Summary: Statement of Work for San Bernardino National Wildlife Refuge Fish Laboratory Building
This is a Design-Build Statement of Work for the U.S. Fish and Wildlife Service (USFWS) Division of Engineering to construct a new Fish Laboratory Building at the San Bernardino National Wildlife Refuge in Douglas, Arizona (7628 North Highway 191). The project involves designing and constructing a 45' x 45' fisheries laboratory building with a 12' x 30' separate dry laboratory room, totaling approximately 2,024 square feet including circulation. The primary function is fisheries management and conservation with capabilities for water quality analysis, breeding studies, soil study, and invasive species research. The facility will house two large recirculating aquaculture system (RAS) tanks (8 feet diameter, 4 feet deep) and tabletop tanks for seasonal, temporary holding of Yaqui chub, Yaqui topminnow, and beautiful shiner species at biosafety level 1. The building will include a Mini split HVAC unit for the dry lab room, floor drains for wastewater management, well water supply, fire extinguisher and eyewash station, non-slip flooring, phenolic resin lab benches in the dry room, and corrosion-resistant doors with high-security mechanical locks.
The project operates under a two-phase approach with a design phase of 60 calendar days and construction phase of 120 calendar days (180 days total). The contractor must achieve 30% energy efficiency improvement over ASHRAE Standard 90.1-2013 and incorporate sustainable design principles. All structural drawings require Arizona-registered professional engineer seals, and designs must comply with International Building Code, NFPA 101 Life Safety Code, and ADA accessibility standards. The contractor is responsible for obtaining all permits, coordinating with utility providers for water and electrical service connections, and managing site preparation including the removal of the existing fish laboratory. The contractor must submit a Design/Build Management Plan within 10 days of Notice to Proceed, including five design phase milestones at 20%, 40%, 70%, 99%, and 100% completion. Construction supervision, materials testing, safety compliance, and closeout documentation including O&M manuals and as-built drawings are contractor responsibilities. The total project firm fixed price (FFP), including all design services, fabrication, installation, site development, utilities, and construction contingencies, will be disclosed to offerors selected for phase two proposals.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
P a g e 1 | 72
SCOPE OF WORK
FOR
SANBERNADINO
NATIONAL WILDLIFE REFUGE
Fish
Laboratory Building
Design-Build Statement of Work
Cochise County, Arizona
Approvals
Refuge Manager/Project Leader
Refuge/Program Supervisor
IMD Chief
Project Manager
Environmental Compliance
Cultural Resources
Energy Compliance
United States Fish and Wildlife Service Division of Engineering 4400 Masthead Street NE Albuquerque, New Mexico 87109.
STATEMENT OF WORK
For Design and Build
San Bernadino National Wildlife Refuge New Headquarters Fish Laboratory Building
December 2025
TABLE OF CONTENTS
PART 1: GENERAL
1.1 SERVICES & SCOPE
1.2 CONTRACTOR RESPONSIBILITY
1.3 CURRENT DESIGN LEVEL
1.4 BUDGET PARAMETERS
1.5 CONSTRUCTION SITE
1.6 GREEN BUILDING PARAMETERS
1.7 PERIOD OF PERFORMANCE
1.8 PROJECT MANAGER
1.9 GOVERNMENT FURNISHED INFORMATION
1.10 CONTRACTOR SUBMITTAL REQUIREMENTS
1.11 DEFINITIONS
PART 2: DESIGN SERVICES
2.1 DESIGN SERVICES SCOPE
2.2 CODES AND STANDARDS
2.3 ENERGY EFFICIENCY
2.4 DRAWING STANDARDS
2.5 STATE REGISTRATION OF DESIGN ARCHITECTS AND ENGINEERS
2.6 SPECIFICATION STANDARDS
2.7 PERMIT RESPONSIBILITY
2.8 DESIGN SCHEDULE AND REVIEW MEETINGS
2.9 PAYMENT FOR DESIGN SERVICES
PART 3: CONSTRUCTION SERVICES
3.1 GENERAL
3.2 PAYMENT PROCEDURES
3.3 PROJECT SAFETY
3.4 WORK HOURS
3.5 PROTECTIONS
3.6 CLOSEOUT PROCEDURES
3.7 CLOSEOUT DOCUMENTS
PART 4: GOVERNMENT RESPONSIBILITIES
4.1 DUTY TO COOPERATE
PART 5: ARCHITECTURAL PROGRAM
5.1 SUMMARY AND REFERENCE DOCUMENTS
5.2 EXHIBITRY
5.3 COMMUNICATION NEEDS
5.4 PUBLIC RESTROOMS
5.5 MATERIALS AND ARCHITECTURAL FEATURES
5.6 SITE FEATURES
5.7 WATER SUPPLY
5.8 SEWER
5.9 ELECTRICAL SERVICE
5.10 TELEPHONE/DATA
5.11 VISITOR CENTER PROMINANCE
5.12 SECURITY REQUIREMENTS
PART 6: MECHANICAL AND ELECTRICAL PROGRAMS
6.1 HVAC SYSTEMS
6.2 PLUMBING SYSTEMS
6.3 ELECTRICAL SYSTEMS
PART 7: SCHEDULE
7.1 DESIGN SCHEDULE
7.2 CONSTRUCTION SCHEDULE
PART 1: GENERAL
1.1 SERVICES AND SCOPE: The services required will include all the design and preparation of construction plans and specifications to include a master plan, and construction of designated portions of the San Bernadino National Wildlife Refuge new Headquarters Fish Laboratory building and Site development at the San Bernadino National Wildlife Refuge (NWR) in Cochise County, Arizona, for the U.S. Fish and Wildlife Service (FWS).
