This is a Design Specifications document for HVAC system repairs at the USDA-ARS Center for Medical and Veterinary Entomology (CMAVE) in Gainesville, Florida, prepared by The Johnson-McAdams Firm, P.A. in May 2026 under Contract No. 12405B21D0003 / Order No. 1232SA25F0354.
The project consists of phased construction across two buildings. Building 1 work includes replacing roof-mounted fans and AHU-1, modifying associated ductwork, performing electrical disconnection and reconnection of HVAC equipment, and modifying the lightning protection system. Building 11 is divided into two phases: Phase 1 encompasses replacing an air-cooled chiller, replacing AHU-1 in the indoor mechanical room, replacing pumps and perimeter fan coil units, and supporting electrical work; Phase 2 includes roof replacement, ceiling replacement, replacing roof-mounted and ground-level fans with duplex laboratory exhaust fans, replacing roof-mounted air handlers (AHU-2, AHU-3, AHU-4), replacing laboratory venturi valves, upgrading the HVAC control system, electrical work, lighting replacement, and modifying the lightning protection system. The contract requires contractor quality control with daily inspection records, submittal of shop drawings (six copies), product data, samples, warranties of construction for one year post-acceptance, and compliance with extensive safety, fire protection, security, and environmental requirements including OSHA standards, NFPA codes, waste management with minimum 10% diversion from landfill, and coordination with ongoing facility operations. Contractors must provide OSHA-certified competent persons on-site, complete training documentation, site-specific safety plans, hot work permits, daily inspection forms, and maintain as-built drawings throughout construction with project completion required within 365 calendar days of Notice to Proceed.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIFICATIONS
REPAIR HVAC SYSTEM,
BUILDINGS 1 AND 11
USDA-ARS
Center for Medical and Veterinary Entomology (CMAVE) 1600 SW 23RD Drive Gainesville, FL
Prepared For:
U.S. Department Of Agriculture Agricultural Research Service (ARS)
Contract No. / Order No.
12405B21D0003 / 1232SA25F0354
Prepared By:
The Johnson-McAdams Firm, P.A.
Greenwood, Mississippi
May 4, 2026
Repair HVAC System, Bldgs. 1 and 11 3925
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 00 01 01/20 WARRANTY OF CONSTRUCTION
01 00 11 06/20 GENERAL PARAGRAPHS
01 00 21 01/20 CONTRACTOR QUALITY CONTROL
01 01 00 03/21 GENERAL REQUIREMENTS
01 33 00 08/18 SUBMITTAL PROCEDURES
01 33 29 02/21 SUSTAINABILITY REQUIREMENTS AND
REPORTING
01 35 26 01/20 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 02/19, CHG 1: 08/23 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 08/23 QUALITY CONTROL
01 50 00 01/20 PROJECT CLOSEOUT
01 57 50 10/19 TEMPORARY ENVIRONMENTAL CONTROLS
01 74 19 02/19, CHG 3: 11/21 CONSTRUCTION WASTE MANAGEMENT AND
DISPOSAL
01 78 23 08/15 OPERATION AND MAINTENANCE DATA
DIVISION 02 - EXISTING CONDITIONS
02 41 00 08/22 DEMOLITION
DIVISION 05 - METALS
05 51 33 02/16, CHG 2: 02/18 METAL LADDERS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 22 00 02/16, CHG 3: 11/18 ROOF AND DECK INSULATION
07 52 00 08/25 MODIFIED BITUMINOUS MEMBRANE ROOFING
07 60 00 08/23, CHG 1: 05/25 FLASHING AND SHEET METAL
07 84 00 05/10, CHG 1: 08/13 FIRESTOPPING
07 92 00 08/23 JOINT SEALANTS
DIVISION 09 - FINISHES
09 90 00 02/21 PAINTS AND COATINGS
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 03 00 11/25 BASIC MECHANICAL MATERIALS AND METHODS
23 05 93 05/25 TESTING, ADJUSTING, AND BALANCING FOR
HVAC
23 07 00 08/24 THERMAL INSULATION FOR MECHANICAL
SYSTEMS
23 08 00 05/23, CHG 1: 08/24 COMMISSIONING OF MECHANICAL SYSTEMS
23 09 00 08/24, CHG 1: 08/25 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 13 11/15, CHG 2: 05/21 INSTRUMENTATION AND CONTROL DEVICES
FOR HVAC
23 21 23 05/25 HYDRONIC PUMPS
23 30 00 02/25 HVAC AIR DISTRIBUTION
23 64 10 05/25 WATER CHILLERS, VAPOR COMPRESSION TYPE
23 64 26 11/25 CHILLED, CHILLED-HOT, AND CONDENSER
WATER PIPING SYSTEMS
DIVISION 26 - ELECTRICAL
PROJECT TABLE OF CONTENTS Page 1
26 20 00 05/25, CHG 1: 08/25 INTERIOR DISTRIBUTION SYSTEM
26 29 23 02/20, CHG 1: 05/21 ADJUSTABLE SPEED DRIVE (ASD) SYSTEMS
UNDER 600 VOLTS
26 41 00 08/23 LIGHTNING PROTECTION SYSTEM
26 51 00 05/20, CHG 2: 11/21 INTERIOR LIGHTING
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 70 08/20 INTERIOR FIRE ALARM SYSTEM, ADDRESSABLE
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 2
SECTION 01 00 01
WARRANTY OF CONSTRUCTION
01/20
PART 1 GENERAL
1.1 WARRANTY OF CONSTRUCTION
1.1.1 General
In addition to any other warranties set out elsewhere in this contract, the Contractor warrants that work performed under this contract conforms to the contract requirements and is free of any defect of equipment, material or design furnished, or workmanship performed by the Contractor or any of his subcontractors or suppliers at any tier. Such warranty shall continue for a period of one year from the date of final acceptance of the project. Under this warranty, the Contractor shall remedy at his own expense any such failure to conform or any such defect. In addition, the Contractor shall remedy at his own expense any damage to Government owned or controlled real or personal property, when that damage is the result of the Contractor's failure to conform to contract requirements or any such defect of equipment, material, workmanship, or design. The Contractor shall also restore any work damaged in fulfilling the terms of this clause. The Contractor's warranty with respect to work repaired or replaced hereunder will run for one year from the date of such repair or replacement.
