36C77625B0002 EHRM Infrastructure Upgrades Construction– Lakemont VAMC Technical Questions and VA Response Tracking Sheet
ITEM
NO.
| DATE QUESTION RECEIVED |
| QUESTION |
| GOVERNMENT RESPONSE |
| 1. |
| 1-6-2025 |
| Do you know when the invitation to bid will go out, or a projected date? |
| The Invitation to Bid was issued to SAM.gov on December 5, 2024. |
| 1. |
| 1-6-2025 |
| Please provide a copy of the Site Visit Attendance Sheet. |
| The Site Visit Attendance Sheet was posted to SAM.gov on December 18, 2024. |
| 1. |
| 1-6-2025 |
| What is the magnitude of this project? |
| The Magnitude of Construction for the project is $2,000,000 to $5,000,000. |
| 1. |
| 1-6-2025 |
| How soon after award is NTP expected to be issued? |
| Approximately 30 to 45 calendar days after Awardee receives the executed contract. |
| 1. |
| 1-6-2025 |
| Is there any second site visit planned for each specialty? |
| A second site visit will not be facilitated. |
| 1. |
| 1-6-2025 |
| Is this project sales tax exempt? If the project is sales tax exempt can the government provide a sales tax exemption certificate? |
| Reference Special Notes Regarding FAR 52.229-3, Offerors are hereby notified that all state and local sales or use taxes for construction materials must be included in their bid or proposal price. It is solely the responsibility of the offeror to include all other applicable taxes in their bid or proposal price as well. |
| 1. |
| 1-6-2025 |
| Is this a tax-exempt project? |
| See #6. |
| 1. |
| 1-6-2025 |
| If tax-exempt, will the government provide the prime contractor with a tax-exempt certificate for use by subcontractors and vendors? |
| See #6. |
| 1. |
| 1-6-2025 |
| Please confirm the order of precedence for the contract documents. Does SOW prevail over the specifications and construction drawings? |
| There is no statement of work attached to this requirement. The specifications are the statement of work. |
| 1. |
| 1-6-2025 |
| Is the VA willing to pay for materials stored on and/or offsite such that it meets requisite FAR and VAR clauses for stored materials. There are materials which have a 12+ week lead time which SDVOSB firms cannot procure up front without taking on the financial risk, any schedule impacts could cause irreparable harm financially. Proof of materials possession would include vendor invoices, materials under security systems, insured and bonded, photos of materials, and inspection upon request. |
| In accordance with contract terms and conditions, Contractors should not bid assuming the Government will approve payment for material and/or equipment procured by the Contractor and stored on the construction site, as space is available, or at a local approved location off the site. Payment of stored materials and/or equipment is at the Contracting Officer’s discretion and will be handled on a case-by-case basis during the contract and under such terms and conditions as the Contracting Officer approves. |
| 1. |
| 1-6-2025 |
| Will the VA fully pay for this material/equipment if stored onsite? |
| See #10. |
| 1. |
| 1-6-2025 |
| Due to current potentially significant tariffs being placed on the importation of building materials such as wood or steel by the current Presidential Executive Branch, if a tariff is placed after bid time and before award will the government consider a price escalation on a contract value for products such as steel or wood should the executive branch levee tariffs effecting such materials? Most of these materials would still have been Buy American compliant as the tariffs would increase pricing on all steel or wood materials, regardless of origin. |
| This will be awarded as a Firm Fixed Price (FFP) contract and all escalation should be factored in your FFP. Additionally, FAR 52.216-4 “Economic Price Adjustment – Labor and Material” is not included in the solicitation and will not be added. |
| 1. |
| 1-6-2025 |
| Does this project comply with the NEW Biden Administration Executive Order 14005 concerning the Buy American Act? This executive order limits the purchase of materials from previously approved countries to include Canada and Mexico. Can you please confirm whether materials or equipment manufactured in these previously approved Buy American Act countries outside the United States can or cannot be used on this project? |
| The process of requesting exceptions to the Buy American Act is detailed in the provision at FAR 52.225-12, Notice of Buy American Requirement—Construction Materials Under Trade Agreements, and the clause at FAR 52.225-11 Buy American—Construction Materials under Trade Agreements, in the solicitation. |
| 1. |
| 1-6-2025 |
| If asbestos and/or mold is found that is not listed in the plans, will this be considered an unforeseen situation? And how would the VA like to handle it. |
| Asbestos/or mold NOT INCLUDED ON THE SURVEY AT ATTACHMENT OF THE SOLICITATION, will be considered an unforeseen CONDITION and constitute a modification, which may come at a cost to the VA |
| 1. |
| 1-6-2025 |
| Spec 01 00 00 1.2(D), says "...retained by the Department of Veterans Affairs..." Please confirm who is responsible for testing per 1.2 D of spec 01 00 00. |
| The GC is responsible for testing. |
1.
01 00 00, 1.2 D states "Before placement and installation of work subject to tests by testing laboratory retained by the Department of Veterans Affairs..."
01 45 29 1.1 (page 127 of 1088) says "This section specifies materials testing activities and inspection services required during project construction to be provided by a Testing Laboratory retained by the General Contractor Department of Veterans Affairs."
Question: Attachment 1 Specs: Spec 01 00 00, 1.2 (D) states that the VA will retain the testing laboratory. However, Spec 01 45 29, 1.1 states testing will be retained by the General Contract Department of Veterans Affairs. This is very confusing. Please confirm who will be responsible for testing per these two spec sections?