1.1.1 The project consists of a new laboratory building and related site improvements.
1.1.2 The description of work: The work shall consist of labor, equipment and materials to build a new fisheries laboratory and the demolition of the existing fish laboratory. The primary purpose and function of the building include Fisheries management and conservation. Housing of biology equipment, tools and supplies. The specific research or testing conducted will include intermittent research and studies such as but not limited to water quality analysis, breeding, soil study, invasives studies. Any holding of fish will be seasonal and temporary. The species of fish that will be housed will potentially be all life stages of Yaqui chub, Yaqui topminnow and beautiful shiner. The expected biosafety level is BSL 1.
Permits or regulations from Institutional Animal Care and Use Committee (IACUC), USDA, state fisheries will not be needed but this facility will meet the standards of these institutions.
Building and space requirements:
Total required floor area (approximate): 45’x45’
Required specific lab areas:
• Aquatic holding area (wet labs): main area of 45x45 building (excluding 12’x30’ room)
1. How many tanks? 2
2. Range of tank sizes? 8ft diameter and 4ft deep
3. Type of system (e.g., recirculating aquaculture system (RAS), flow-through)? RAS
• Dry laboratory area: For analysis and data collection. One 12’x30’ room
• Microbiology/Pathology lab: For culturing and disease diagnostics. None
• Preparation rooms: For feed preparation, media, or equipment. Within main area
• Quarantine area: For new fish or disease investigation. NA- a part of the main area could be set up for quarantine tabletop tanks if needed.
• Equipment rooms: For HVAC, water filtration, and electrical systems. Within main area and/or 12’x30’ room.
• Administrative/Office space: For staff and researchers. None
• Storage areas: For feed, chemicals, and equipment. Dual use of both main area and smaller room.
• Waste management area: For handling solid and biological waste. None
Workflow: Describe the flow of materials, people, and animals through the facility. Personnel workflow will include entry for access to biology field equipment, tools and supplies that are not otherwise kept in the biology office (this excludes chemicals which are all maintained within a chemical Connex onsite). Personnel will intermittently access buildings to manage fish. Fish will be held in the building temporarily when conditions necessitate, likely once a year during dry conditions.
Water systems and quality management
Water source: (e.g., city water, well water, reverse osmosis (RO)) well water
Water treatment requirements:
• What type of filtration is needed? (e.g., mechanical, biological, UV sterilization, activated carbon) None- mechanical filters are maintained at well head location.
• Will water quality parameters (pH, temperature, dissolved oxygen) be continuously monitored and logged?) Well water is tested quarterly. When fish are housed in water the water quality is monitored and logged.
Wastewater treatment: How will wastewater, including contaminated water, be handled and decontaminated before discharge? No toilet will be installed. No contaminated water is expected. Gray water from sink should tie into floor drain, or drained to field. Periodic flushing of fish holding tanks will be drained via floor drains into field.
Emergency systems:
• What backup power systems are required for critical equipment (e.g., pumps, life support)? None
• What are the alarm requirements for system failures (e.g., temperature, oxygen)? None
Environmental and HVAC Temperature control: 12’x30’ room is to have a Mini split unit installed as part of build.
• What are the required temperature ranges for the animal holding areas and labs? None, general venting of main area is sufficient
• Are heating and cooling units required for water systems? No
Ventilation:
• Will the building or specific rooms require negative air pressure? No
• What air changes per hour are needed? None
Humidity control: Are specific humidity ranges required for wet labs? No
Lighting:
• What lighting cycle (photoperiod) is needed for fish? None
• Are adjustable or programmable lighting systems required? No, but desired
Materials and construction Flooring: What type of flooring is preferred? (Must be non-slip, impervious to liquids, and resistant to chemicals) a basic non-slip flooring is sufficient
Walls and ceilings: What materials will be used? (Should be durable, washable, and resistant to detergents/disinfectants) we are open to suggestions. For the 12’x30’ room just finished drywall is sufficient.
Casework and benches:
• What material is preferred for lab benches? (Must be resistant to heat and chemicals) Phenolic Resin
• What layout is required? (e.g., benching, cabinets, sinks) see floor plan (bench and cabinets in 12x30 room)
Doors: Should be corrosion-resistant and have seals to prevent water escape.
Plumbing: Are specific materials required for corrosion resistance? No
Equipment Equipment that needs to be moved and integrated:
• Shelving units
• Work bench tables
• Desks
• Bookshelves
• Filing cabinets
• Large Specimen cabinets
Equipment:
• Fish traps
• Fish nets
• Waders/boots
• Misc. biology equipment
Tanks:
• Two large Tanks and stands and filter systems
• Tabletop fish tanks
• Tabletop terrariums
Safety and security.
Safety features:
• What safety features are required? (e.g., eyewash stations, safety showers, emergency shut-offs, fire suppression) eyewash station and fire extinguisher
• Will the lab require access control? No
1.1.3 This building will not be required to be designed and built in accordance to LEED standards. Design and materials shall be of high quality, durable, easily maintained and hardened to withstand the arid zone weather environment.
1.2 CONTRACTOR RESPONSIBILITY: The contractor shall be responsible for the professional quality, technical accuracy and coordination of all designs, drawings, specifications and other documents or publications upon which construction is based.
1.3 CURRENT DESIGN LEVEL: The current design level has been developed to approximately 10% completion (Schematic Design
1.4 BUDGET PARAMETERS: Total project Firm Fixed Price (FFP) which includes all design services; fabrication and installation; and all construction described herein, all site development, utilities, and construction contingencies will be disclosed to offeror's selected to submit phase two proposals.
1.5
1.6 CONSTRUCTION SITE: The new building will be constructed on the existing
San Bernadino National Wildlife Refuge, Headquarters Site, located at 7628 North Highway 191 (31.50354, -109.65588) Douglas, AZ. 85607
1.7 GREEN BUILDING CONSIDERATIONS: Executive Orders 13101 and 13123 require the Government to use “Sustainable Design” for all new facilities. Design shall promote waste and pollution prevention, water and energy conservation, and utilize materials that have the highest percentage of recovered materials practical, considering price, availability, and performance.