1.1.2 Notification and Compliance
The Government shall notify the Contractor in writing within a reasonable time after the discovery of any failure, defect, or damage. Should the Contractor fail to remedy any failure, defect, or damage described in paragraph 1.1.1 above within a reasonable time after receipt of notice thereof, the Government shall have the right to replace or repair and have the cost billed to the Contractor.
1.2 EXPRESSED WARRANTY
In addition to the other rights and remedies provided by this clause, all subcontractors', manufacturers', and suppliers' warranties expressed or implied, respecting any work and materials shall, at the direction of the Government, be enforced by the Contractor for the benefit of the Government. In such case, if the Contractor's warranty under paragraph
1.1.1 above has expired, any suit directed by the Government to enforce a subcontractor's, manufacturer's, or supplier's warranty shall be at the expense of the Government. The Contractor shall obtain any warranties which the subcontractors, manufacturers, or suppliers would give in normal commercial practice. If so directed by the Contracting Officer, the Contractor shall require any such warranties to be executed in writing to the Government.
1.3 LATENT DEFECTS
The Warranty specified herein shall not limit the Government's rights with respect to latent defects, gross mistake, or fraud.
SECTION 01 00 01 Page 1
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 00 01 Page 2
SECTION 01 00 11
GENERAL PARAGRAPHS
06/20
PART 1 GENERAL
1.1 DESCRIPTION OF WORK
1.1.1 Work To Be Done
The work to be done consists of furnishing all labor, materials, and equipment and performing all work in strict accordance with these specifications for the Repair HVAC System, Bldgs. 1 and 11 in Gainesville, Florida. Bidder shall provide Base Bid pricing and Alternate pricing as defined in the contract documents.
1.1.2 Location
The site of work is at the USDA Center for Medical Agricultural and Veterinary Entomology (CMAVE) in Gainesville, Florida.
1.1.3 Principal Features of Work
This project consists of phased construction. Submit a separate, stand-alone bid for each work phase. The scope of each phase is summarized below. Refer to plans for specific work for each phase.
Perform all work as shown on the plans.
1.1.3.1 Building 1
1. Replace the existing roof mounted fans. The design intent is to replace the existing fans in kind. The replacement fans will connect to the existing ductwork. Modify ductwork as required to accommodate the replacement fans.
2. Replace roof mounted AHU-1. The intent is to replace the AHU in kind. The replacement AHU will connect to the existing ductwork.
Modify ductwork as required to accommodate the replacement AHU.
3. AHU-2 and AHU-3 are existing to remain.
4. Electrical work is primarily in support of the mechanical work.
Disconnect and reconnect HVAC equipment as shown.
5. Modify the existing lightning protection system (LPS) as required to accommodate new roof-mounted equipment.
1.1.3.2 Building 11 Phase 1
1. Replace one of the existing air-cooled chillers.
2. Replace AHU-1 located in the indoor mechanical room. The intent is to replace the AHU in kind. The replacement AHU will connect to the existing ductwork. Modify ductwork as required to accommodate the replacement AHU.
3. The roof-mounted air handlers and fans are existing to remain.
(see Phase 2 documents.)
SECTION 01 00 11 Page 1
4. Replace existing pumps in the mechanical room.
5. Replace existing perimeter fan coil units on the first and second floor.
6. Electrical work is primarily in support of the mechanical work.
Disconnect and reconnect HVAC equipment as shown.
1.1.3.3 Building 11 Phase 2
1. Replace the existing roof.
2. Replace the existing lay-in ceiling in the corridors.
3. Replace the existing fans located on the roof, mounted to the walls and located on the ground. The general design intent is to remove the existing stand-alone laboratory fume hood exhaust fans and replace them with duplex laboratory exhaust fans with bypass plenum.
