ATTACHMENT 3 - Phasing Instructions.pdf
PDF 73 KB Posted
- Solicitation number
- 36C77625B0002
About this file
This is a phasing instruction document for an EHRM Infrastructure Upgrades Construction project at Lakemont in Orlando, FL, issued by the Department of Veterans Affairs Technology Acquisition Center.
The document outlines a sequential construction approach where closets will be built one at a time. Each phase requires building a new closet, obtaining approval, moving all switches to the new closet, and then demolishing the old closet as needed before proceeding to construct the next TR (telecommunications room). All work must be performed during the hours specified in the project specifications, though specific hours are not detailed in this document.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Phasing Instructions
Phasing for the project at Lakemont will be for one closet to be built at a time. Once the closet is approved and all switches are moved to it, start any demo in the old closet that needs to be accomplished and contractor will be able to start construction of the next TR. This will be done until completion of the project. All work needs to be accomplished during the hours listed in the specifications.