1.7.1 Use the most energy efficient equipment that is practical in all mechanical, electrical and plumbing systems, and design these systems to promote a healthy environment for the occupants of the building.
1.7.2 Research and specify “Environmentally Preferable Products” and “Recycled Products” wherever possible. This requirement shall include, but not limited to considering products containing recycled content for concrete, steel, masonry units, thermal insulation, carpet, acoustical ceiling tile, gypsum board, wood floors, ceramic tile, paints and coatings, etc.
Utilize products that are designated in the Environmental Protection Agency’s Comprehensive
Procurement Guideline (www.epa.gov/cpg/).
http://www.epa.gov/cpg/)
1.7.3 LEED Certification: The laboratory building will not require LEED Certification.
1.8 PERIOD OF PERFORMANCE: Design Phase 60 Calendar Days and Construction Phase 120 Calendar Days totaling 180.
1.9 GOVERNMENT FURNISHED INFORMATION: See also Section J of
the solicitation /contract.
Appendix 1. AREA RECORD SURVEY: The Headquarters Area Record of Survey dated July 2025 prepared by USFWS is provided for proposal purposes only. If the DB requires additional survey information for building corner locations or other purposes (such as topography) that shall be their responsibility as part of the contract.
Appendix 2. VICINITY MAP
Appendix 3. FEMA FLOOR INSURANCE MAP
Appendix 4. CURRENT LANDUSE AT THE HEADQUARTER’S SITE
Appendix 5. ARCHITECTURAL PROGRAM
Appendix 6. CONCEPTUAL ARCHITECTURAL DRAWING
Appendix 7. GEOTECTNICAL REPORT: Geotechnical Engineering Report: It is the responsibility of the DB to obtain an updated geotechnical report to properly design the foundation and parking areas of the building. The attached Geotechnical Report dated 10/2/2025 is for reference only. All Subcontractor (A/E) designed structural drawings must reference a Contractor provided Geotechnical Investigation and Report.
1.9.1 The government-furnished documents describe the general intent and desired components, functions and adjacencies. Modifications in the Contractor's proposal and during the design phase that are deemed to enhance the overall building and site development and/or result in improvements to aesthetics, functionality or construction and cost, will be considered by the government.
1.10 CONTRACTOR SUBMITTAL REQUIREMENTS:
1.10.1 Submit submittal for approval of the Contracting Officer Representative within 10 days of Notice to Proceed, a Design/Build Management Plan for this project which includes a schedule of design review meetings and design submittals. The Contracting Officer may revise this schedule in consultation with the DB and FWS Project Manager and when approved this will become the schedule for the design portion of the project. There will be a minimum of five design phase milestones: A Design Kickoff Meeting; a Schematic Design documents (20%) review; a Design Development documents (40%) review; a Preliminary Construction Documents (70%) review, and a Final Documents review (99%). The reviews shall include all aspects of design, including exhibits.
1.10.2 In addition to submitting the reports required in Section H, the contractor shall submit monthly status reports to the FWS Project Manager (Contracting Officer’s Representative.)
1.10.3 Submittals during the construction phase are discussed in Part 3 Construction Services.
1.11 DEFINITIONS
1.11.1 Commissioning is the act of statically and dynamically testing the operation of equipment and building systems to ensure they operate as designed and can satisfactorily meet the needs of the building throughout the entire range of operating conditions per LEED Certification plan.
1.11.2 Construction is defined as, but not limited to, constructing (giving form by combining the parts), altering, repairing, adding to, subtracting from, improving, restoring, moving, wrecking or demolishing any building, highway, road, excavation or other structure, project, or improvement attached to real estate.
1.11.3 Contracting Officer's Representative (COR) for this project is the Project Manager and is the Point of Contact for all technical questions and issues.
1.11.4 CI means the Government Construction Inspector.
1.11.5 Day or Days shall mean calendar days unless otherwise specifically noted.
1.11.6 DB means Design-Builder and is the contracting entity selected to design and build the project.
1.11.7 Design Consultant is a qualified, licensed design professional who furnishes design services required under the Contract Documents. This may be an employee of the DB, is retained by DB, or is employed or retained by anyone under contract with DB.
1.11.8 Service or FWS means United States Department of Interior, Fish and Wildlife Service, Region 2 (Southwest Region).
1.11.9 Government may also be referred to as the Owner or Department of Interior
1.11.10 Incident Rate (IR) is the number of recordable incidents resulting in days away from work for each 100 full-time employees per year, based on 2,000 hours worked per employee per year.
1.11.11 LEED means Leadership in Energy and Environmental Design.
1.11.12 Local Authority Having Jurisdiction: Duly adopted local code authority, agency, or serving utility governing or serving the location of the project.
1.11.13 Management Plan: DB's project approach for planning, design, and construction and includes, at a minimum, but is not limited to the following:
1.11.13.1 Schedule (design and construction activities)
1.11.13.2 Project Staffing Plan
1.11.13.3 Safety Plan
1.11.13.4 Subcontracting Plan
1.11.13.5 Organization Chart with Roles and Responsibilities
1.11.13.6 Quality Assurance/Quality Control (QA/QC) Plan
1.11.13.7 Commissioning Plan
1.11.14 Notice to Proceed (NTP): Each Project Phase, i.e., design phase and construction phase, requires a written NTP from the Contracting Officer (CO). The NTP will identify the next Project Phase(s) that are approved. The NTP will identify any qualifications, limitations, or exceptions to the work in each Phase.
1.11.15 Open Book Accounting is the allowance of the government to have free and open access to financial and accounting documents that the Design/Builder has associated with the project being designed and constructed.