(This does not apply to all fans. Refer to plans for the specific work.)
4. Replace roof mounted air handlers, AHU-2, AHU-3 and AHU-4. The intent is to replace the ahus in kind. The replacement ahus will connect to the existing ductwork. Modify ductwork as required to accommodate the replacement AHU.
5. Indoor air handler, AHU-1, is part of Phase 1.
6. Replace existing laboratory venturi valves. (Fume hood exhaust, general exhaust and outdoor air supply.) Existing VAV boxes are to remain.
7. Upgrade the existing HVAC control system to support the new equipment.
8. Electrical work is primarily in support of the mechanical work.
Disconnect and reconnect HVAC equipment as shown.
9. Replace existing lighting.
10. Contractor shall modify the existing lightning protection system (LPS) as required to accommodate new roof-mounted equipment.
1.2 SITE VISIT
USDA will conduct a single pre-bid site inspection for all interested contractors that will be coordinated with Kevin MaGee. Contractor must be able to provide valid US or state photo ID and must be with USDA escort for access.
Contact:
U.S. Department of Agriculture, ARS Attn: John Ohlson USDA FACILITY 1600 SW 23rd Drive Gainesville, Florida 32608 Contact Person E-mail: john.ohlson@usda.gov Contact Person Phone Number: 352-316-1514
SECTION 01 00 11 Page 2
1.3 COORDINATION OF WORK
1. Work space and space available for storing materials shall be subject to the approval of the Contracting Officer. Do not store materials and equipment in other than assigned areas.
2. Execute work so as to interfere as little as possible with normal functioning of the facility, including operations of utility services and any existing equipment, and with work being done by others.
3. Minimize interference of construction activities with the flow of traffic by keeping roads, walks and entrances to grounds, to parking areas and to occupied areas of buildings clear of construction materials, debris, construction equipment and vehicles except where noted on plans or in specifications. Provide unobstructed access to areas required to remain in operation.
4. The Contractor shall complete all work within 365 consecutive calendar days after Notice to Proceed. Within 14 calendar days after Contract Award, the Contractor shall provide the Government with a detailed schedule of dates on which the Contractor plans to accomplish the work. In addition, the Contractor shall notify the Contracting Officer 20 days in advance of starting work. A planned work schedule shall be submitted to the Contracting Officer for approval. The schedule shall include a detailed description of the methods and equipment to be used for each operation and the sequence of operations. This schedule shall be updated monthly and submitted to the Contracting Officer for approval.
5. The Contractor shall take all measures and provide all material necessary for protecting existing equipment, property, and ongoing operations in affected areas of construction against dust, noise and debris.
6. Power sources for the Contractor's operations will be available and supplied by the Government to the Contractor as long as its use does not interfere with the operations of the Government's facilities. Water sources will be available and supplied by the Government to the Contractor as long as its use does not interfere with the operations of any building. The Contractor is responsible for extending utility sources to his work locations. Such extensions shall be removed after work is completed, to the satisfaction of the Contracting Officer.
7. All references in the specifications to the Contracting Officer and Contracting Officer's Representative shall constitute referrals initially to the Contracting Officer's Representative.
8. Contractor shall provide sanitary facilities for use by his employees and the employees of his subcontractors working on job site.
1.4 DRAWINGS
All dimensions shown of existing work and all dimensions required for work that is to be connected with existing work shall be verified by the Contractor by actual field measurements. Any work at variance with that specified or shown on the drawings, shall not be performed by the Contractor until the Contractor has received approval in writing from the
SECTION 01 00 11 Page 3
Contracting Officer.
1.5 MATERIAL SAFETY DATA SHEETS (MSDS)
Material Safety Data Sheets must be submitted to the Contracting Officer prior to the commencement of any work with any substance that may be considered hazardous.
1.6 UTILITIES OR STRUCTURAL ITEMS CONFLICTING WITH PROPOSED CONSTRUCTION
In the event the Contractor finds an area where existing utilities or structural items conflict with proposed construction, the Contracting Officer shall be notified immediately. The Contractor shall then propose a method of solving the problem. Work shall not resume in the problem area until the Contractor has received written approval from the Contracting Officer. There shall be no additional cost to the Government.
1.7 ACCEPTANCE OF WORK
1. Final inspection will not be made until the contract work is completed. The Contractor shall notify in writing the Contracting Officer fifteen working days prior to the date on which the work will be ready for final inspection.
2 Final inspection and acceptance of the work shown by the drawings and specifications forming a part of this contract shall not be binding or conclusive on the Government if it shall be shown that (1) the Contractor has willfully or through collusion with persons or firms engaged in the performance of the contract supplied inferior materials, equipment, or workmanship, or (2) the Contractor has otherwise departed from the terms of the contract.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
SECTION 01 00 11 Page 4
SECTION 01 00 21
CONTRACTOR QUALITY CONTROL
01/20
PART 1 GENERAL
1.1 GENERAL
This section covers the quality control inspection, sampling, and testing of all materials, services, and workmanship required to be performed by the contract drawings, specifications, and other contract requirements.