The GC is responsible for testing activities and inspections services.
| 1. |
| 1-6-2025 |
| How many telecom rooms require the described modifications in this solicitation |
| There are a total of 14 rooms being modified. |
| 1. |
| 1-6-2025 |
| For the multifactor authentication and the cameras, is there existing network connectivity in the rooms, and will these devices need to be on a separate and closed network |
| The latest OVAHCS for Orlando VA is attached (ATTACHMENT 10 - OVAHCS Physical Security Systems Technical Specs 10-03-24) and provided in Amendment 0003. Contractors must follow VA Security design guidelines which are available to all in the VA website, the latest version can be downloaded from the design guide website. The attached document further explains what the Orlando VA utilizes or follows based on the VA Security design guide, is just a tool and communication with VA police is CRUCIAL when determining the equipment needed for VA Security. |
| 1. |
| 1-6-2025 |
| Will the multifactor authentication devices and the cameras require an ATO before use and is the installation company required to obtain that ATO before the project is completed (we do have the ability and skill sets on the team if this is a requirement) |
| Yes, an ATO is required before use. |
| 1. |
| 1-6-2025 |
| Will power specifications for the backup power source be provided per room or is there going to be a site survey to determine specific power requirements |
Please see sheet ET2-501.
| 1. |
| 1-6-2025 |
| The data drops and data runs identified in the solicitation, is there current infrastructure in place for these runs and drops, or will the bidder be expected to establish the infrastructure as part of the bid. In other words, is there available connectivity between the telecom rooms or will all connectivity need to be completely put in place by the contractor |
It is expected that the contractor install new infrastructure.
| 1. |
| 1-6-2025 |
| Is there power currently available to support the PDU's, or will additional power need to be upgraded in the rooms |
| Currently, for the new TR’s, no there are not sufficient power. |
| 1. |
| 1-6-2025 |
| Are CISCO Network electronics/Switches, SFP’s required to be provided by the GC/Div. 27 or Div 28? |
| Yes, the network switches are intended to be by contractor |
| 1. |
| 1-6-2025 |
| Will there be an MCR Rack Face Elevation drawing issued? |
| Elevations are shown on sheet ET2-502. |
| 1. |
| 1-6-2025 |
| Will there be a 1-line connectivity drawing for the MCR reflecting the MDA, HDA cabinet connectivity for FIBER and CAT6A requirements? These are referenced in the specs |
The one-line is shown on sheet ET2-601.
| 1. |
| 1-6-2025 |
| Will there be a Fiber Optic cable and connectivity requirement for this Lakemont building to be connected to the Lake Baldwin Facility? |
| No. |
| 1. |
| 1-6-2025 |
| · DIV 28 – “ATTACHMENT 5 - Brand Name Justification - Lakemont Redacted” -> Mentions in multiple line items that the “Video Surveillance Support (Switch)” is CISCO. “Description” states “Complete installation and programming of network switches …”. |
· Q: Is the DIV 28 Contractor responsible for all parts of Purchase, Supply, Installation and Programming of CISCO Network Switches to support the DIV 28 Scope?
· If so; Please provide the CISCO Switch Model w/ Port Count P/N, Redundant PWR P/N, DNA Term P/N, and Network Module P/N preferred/required?
· If Not; who is to supply the CISCO Switch switches?
The latest OVAHCS for Orlando VA is attached (ATTACHMENT 10 - OVAHCS Physical Security Systems Technical Specs 10-03-24) and provided in Amendment 0003.
| 1. |
| 1-6-2025 |
| · DIV 27 – Similar to last question above, but Minus the Reference “Video Surveillance Support (Switch)”: |
· Q: Is the DIV 27 Contractor responsible for all parts of Purchase, Supply, Installation and Programming of CISCO Network Switches to support the DIV 27 Scope?
· If so; Please provide the CISCO Switch Model w/ Port Count P/N, Redundant PWR P/N, DNA Term P/N, and Network Module P/N preferred/required?
· If Not; who is to supply the CISCO Switch switches?
The latest OVAHCS for Orlando VA is attached (ATTACHMENT 10 - OVAHCS Physical Security Systems Technical Specs 10-03-24) and provided in Amendment 0003. See #18.
| 1. |
| 1-6-2025 |
| · DIV 28 – Video Surveillance VMS – Please provide the VMS Manufacturer Name? Software Version? Software Level (Advanced, Professional, Enterprise, etc.)? |
· Also, Is the DIV 28 Contractor required to provide New (Manufacture Name) NVR’s or Server’s to support the New Cameras?
· If Not; Are Existing NVR or Server VMS Channels available for use for New Pelco Cameras to be provided and installed per this project scope? Effectively DIV 28 contactor not responsible.
The latest OVAHCS for Orlando VA is attached (ATTACHMENT 10 - OVAHCS Physical Security Systems Technical Specs 10-03-24) and provided in Amendment 0003..
| 1. |
| 1-6-2025 |
| Access Control card reader/pin pad, & Bid spec documents specify LENEL: |
| a. | Who is the desired manufacturer of the Card Readers to be installed? |
| b. | What is the software version of the access control system operating? |
| c. | Are we expected to support version updates as part of this contract? |
| d. | Are there sufficient Access Control Software licenses to support the new doors? |
| e. | Is there any existing integration between the access control and CCTV systems? |
f. IF so, what is the base platform (Access Control or Video) that operate both?
g. Is there a current vendor/installer of this system that we can contact?
h. Is there an existing SSA in place for Access Control, and who is vendor servicing SSA?
i. Are there existing software licenses available from the VA that can be used for new reader / Controllers?
j. Does new access control need to be FICAM Compliant? Is there a current FICAM License?
k. Is CESIP Certification required?
l. Is there an existing interface between Access Control & Video.
m. Does the VA currently have High Assurance & Registration Software?
The latest OVAHCS for Orlando VA is attached (ATTACHMENT 10 - OVAHCS Physical Security Systems Technical Specs 10-03-24) and provided in Amendment 0003. See #18.
| 1. |
| 1-6-2025 |
| Drawings for CCTV cameras & Bid spec documents do not specify what Camera system is currently in place for this project, please answer the following questions: |
| a. | WHO is the manufacturer of the current video management system? |
| b. | On what existing software version is the current video management system operating? |
| c. | Are we expected to support version upgrades as part of this contract? |
| d. | Are there sufficient existing Camera Licenses to support the new cameras? |
| e. | Are the cameras to be 2MP pan/tilt/zoom or fixed dome? |
| f. | Is there a current vendor/installer of this system that we can contact? |
e. is there a main Video Server or are NVR’s in use?
f. What is the preferred camera brand, megapixel, stationary, PTZ, VF?
g. Will the VA provide all Network switches?
h. Is there an existing SSA in place for VIDEO, and who is vendor servicing SSA?
i. Is there an existing interface between Video & Access Control The latest OVAHCS for Orlando VA is attached (ATTACHMENT 10 - OVAHCS Physical Security Systems Technical Specs 10-03-24) and provided in Amendment 0003. See #18.