1.11.16 Project Specifications are specifications that state what the required results will be with measurable or observable criteria for verifying compliance. This may include the use of specific product cut sheets in addition to specifications.
1.11.17 Schedule is a chronological layout of the work to be performed prepared using commercially available scheduling software.
1.11.18 Subcontractor is any person or entity retained by DB as an independent contractor to perform a portion of the Work and shall include materialmen and suppliers.
1.11.19 Sub-Subcontractor is any person or entity retained by a Subcontractor as an independent contractor to perform any portion of a Subcontractor's work and shall include materialmen and suppliers.
1.11.20 Work is comprised of all DB's design, permitting, construction and other services required by the Contract Documents, including procuring and furnishing all materials, equipment, services and labor reasonably inferable from the Contract Documents.
PART 2 DESIGN SERVICES
2.1 DESIGN SERVICES SCOPE: Services shall include the full range of architectural, interior decoration, structural, mechanical, electrical, furniture, landscape and civil engineering, design and documentation for construction of the new facility by contract including the preparation of plans and specifications, and schedule of values.
2.2 CODES AND STANDARDS: The DB shall assure that the design meets the requirements of all applicable local, state, and federal codes in the latest editions, including but not limited:
• International Building Code
• International Mechanical Code
• International Plumbing Code
• International Electrical Code
• NFPA 101 Life Safety Code
• Sheet Metal and Air Conditioning Contractors National
Association (SMACNA)
• NEC-2017 (2017 NFPA-70)
• American Disabilities Act Accessibility Guidelines
• LEED standards, functional relationships, and the logical integration of architectural, structural, mechanical, and electrical systems
• ANSI/ASHRAE Standard/ IESNA90.1-2013- Energy Standard for
Buildings (Except Low-Rise Residential Buildings Plus Supplemental Addenda).
• ANSI/ASHRAE Standard 55-2013 - Thermal Environmental Conditions for Human O c c u p a n c y.
• ANSI/ASHRAE 62-2013 Ventilation for Acceptable Indoor Air Quality with Appendix H.
• Standards for New Federal Buildings 10 CFR 435 (Appendix 13)
• OSHA Regulations Consumer Product Safety Commission 16 CFR 1201
Safety Standards for Architectural Glazing Materials
• Clean Water Act
• NPDES Permits and other federal, state, and local environmental and sanitary/ health rules, regulations, and requirements, as applicable
• Architectural Barriers Act
• American Association of State Highway Transportation Officials
(AASHTO) Policies and Guidelines for the Design of Highways, Streets, pavements, and Roadside Safety.
2.3 ENERGY EFFICIENCY: The overall building’s energy efficiency design shall 30% better than that predicted by ASHRAE Standard 90.1-2013. This is required by section 109 of the Energy Policy Act of 2005 – August 8, 2005. Contractor may refer to ASHRAE’s “Advance Energy Design Guide” and implement as many of the energy conserving “Recommendations” and “How-To’s” for Climate Zone #2-moist, which are economically effective. Economic effectiveness shall be based upon a 40-year life cycle cost analysis using NIST’s BLCC-5.3 software which may be downloaded from the FEMP’s website.
2.4 DRAWING STANDARDS:
2.4.1 Furnish full, complete, accurate and coordinated architectural, civil engineering, structural engineering, mechanical engineering, electrical engineering and landscape architectural working drawings and schedules.
2.4.2 All drawings shall be prepared using AutoCAD release 2018. Flash drives of drawing files (.DWG) and specifications shall be submitted at the final submittal. Also, Adobe .PDF files of each .DWG file shall be submitted on flash drives at the final submittal.
• General: Ensure that drafting and lettering on all drawings is done to such scale and legibility to permit clear and accurate readability by construction personnel.
• Sheet size: 24" X 36" with 1/2 inch borders on three (3) sides and 1½ inch border on the binding side.
• Lettering size: 1/8" (actual size) minimum height.
• Minimum scale of floor plans: 1/8"=1"-0".
• Title Blocks: FWS typical title block will be furnished to the DB upon request. Use “Title Sheet Block” on first drawing only. Use “Standard Title Block” on all other drawings.
• Index to drawings: on first sheet (Title Sheet).
• Location/Vicinity map: On first sheet (Title Sheet).
• Project Number: Place FWS furnished Project Number on each drawing sheets in the appropriate place in each title block.
• Asset Numbers, Work Order Numbers, etc: Place FWS furnished asset numbers and other data on the Title Sheet as directed by FWS Project Manager.
• Graphic Scale: All drawings shall have a graphic scale in both English and Metric units for all scales used on that sheet.
• Arrange all categories of drawings, i.e.; A-1, A-2, A-3; M-1, M-2, M-3, etc.
so that individual buildings and their respective plans, sections, details, etc.
within that category are grouped together in such a way that they can easily be separated or removed from the drawings. Do not mix one building’s details with another.
2.5 STATE REGISTRATION OF DESIGN ARCHITECTS AND ENGINEERS: The Architects and Engineers responsible for the design of this facility shall have a current license to practice their profession in the State of Arizona. In addition, the DB team, including individual professionals, as well as architectural, engineering and construction firms, shall be experienced in the design of structures and infrastructure in the Mountain and Arid Region of the United States, and specifically the climate, soil conditions, architectural styles, building codes, urban and environmental conditions of the Arizona area. All final drawings and specifications prepared by the DB shall bear the signatures and professional seals of the architect or engineer under whose direct supervision the documents were produced and who is licensed to practice that profession in the State of Arizona.
2.6 SPECIFICATION STANDARDS:
2.6.1 Specifications shall be written specifically for this project. Specifications shall be developed using Masterspec + or Microsoft Word software. Provide compact disks containing all specification sections with the final Contract Document submittal. Note: Copy the specifications onto compact disks as a single document file) and copy each section as a separate document (file). Adobe .PDF files of each specification section shall be submitted on compact disks at the final submittal.
