This is a Scope of Work document for a federal contract project at a U.S. military installation (Panzer, Building 2901, Rooms 208-212) managed by the Directorate of Public Works. Project #L6-00089-6P covers carpet repair and replacement work requiring comprehensive removal and installation of flooring materials and associated components.
The work scope includes removal and disposal of existing carpet, baseboards, and substructure; installation of new substructure and carpet tiles (Atlas 863 holunder in col./Kugelgarn with color-matched baseboard at 10cm height); furniture movement and repositioning; door and crossbar adjustment; final cleaning; and notification of relevant parties including the Fire Department regarding smoke detector disconnection. The contractor must coordinate a three-week advance notice to the customer's Point of Contact, arrange parking lot closure for construction activities, ensure all equipment and property are removed by the customer prior to construction, and submit tools and materials for inspection (excluding devices equipped with Bluetooth or Internet). The period of performance is 80 calendar days from task order award, with estimated on-site construction time of approximately 10 working days excluding delivery. The contractor will be escorted into the building and must operate under U.S. supervision during delivery and installation. No inventory lists, as-built drawings, or OEM manuals are required.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Scope of Work
PROJECT #: L6-00089-6P
LOCATION BLDG / ROOM SHORT DESCRIPTION TYPE
Panzer 2901 /208-212 Carpet Repair
On this Date the DPW Project Manager met with the Customer to confirm the scope of requested work.
The Scope of work planned for by the Directorate of Public Works is as follows:
Work Description
- Move and remove furniture back to place, customer clears cabinet prior construction, (customer is responsible for movement of technical equipment, personal items, etc., )
- Remove and dispose old carpet, baseboards and substructure
- Provide and install new substructure and carpettiles, (col./Kugelgarn, Atlas 863 holunder), Baseboard “gekettelte” , high 10cm, (Color-matched to the floor)
- Adjust all doors and crossbar if necessary
- Perform final cleaning
- Provide time frame for installation to customers POC (Inform customers 3 weeks before work starts)
- Fire Department need to be informed, when disconnect smoke detectors
- Parking lots will be closed for construction dumpster and loading and unloading of material, clarify POC
- Material and tools are checked, (tool is not allowed to be equipped with Bluetooth and Internet)
Required Days after Task Order Award (Period of Performance):
» Government «
80 Calendar Days Inventory list: not required
As Builts Drawings: not required OEM Manuals: not required
INFO: (Space is provided below for Information and/or additions to the Scope of Work)
- The estimated construction time (on-site) for this Project will be approx. 10 Working days without delivery time.
- All Equipment and Government/private Property has to be removed by the Customer prior construction.
- Contractor must be escorted into building and will be under U.S. supervision during delivery/installation.