| 1. |
| 1-6-2025 |
| Ref drawing AE2-201 & 202- Will keynote numbers be provided within symbols and will keynotes be provided on each drawing? |
| The latest OVAHCS for Orlando VA is attached (ATTACHMENT 10 - OVAHCS Physical Security Systems Technical Specs 10-03-24) and provided in Amendment 0003. See #18. |
| 1. |
| 1-6-2025 |
| Ref drawing AE2-103- Will keynote be provided for detail 1? Are all data symbols shown new or existing? |
| There are no keynotes associated with the plan. See floor plan symbols for new and existing data drops. |
| 1. |
| 1-6-2025 |
| Question: ET2-800 shows a complete grounding network with new grounding electrodes. Does the VA want this total system and routing installed including Air terminals and antenna grounding? |
| Yes, grounding riser detail on ET2-800 is the VA standard total grounding system. Provide as shown. |
| 1. |
| 1-6-2025 |
| Question: ET2-800 shows a complete grounding network with new grounding electrodes. Does the VA want this total system and routing installed including Air terminals and antenna grounding? |
| See above. |
| 1. |
| 1-6-2025 |
| Question: In areas such as 3rd floor common area and Rm 123B, how would the VA like to drop data/com cables to access RJ45s? |
| Usage of power poles are acceptable. Location of proposed power poles would need to be coordinated with COR. |
| 1. |
| 1-6-2025 |
| Question: Will the VA require all new network racks, network switches, and patch panels for all new TRs being renovated and built? |
| Yes |
| 1. |
| 1-6-2025 |
| Question: ET2-101, ET2-201, and ET2-301 shows cable tray routing in the drop ceiling. Are these routes existing? |
| These cable tray do not exist and are intended to be new. These routing are for diagrammatical purposes only, actual routing is depended on field conditions and existing overhead utilities. |
| 1. |
| 1-6-2025 |
| Question: Can our team get a set of electrical as-builts with the locations of panel rooms vs. TRs (distances)? |
| Review the VA supporting documents made available in the zip file labeled Additional Site Docs -2-3-25 for QA, posted in amendment 0003, posted to SAM.gov. These documents will contain the answer to this question. |
| 1. |
| 1-6-2025 |
| Do any of the VA Hospital, Orlando, FL. "OVAHCS" requirements apply to Lakemont? |
If so, Which ones apply?
The latest OVAHCS for Orlando VA is attached (ATTACHMENT 10 - OVAHCS Physical Security Systems Technical Specs 10-03-24) and provided in Amendment 0003. See #18.
| 1. |
| 1-6-2025 |
| Are there specific Pelco, Lenel, Cisco model #'s required? |
| The latest OVAHCS for Orlando VA is attached (ATTACHMENT 10 - OVAHCS Physical Security Systems Technical Specs 10-03-24) and provided in Amendment 0003. See #18. |
| 1. |
| 1-6-2025 |
| Structured Cabling - |
1. Per the site visit, we think Room 131 physical location might be inaccurately depicted on the ET drawings. Can you confirm if the entry / exist door and overall location is correct?
1. The specifications state in various places that the building is a “Medical Center”. It also states “The Medical Center must maintain its operation 24 hours a day 7 days a week. Please confirm if this is true, or is it an administrative building?
1. Specification section 01 00 00 -1, page 8 states core working hours are Monday-Friday, 7:00 a.m. to 4:30 p.m. except weekends and established federal holidays. However, the Phasing plan states the Medical Center must maintain its operation 24 hours a day 7 days a week. We need to determine how much weekend and or holiday time our workers need to be on site. Can you please clarify?
1. Per the site visit, we noticed most of the rooms on all 3 floors were fully occupied with employees. Most furniture appears to be cubicles that have work stations which will require access by our telecom technicians. For our proposed phasing plan, will the existing employees in specific sections be relocated prior to our work being done, or do we need to account for a certain percent of work tasks being done after normal work hours? If so, where will the employees in the section/floor we are during normal work hours be relocated?
1. Per specification 27 05 33 – 2, Innerduct is required in the cable tray. There is nothing mentioned in the specs or the drawings whether the cable should be armored or not. Can we include armored fiber optic cable in lieu of Innerduct and non-armored fiber optic cable?
0. Location of Room 131 is accurate as it is consistent throughout the entire set.
0. The building is Administrative.
0. See the revised S02 - ATTACHMENT 3 - Phasing Instructions Revised - 2-5-25. The hours listed in the specs are the hours the building is in operation. The work for this project will need to take place after hours. Follow the WHEN procedures in the revised attachment. All daytime work that may need to be performed, needs to be coordinated with the COR for prior approval.
0. The work will be performed after hours, when the employees are not working.
0. Armored fiber optic cables are acceptable.
1. We did not see any Networking switches in Division 27 specs. They only mention installing and configuring but not providing switches. Can you confirm if we are just providing labor for installing and configuring switches, or if we need to provide the hardware as well?
2. The Division 28 specs only reference Security Networking, and the drawings make mention of the CISCO C9300 – 48P. Are Division 27 networking switches also required for the whole facility?
3. If Networking switches are required, please confirm if the CISCO C9300 model is being requested, or if there are other specs the switches need to meet?
The latest OVAHCS for Orlando VA is attached (ATTACHMENT 10 - OVAHCS Physical Security Systems Technical Specs 10-03-24) and provided in Amendment 0003. See #18.
| 1. |
| 1-6-2025 |
| Access Control – |
1. The document titled “ATTACHMENT+5+-+Brand+Name+Justification+-+Lakemont+Redacted” says “Complete installation and programming of card readers and communication components matching existing to ensure and maintain proper operation of the existing physical access control system (PACS).” Is the existing Lenel OnGuard system a local on-site system or is it part of a multi-facility Enterprise system? What version of OnGuard is the Software?
2. The document titled “ATTACHMENT+5+-+Brand+Name+Justification+-+Lakemont+Redacted” says “Complete installation and programming of video surveillance system matching existing to ensure and maintain proper operation of the existing physical access control system (PACS).” Is the existing Video Xpert Enterprise or the Professional version? Is additional camera licenses and video storage servers needed for the additional cameras?
3. The document titled “ATTACHMENT+5+-+Brand+Name+Justification+-+Lakemont+Redacted” says “Complete installation and programming of network switches to support surveillance system matching existing to ensure and maintain proper operation of the existing surveillance system.” What model number of Cisco PoE switches are currently being used for the existing surveillance system?