2.6.2 COR will provide applicable sections of Division 1 specifications. DB shall prepare other divisions. Prepare specifications following Constructions Specifications Institute Division and Section format.
2.6.3 Color Board: Submit recommendations for interior colors, for the buildings, including ceilings, wall treatments, window coverings, floor surfaces, etc. where no decision has been made per this document. Recommendations shall be displayed on a “Color Board”, keyed to the Finish Schedule, showing materials, colors, textures, etc.
2.6.4 Submit updated copies of the Management Plan with each design submittal. This shall include outline copies of the Safety Plan, QA/QC Plan, Scheduling, Schedule of Items, and Commissioning Plan. These plans shall continue to be developed during the design process and finalized documents shall be submitted before construction of the project begins.
2.7 PERMIT RESPONSIBILITY: The DB shall obtain and pay for any permits applicable to Federal construction projects including, but not limited to environmental permits, government review charges, utility tap and meter fees and inspection fees necessary for the prosecution of the Work pertaining to transportation, utilities, sewage disposal systems, erosion and sedimentation control plans, and any storm water discharge permits associated with construction activities, as required.
2.8 DESIGN SCHEDULE AND REVIEW MEETINGS: Periodically meet with COR and other FWS representatives to review the design and to discuss and resolve issues. The design shall be refined and developed so that the DB can move forward to the next phase of the process.
Meeting times and locations shall be as agreed to by DB and COR. Meetings shall include a Design Kickoff Meeting; Schematic Design (20%) Review Meeting; Design Development (40%) Review Meeting; Preliminary Construction Documents (70%) Review Meeting; and a Final Documents (99%) review meeting.
Meeting notes will be made by the DB Contractor and distributed to their Design consultants, the Contracting Officer, the COR, and the Refuge Manager. After review by the FWS, notes will be corrected if necessary, by the DB Contractor and redistributed to the same group named above.
2.8.1 Kick-Off: Conduct a site visit and design meeting with FWS personnel, to include a site visit to the Refuge construction site. The time and date of this meeting will be mutually agreed upon by the Refuge Manager, the DB Contractor and the COR. The DB Contractor shall have, at a minimum, their Project Manager, Civil Engineer and Architect, to attend this meeting.
The purpose of the meeting will be to review the design program, review and determine applicability of the FWS furnished project information of the project, verify existing conditions, discuss any DB proposed changes to FWS provided information, and start the Schematic design process.
2.8.2 Schematic Design Documents (20%): Based on government-furnished documents and design kick-off meeting, provide at least 2 distinct schematic floor plans, and 2 distinct exterior elevation concept drawings, for discussion and selections by FWS staff.
2.8.2.1 A Design Review Meeting for this submittal will be held and attended by at a minimum, the DB contractor and Architect. The Government will require 5 working days for review of these documents.
2.8.3 Design Development Documents (40%): Based on government-furnished documents, Schematic Design comments, and initial design meeting, provide outline specifications, drawings of the floor plan, site plan, exterior elevations, building and wall sections and general elements of the architectural and structural concept for the buildings. Drawings and outline specifications shall also address the civil, landscaping, mechanical and electrical systems, any special systems (such as; Hazardous waste, Oil/water separator, Vehicle wash station, Fire alarm, fire sprinkler system, security alarm), and documents. Provide drawings and schedules which address interior and exterior materials and finishes being proposed. Specifications shall be developed that indicate material type in a thorough, prescriptive, and generic Construction Specification Institute (CSI) format and the specifications shall include a submittal log. The Government will require 10 working days for review of these documents.
2.8.3.1 Design Development shall include coordination with all utility providers, including water and sewer service highway authorities for obtaining driveway permits, Fire Department for design of hydrants and fire sprinkler system, electrical utility service provider, phone and internet service providers, and others required and listed with contact information.
2.8.4 Preliminary Construction Documents (70%): Provide preliminary construction documents showing important construction details, developed specifications, and exterior and interior material and color boards. Specifications shall be developed that indicate material type in a thorough, prescriptive, and generic CSI format and the specifications shall include a submittal log to allow construction to continue schedule. Provide engineering calculations to permit an evaluation of the design for the proposed structural, plumbing, HVAC, electrical, lighting, phone, security, data, and radio systems, and other major systems and components. (Calculations shall bear the stamp of Arizona registered Professional Engineer prior to acceptance of 100% complete documents.) The Government will require 10 days for review of these documents.
2.8.4.1 Calculations at 70% include the following:
• Building heat load calculation shall be conducted in accordance with the methods established by ASHRAE.
• Provide heat transmission calculations for each type of building construction components such walls, roof, floor, etc.
• Submit the ASHRAE’s recommended psychrometric values used in the heat load calculations. They shall include values for both outdoor and indoor.
• Submit building heat load calculations for both heating and cooling for each building room. They shall show all factors used to calculate the following room load values.
o Transmission sensible loads o Solar heat gains o Infiltration sensible and latent loads o Equipment sensible and latent loads for each type of equipment o Occupancy People sensible and latent loads o Submit total heating and cooling loads for each HVAC air handler serving the building zones. The cooling loads shall include the air handler total air flow rate, sensible heat loads, latent heat loads, amount of outside air treated by air handler, and the outside air psychrometric conditions.
• Submit light level calculations for each room in the building along with rooms lighting type and lighting control.
• Submit NEC electrical feeder and service conductor ampacity load calculations.
• Submit short circuit amperage calculations for each electrical service equipment and distribution equipment as required by NEC.
2.8.4.2 A Design Review Meeting for this submittal will be held, attended by the DB contractor, Civil Engineer, Architect, Mechanical Engineer and Electrical Engineer.