The Contractor shall perform all quality control inspection, sampling, and testing required by this contract and shall review and certify that each submittal is correct and in strict conformance with the contract drawings and specifications for all shop drawings and lists of materials, fixtures, and equipment. All work performed under this contract shall be in strict accordance with procedures and requirements detailed on the plans and specifications.
1.1.1 Certificate of Compliance
Upon completion of the contract work and prior to final acceptance, the Contractor shall submit to the Contracting Officer a certificate of compliance which states that all materials, equipment, design, and workmanship incorporated in the work are in strict compliance with contract drawings and specifications except for approved deviations. The certificates of compliance shall be signed and dated by both the manufacturer's representative and the Contractor. Based upon this certificate of compliance and other contract requirements, the Contractor shall be responsible for correcting at his expense any defects, omissions, and deviations (other than those previously approved) which are detected during the contract period or during the one-year warranty period as defined in Section 01 00 01 , WARRANTY OF CONSTRUCTION.
1.2 INSPECTION
The Contractor shall inspect all materials, services, and workmanship to assure conformance with contract requirements.
1.3 REVIEW AND APPROVAL OF SHOP DRAWINGS, SUBMITTALS, MATERIALS, FIXTURES,
AND EQUIPMENT
1. Prior to submission to the Government for approval, the Contractor shall review and certify that all shop drawings, submittals, lists of materials, fixtures, and equipment as called for under the various headings of these specifications are correct and in strict compliance with the contract drawings and specifications. These drawings, submittals and lists shall be accurate, complete, and adequately detailed. The top copy of data comprising each item listed on the transmittal form shall be identified as having received the quality control inspector's approval by being so stamped, signed and dated.
Approval of shop drawings, submittals, materials, fixtures, and equipment by the Contracting Officer will not relieve the Contractor of the responsibility for any errors which may exist and the Contractor shall be responsible for the satisfactory construction of all work. All samples of materials submitted as required by these specifications shall be properly identified and labeled for ready identification, and upon being approved, stored at the site of the
SECTION 01 00 21 Page 1 work for jobsite use until all work has been accepted by the Contracting Officer. The Contractor shall provide four (4) sets of all shop drawings.
2. All proposed deviations required by the Contractor shall be noted in the "Remarks" column of the Form. The Contractor shall set forth in writing the reason for any deviations and annotate such deviations on the shop drawing. The Government reserves the right to rescind inadvertent approval of shop drawings containing unnoted deviations.
1.4 DAILY RECORDS
The Contractor shall maintain a daily record of quality control measures performed for each shift of Contractor or Subcontractor operations on an appropriate format. These records shall provide factual evidence that continuous quality control inspections have been performed, including but not limited to the following: job progress, problems encountered;
problems resolved; type and number of inspections; results of inspections or tests including all computations; nature of defects; causes for rejection; safety violations; proposed remedial action; and corrective action taken. These records shall cover both conforming and defective items and shall include a statement that all supplies and materials incorporated in the work are in full compliance with the terms of the contract. The Contractor shall maintain a current record of all inspections and shall furnish to the Contracting Officer on a daily basis, legible copies of all inspection records for his permanent retention. The daily records of inspections shall cover all work placement subsequent to the previous report and shall be verified by the Contractor's designated representative.
1.5 RECURRING DEFICIENCIES
If recurring deficiencies in an item or items being inspected by the Contractor indicate that the inspection system is not providing adequate quality control, the Contractor shall take such corrective measures as deemed necessary by the Contracting Officer.
1.6 CONFLICTS
In the event of a difference of opinion between the Contractor and the Contracting Officer, the Contracting Officer shall govern.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
SECTION 01 00 21 Page 2
SECTION 01 01 00
GENERAL REQUIREMENTS
03/21
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM E84 (2025) Standard Test Method for Surface Burning Characteristics of Building Materials
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 10 (2022; ERTA 1 2021) Standard for Portable Fire Extinguishers
NFPA 30 (2021; TIA 20-1; TIA 20-2) Flammable and Combustible Liquids Code
NFPA 51B (2019) Standard for Fire Prevention During Welding, Cutting, and Other Hot Work
NFPA 70 (2026; TIA 26-1; ERTA 26-1; TIA
26-2; TIA 26-3; TIA 26-4; TIA
26-5; TIA 26-6; TIA 26-7; ERTA
26-2; ERTA 26-3) National Electrical Code
NFPA 241 (2022; ERTA 22-1) Standard for Safeguarding Construction, Alteration, and Demolition Operations
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
29 CFR 1926 Safety and Health Regulations for Construction
1.2 GENERAL INTENTION
A. Contractor shall completely prepare the site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work as required by the contract documents.
B. All employees of general contractor and subcontractors shall comply with ARS security management program, obtain permission of the ARS Location Manager, be identified by project and employer by wearing contractor issued identification badges at all times on ARS property, and restricted from unauthorized access.
