About this file

This document includes a past performance questionnaire template and details of a federal contract solicitation for construction of a Low Observable Component Repair Facility at Langley Air Force Base in Virginia. The past performance questionnaire is to be completed by clients of the offeror on previous relevant contracts and addresses quality, schedule, management, cost and safety. The solicitation seeks construction of a 6,735 square meter facility with three low observable critical repair bays, one wash rack bay, shops, administration spaces and utilities to support maintenance of additional relocated F-22A aircraft. The single award firm fixed-price design-bid-build contract is for a 730 calendar day performance period. The facility must meet anti-terrorism and seismic standards and be designed sustainably.

View the file

Other files for this federal contract opportunity

Other files attached to F-22 Low Observable Component Repair Facility (LOCRF), newest first.
File Type Posted
Attachment 8 - Revised Bid Schedule.pdf PDF
W9123621R2023 Amendment 13.pdf PDF
Attch 40 06 61 16 AMENDMENT 09 FEB 22.pdf PDF
Attch 38 LOCRF DRAWINGS AMENDMENT 09FEB2022.pdf PDF
Attch 41 Copy of GFE Equipment List_mjm edits 2020.09.24.xlsx XLSX spreadsheet
Attch 38 08 81 00 Glazing.pdf PDF
Attachment 8 - Revised CLIN Schedule.pdf PDF
Attch 35 32 01 19.61 SEALING OF JOINTS IN RIGID PAVEMENT.pdf PDF
Attch 25 01 11 00 Appendix to 01 11 00 Government Furnished Equipment.pdf PDF
Attch 24 P 601 PLUMBING SCHEDULES.pdf PDF
Attch 23 A 533 ROOF DETAILS.pdf PDF
Attch 22 A 011 EQUIPMENT SCHEDULE METALS TECH and SHOPS.pdf PDF
Attch 36 32 13 14.13 CONCRETE PAVING FOR AIRFIELDS AND OTHER HEAVY DUTY PAVEMENTS.pdf PDF
Attch 33 10 56 26.13 MOBILE STORAGE SHELVING UNITS (MECHANICALLY-ASSISTED).pdf PDF
Attch 32 09 97 13.27 HIGH PERFORMANCE COATING FOR STEEL STRUCTURES.pdf PDF
Attch 31 09 90 00 PAINTS AND COATINGS.pdf PDF
Attch 30 08 34 16 CORROSION CONTROL HANGAR DOORS.pdf PDF
Attch 27 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS.pdf PDF
Attch 26 01 14 00 WORK RESTRICTIONS.pdf PDF
Attch 37 33 32 16 PACKAGED UTILITY WASTEWATER PUMPING STATION.pdf PDF
Attch 34 13 34 19 METAL BUILDING SYSTEMS.pdf PDF
Attch 28 03 45 00 PRECAST ARCHITECTURAL CONCRETE.pdf PDF
W9123621R2023 Amendment 10.pdf PDF
Site Visit 10 January.pdf PDF
W9123621R2023 Amendment 9.pdf PDF
Attachment 19 LOCRF RTA SID PACKAGE.pdf PDF
Attachment 16 LOCRF RTA DWGS PART 2 OF 3.pdf PDF
Attachment 15 LOCRF RTA DWGS PART 1 OF 3.pdf PDF
Attch 13- LOCRF 20Oct21 Blended Drawings Part 3 of 3.pdf PDF
Attch 10- LOCRF 20Oct21 Blended Drawings Part 1 of 3.pdf PDF
W9123621R2023 Amendment 8.pdf PDF
Attch 11- LOCRF 20Oct21 Blended Drawings Part 2 of 3.pdf PDF
W9123621R2023 Amendment 7.pdf PDF
W9123621R2023 Amendment 6.pdf PDF
W9123621R2023 LOCRF Amend 5.pdf PDF
W9123621R2023 Amendment 4.pdf PDF
A.07.24 - Amendment 3.pdf PDF
A.07.24 - Amendment 2.pdf PDF
Attch 12 - LOCRF 100 Specification Part 1 of 1.pdf PDF
Attachment 7 - Small Business Participation Plan.pdf PDF
Attachment 4 - Telephone Interview Questionnaire (For Government Use Only).pdf PDF
Attachment 6 - Small Business Subcontracting Record.pdf PDF
Solicitation W9123621R2023.pdf PDF
Attch 11 - LOCRF 100 Dwgs Part 2 of 2.pdf PDF
Attachment 2 - Company Specialized Experience.pdf PDF
Attachment 8 - CLIN Schedule.pdf PDF
Attch 10 - LOCRF 100 Dwgs Part 1 of 2.pdf PDF
Attachment 1 - Proposal Data Sheet.pdf PDF
Attachment 5 - Letter of Commitment Sample.pdf PDF
Attachment 9 - Langley Environmental Management Special Conditions.pdf PDF
Show all 50