2.8.5 Construction Documents (99%): Provide drawings and specifications, which are complete with the exclusion of minor details. Submittal shall also indicate refinement of all exterior and interior materials and finishes, color schemes and material samples.
Specifications shall be developed that indicate material type in a thorough, prescriptive, and generic CSI format and the specifications shall include a submittal log. Provide final structural calculations. Provide cut sheets or instructions for HVAC control and special systems like solar electric power and fire alarm systems. Provide completed LEED design, specifications, and documents for construction. The Government will require 15 days for review of these documents.
2.8.6 Final Construction Documents (100%): Revise, respond to and resolve each comment made by FWS following review of the 99% Final Construction Documents and then provide the final deliverables as defined.
2.9 PAYMENT FOR DESIGN SERVICES: Payment for Design Services will be made for each item listed in the Schedule of Items attached at Section J, after each progress goal is completed by the Contractor and approved by the Government.
PART 3 CONSTRUCTION SERVICES
3.1 GENERAL
3.1.1 Possess and maintain, for the duration of this project, (to include warranty period) a state license as a general contractor in the State of Arizona.
3.1.2 Provide supervision, labor, materials, equipment, tools, construction equipment and machinery, inspection, testing, start-up, water, heat, utilities, transportation, and other facilities and services necessary for proper execution and completion of the Work, whether temporary or permanent and whether or not incorporated or to be incorporated in the Work.
3.1.3 Have at least one qualified supervisor capable of reading, writing, and conversing fluently in the English language on the job site during working hours.
3.1.4 Perform all construction activities efficiently and with the requisite expertise, skill, and competence to satisfy the requirements of the Contract Documents. At all times exercise complete and exclusive control over the means, methods, sequences, and techniques of construction.
3.1.5 Utilize Subcontractors who are duly licensed and qualified to perform the Work consistent with the Contract Documents. Government may reasonably object to DB's selection of any Subcontractor based on its information with respect to the subcontractor’s past performance and technical qualifications.
3.1.6 DB is responsible for quality control of its own work and work performed by its subcontractors and their sub-subcontractors. Provide and pay for the services of an independent construction materials testing laboratory accredited by an acceptable laboratory accreditation authority. Laboratory shall sample and test materials and perform required special inspections.
Copies of all test reports shall be submitted to the designer of record and the COR as soon as practicable. Laboratory shall be authorized to perform work in the state of Arizona.
Government may reasonably object to DB's selection of laboratory.
3.1.7 Design Consultants, in coordination with the COR, shall visit the site a minimum of four times to inspect the construction. They shall prepare a site visit report for each visit and shall submit the reports to the COR within 5 calendar days after the visit. The reports shall include comments about overall quality and accuracy of the construction. The reports shall also note all deficiencies observed.
3.1.8 RFIs: During construction, Design Consultants shall provide supplemental information and answer questions to clarify design. This information shall be documented on Request for Information (RFI) forms. The DB may use any format they choose for the Request for Information form, but all shall be identified with the words “Request for Information” at the top of the form along with the Government Contract Number, Project Location, Project Title and the Design-Build Contractor’s Name. RFI’s shall be logged and filed and shall be part of the Closeout Documents submitted to the Government. As RFI’s are generated and answered, submit copies to the COR and CO for information.
3.1.9 Product and Material Submittals: During construction, Contractor shall provide design consultants with product and material submittals for all items requiring submittals in the contract specifications. Those items specified on a proprietary basis, by manufacture and/or model number, or with product stamps allowing inspectors to verify compliance with the specifications, do not require submittals, unless the DB elects to do so. This information shall be documented on submittal forms. The DB may use any format they choose for the submittal forms but all shall be identified with the words "Submittal" at the top of the form along with the Government Contract Number, Project Location, Project Title, Specification Section and/or Drawing reference, and the Design-Build Contractor’s Name. Submittals shall be logged and filed and shall be part of the Closeout Documents submitted to the Government. As product submittals are generated and answered, submit copies to the COR and CO for information.
3.1.10 Assume responsibility for the proper performance of the Work of Subcontractors and all acts and omissions in connection with such performance. Nothing in the Contract Documents is intended or deemed to create any legal or contractual relationship between Government and any Subcontractor or Sub Subcontractor.
3.1.11 Record Drawings and Specifications: Maintain one set of working drawings and specifications, for record purposes, on the project site while work is in progress. Clearly and accurately record the as-constructed work in red. Record swing-tie distances from permanent points for all underground items. Include modifications, submittal log, and RFIs.
3.1.12 Government buildings and other facilities are not available for storage of DB's materials, equipment, and tools except for designated staging areas. Government owned equipment is not available for DB's use to accomplish any work.
3.1.13 Housing for workers and campsites are not available on site.
3.1.14 Contractor shall furnish and pay for all temporary facilities and utilities needed including heat, light, power, water, telephone, sanitary facilities, job offices, material handling equipment, temporary construction aids, and storage enclosures; except if suitable water is present at the site, it may be used for construction purposes at no cost if it does not adversely impact the operations of the station. The DB is responsible for all temporary connections and disconnections. Government furnished electricity is not available for DB’s use.
3.1.15 Contractor is encouraged to purchase construction materials and supplies locally.
3.2 PAYMENT PROCEDURES
3.2.1 Payment shall be made in accordance procedures outlined in the Solicitation.
3.2.2 Construction progress payments will be made monthly based on the work completed per the approved Schedule of Values, as agreed to by the Construction Inspector and the DB Superintendent or Project Manager.
3.2.3 Retainage will not be implemented unless the Contracting Officer determines that construction progress and/or quality are not satisfactory.