C. Prior to commencing work, the general contractor shall provide proof
SECTION 01 01 00 Page 1 that an OSHA certified "competent person" (CP) (29 CFR 1926.20(b))(2) will maintain a presence at the work site whenever the general or subcontractors are present.
D. Training:
1. All employees of the general contractor or subcontractors shall have the 10-hour OSHA certified Construction Safety course and /or other relevant competency training. Supervisors shall have completed the 30-hour OSHA training.
2. Submit training records of all such employees to the Contracting Officer for approval before the start of work.
1.3 STATEMENT OF BID ITEMS
A. ITEM I, GENERAL CONSTRUCTION: Work includes general construction, alterations, and removal of existing structures and construction and certain other items.
1.4 PROJECT COORDINATION
A. Construction Project Schedule: See contract, FAR 52.236-15 Schedules for Construction Contracts. The Contractor will not begin actual work until the construction project schedule has been approved by the Contracting Officer. The Contractor shall submit one electronic copy of the updated construction project schedule with each progress payment request.
B. Contract Inspector's Daily Report:
C. Contractor shall submit to the Contracting Officer a daily report listing the names of all those present on the job site each day, along with their Job Classification, hours of work and a brief description of the work performed by each on that day. The Contract Inspector's Daily Report is to be submitted at the beginning of work each day for the previous day's work and shall be maintained throughout the term of the contract.
D. Formal Meetings:
1. Any meeting (deemed formal by the contractor, the COR, or the Contracting Officer) will have the minutes of said meeting prepared by the contractor (and a copy provided to the Contracting Officer). The minutes will include: Date, Name of Attendees (with contact info), Old Business, and New Business subjects (or narratives). Regardless of who requests a meeting (the COR or the Contractor or the Contracting Officer) the contractor may be required to provided hard copy pictures of the issues to be discussed. Each issue will be linked to a contract specification section number and/or subject area by page number. Issues discussed will also include an action/completion date.
1.5 SAFETY SUBMITTALS
A. Contractor shall submit a "site specific" Safety Plan to the Contracting Officer that describes how the contractor is to comply with all applicable OSHA standards and NFPA codes pertaining to construction work to include, but not limited to: General Safety and Health
SECTION 01 01 00 Page 2
Provisions, Occupational Health and Environmental Controls, Personal Protective and Life Saving Equipment, Hand and Power Tools, Welding and Cutting, Electrical, Scaffolds, Fall Protection, Excavations, Demolition, Stairways, and Ladders, Toxic and Hazardous Substances, Confined Space Entry, Lockout/Tagout, Respiratory Protection, Hearing Protection. Safety Plan shall identify Contractor and sub-contractor employees who are authorized/qualified to perform electrical work. No work shall proceed until written approval of the Safety Plan by the Contracting Officer.
Safety Plan shall describe how the Contractor and/or sub-contractors are to secure equipment, supplies, tools, and chemical products. Contractor and/or sub-contractor equipment, supplies, tools, and chemical products are to be under the control of the Contractor at all times, equipment, supplies tools, and chemical products found not to be under the control of the Contractor or sub-contractor are subject to confiscation and will be reported to the Contracting Officer.
1. Pandemic Specific Requirements for Access to ARS Locations/Worksites. Check with Site Safety Officer for specific requirements as requirements change from site to site, nature of the specific project and USDA guidelines per affected date.
a. Contractor must follow all State and Local guidelines for entry into the state which may include testing, quarantine, etc.
b. Plans must show compliance with any State Construction Guidelines
B. The Contractor shall inspect the entire construction site daily, including days without construction work if there are NFPA 101 Life Safety Code deficiencies existing while construction work is shut down, the results of that inspection shall be documented on the attachment "DAILY INSPECTION FORM", and the form is to be signed and submitted to the Contracting Officer.
C. Contractor shall provide continuous monitoring for noise, dust, chemical vapor generation, volatile organic compounds, and vibration. At no time shall noise exposure to any ARS staff exceed 75 dB. Contractor shall provide to the Contracting Officer a written weekly update of the all test results and also for proposed work for the subsequent two weeks (a two week "look-ahead") involving any construction activity that will produce loud noises, heavy vibrations, strong smells, or significant dust inside ARS staff occupied space.
D. Contractor and sub-contractors shall notify in writing the Contracting Officer at least one week prior to executing high risk work (this may be included in the two week "look-ahead" update). High risk work includes, but is not limited to, tasks requiring Lockout/Tag Out, live electrical work, hot work, work at heights, trenching/ shoring, crane operations, and confined space entry. Contractor's Competent Person shall provide the Contracting Officer written weekly documented safety inspection results.
E. Contractor shall provide to the Contracting Officer for approval, copies of Safety Data Sheets (SDS) for EVERY CHEMICAL WITHOUT EXCEPTION prior to bringing such chemical on the work site.