F-22 Low Observable Component Repair Facility (LOCRF) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

F-22 LOCRF Langley AFB, VA

W91236-21-R-2023

ATTACHMENT 3

PAST PERFORMANCE QUESTIONNAIRE

NAVFAC/USACE PAST PERFORMANCE QUESTIONNAIRE (Form PPQ-0)

CONTRACT INFORMATION (Contractor to complete Blocks 1-4)

1. Contractor Information

Firm Name: CAGE Code:

Address: DUNs Number:

Phone Number:

Email Address:

Point of Contact: Contact Phone Number:

2. Work Performed as: Prime Contractor Sub Contractor Joint Venture Other (Explain)

Percent of project work performed:

If subcontractor, who was the prime (Name/Phone #):

3. Contract Information

Contract Number:

Delivery/Task Order Number (if applicable):

Contract Type: Firm Fixed Price Cost Reimbursement Other (Please specify):

Contract Title:

Contract Location:

Award Date (mm/dd/yy):

Contract Completion Date (mm/dd/yy):

Actual Completion Date (mm/dd/yy):

Explain Differences:

Original Contract Price (Award Amount):

Final Contract Price (to include all modifications, if applicable):

Explain Differences:

W91236-21-R-2023

4. Project Description:

Complexity of Work High Med Routine How is this project relevant to project of submission? (Please provide details such as similar equipment, requirements, conditions, etc.)

CLIENT INFORMATION (Client to complete Blocks 5-8)

5. Client Information

Name:

Title:

Phone Number:

Email Address:

6. Describe the client’s role in the project:

7. Date Questionnaire was completed (mm/dd/yy):

8. Client’s Signature:

NOTE: USACE REQUESTS THAT THE CLIENT COMPLETES THIS QUESTIONNAIRE AND SUBMIT DIRECTLY BACK TO THE OFFEROR. THE OFFEROR WILL SUBMIT THE COMPLETED QUESTIONNAIRE TO USACE WITH THEIR PROPOSAL, AND MAY DUPLICATE THIS QUESTIONNAIRE FOR FUTURE SUBMISSION ON USACE SOLICITATIONS. CLIENTS ARE HIGHLY ENCOURAGED TO SUBMIT QUESTIONNAIRES DIRECTLY TO THE OFFEROR. HOWEVER, QUESTIONNAIRES MAY BE SUBMITTED DIRECTLY TO USACE. PLEASE CONTACT THE OFFEROR FOR USACE POC INFORMATION. THE GOVERNMENT RESERVES THE RIGHT TO

VERIFY ANY AND ALL INFORMATION ON THIS FORM.

W91236-21-R-2023

ADJECTIVE RATINGS AND DEFINITIONS TO BE USED TO BEST REFLECT

YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE

RATING DEFINITION NOTE

(E) Exceptional Performance meets contractual requirements and exceeds many to the Government/Owner’s benefit.

The contractual performance of the element or sub-element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor was highly effective.

An Exceptional rating is appropriate when the Contractor successfully performed multiple significant events that were of benefit to the Government/Owner. A singular benefit, however, could be of such magnitude that it alone constitutes an Exceptional rating.

Also, there should have been NO significant weaknesses identified.

(VG) Very Good Performance meets contractual requirements and exceeds some to the Government’s/Owner’s benefit.

The contractual performance of the element or sub-element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.

A Very Good rating is appropriate when the Contractor successfully performed a significant event that was a benefit to the Government/Owner. There should have been no significant weaknesses identified.

(S) Satisfactory Performance meets minimum contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.

A Satisfactory rating is appropriate when there were only minor problems, or major problems that the contractor recovered from without impact to the contract. There should have been NO significant weaknesses identified. Per DOD policy, a fundamental principle of assigning ratings is that contractors will not be assessed a rating lower than Satisfactory solely for not performing beyond the requirements of the contract.

(M) Marginal Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor's proposed actions appear only marginally effective or were not fully implemented.

A Marginal is appropriate when a significant event occurred that the contractor had trouble overcoming which impacted the Government/Owner.

(U) Unsatisfactory Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains serious problem(s) for which the contractor's corrective actions appear or were ineffective.