3.3 PROJECT SAFETY
1. The DB is ultimately responsible for safety on the project site.
3.3.1 Initiate and maintain, throughout the performance of this contract, an effective site-specific safety and health program that provides adequate policies, procedures, and practices to protect employees from, and allow them to recognize, job-related safety and health hazards. The program shall include provisions for the identification, evaluation, prevention and control of general work site hazards, specific job hazards, and potential hazards that may arise from foreseeable construction methods and conditions, as well as providing a competent person to conduct (documented) frequent and regular inspections. Each employee (DB and subcontractors) must be instructed in the recognition and avoidance of unsafe conditions and the regulations applicable to the work environment.
3.3.2 Provide barricades and warning devices as necessary to safeguard the public, workers, and government personnel. Where project work affects public roads, provide signage in accordance with the current edition of the Manual on Uniform Traffic Control Devices (MUTCD) as published by the US Department of Transportation, Federal Highway Administration.
3.3.3 Rollover Protection and Seat Belts: In addition to the Safety and Health requirements (OSHA) shall be extended to include equipment regardless of the year of manufacture.
3.4 WORK HOURS:
3.5 PROTECTIONS
3.5.1 Comply with all applicable federal, state, and local environmental laws and regulations. This condition applies to, but is not limited to, laws and regulations governing noise levels, air and water quality standards, erosion control, surface runoff, and cultural resources.
3.5.2 Provide erosion control methods (such as watering dry soils) and appurtenances (such as silt fence) as necessary to prevent wind-borne dust and water-borne silt from leaving the immediate work area.
3.5.3 If paleontological, archaeological or historical remains (including burials or skeletal material) are encountered, immediately stop the work and notify the Construction Representative, COR, or Contracting Officer. The Contracting Officer will notify the Regional Archaeologist, (Resource Discovered During Construction) and other relevant laws are followed. Work will cease in the immediate vicinity until permitted to resume by written order from the Contracting Officer. Work in other areas may proceed as approved by the Contracting Officer.
3.5.4 Heavy equipment operated on FWS roads and parking areas shall comply with highway-legal load limits unless explicitly approved otherwise.
3.5.5 Clearing and working limits shall be no greater than 100 feet from the affected construction areas and no greater than 50 feet from road edges. Any additional clearing needed to complete the project more than the outlined limits, will require approval by the COR.
3.6 CLOSEOUT PROCEDURES
3.6.1 Training: Thoroughly familiarize the Refuge staff with the building systems and train them to be proficient in its overall system operation and maintenance.
3.6.2 Tools and spare parts: Deliver to the project site all specialty tools, valve handles, fan belts, filters, spare parts, keys and similar devices such that the Refuge staff is able to operate and maintain the work.
3.6.3 Maintenance Materials: Deliver maintenance materials to Station Manager;
coordinate location of storage. (Provide consumable items in such quantities as needed for the first year of operation.)
3.6.4 Building Commissioning: Before Final Inspection, the Contractor shall implement the Commissioning Plan. A report will be submitted demonstrating that the equipment and building systems operate as designed and meet the needs of the building throughout the entire range of operating conditions.
3.6.5 Final Inspection: Notify the COR at least 10 calendar days prior to the anticipated date of completion of all work. The COR will proceed with Final Inspection as promptly as practicable. The time required for such Final Inspection and for making any corrections as a result thereof shall be included in the contract performance time. The DB representative responsible for the work shall be present at the Final Inspection and shall submit a preliminary list of unfinished work prior to Final Inspection. See Section E of the solicitation /contract.
3.7 CLOSEOUT DOCUMENTS
3.7.1 Operation and Maintenance Manuals: Submit two (2) copies of Operation and Maintenance manual (one to the Refuge office and one to the COR for the mechanical and electrical equipment, architectural treatments, doors, and windows. The manuals shall be clear, well organized, clearly indexed, tabbed, highlighted, tailored to the specific make, model, and wiring configuration of the systems; and shall include schedules and instructions for routine operation, trouble shooting, and periodic maintenance. The manuals shall include complete parts lists keyed to suppliers (name, address, websites, and telephone numbers for each).
3.7.2 Submit a full-size set of red-lined drawings and complete set of specifications that clearly indicates the as-constructed work. Submit one set of final working drawings (full scale), one set of reproducible drawings (full scale) on bond paper showing as-constructed conditions, and one electronic set complying with FWS CAD Standards.
3.7.3 Submit fully executed manufacturer's standard material, product, and equipment warranties, assigned to the Government without any requirement that the Government incur any costs to maintain the warranties in force.
3.7.4 Submit any requested regulatory-agency clearance documents indicating the work complies with their requirements such as finalized plumbing/gas/electrical inspections.
3.7.5 After completion of the work and prior to final payment, submit the Release of Claims (Form DI-137 provided by the Contracting Officer), properly executed by the DB, releasing claims against the United States arising out of this contract, other than claims specifically excepted from the operation of the release. See Section I of the solicitation /contract.
PART 4 GOVERNMENT RESPONSIBILITIES
4.1 DUTY TO COOPERATE
4.1.1 Government will, throughout the performance of the Work, cooperate with DB and perform its responsibilities, obligations, and services in a timely manner to facilitate DB's timely and efficient performance of the Work and to not unreasonably delay or interfere with DB's performance of its obligations under the Contract Documents.
4.1.2 Government will provide timely reviews and approvals of interim design submissions and Construction Documents consistent with the turnaround times set forth in DB's approved schedule. Contractor agrees to revise the design submittals and construction documents at no cost to the Government until the documents are acceptable to the Government in its reasonable judgment.
PART 5 ARCHITECTURAL PROGRAM
5.1 SUMMARY AND REFERENCE DOCUMENTS: The Architectural Programs are reflected in the government-furnished Architectural Program. The COR and Refuge Manager, at a minimum will meet with the DB to assure there is full understanding of the intent.
Alterations suggested by the DB will be considered and mutually agreed upon before implementation.