4. What model or part number for the cameras is required for this project?
5. What is the model or part number of the existing card readers/keypads?
6. Does each closet require a new door controller, power supply and network switch or are there existing door controllers, power supplies and switches already in the closet locations?
1-5. The latest OVAHCS for Orlando VA is attached (ATTACHMENT 10 - OVAHCS Physical Security Systems Technical Specs 10-03-24) and provided in Amendment 0003. See #18.
6. Closets will need new hardware.
| 1. |
| 1-6-2025 |
| Who is responsible for providing and installing the Communication Data Networks switches? |
| The Contractor. |
| 1. |
| 1-6-2025 |
| Will new Wireless Access Point be GFCI? |
| No. |
| 1. |
| 1-6-2025 |
| Will existing Wireless Access Point need new category 6A cabling? |
| Yes, new CAT6A cabling |
| 1. |
| 1-6-2025 |
| Will CCTV Pre-Cabling be required? Cameras not shown in drawings except for IT Rooms. |
| Under this project, cameras are only for IT rooms and will be installed by awardee to include offeror running necessary cabling. |
| 1. |
| 1-6-2025 |
| Will Existing Data Room cameras require new cabling? |
| No. |
| 1. |
| 1-6-2025 |
| Drawing ET2-404 Tray Reno details shows single layer of tray. Drawing ET2-800 shows a 2-tier |
tray system (1) for backbone and (1) for horizontal cabling. Which drawing detail is correct?
ET2-404 is for diagrammatical 2D view while ET2-800 is a 2-tier is more an “elevation view”. Provide as shown on ET2-800.
| 1. |
| 1-6-2025 |
| Specification 270536, note 2.2 Fiber Optic Cable Raceway calls out 4”x4” PVC raceway. Drawing |
ET2-404 IT Room Reno Plans does not show fiber raceway. Will the 4”x4” raceway be needed in the IT Rooms?
Provide as shown in specs for fiber optic.
| 1. |
| 1-6-2025 |
| Drawing example ET2-303. Data drops marked with 4D, 7D, 8D, 9D,10D, 11D and 14D are these |
equal to number next to the D or will these be considered dual data cables to each. According to specification 271000, note 2.4B (B. All horizontal structured cabling shall have a minimum of 2 cables per WAO).
The number adjacent to the “D” is intended to be the number of data ports/cables.
| 1. |
| 1-6-2025 |
| How are the furniture locations being fed? Power Poles, Wall Junction Boxes or Floor boxes? |
| Usage of power poles are acceptable. Location of proposed power poles would need to be coordinated with COR. |
| 1. |
| 1-6-2025 |
| What is FMS network cabling? |
| FMS network cabling belongs to the VA’s facilities maintenance system and is separate from sensitive records; EHRM. |
| 1. |
| 1-6-2025 |
| Data outlets, per print ET2-103 general note A, a new data outlet needs to be added adjacent to |
existing outlets. Some walls are covered with data outlets, the installation of a new data drop in addition to the existing ones could be challenging due wall spaces. Could you please clarify if existing pathways can be used in lieu of a new one?
The intent for new data drops adjacent to the existing is to maintain the existing until new TR’s are fully functional. Eliminating down time.
| 1. |
| 1-6-2025 |
| Data outlets, some desks are shown on the prints, but no data outlets are associated with them. |
Could you please confirm that it is correct?
That is correct.
| 1. |
| 1-6-2025 |
| Could you please confirm if panel ELDP-B requires 42 KAIC? |
| Based on the feeder schedule and calculations, the panel is required to have a minimum of 26.93kAIC. The next available standard size is 42kAIC. |
| 1. |
| 1-6-2025 |
| Is Tuberculosis Testing (TBT) required for all personal? |
| Pursuant to Paragraph 9(p), Responsibilities of the Contractor, Post Award Conference Notes, Tuberculosis Screening (see Specifications Section 01 35 26) is required ninety (90) days prior to assignment to the worksite. |
| 1. |
| 1-6-2025 |
| Could you please confirm if ELDP-B and transformer XFMR ELDP-B locations are correct? Per site |
visit this area seems to be occupied by other electrical equipment’s.
The VA is unable to answer this question based on lack of specific details.
| 1. |
| 1-6-2025 |
| Per print ET2-401 not e7 a new TMGB needs to be installed and connected to the intersystem |
bonding system per print ET2-800. Could you please confirm the location of the intersystem bonding terminations?
Location is in the main electrical room.
| 1. |
| 1-6-2025 |
| Prints calls for provide a grounding and bonding system per TIA-607-D. Print ET2-404 note #1 |
calls for a #4 CU from the SBB to the TMGB. Please confirm that #4 is correct.
Please utilize #4.
| 1. |
| 1-6-2025 |
| Please confirm the model of POE network switch required for the CCTV and Access Control |
equipment ((including any required software, number of ports, redundant power (including wattage), etc.)).
The latest OVAHCS for Orlando VA is attached (ATTACHMENT 10 - OVAHCS Physical Security Systems Technical Specs 10-03-24) and provided in Amendment 0003. See #18.
| 1. |
| 1-6-2025 |
| Section 280500 (page 49) states 8-hours of runtime is needed for the security equipment’s UPS, |
281300 states 12 hours (page 45), and 281353 (page 8) lists 90 minutes. Please clarify which is correct.
12 hours.
| 1. |
| 1-6-2025 |
| Please confirm the approved model numbers or manufacturers of the CCTV equipment. |
| The latest OVAHCS for Orlando VA is attached (ATTACHMENT 10 - OVAHCS Physical Security Systems Technical Specs 10-03-24) and provided in Amendment 0003. See #18. |
| 1. |
| 1-6-2025 |
| Please confirm the approved model numbers or manufacturers of the Access Control and |
Intrusion Detection equipment.
The latest OVAHCS for Orlando VA is attached (ATTACHMENT 10 - OVAHCS Physical Security Systems Technical Specs 10-03-24) and provided in Amendment 0003. See #18.
| 1. |
| 1-6-2025 |
| Will the new cameras be connected to an existing NVR or will a new recorded need to be |
included in the bid?
Provide new in bid.
| 1. |
| 1-6-2025 |
| Are the motion detectors shown in the telecom rooms reporting back to an IDS panel or the |
access control system?
