file once the Q&As are approved and final -Christopher McCall - PMAA-C
ERCOT
| ERCOT PRICE COMPONENT CONFIRMATION TABLE | ||||
| Price Component | Treatment | Include in Bid Price? | Requires Individual Line Item Billing? | Notes |
| Energy Commodity Costs | Fixed | Yes | No - Included in Bid Price | |
| Ancillary services (Including but not limited to Congestion Revenue Rights (CRR), Firm Fuel Supply Service and Reg Up, Reg Down, Responsive Reserve, Non-Spin, RUC Clawback Payment and RUC Decommitment Charge, RUC Make Whole Uplift Charge, ERCOT Contingency Reserve Service Charge (ECRS) ) | Fixed | Yes | No - Included in Bid Price | |
| Scheduling | Fixed | Yes | No - Included in Bid Price | |
| Balancing and Congestion Costs (Including Basis Costs and Nodal Congestion) | Fixed | Yes | No - Included in Bid Price | |
| Fuel Costs | Fixed | Yes | No - Included in Bid Price | |
| Independent System Operator (ISO) / Qualified Scheduling entity (QSE) Admin Charges and Fees | Fixed | Yes | No - Included in Bid Price | |
| Line Losses including Distribution Losses to the End-use Meter | Fixed | Yes | No - Included in Bid Price | |
| Operating Reserve Demand Curve (ORDC / RT Imbalance costs | Fixed | Yes | No - Included in Bid Price | |
| TX Renewable Portfolio Standards (RPS) Compliance Costs | Fixed | Yes | No - Included in Bid Price | Offers are instructed to include known costs at time of award, any future changes after the date of award will be handled under Section A.14 Electric Regulatory Changes |
| Reliability Unit Commitment (RUC ) Capacity Short Charge Costs | Fixed | Yes | No - Included in Bid Price | |
| Reliability Must Run (RMR) | Fixed | Yes | No - Included in Bid Price | |
| Auction Revenue Rights (ARRs) | Fixed | Yes | No - Included in Bid Price | |
| Minimum of +/- 20 % Annual Bandwidth Based on the Aggregated Usage of Each Pricing Group | Fixed | Yes | No - Included in Bid Price | |
| Enel X Inc. Fee of $.0007 per kWh | Fixed | Yes | No - Included in Bid Price | |
| Renewable Energy Certificates (RECs) that Comply with Section A.12 of this Solicitation (as applicable) | Fixed | Yes | No - Included in Bid Price | |
| Market Securitization Default | Pass-through at cost | No | No | |
| Market Securitization Uplift | Pass-through at cost | No | No | |
| Bridging Solution Option (Phase II Market Redesign) | Pass-through at cost | No | No | Offers are instructed to include known costs at time of award, any future changes after the date of award will be handled under Section A.14 Electric Regulatory Changes |
| ERCOT Emergency Pricing Program (PUCT Rule Section 25.509 and Project No. 54585) | Pass-through at cost | No | No | Offers are instructed to include known costs at time of award, any future changes after the date of award will be handled under Section A.14 Electric Regulatory Changes |
| Applicable Taxes (Including but not limited to TX Gross Receipts Tax (GRT) and TX Public Utility Commission Gross Receipts Assessment tax (PUCA)) | Pass-through at cost | No | Yes | |
| Applicable excise taxes and TDSP charges (Including but not limited to Transmission Cost Recovery Factor, Distribution Cost Recovery Factor, Distribution System Charge, Metering Charge and Customer Charge) | Pass-through at cost | No | Bill Per TDSP Requirements |
000000 INTERNAL#_x000D_
ISONE
| ISONE PRICE COMPONENT CONFIRMATION TABLE | ||||
| Price Component | Treatment | Include in Bid Price? | Requires Individual Line Item Billing? | Notes |
| Block Energy Commodity Costs | Fixed | Yes | No - Included in Bid Price | |
| Ancillary Services and other ISO Costs (Including but not limited to OATT Tariff, Operating Reserves, ISO Administrative Fees, Public Service Commission and/or Public Utility Commission fees) | Fixed | Yes | No - Included in Bid Price | |
| Transmission Loss Credits (TLCs) | Fixed | Yes | No - Included in Bid Price | |
| Auction Revenue Rights (ARRs) | Fixed | Yes | No - Included in Bid Price | |
| Reliability Must Run (RMR) | Fixed | Yes | No - Included in Bid Price | |