F. HOT WORK PERMITS:
1. The Contractor will not be permitted to work without this permit when performing hot work.
SECTION 01 01 00 Page 3
1.6 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Contractor Personnel
1. CNRC requres a valid US or state photo ID.
Outside - CNRC will not issue badges for work outside. Prefer that contractors wear company identification.
Inside - Inside work requres CNRC badge, CNRC prefers issuing a badge to a crew leader for groups of 2-3. Badges and keys check in and out daily. Otherwise, company identification will suffice.
C. Security Procedures:
1. Contractor's employees shall not enter the project site without appropriate badges. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. For working outside the "regular hours" as defined in the contract, The Contractor shall give a ten (10) day notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of ARS premises is allowed without written permission of the Contracting Officer.
4. ARS reserves the right to close down or shut down the project site and order the Contractor's employees off the premises in the event of a national emergency or Government shutdown. The Contractor may return to the site only with the written approval of the Contracting Officer.
D. Document Control:
1. The Contractor is responsible for safekeeping of all drawings, project manuals and other project information. This information shall be shared only with those with a specific need to accomplish the project.
2. These documents shall not be removed or transmitted from the project site without the written approval of Contracting Officer.
3. All paper waste or electronic media such as CD's and diskettes shall be shredded and destroyed in a manner acceptable to the ARS.
E. Motor Vehicle Restrictions
SECTION 01 01 00 Page 4
1. No parking restrictions at Tallahassee site. Coordinate parking area with location. No permits or authorization requests needed at Tallahassee site.
1.7 FIRE SAFETY
A. Applicable Publications: Publications listed below form part of this Article to extent referenced. Publications are referenced in text by basic designations only.
1. American Society for Testing and Materials (ASTM):
ASTM E84 Surface Burning Characteristics of Building Materials
2. National Fire Protection Association (NFPA):
NFPA 10 Standard for Portable Fire Extinguishers
NFPA 30 Flammable and Combustible Liquids Code
NFPA 51B Standard for Fire Prevention During Welding, Cutting and Other Hot Work
NFPA 70 National Electrical Code
NFPA 241 Standard for Safeguarding Construction, Alteration, and Demolition Operations
3. Occupational Safety and Health Administration (OSHA):
29 CFR 1926 Safety and Health Regulations for Construction
B. Fire Safety Plan: Establish and maintain a fire protection program in accordance with 29 CFR 1926 . Prior to start of work, prepare a plan detailing project-specific fire safety measures, including periodic status reports, and submit to the Contracting Officer for review for compliance with contract requirements. Prior to any worker for the contractor or subcontractors beginning work, they shall undergo a safety briefing provided by the contractor's competent person per OSHA requirements. This briefing shall include information on the construction limits, ARS safety guidelines, means of egress, break areas, work hours, locations of restrooms, use of ARS equipment, etc. Documentation shall be provided to the Contracting Officer that individuals have undergone contractor's safety briefing.
C. Site and Building Access: Maintain free and unobstructed access to facility emergency services and for fire, police and other emergency response forces in accordance with NFPA 241 .
D. Separate temporary facilities, such as trailers, storage sheds, and dumpsters, from existing buildings and new construction by distances in accordance with NFPA 241 . For small facilities with less than 20 feet exposing overall length, separate by 10 feet.
E. Temporary Construction Partitions: Install and maintain temporary construction partitions to provide smoke-tight separations between construction areas and adjoining areas. Construct partitions of gypsum board or treated plywood (flame spread rating of 25 or less in accordance
SECTION 01 01 00 Page 5 with ASTM E84) on both sides of fire retardant treated wood or metal steel studs.
F. Temporary Heating and Electrical: Install, use and maintain installations in accordance with 29 CFR 1926 , NFPA 241 and NFPA 70 .
G. Means of Egress: Do not block exiting for occupied buildings, including paths from exits to roads. Minimize disruptions and coordinate with Contracting Officer.
H. Egress Routes for Construction Workers: Maintain free and unobstructed egress. Inspect daily. Report findings and corrective actions weekly to the Contracting Officer.
I. Fire Extinguishers: Provide and maintain extinguishers in construction areas and temporary storage areas in accordance with 29 CFR 1926 , NFPA 241 and NFPA 10 .
J. Flammable and Combustible Liquids: Store, dispense and use liquids in accordance with 29 CFR 1926 , NFPA 241 and NFPA 30 .
K. Existing Fire Protection: Do not impair automatic sprinklers, smoke and heat detection, and fire alarm systems, except for portions immediately under construction, and temporarily for connections. Provide fire watch for impairments more than 4 hours in a 24-hour period. Request interruptions in accordance with Paragraph "OPERATIONS AND STORAGE AREAS", and coordinate with the Contracting Officer. All existing or temporary fire protection systems (fire alarms, sprinklers) located in construction areas shall be tested as coordinated with the Contracting Officer.
Parameters for the testing and results of any tests performed shall be recorded by the General Contractor and copies provided to the Contracting Officer.
L. Smoke Detectors: Prevent accidental operation. Remove temporary covers at end of work operations each day. Coordinate with the Contracting Officer.