Motion detectors report back to the IDS panel.
| 1. |
| 1-6-2025 |
| Will all security cabling be run in conduit or via j-hooks? |
| Please run security cabling through conduit. |
| 1. |
| 1-6-2025 |
| Do we need to x-ray (GPR) if any vertical penetrations are required? |
| Yes |
| 1. |
| 1-6-2025 |
| Who is providing the Category 6A patch cords from the patch panel to the network switches? |
| Contractor |
| 1. |
| 1-6-2025 |
| Will this work need to be performed during normal working hours or during the afterhours? |
| Work will need to be performed during WHEN (Weekends, Holidays, Evenings, Nights) hours. Site contractor access hours will be between 1600 to 0600 Sunday through Saturday. |
| 1. |
| 1-6-2025 |
| Will this project require the use of HEPA Carts? |
| Follow ICRA/PCRA level requirements. Document was provided |
| 1. |
| 1-6-2025 |
| Is there is any Mold and/or Asbestos present in the project areas that require abatement? Can you please provide the latest Asbestos & Mold survey / inspection of the work areas. |
| Asbestos documents were already provided in the Solicitation as ATTACHMENT 4 - Asbestos Report - Part 1, ATTACHMENT 4 - Asbestos Report - Part 2, and ATTACHMENT 4 - Asbestos Report - Part 3. No other documents are available. |
| 1. |
| 1-6-2025 |
| If found would mold/ remediation and/or asbestos abatement be consider an unforeseen situation and can be part of a potential additional request for compensation? |
| If these conditions were not communicated to the contractor in the contract documents upon award of the contract, these would be compensable conditions if the contractor follows the provisions of FAR 52.236-2 Differing Site Conditions. |
| 1. |
| 1-6-2025 |
| Will there be designated parking at the job site, as the parking at this location is very limited. |
| Parking will be designated. |
| 1. |
| 1-6-2025 |
| Please provide Cut-Sheets for the Access Points. |
| The latest OVAHCS for Orlando VA is attached (ATTACHMENT 10 - OVAHCS Physical Security Systems Technical Specs 10-03-24) and provided in Amendment 0003. See #18. |
| 1. |
| 1-6-2025 |
| Do you require plenum or non-plenum CAT 6A cables? |
| Plenum. |
| 1. |
| 1-6-2025 |
| Existing data cables and jumpers in the Data Closets are live and active. |
In some cases, the existing conditions may require moving around, or in worst case scenario, disconnection of jumpers for the installation of the new patch panel an or punch down.
• Will OI&T be present to oversee the installation of the new patch panels?
• Who is responsible for existing cable management in the Data Closets during the installation of the new patch panels and cable punch-down?
Coordination with VA‘s OI&T will be required for both questions.
| 1. |
| 1-6-2025 |
| ICRA (Infection Control Risk Assessment): will this project include implementing ICRA, and if so can the VA provide clarification on which areas and which class of ICRA will be required in those areas? |
| See ICM on GI.00 of the ATTACHMENT 2 – Drawings posted in the Solicitation. |
| 1. |
| 1-6-2025 |
| Can the VA clarify what Color the cable installed into the conduit needs to be? |
| FA-Red |
Comm-Orange BMS-Blue Nurse Call-Green Paging-White
But this can be further clarified by awardee through the normal submittal process
| 1. |
| 1-6-2025 |
| Will the VA be designating a person/persons, to allow access to areas that have been scheduled to be worked in that may be locked or require special access? |
| VA will work with awardee for badging. |
| 1. |
| 1-6-2025 |
| Will the onsite superintendent be required to be employed by the Prime Contractor or can that person be provided by the subcontractor. |
| Prime firm is responsible |
| 1. |
| 1-6-2025 |
| How many areas can be work at one time for rough in, installations overall such as installing conduit in? |
| The VA will work with awardee to allow them access to the site in a controlled manner, in order to achieve this, no more than two areas can be worked at the same time. |
| 1. |
| 1-6-2025 |
| What type of firestop is required? |
| See spec section 07 84 00 |
| 1. |
| 1-6-2025 |
| What hours can be worked after hours? |
| Work will need to be performed during WHEN (Weekends, Holidays, Evenings, Nights) hours. Site contractor access hours will be between 1600 to 0600 Sunday through Saturday. |
| 1. |
| 1-6-2025 |
| How is installation in the restricted areas being handled? |
| Badging and escorts, if necessary, will be provided to awardee. |
| 1. |
| 1-6-2025 |
| Please clarify if a superintendent can be a dual hat to cover the requirements of SSHO? |
| Yes. The superintendent can also be the SSHO. |
| 1. |
| 1-6-2025 |
| If no to the question above, will the SSHO need to be full-time for this project? |
| No longer applicable as the SSHO can also be the Superintendent. The Superintendent must be full time. |
| 1. |
| 1-6-2025 |
| The area of work on adjacent areas going to be active with patients and VA Staff, can you confirm the best path for ingress and egress for this area during the duration of the project? |
| Active with VA staff. |
| 1. |
| 1-6-2025 |
| Will the VA provide VA badging to subcontractors or as long as they have a chaperone with a VA badge will be okay? |
| VA will work with the awardee for badging |
| 1. |
| 1-6-2025 |
| The project's SOW states that the working hours would be regular hours. Can this work be performed during not regular hours (afterhours, nighttime or weekends)? |
| See #71. |
| 1. |
| 1-6-2025 |
| Would the VA be okay to use Procore as a project record system for all project documents (Submittals, RFIs, daily reports, Correspondence, etc.) |
| Acceptable. |
| 1. |
| 1-6-2025 |
| What would be the hours that the contractor can do noise, such as demolition and other tasks, since there is a lot of activity around the work area. |
| Work will need to be performed during WHEN (Weekends, Holidays, Evenings, Nights) hours. Site contractor access hours will be between 1600 to 0600 Sunday through Saturday. |
| 1. |
| 1-6-2025 |
| Is there a designated laydown and dumpster area for the contractor? |
| An area will be assigned for laydown and dumpster. |
| 1. |
| 1-6-2025 |
| Please provide the required outage request lead-time and process for service shutdown related MEP? |
| Normal 14 days |
| 1. |
| 1-6-2025 |
| Has the VA validated the equipment schedules for MEP can comply with Buy American Act? |
| Contractor is responsible to meet Buy America Act, any deviations will have to be approved by CO. |
| 1. |
| 1-6-2025 |
| Will the VA allow deviations to Buy American Act if the noted products are not available? |
| The process of requesting exceptions to the Buy American Act is detailed in the provision at FAR 52.225-12, Notice of Buy American Requirement—Construction Materials Under Trade Agreements, and the clause at FAR 52.225-11 Buy American—Construction Materials under Trade Agreements, in the solicitation. |
| 1. |
| 1-6-2025 |
| Will pay applications for materials secured on site or in a bonded warehouse be approved for payment? |
