ATTACHMENT 3 - Phasing Instructions.pdf

PDF 73 KB Posted

Attached to
Y1DA--675-22-706B EHRM Infrastructure Upgrades Construction Lakemont – Orlando, FL
Solicitation number
36C77625B0002
Issued by

About this file

This is a phasing instruction document for an EHRM Infrastructure Upgrades Construction project at Lakemont in Orlando, FL, issued by the Department of Veterans Affairs Technology Acquisition Center.

The document outlines a sequential construction approach where closets will be built one at a time. Each phase requires building a new closet, obtaining approval, moving all switches to the new closet, and then demolishing the old closet as needed before proceeding to construct the next TR (telecommunications room). All work must be performed during the hours specified in the project specifications, though specific hours are not detailed in this document.

View the file

Other files

File Type Posted
Bid Opening Info..docx DOCX document
36C77625B0002 - 2-18-2025.pdf PDF
36C77625B0002 0007.pdf PDF
36C77625B0002 0006.pdf PDF
675-22-706B Technical Questions Spreadsheet - Lakemont Rev 2-14-25.docx DOCX document
Bid Opening Info.docx DOCX document
36C77625B0002 - 2-13-2025.pdf PDF
36C77625B0002 0005.pdf PDF
Additional Site Docs for QA - 2-3-25.zip ZIP file
ATTACHMENT 10 - OVAHCS Physical Security Systems Technical Specs 10-03-24.pdf PDF
ATTACHMENT 3 - Phasing Instructions Revised - 2-5-25.pdf PDF
36C77625B0002 0004.pdf PDF
675-22-706B Technical Questions Spreadsheet - Lakemont 2-5-25.docx DOCX document
Construction Wage Rates - Orange - 1-24-25.pdf PDF
36C77625B0002 0003.pdf PDF
36C77625B0002 0002.pdf PDF
Construction Wage Rates - Orange - 1-3-25.pdf PDF
Site Visit Sign-in Sheet - Lakemont.pdf PDF
36C77625B0002 0001.pdf PDF
36C77625B0002_1.docx DOCX document
ATTACHMENT 4 - Asbestos Report - Part 1.pdf PDF
ATTACHMENT 4 - Asbestos Report - Part 2.pdf PDF
ATTACHMENT 2 - Drawings.pdf PDF
ATTACHMENT 8 - Construction Wage Rates - Orange - 11-1-24.pdf PDF
ATTACHMENT 9 - Site Visit Instructions.pdf PDF
ATTACHMENT 4 - Asbestos Report - Part 3.pdf PDF
ATTACHMENT 5 - Brand Name Justification - Lakemont Redacted.pdf PDF
ATTACHMENT 1 - Specifications.pdf PDF
ATTACHMENT 7 - Limitations on Subcontracting - Construction.docx DOCX document
ATTACHMENT 6 - Pre-Construction Risk Assessment.pdf PDF
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Phasing Instructions

Phasing for the project at Lakemont will be for one closet to be built at a time. Once the closet is approved and all switches are moved to it, start any demo in the old closet that needs to be accomplished and contractor will be able to start construction of the next TR. This will be done until completion of the project. All work needs to be accomplished during the hours listed in the specifications.

File details come from the government source that posted it. Updated .