This is a Section C (Description and Specifications) from a federal solicitation for the Lake Alva Campground Water System Improvements project located on the Seeley Ranger District near Seeley Lake, Montana.

The project encompasses replacement of the existing water system, electrical system, and repaving of a campground loop. Water system work includes replacing all components in the well pumphouse (pressure tanks, flow meter, pressure relief valve, and associated valves and appurtenances) and installing new 2-inch HDPE water main throughout the campground while abandoning the existing water main in place. Electrical upgrades include demolishing existing equipment, installing new grounding equipment, low-voltage power conductors and cables, cable conduit, miscellaneous connectors, new power outlet pedestals, and new circuit breakers. Option Item #1 includes repaving asphalt road sections, patching areas where the new water main intersects the road, and replacing existing wheel stops in designated parking areas. The contract price range is between $500,000 and $1,000,000, with an estimated work start date of July 1, 2026, and a period of performance extending from July 1, 2026 through December 1, 2027. A site visit is scheduled for May 13, 2026 at 10 a.m. at the Seeley Lake Ranger District. No formal pre-bid conference is scheduled. Technical specifications specific to this project are incorporated as part of the solicitation and resulting contract. Questions may be directed to Brian Story at (406) 529-8534 or brian.story@usda.gov. No government-furnished property is being provided for this project.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Lake Alva Campground Water System Improvements

Section C - Description and Specifications

C- 1 Description of Work

a) Description of Work: This project replaces the existing water system, electrical system, and re-paves a loop of the Lake Alva Campground on the Seeley Ranger District. Project work includes replacing all water system components in the well pumphouse including new pressure tanks, flow meter, pressure relief, and all valves and appurtenances. Outside the pumphouse the project includes installing new 2” HDPE water main throughout the campground, and abandoning the existing water main in place. Aside from the water system upgrades, there will also be electrical upgrades throughout the campground including demolishing some existing equipment, new grounding equipment, low-voltage power conductors and cables, cable conduit and miscellaneous box connectors, couplers, etc., installing new power outlet pedestals, and new circuit breakers.

Option Item #1 includes repaving sections of the campground asphalt road, patching areas where the new water main intersects the road, and replacing some existing wheel stops in designated parking areas.

b) Project Location: From Seeley Lake, Montana head north on MT-83 for 11.3 miles.

Campground will be on the left.

c) Price Range: Between $500,000 and $1,000,000

d) Site Visit. A site visit is scheduled for May 13, 2026 at 10 am at the Seeley Lake Ranger

District. Questions regarding the project may be directed to Brian Story at (406) 529-8534 or brian.story@usda.gov

e) Pre-Bid Conference. No formal pre-bid conference is scheduled.

f) Start Work: It is estimated that work will begin July 1, 2026.

g) Period of Performance: July 1, 2026 – December 1, 2027

C- 2 Government-Furnished Property None

C- 3 Standard Specifications

Technical Specifications have been generated for this specific project and included in this solicitation. The requirements contained in these Specifications are hereby made a part of this solicitation and any resultant contract.

mailto:brian.story@usda.gov jcurry Highlight

Lake Alva Campground Water System Improvements
C- 2 Government-Furnished Property
C- 3 Standard Specifications

File details come from the government source that posted it. Updated .