| See #11. |
| 1. |
| 1-6-2025 |
| Please confirm the order of precedence for the contract documents. Does SOW prevail over the specifications and construction drawings? |
| See #9. |
| 1. |
| 1-6-2025 |
| Will the VA allow deviations to Buy American Act if the noted products are not available? |
| Contractor is responsible to meet Buy America Act, any deviations will have to be approved by CO |
| 1. |
| 1-6-2025 |
| Will the VA accept contract modification if the as-built drawings demonstrate conditions that exclude design considerations or impart differing site conditions? |
| All design considerations must be submitted on a RFI and approved both by the AE of record and the COR which will may constitute a modification resulting in an increase of price to the total contract value. Per FAR 52.236-2, allows for differing site conditions that arise during construction, which may come at a cost to the VA. Changes to the contract will follow FAR 52.243-1/4. |
| 1. |
| 1-6-2025 |
| To promote fairness in bids received, please specify what quantity of hazardous materials we should plan to abate in each TR room. |
| Asbestos documents provided |
| 1. |
| 1-6-2025 |
| Will the Owner or GC be responsible for purchasing testing and lab services? |
| See #15. |
| 1. |
| 1-6-2025 |
| Is there any Project Phasing and the estimated duration of each phase that the VA would prefer? |
| See the revised S02 - ATTACHMENT 3 - Phasing Instructions Revised - 2-5-25. Each room is unique and is the responsibility of the GC to complete. |
| 1. |
| 1-6-2025 |
| Please confirm the current design documents meet current VA TIL guidelines. |
| The documents in the solicitation are to be considered current unless Government guidance is provided otherwise. |
| 1. |
| 1-6-2025 |
| Please confirm the issued drawing set is the latest and complete set. |
| The drawings and attachments listed in the solicitation are the latest and complete set. Based on the answers to the Technical Questions, an Updated Bid Set to include the updated areas resulting from the technical questions may be issued as part of the contract to the awarded GC. |
| 1. |
| 1-6-2025 |
| Are there any ongoing or planned projects that the general contractor will need to coordinate with? (For example, access control replacement projects) |
| Not at the time of answering RFIs. |
| 1. |
| 1-6-2025 |
| If there is any unforeseen situation in a certain IT Room, will the GC be able to start the next phase while the issue is resolved? Or will the project stop? |
| If this type of situation occurs, there may be a possibility that the work can move to another area. However, this is dependent on the situation and the Post Award CO's full knowledge of the situation. The Post Award CO will always work with the COR and GC to develop a solution to keep the project moving, provide the GC with the maximum ability to control "means and methods" and as a last resort, if necessary, issue a Suspension of Work. |
| 1. |
| 1-6-2025 |
| Please provide missing RCP keynotes on sheets AE2-201 and AE2-202. |
| See #32. |
| 1. |
| 1-6-2025 |
| There is no pre-demolition note requiring the pre-T&B of the second floor. Is it the A/E's intention to have this area pre-T&B and returned to same air flows after construction? As with the 1st and 3rd floors? |
| Yes. Follow design |
| 1. |
| 1-6-2025 |
| Will each zone be completely unoccupied during construction? |
| VA staff will use building during Normal hours. |
| 1. |
| 1-6-2025 |
| Please confirm that this is a dual hat project with a Super/QCM and a separate SSHO. |
| The superintendent can dual hat as the SSHO. A separate QCM is required. |
| 1. |
| 1-6-2025 |
| What is required for equipment protection that is to remain. |
| Question could not be answered as it is incomplete. |
| 1. |
| 1-6-2025 |
| Where will the project laydown area be? |
| A laydown area will be identified after award. |
| 1. |
| 1-6-2025 |
| If spec Section 01 45 35 Special Inspections will be required, please provide the schedule of special inspections. If it is not required, please confirm it is not applicable to this project. |
| The GC shall provide a QC plan and identify the special inspections required as it relates to the Specifications. Review the Specifications and provide special inspections as required by the ICC. Per the spec the GC should include the special inspections plan in the CQC plan. |
| 1. |
| 1-6-2025 |
| Part of the scope mentions hazardous material abatement. What hazardous material is expected? The HazMat survey in the solicitation did not locate any expected HazMat. |
| Available documents have been provided in the solicitation. |
| 1. |
| 1-6-2025 |
| For the phasing plan, are temp barriers to be constructed that cut off portions of rooms as shown on the drawings? Or is it the intention that the phasing will include rooms in their entirety with the existing partition walls acting as the perimeter of the phase? |
| No, the space will be used by the VA during the day. Contractor to work nights. See the revised S02 - ATTACHMENT 3 - Phasing Instructions Revised - 2-5-25. The hours listed in the specs are the hours the building is in operation. The work for this project will need to take place after hours. Follow the WHEN procedures listed in the revised attachment. All daytime work that may need to be performed, needs to be coordinated with the COR for prior approval. |
| 1. |
| 1-6-2025 |
| Detail 6 on Sheet ET2-401 shows the new transformer to be installed adjacent to the double doors. During the site visit, it did not appear that there was sufficient space to allow for the installation in this area. Please confirm. |
| Please provide proposed location within the same room for AE to review. |
| 1. |
| 1-6-2025 |
| Will pay applications for materials secured on site or in a bonded warehouse be approved for payment? |
| See #11. |
| 1. |
| 1-6-2025 |
| Due to the current economic inflation, Will the government reduce the amount of time that contractors must hold their numbers to 60 days? By reducing the inflation risk, the government will avoid escalations costs that general contractors and subcontractors must account for. |
| No. |
| 1. |
| 1-6-2025 |
| Will the government consider the inclusion of an Economic Price Adjustment Clause in accordance with Federal Acquisition Regulations (FAR), Subpart 16.203 "Fixed-price contracts with economic price adjustment" and the related contract clause language in FAR 52.216-2, 3, 4? We believe such a clause is appropriate for the following reasons: |
· The contract involves an extended period of performance with significant costs to be incurred beyond 1 year after performance begins;
· The contract amount subject to significant fluctuations in price is substantial [may want to list specific examples of highly unstable pricing items within the scope]; and The economic variables for labor and materials are too unstable to permit a reasonable division of risk between the Government and the contractor, without this type of clause."