5.2 COMMUNICATION NEEDS: Not applicable.
5.2.1 Network/data: Not applicable
5.3 MATERIALS AND ARCHITECTURAL FEATURES
5.3.1 General: Specific materials and architectural styles will be selected by the FWS based on Contractor's proposals and design submissions, metal building or metal roof/siding is preferred. Materials shall be durable, low maintenance, and local (to the extent practical).
Architectural style shall reflect the setting and the nature- oriented function of the facilities.
Technical submittals shall list proposed materials, systems and equipment, including the industry standard quality ratings, to the greatest extent practical in the Phase I technical submittal, with a more detailed list and description in the Phase II technical submittal. This information will be considered by the government as part of the evaluation and rating of proposals and will become part of the contract requirements for the successful Contractor. See Solicitation Sections L and M for details.
5.3.2 "Flat" roofs are not acceptable.
5.3.3 Foundation/Slab: Design based on the DB obtained Geotechnical Report.
5.3.4 Floors: None slip
5.3.5 Storage: Not applicable.
5.3.6 Design and materials shall be of high quality, durable, easily maintained and hardened to withstand the high desert weather environment.
5.4 SITE FEATURES
5.4.1 Site Development Program: Site development requirements to be determined by the DB. New roads are not anticipated.
5.4.2 Excavation and Fill: shall be determined by the DB and shall meet the elevations to ensure that the buildings are constructed above the FEMA 100-year flood plain elevations per the FIRM maps. The depth of excavations shall be terminated if ground water is encountered.
5.4.3 Landscaping: Not applicable.
5.4.4 Re-Use Water:
5.4.4.1 Cisterns: Not applicable
5.4.5 Contractor staging areas shall be shown on the plans produced by the DB.
5.5 WATER SUPPLY: Contractor shall provide supply line from existing location to the new building. Easements, permits, routing of supply lines and connections shall be coordinated and paid for by the Contractor if required (Water system is owned by the Refuge).
5.5.1 Fire Flow & Hydrants: Not applicable.
5.6 SEWER: Not applicable
5.7 ELECTRICAL SERVICE: Contractor shall provide power from existing headquarter location to the new building. Easements, permits, routing of power lines and connections shall be coordinated with the Utility and paid for by the Contractor (if required). Existing power poles not required for facility development shall be removed completely. All new electrical service shall be located underground. DB shall coordinate activities with utility provider.
5.8 TELEPHONE/DATA: Not applicable
5.9 SECURITY REQUIREMENTS: The facilities have been designated Security Level 3 (minimum level) per FWS policy (432 FW 1).
5.9.1 Landscaping: Not applicable.
5.9.2 Site Lighting: Install exterior lighting at entrances and exits (see 6.3.4 for additional information). Lighting should meet Illuminating Engineering Society Guide G-1-16: Security Lighting for People, Property and Critical Infrastructure; Interagency Security Committee standards. Consideration should be given to all entrances, exits, walkways, parking areas and entry gate areas. Site lighting shall be designed in accordance with the Dark Skies Act.
5.9.3 Burglary Resistance of Windows: Lock any operable ground floor windows.
5.9.4 Protection of Air Intakes: Provide emergency shutdown, SIP, and evacuation procedures.
As per the GSA Design Guide (P100) for federal facilities, all ground floor air intakes shall be secured from tampering. On buildings more than 12 m (40 ft.) tall, intakes must be located a minimum of 12 m (40 ft.) above grade. On buildings less than 12 m (40 ft.), the intakes must be located as high as practical on the roof or on a wall. If the system is a closed loop system with no intakes, then this standard is not applicable.
5.9.5 Regulatory Signage: Not applicable.
5.9.6 Employee Access Control: Not applicable.
5.9.7 Perimeter Doors & Door Locks: Secure perimeter doors with high-security mechanical locks keyed alike to the existing refuge office door locks.
5.9.8 Emergency Exit Doors: Secure emergency exit doors using an automatic door closer and exit hardware that are compliant with applicable life safety codes and standards.
5.9.9 Access to Nonpublic Areas: Not applicable.
5.9.10 Security of Critical Areas: Not applicable.
5.9.11 Building Systems and Roof Access: I f a p p l i c a b l e secure utility, mechanical, electrical, and telecom-data rooms, and access to interior space from the roof with locks.
5.9.12 Intrusion Detection System (IDS) Coverage: Not applicable.
PART 6 MECHANICAL AND ELECTRICAL PROGRAMS
6.1 HVAC SYSTEMS
6.1.1 Buildings shall be divided into enough HVAC zones to provide energy efficient HVAC systems, which provide uniform comfort through a zone. Zone comfort shall comply with ASHRAE standard 55.1-2004.
6.1.2 HVAC zones shall have adjustable temperature set-back controls to conserve energy during unoccupied periods.
6.1.3 HVAC systems shall have interlocking controls to shut down any associate exhaust fan, close make-up air and exhaust air dampers when the zone air handler shuts down.
6.1.4 To simplify mechanical systems, heat pumps should be considered. SEER/EER ratings shall exceed the recommended minimum by ASHRAE’s “Advance Energy Design Guide”.
6.1.5 HVAC system design should not allow a complete loss of capacity with an undetected refrigerant leak. System should perform in a reduced capacity until leak repairs can be performed.
6.1.6 Building outside ventilation shall comply with the requirements of ASHRAE 62.1- 2004 and the IECC for Climate Zone 2. Provide discussion with Refuge and Project Manager on advantages and disadvantages of using operable windows to take advantage of the cool morning air. Also consider using CO2 sensors to control amount of outside air as recommended in ASHRAE’s “Advance Energy Design Guide” in the discussions with the refuge.
6.1.7 HVAC heating and cooling ducts shall be designed, sealed, tested and insulated as recommended by ASHRAE’s “Advance Energy Design Guide”. Air ducts shall be installed inside the building; out-side ducts shall be minimized.