M. Hot Work: Perform and safeguard hot work operations in accordance with NFPA 241 and NFPA 51B. Coordinate with the Contracting Officer.
Designate contractor's responsible project-site fire prevention program manager to coordinate permit hot work.
N. Fire Hazard Prevention and Safety Inspections: Inspect entire construction area weekly. Coordinate with, and report findings and corrective actions weekly to the Contracting Officer.
O. Smoking: Smoking is prohibited in and adjacent to construction areas inside existing buildings and additions under construction. In separate and detached buildings under construction, smoking is prohibited except in designated smoking rest areas.
P. Dispose of waste and debris in accordance with NFPA 241 . Remove from buildings daily.
Q. Perform other construction, alteration and demolition operations in accordance with 29 CFR 1926 .
SECTION 01 01 00 Page 6
1.8 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting Officer, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be as determined by the Contracting Officer.
E. Workers are subject to rules of the Location applicable to their conduct which shall be provided by the Contracting Officer.
F. Execute work so as to interfere as little as possible with normal functioning of Location as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied during construction except as permitted by the Contracting Officer where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by the ARS in quantities sufficient for not more than two work days.
3. Where access by ARS personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment may be permitted subject to fire and safety requirements.
G. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the ARS operations will not be hindered. Contractor shall permit access to ARS personnel through construction areas which serve as routes of access to such affected areas and equipment. Coordinate alteration work in areas occupied by ARS so that operations will continue during the construction period.
SECTION 01 01 00 Page 7
H. When an unoccupied building is turned over to Contractor to complete construction as required, Contractor shall accept entire responsibility until contract completion.
I. Utilities Services: Maintain existing utility services for ARS at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by the Contracting Officer.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior written approval of the Contracting Officer. Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without the Contracting Officer's prior knowledge and written approval.
2. Contractor shall submit a request to interrupt any such services to the Contracting Officer, in writing, Two weeks advanced notice and again 48 hours in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of ARS. Interruption time approved by ARS may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 21 calendar days prior to the desired time and shall be performed as directed by the Contracting Officer. It is the Contractor's responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the mitigating life safety measures to be used during the work, and a schedule defining the duration of the work with milestone subtasks.
5. In case of a contract construction emergency, service will be interrupted on approval of the Contracting Officer. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
J. To minimize interference of construction activities with flow of ARS traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.
SECTION 01 01 00 Page 8
2. Method and scheduling of required cutting, altering and removal of existing roads; walks and entrances must be approved by the Contracting Officer.
K. Coordinate the work for this contract with other construction operations as directed by Contracting Officer. This includes the scheduling of traffic and the use of roadways, as specified in Paragraph
"USE OF ROADWAYS".
1.9 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the Contracting Officer, of areas of the building in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed, to the Contracting Officer.
1. Shall note any discrepancies between drawings and existing conditions at site.
2. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and Contracting Officer.
1.10 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re installation and reuse. Store such items where directed by Contracting Officer.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from ARS property.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the ARS during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are indicated on drawings and which are not scheduled for discontinuance or abandonment.
SECTION 01 01 00 Page 9
1.11 AS-BUILT DRAWINGS
A. The Contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To insure compliance, as-built drawings shall be made available for the Contracting Officer's review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built drawings and one electronic version to the Contracting Officer within 15 calendar days after each completed phase and after the acceptance of the project by the Contracting Officer.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.12 USE OF ROADWAYS
A. For hauling, use only established public roads and roads on ARS property and, when authorized by the Contracting Officer, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed by the Contractor at Contractor's expense.
1.13 TEMPORARY TOILETS
A. Provide for use of all Contractors' workers ample temporary sanitary toilet accommodations with suitable sewer and water connections; or, when approved by Contracting Officer, provide suitable dry closets where directed. Keep such places serviced regularly, clean and free from all pests and all connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfectly clean.
1.14 AVAILABILITY AND USE OF UTILITY SERVICES
A. See contract, FAR Clause 52.236-14, Availability and Use of Utility Services.
B. Heat: Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, is prohibited. Maintain minimum temperatures as specified for various materials and equipment as recommended by the manufacturer of the materials and equipment.
C. Electricity (for Construction and Testing): Furnish all temporary electric services.
1. Obtain electricity by connecting to the ARS electrical distribution system. The Contractor shall meter and pay for electricity required for electric cranes and hoisting devices, electrical welding devices and any electrical heating devices providing temporary heat. Electricity for all other uses is available at no cost to the Contractor.
D. Water (for Construction and Testing): Furnish temporary water service.
1. Obtain water by connecting to the ARS water distribution system.
SECTION 01 01 00 Page 10
Provide reduced pressure backflow preventer at each connection. Water is available at no cost to the Contractor.
2. Maintain connections, pipe, fittings and fixtures and conserve water use so none is wasted. Failure to stop leakage or other wastes will be cause for revocation (at Contracting Officer's discretion) of use of water from ARS system.
1.15 TESTS
A. Conduct final tests required in various sections of specifications in presence of an authorized representative of the Contracting Officer.