This procurement will remain as a firm fixed priced award. The government will not consider this request.
| 1. |
| 1-6-2025 |
| Who is responsible for providing the Cisco “managed” switches for the PACs System (access controls)? |
| The latest OVAHCS for Orlando VA is attached (ATTACHMENT 10 - OVAHCS Physical Security Systems Technical Specs 10-03-24) and provided in Amendment 0003. |
| 1. |
| 1-6-2025 |
| Who is responsible for providing the Cisco “managed” switches for the CCTV System (cameras)? |
| The latest OVAHCS for Orlando VA is attached (ATTACHMENT 10 - OVAHCS Physical Security Systems Technical Specs 10-03-24) and provided in Amendment 0003. |
| 1. |
| 1-6-2025 |
| Reference 01 91 00 General Commissioning Requirements, 1.8 . Is the Prime Contractor required to provide a Commissioning Agent (CxA)? |
| Per the 01 91 00 specification, 1.8B(1) The Prime Contractor will engage the CxA under this contract to act as a third party entity which reports directly to the VA. |
| 1. |
| 1-6-2025 |
| Will the VA allow deviations to Buy American Act if the noted products are not available? |
| The process of requesting exceptions to the Buy American Act is detailed in the provision at FAR 52.225-12, Notice of Buy American Requirement—Construction Materials Under Trade Agreements, and the clause at FAR 52.225-11 Buy American—Construction Materials under Trade Agreements, in the solicitation. |
| 1. |
| 1-6-2025 |
| Will the VA accept contract modification if the as-built drawings demonstrate conditions that exclude design considerations or impart differing site conditions? |
| All design considerations must be submitted on a RFI and approved both by the AE of record and the COR which will may constitute a modification resulting in an increase of price to the total contract value. Per FAR 52.236-2, allows for differing site conditions that arise during construction, which may come at a cost to the VA. Changes to the contract will follow FAR 52.243-1/4. |
| 1. |
| 1-6-2025 |
| To promote fairness in bids received, please specify what quantity of hazardous materials we should plan to abate in each TR room. |
| See #73. |
| 1. |
| 1-6-2025 |
| Will the VA or the Prime Contractor be responsible for purchasing testing and lab services? |
| See #15 and #16. |
| 1. |
| 1-6-2025 |
| As a result of the effect of COVID-19 throughout the U.S., and the resulting Federal, State and local governments’ responses / requirements are there any new work requirements or mandates that will be required by VA on this project. |
| No current mandates |
| 1. |
| 1-6-2025 |
| Has the VA validated that the equipment schedules for MEP can comply with Buy American Act? |
| Meet Buy America, any deviations have to be discussed and approved by CO |
| 1. |
| 1-6-2025 |
| Please clarify if WHEN hours are required for all work. |
| Work will need to be performed during WHEN (Weekends, Holidays, Evenings, Nights) hours. Site contractor access hours will be between 1600 to 0600 Sunday through Saturday. |
| 1. |
| 1-6-2025 |
| Can this work be performed during not regular hours (afterhours, nighttime, or weekends) to expedite the remediation process, and minimize the impact to patient and staff care. |
| Work will need to be performed during WHEN (Weekends, Holidays, Evenings, Nights) hours. Site contractor access hours will be between 1600 to 0600 Sunday through Saturday. |
| 1. |
| 1-6-2025 |
| Is there any ICRA requirement for this project? If yes, could you please confirm what are the areas that require them? |
| See ICM on GI.00 of the ATTACHMENT 2 – Drawings posted in the Solicitation. |
| 1. |
| 1-6-2025 |
| Is there any Project Phasing and the estimated duration of each phase? |
| See answer to question #104. |
| 1. |
| 1-6-2025 |
| Is the VA’s (PSRDM) Physical Security and Resiliency Design Manual Revised January 1, 2024, applicable to this project? |
| Security measures have been implemented, provide bids per the documents. |
| 1. |
| 1-6-2025 |
| Reference Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS, para 1.7 SYSTEMS TO BE COMMISSIONED |
Can the VA confirm that the list of systems provided is all that is required for 01 91 00?
GC to FOLLOW the list provided in this spec section.
| 1. |
| 1-6-2025 |
| Reference Section 01 91 00, para 1.7 SYSTEMS TO BE COMMISSIONED |
The drawings do not appear to have anything related to a new boiler fuel system or generator fuel system as noted in the list. Can the VA confirm that a boiler fuel system or generator fuel system is not within the scope of this project?
GC to FOLLOW this spec section. There is no work required for boiler fuel system, this was left as reference only.
| 1. |
| 1-6-2025 |
| Reference Section 01 91 00, para 1.7 SYSTEMS TO BE COMMISSIONED |
The list of systems to be commissioned seems to be missing many of the systems included under the drawing packages HVAC IT, & fire protection. Are we to include commissioning of these systems or just what is on the list?
GC to FOLLOW this spec section. The project work is for IT which include Fire protection in and around new IT closets to be built in this project.
| 1. |
| 1-6-2025 |
| Can the required SSHO positions be fulfilled by the qualified superintendent? |
| See answers to question 87. |
| 1. |
| 1-6-2025 |
| Will the Government provide comprehensive written badging requirements for the project if badging is required? |
| VA will work with awardee for badging |
| 1. |
| 1-6-2025 |
| Where will the designated parking area be for workers accessing the construction site? |
| Parking area will be provided. |
| 1. |
| 1-6-2025 |
| Will the VA accept the use of Procore Project Management software as the primary submittal and data tracking tool for this project? |
| Acceptable |
| 1. |
| 1-6-2025 |
| Does the VA have a fire alarm service provider that they currently work with? What is the name and contact information of the person or persons that will need to be coordinated with for security and fire alarm and suppression systems work and/or disruptions? |
| The VA has a Fire Alarm contract with Dynafire, however awardee to provide their own sub for this portion and must meet VA design guide. |
| 1. |
| 1-6-2025 |
| Is AISC (American Iron and Steel Certification) required for the structural steel fabrication and/or erection for this project? |
| Meet Buy America Act and appropriate clauses and provisions in the Solicitation. |
| 1. |
| 1-6-2025 |
| Reference Electrical Panel Schedules |
Can the VA confirm that circuits not identified as “SPACE” on any given schedule vs. having “SPARE”, that “SPARE” means new breakers are required to be installed in all panels that are existing?
