Attachment_0007_Responses_to_Questions_from_Solicitation_-_0415_04162026_0004.pdf
PDF 82 KB Posted
- Attached to
- Design Build Service New Headquarters
- Solicitation number
- 140FC126R0006
About this file
This document is a Questions and Answers (Q&A) response file for the San Bernardino National Wildlife Refuge (NWR) design-build solicitation, issued on April 15-16, 2026. The solicitation concerns construction of a 45' x 45' pre-engineered metal laboratory building with associated infrastructure and equipment integration at the refuge facility.
Project Scope and Key Requirements: The contractor is responsible for design, construction, and integration of heavy equipment from the old facility to the new building. The contractor must supply and install workroom countertops, wall cabinets, and workroom tables/benches. The contractor is not responsible for supplying casework, benches, 8-foot diameter tanks, or the deep freezer; these will be furnished by the Fish and Wildlife Service (FWS). The design phase allows 60 days with submittal reviews at 20%, 40%, 70%, and 99% completion stages. The total period of performance is 180 days, with the actual period to be specified in the Notice to Proceed. The proposal due date is 1400 Local Time per SF1442. Work hours are 7:30 AM to 4:30 PM. Design consultants must conduct a minimum of four site visits to inspect construction, with reports submitted to the Contracting Officer's Representative (COR) within five calendar days of each visit.
Specifications and Technical Requirements: The wet lab requires ASHRAE 62.1 2023 ventilation compliance year-round with manual fan control; a mini-split air conditioning system with separate condenser is preferred over PTAC units. An HVLS fan should be considered for the large wet lab space. A 220-volt power supply must be provided for a deep freezer in specimen storage. No freeze protection, hot water, communication data outlets, temporary construction fencing, or separate potable water metering is required. The eyewash station does not require a shower unit, and the fire alarm does not require radio connectivity. Interior and exterior materials and finishes are the contractor's design responsibility. The geotechnical report provided is for reference only; contractor means and methods for geotechnical investigation are the contractor's responsibility.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
04/15/2026
SAN BERNADINO NWR – Responses to questions received from the solicitation
Please provide responses to the following questions:
1. Section 11 of the SF 1442 shows 180 period of performance while Form 336 state Period of Performance: 03/01/2026 to 03/01/2027?
The period of performance listed on the SF1442 is automatically generated. The actual period of performance will be specified in the Notice to Proceed after award.
Q: Which is correct?
2. SF1442 specified the proposal due time as 1400 local time while Form 336 says 1:PM
Eastern.
The proposal due date is 1400 Local Time specified in the via SF1442.
Q: Which is correct?
3. SOW section 3.4 Work Hours is not specified.
Q: Please specify. 7:30am to 4:30pm
4. SOW mentions casework and benches.
Q: Are these to be furnished and installed by the contractor or FWS? ANSWER: To be furnished BY FWS
5. SOW Part 1 mentions 8ft diameter 4ft deep tanks.
Q: Are they to be furnished and installed by the contractor or FWS? ANSWER: To be furnished BY FWS
6. SOW page 8 of 72 under Equipment lists equipment and tanks and accessories. The beginning of this paragraph states “Equipment that needs to be moved and integrated”.
Please clarify scope:
a. Q1: Which equipment/components need to be moved? ANSWER: Contractor will move heavier equipment from the old facility to the new.
b. Q2: Is the contractor to move the equipment/components? ANSWER: Contractor will move heavier equipment from the old facility to the new.
c. Q3: Which equipment are to be supplied and installed by the contractor? ANSWER: No equipment is to be supplied by the contractor.
7. SOW page 9 of 72, Safety and security calls for eyewash station and fire extinguisher.
Question: is the eyewash station to include shower unit? ANSWER: No
8. Q: What is the project supervision requirement? Can the Superintendent cover the QC
Manger and Safety Officer roles? ANSWER: The contractor’s means and method are within the company’s responsibility.
9. SOW page 10 of 72 SOW states “It is the responsibility of the DB to obtain an updated geotechnical report to properly design the foundation and parking areas of the building.
The attached Geotechnical Report dated 10/2/2025 is for reference only. All
Subcontractor (A/E) designed structural drawings must reference a Contractor provided Geotechnical Investigation and Report.”
Q1: Is the contractor to provide a new Geotechnical Investigation and Report?
ANSWER: We are satisfied with the Geotechnical Investigation and Report our Geotechnical consultants produced. We included it in the SOW for reference only. It is not binding on the contractor. The contractor’s means and method are within the company’s responsibility.
10. SOW page 10 of 72 specifies 180 as total period of performance including 60 days for design. Section 1.10.1 calls for design submittals and review of 20%, 40%, 70%, and
99%.
Q1: (60) days assigned for design is a short period of time to produce construction plans
ANSWER: This is a 45’ x 45’ pre-engineered metal building. It is a simple square building. 60 days for the design is more than enough. Attached to the SOW is a conceptual design that includes floor plan, roof plan, and elevations.
04/16/2026
SAN BERNADINO NWR – Responses to questions received from the solicitation
Please provide responses to the following questions:
1. What type of freeze protection, if any is required in the wet lab?
ANSWER: None
Does the fire alarm have a radio type or hard wired connection required? ANSWER:
No
2. Does the user want a through the wall PTAC as was shown in the plans versus an actual min-split that has a separate condenser? We recommend the mini-split.
ANSWER: Mini-split with separate condenser
In the winter, when outdoor temperatures are less conducive to bringing in a large volume of ventilation air, is the wet lab still expected to be ventilated as required by ASHRAE 62.1 2023? ANSWER: Yes
3. Is it acceptable to have the control of the ventilation fan in the wet lab by manual means only? ANSWER: Yes
4. Are there any requirements for space temperature tracking for remote management? ANSWER: No.
5. A large space, like the wet lab can have significant comfort level gains by installing a HVLS fan. Should one be considered? ANSWER: Yes
1. RFI responses dated 04/06/2026, item #2: Could you please have the End User specify the required finish for pricing purposes? ANSWER: This is a design build project. The contractor, through his design consultants is expected to “Provide drawings and schedules which address interior and exterior materials and finishes being proposed”.
2. Are the workroom countertop and wall cabinets to be supplied and installed by the contractor? ANSWER: YES
3. Are the workroom tables/benches to be supplied and installed by the contractor? ANSWER: YES
4. SOW 3.1.7 calls for a minimum of (4) site visit by the design consultants to inspect construction. Please confirm this requirement.
ANSWER: Design Consultants, in coordination with the COR, shall visit the site a minimum of four times to inspect the construction. They shall prepare a site visit report for each visit and shall submit the reports to the COR within 5 calendar days after the visit. The reports shall include comments about overall quality and accuracy of the construction. The reports shall also note all deficiencies observed.
5. Is temporary construction fencing required for this project? ANSWER: NO
6. SOW 6.2.3 Potable Water Metering: The new laboratory’s potable water shall be metered to comply with Executive Order (EO) 13423-January 2007. Q: Is a separate water meter required for this new building? ANSWER: NO
7. Is hot water required for this building? If yes, which location? ANSWER: NO
8. Is there any communication data outlets required for this building? ANSWER: NO
9. What is the available electric power at the proposed tie-in point? (Voltage, Phase, Panel, Transformer)?
10. Appendix 5 ARCHITECTURAL PROGRAM PAGE 1, table indicates a need for 220v power for deep freezer at the Specimen Storage.
Q1: Please confirm this requirement. ANSWER:
YES Q2: Is the contractor to provide the deep freezer? ANSWER: NO Q3: If yes, what is the freezer specification? ANSWER: N/A