| Scheduling | Fixed | Yes | No - Included in Bid Price | |
| Balancing and Congestion Costs | Fixed | Yes | No - Included in Bid Price | |
| Enel X Inc. Fee of $.0007 per kWh | Fixed | Yes | No - Included in Bid Price | |
| Renewable Energy Certificates (RECs) that Comply with Section A.12 of this Solicitation (as applicable) | Fixed | Yes | No - Included in Bid Price | |
| Minimum of +/- 20 % Annual Bandwidth Based on the Aggregated Usage of Each Pricing Group | Fixed | Yes | No - Included in Bid Price | |
| Locational Forward Reserves | Fixed | No | No | |
| Locational Price Differentials | Fixed | No | No | |
| Financial Transmission Rights (FTR) | Fixed | No | No | |
| Marginal Loss Credits (MLCs) | Fixed | No | No | |
| State Mandated Renewable Portfolio Standards (RPS) and Alternate Energy Portfolio Standard (AEPS) Compliance Costs ( Including but not limited to Massachusetts requirements for Clean peak Standard (CPS); Clean Energy Portfolio Standard (CES); and Clean Energy Portfolio Standard – Existing (CES-E), and Maine requirements for Thermal RECs and Class IA RECs. | Pass-through at cost | No | No | Offers are instructed to include known costs at time of award, any future changes after the date of award will be handled under Section A.14 Electric Regulatory Changes |
| Capacity Costs (ICAP ) | Pass-through at cost | No | No | |
| Line Losses including Distribution Losses to the End-use Meter | Pass-through at cost | No | No | |
| FERC Order 745 and FERC 494 / EL05-121-009 Compliance Costs | Pass-through at cost | No | No | |
| Fuel Security Costs (Mystic Cost of Service, Inventoried Energy Program Energy Security Improvements) | Pass-through at cost | No | No | |
| Regional Transmission Rights | Pass-through at cost | No | No | |
| Fuel Costs | Pass-through at cost | No | No | |
| Day-Ahead Ancillary Services Initiative | Pass-through at cost | No | No | |
| Applicable Taxes | Pass-through at cost | No | Yes |
CAISO
| CAISO PRICE COMPONENT CONFIRMATION TABLE | ||||
| Price Component | Treatment | Include in Bid Price? | Requires Individual Line Item Billing? | Notes |
| Energy Commodity Costs | Fixed | Yes | No - Included in Bid Price | |
| Minimum of +/- 20 % Annual Bandwidth Based on the Aggregated Usage of Each Pricing Group | Fixed | Yes | No - Included in Bid Price | |
| Ancillary Services and other ISO Costs (Including but not limited to OATT Tariff, Operating Reserves, ISO Administrative Fees, Public Service Commission and/or Public Utility Commission fees) | Fixed | Yes | No - Included in Bid Price | |
| Balancing and Congestion Costs (Including Congestion Basis Costs) | Fixed | Yes | No - Included in Bid Price | |
| Line Losses including Distribution Losses to the End-use Meter | Fixed | Yes | No - Included in Bid Price | |
| Enel X Inc. Fee of $.0007 per kWh | Fixed | Yes | No - Included in Bid Price | |
| Renewable Energy Certificates (RECs) that Comply with Section A.12 of this Solicitation (as applicable) | Fixed | Yes | No - Included in Bid Price | |
| Marginal Loss Credits (MLCs) | Fixed | Yes | No - Included in Bid Price | |
| Transmission Loss Credits (TLCs) | Fixed | Yes | No - Included in Bid Price | |
| CA Renewable Portfolio Standards (RPS) Compliance Costs | Fixed | Yes | No - Included in Bid Price | Offers are instructed to include known costs at time of award, any future changes after the date of award will be handled under Section A.14 Electric Regulatory Changes |
| Scheduling | Fixed | Yes | No - Included in Bid Price | |
| Resource Adequacy (RA) | Fixed | Yes | No - Included in Bid Price | |
| Financial Transmission Rights (FTR) | Fixed | Yes | No - Included in Bid Price | |
| Reliability Must Run (RMR) | Fixed | Yes | No - Included in Bid Price | |
| Auction Revenue Rights (ARRs) | Fixed | Yes | No - Included in Bid Price | |
| FERC Order 745 and FERC 494 / EL05-121-009 Compliance Costs | Fixed | Yes | No - Included in Bid Price | |
| State Energy Resource Charge | Fixed | Yes | No - Included in Bid Price | |
| Applicable Taxes | Pass-through at cost | No | Yes |
000000 INTERNAL#_x000D_