For all new panels, if labeled as “spare” the intent is to have contractor provide spare breakers.
It is not intended to provide spare breakers in existing panels.
| 1. |
| 1-6-2025 |
| Can the VA provide the floor to deck heights of each floor? |
| Review the VA supporting documents made available in the zip file labeled Additional Site Docs for QA - 2-3-25, posted in amendment 0003, posted to SAM.gov. These documents will contain the answer to this question. |
| 1. |
| 1-6-2025 |
| Can the VA provide the deck type of each floor IE; concrete, bar joists? |
| Review the VA supporting documents made available in the zip file labeled Additional Site Docs -2-3-25 for QA, posted in amendment 0003, posted to SAM.gov. These documents will contain the answer to this question. |
| 1. |
| 1-6-2025 |
| Can the VA provide the utility-owned communication demarcation entrance room locations? |
| Room 134. |
| 1. |
| 1-6-2025 |
| Can the VA provide the utility-owned communication service paths for the campus? |
| Review the VA supporting documents made available in the zip file labeled Additional Site Docs -2-3-25 for QA, posted in amendment 0003, posted to SAM.gov. These documents will contain the answer to this question. |
| 1. |
| 1-6-2025 |
| Can the VA provide the inter-building A/B side fiber conduit/cabling routing from the entrance rooms of each floor to the TR or TE rooms in order to meet the PSRDM of 50’ separation? |
| The drawings are diagrammatical, the contractor would need to field verify and coordinate with existing utilities. |
| 1. |
| 1-6-2025 |
| Per the PDSM “Pathways must not be located closer than 50 feet (15 m) to each other; pathways must enter served buildings at different locations and must not be exposed on the building exterior.” Can the VA provide the room locations for the OSP entrances per building meeting the PDSM having two entrances 50’ apart? |
| Room 134. |
| 1. |
| 1-6-2025 |
| Reference all architectural new work plans |
The drawings do not specify the wall type at walls where the door is to be removed and infilled. Can the VA clarify which wall type we should use for all the doors being removed and infilled?
See wall type call outs and wall types on sheets AE-505. Infill walls will match adjacent construction and finish.
| 1. |
| 1-6-2025 |
| Can the VA clarify that it is acceptable to run loose 6A cabling in the wall space at locations that do not have conduits to a backbox? |
| Please provide conduit in walls. |
| 1. |
| 1-6-2025 |
| Can the VA clarify that it is acceptable to install the new 6A cabling in the existing conduit provided the fill rate is not exceeded? |
| The intent for new data drops adjacent to the existing is to maintain the existing until new TR’s are fully functional. Eliminating down time. |
| 1. |
| 1-6-2025 |
| Can the VA clarify that all existing conduit drops to the backbox are ½” EMT therefore that is why the drawings reflect installing and new drop next to the existing? |
| The intent for new data drops adjacent to the existing is to maintain the existing until new TR’s are fully functional. Eliminating down time. |
| 1. |
| 1-6-2025 |
| Can the VA clarify that that if the existing EMT is ¾” to a backbox the existing can be used for the 2 data cables required per the drawings even though this would exceed the max fill rate? |
| The intent for new data drops adjacent to the existing is to maintain the existing until new TR’s are fully functional. Eliminating down time. |
| 1. |
| 1-6-2025 |
| Can the VA clarify each location where furniture system cabling is required? |
| See Floor plans. |
| 1. |
| 1-6-2025 |
| Can the VA clarify if the use of flex conduit can be used for the new data drop locations? |
| Flex conduit is acceptable in walls. |
| 1. |
| 1-6-2025 |
| Can the VA provide the locations that currently have Fireproofing? |
| Review the VA supporting documents made available in the zip file labeled Additional Site Docs -2-3-25 for QA, posted in amendment 0003, posted to SAM.gov. These documents will contain the answer to this question. |
| 1. |
| 1-6-2025 |
| Can the VA confirm that when routing fiber inside buildings a minimum of 50’ separation to be maintained, with the possible exception of routing being next to each other if the fiber is in opposite directions? |
| The drawings are diagrammatical, the contractor would need to field verify and coordinate with existing utilities. |
| 1. |
| 1-6-2025 |
| Can the VA clarify if the contractor is responsible for installing any 25 Pair Phone cable to each TR and/or TE room 110 block? |
| Contractor’s responsibility. |
| 1. |
| 1-6-2025 |
| Can the VA clarify if the new 30 AMP 2 POLE/NEMA 3R, NON FUSIBLE DISCONNECTS for the multiple condensing units are to be motor-rated switches? |
| Please provide non-fusible disconnects as shown on drawings. |
| 1. |
| 1-6-2025 |
| Can the VA clarify whether 1-1/4" Flex Conduit can be used in existing walls for communication cabling? |
| Flex conduit is acceptable in walls. |
| 1. |
| 1-6-2025 |
| Can the VA clarify if all new WAO’s are Standard Density? |
| Standard density. |
| 1. |
| 1-6-2025 |
| Can the VA provide which floors have interstitial space? |
| No interstitial |
| 1. |
| 1-6-2025 |
| Reference 01 91 00 General Commissioning Requirements, 1.3 RELATED WORK |
This para retained Section 33 08 00 COMMISSIONING OF SITE UTILITIES, however the section was not provided. Can the VA clarify if this section is applicable to the project?
No site work.
| 1. |
| 1-6-2025 |
| Reference 06 10 00 ROUGH CARPENTRY, 1.2 RELATED WORK |
This para retained “Section 06 16 63, CEMENTITIOUS SHEATHING”, however this section was not provided.
Can the VA clarify if the section is applicable to the project?
Division 6 was removed as part of the final spec edits.
| 1. |
| 1-6-2025 |
| Reference 06 20 00 FINISH CARPENTRY |
Can the VA clarify if the section is applicable to the project?
Division 6 was removed as part of the final spec edits.