Contractor shall furnish all labor, materials, equipment, instruments, and forms, to conduct and record such tests.
1.16 INSTRUCTIONS
A. Contractor shall furnish maintenance and operating manuals, verbal instructions and formal training when required by the various sections of the specifications and as hereinafter specified.
1.17 RELOCATED EQUIPMENT AND ITEMS
A. Contractor shall disconnect, dismantle as necessary, remove and reinstall in new location, all existing equipment and items indicated to be relocated in accordance with statement of work, government approved drawings or Contracting Officer's direction.
B. Perform relocation of such equipment or items at such times and in such a manner as directed by the Contracting Officer.
1.18 CONSTRUCTION WASTE MANAGEMENT
A. Responsibilities. The contractor shall employ processes that ensure the generation of as little waste as possible and shall avoid the generation of waste due to the following:
1. Over-packaging.
2. Error.
3. Poor planning, layout.
4. Over ordering.
5. Breakage.
6. Mishandling.
7. Contamination.
8. General weather damage, excluding extreme acts of nature (i.e.
tornados, hurricanes, flash floods, blizzards, etc.).
B. Procedures.
1. Of the inevitable waste that is generated, as many of the waste materials as economically feasible shall be reused, salvaged or recycled.
SECTION 01 01 00 Page 11
2. Waste disposal in landfills shall be minimized to the greatest extent possible.
i. Waste Diversion Goals.
a) Demolition, Major Remodeling: Minimum 10% of total project waste shall be diverted from landfill.
b) Interior Remodeling: Minimum 10% of total project waste shall be diverted from landfill.
ii. The following waste categories, at a minimum, shall be diverted from landfill:
a) Green waste (biodegradable landscaping materials).
(i) Soil.
(ii) Inert material (concrete, asphalt, masonry).
(iii) Clean dimensional wood, palette wood.
(iv) Engineered wood products: plywood, particle board, I-joists, etc.
(v) Cardboard, paper, packaging.
(vi) Asphalt roofing materials.
(vii) Insulation.
(viii) Gypsum board.
(ix) Carpet and pad.
(x) Paint.
(xi) Plastics: ABS, PVC.
(xii) Beverage containers.
C. Description of Work.
1. Includes:
i. Waste Management Plan development and implementation.
ii. Meetings to discuss goals, issues and training for the Waste Management Plan.
iii. Techniques to minimize waste generation.
iv. Sorting and separation of waste materials.
v. Reuse of salvaged materials on site.
vi. Salvage of existing materials and items for reuse or resale.
SECTION 01 01 00 Page 12
vii. Recycling of materials that cannot be reused or sold.
viii. Record keeping of receipts and records of salvaged, recycled or land filled materials.
2. Related Elements:
i. Alternates.
ii. Construction Waste Management.
iii. Site Demolition.
iv. Site Clearing.
v. Slope Protection/Erosion Control.
vi. Asphalt Concrete.
vii. Crushed Stone Paving.
viii. Portland Cement Concrete Paving.
ix. Valve Boxes.
x. Storm Sewers.
xi. Chain Link Fences and Gates.
xii. Walk, Road and Parking Appurtenances.
xiii. Miscellaneous Landscaping Materials.
xiv. Concrete, Concrete Formwork, and Concrete Reinforcement.
xv. Cast-in-Place Concrete.
xvi. Unit Masonry.
xvii. Structural Steel.
xviii. Steel Roof Deck/Steel Floor Deck.
xix. Cold Formed Metal Framing.
xx. Metal Fabrications.
xxi. Rough and Finish Carpentry.
xxii. Engineered Structural Wood.
xxiii. Plastic Lumber.
xxiv. Building Insulation.
xxv. Modified Bitumen Roofing.
xxvi. Metal Doors.
SECTION 01 01 00 Page 13
xxvii. Wood and Plastic Doors and Frames.
xxviii. Metal Support Systems.
xxix. Gypsum Wallboard.
xxx. Acoustical Treatment.
xxxi. Resilient Flooring.
xxxii. Tile and Carpet.
xxxiii. Painting.
xxxiv. Toilet Compartments.
xxxv. Louvers and Vents.
xxxvi. Signage and Graphics.
xxxvii. Ductwork and Ductwork Accessories
D. Definitions.
1. Class III Landfill: A landfill that accepts non-hazardous resources such as household, commercial and industrial waste resulting from construction, remodeling, repair and demolition operations.
2. Clean: Untreated and unpainted; uncontaminated with adhesives, oils, solvents, mastics and like products.
3. Construction and Demolition Waste: Includes all non-hazardous resources resulting from construction, remodeling, alterations, repair and demolition operations.
4. Dismantle: The process of parting out a building in such a way as to preserve the usefulness of its materials and components.
5. Disposal: Acceptance of solid wastes at a legally operating facility for the purpose of land filling (includes Class III landfills and inert fills).
6. Inert Backfill Site: A location, other than inert fill or other disposal facility, to which inert materials are…