An Unsatisfactory rating is appropriate when multiple significant events occurred that the contractor had trouble overcoming and which impacted the Government/Owner. A singular problem, however, could be of such serious magnitude that it alone constitutes an unsatisfactory rating.

W91236-21-R-2023

(N) Not Applicable No information or did not apply to your contract Rating will be neither positive nor negative.

TO BE COMPLETED BY CLIENT

PLEASE CIRCLE THE ADJECTIVE RATING WHICH BEST REFLECTS

YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE.

1. QUALITY:

a) Quality of technical data/report preparation efforts E VG S M U N

b) Ability to meet quality standards specified for technical performance E VG S M U N

c) Timeliness/effectiveness of contract problem resolution without extensive customer guidance

E VG S M U N

d) Adequacy/effectiveness of quality control program and adherence to contract quality assurance requirements (without adverse effect on performance)

E VG S M U N

2. SCHEDULE/TIMELINESS OF PERFORMANCE:

a) Compliance with contract delivery/completion schedules including any significant intermediate milestones. (If liquidated damages were assessed or the schedule was not met, please address below)

E VG S M U N

b) Rate the contractor’s use of available resources to accomplish tasks identified in the contract

E VG S M U N

3. CUSTOMER SATISFACTION:

a) To what extent were the end users satisfied with the project? E VG S M U N

b) Contractor was reasonable and cooperative in dealing with your staff (including the ability to successfully resolve disagreements/disputes;

responsiveness to administrative reports, businesslike and communication)

E VG S M U N

c) To what extent was the contractor cooperative, businesslike, and concerned with the interests of the customer?

E VG S M U N

d) Overall customer satisfaction E VG S M U N

4. MANAGEMENT/ PERSONNEL/LABOR

a) Effectiveness of on-site management, including management of subcontractors, suppliers, materials, and/or labor force?

E VG S M U N

b) Ability to hire, apply, and retain a qualified workforce to this effort E VG S M U N

c) Government Property Control E VG S M U N

d) Knowledge/expertise demonstrated by contractor personnel E VG S M U N

e) Utilization of Small Business concerns E VG S M U N

f) Ability to simultaneously manage multiple projects with multiple disciplines E VG S M U N

W91236-21-R-2023

For Official Use Only

g) Ability to assimilate and incorporate changes in requirements and/or priority, including planning, execution and response to Government changes

E VG S M U N

h) Effectiveness of overall management (including ability to effectively lead, manage and control the program)

E VG S M U N

5. COST/FINANCIAL MANAGEMENT

a) Ability to meet the terms and conditions within the contractually agreed price(s)?

E VG S M U N

b) Contractor proposed innovative alternative methods/processes that reduced cost, improved maintainability or other factors that benefited the client

E VG S M U N

c) If this is/was a Government cost type contract, please rate the Contractor’s timeliness and accuracy in submitting monthly invoices with appropriate back-up documentation, monthly status reports/budget variance reports, compliance with established budgets and avoidance of significant and/or unexplained variances (under runs or overruns)

E VG S M U N

d) Is the Contractor’s accounting system adequate for management and tracking of costs? If no, please explain in Remarks section.

Yes No

e) If this is/was a Government contract, has/was this contract been partially or completely terminated for default or convenience or are there any pending terminations? Indicate if show cause or cure notices were issued, or any default action in comment section below.

Yes No

f) Have there been any indications that the contractor has had any financial problems? If yes, please explain below.

Yes No

6. SAFETY/SECURITY

a) To what extent was the contractor able to maintain an environment of safety, adhere to its approved safety plan, and respond to safety issues?

(Includes: following the users rules, regulations, and requirements regarding housekeeping, safety, correction of noted deficiencies, etc.)

E VG S M U N

b) Contractor complied with all security requirements for the project and personnel security requirements.

E VG S M U N

7. GENERAL

a) Ability to successfully respond to emergency and/or surge situations (including notifying COR, PM or Contracting Officer in a timely manner regarding urgent contractual issues).

E VG S M U N

b) Compliance with contractual terms/provisions (explain if specific issues) E VG S M U N

c) Would you hire or work with this firm again? (If no, please explain below) Yes No

d) In summary, provide an overall rating for the work performed by this contractor.

E VG S M U N

Please provide responses to the questions above (if applicable) and/or additional remarks. Furthermore, please provide a brief narrative addressing specific strengths, weaknesses, deficiencies, or other comments which may assist our office in evaluating performance risk (please attach additional pages if necessary):