This is a Scope of Work document for a federal repair project (L6-00071-6P) at Panzer Building 2901, second floor restrooms remodel, managed by the Directorate of Public Works.

The work encompasses comprehensive renovation of both male and female restroom facilities. For the male restroom: removal and disposal of existing sanitary ware, tiles, ceiling, and utilities (retaining floor drains); preparation of substructures; installation of new tiles, gypsum board with LED panels and sensor controls; provision of sanitary fixtures including 2 sinks with faucets, 2 mirrors, 1 metal sink, 3 urinals with infrared flushers, 2 urinal partitions (Kemmlit brand), 3 toilet bowls with concealed tanks, radiator removal and reinstallation, toilet stall removal and reinstallation, partition installation at sinks, removal of long partition wall, entrance door replacement, and fire protection system modifications as required. The female restroom scope includes similar base work with the addition of 2 walk-in showers with enclosures and fixtures, floor drain installation and connection to main drainage, and locker installation selected by the customer. Common requirements for both areas include final cleaning, site preparation prior to government delivery, provision of detailed installation schedules to the DPW Project Manager and fire department, and contractor escort requirements under U.S. supervision during delivery and installation. The contract requires 120 calendar days for performance, with approximately 60 working days of on-site construction time. Deliverables required prior to final inspection include an inventory list and OEM manuals; As-Built drawings are not required.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Scope of Work

PROJECT #: L6-00071-6P

LOCATION BLDG / ROOM SHORT DESCRIPTION TYPE

Panzer 2901 second floor restrooms remodel Repair

On this Date the DPW Project Manager met with the Customer to confirm the scope of requested work.

The Scope of work planned for by the Directorate of Public Works is as follows:

Work Description

***Male***

- Remove and dispose: sanitary ware, floor/wall tiles, ceiling, cabling & water/sewer line, keep floor drain, fire department need to be informed of disconnecting/covering of fire protection equipment if necessary.

- Prepare substructure of floor/wall/ceiling, prepare new plumbing/electrical connections.

- Provide and place tiles, entire floor and wall's

- Provide and install gypsum board / ceiling tiles, white, to include LED panel, sensor control.

- Provide and install sanitary ware & wall finishes,room include 2x sinks, 2x faucets, 2x wall-mounted mirrors,1x metal sink with faucet and water hose-connector, 3x urinals with Infrared Urinal Flusher ,2x urinal partition manufacturer-"Kemmlit",

- (One urinal is no longer needed. Instead, a metal sink will be installed.)3 x toilet bowls and 3x concealed flush tanks.

- Removing and Reinstalling Radiators for Tile Work

- Remove the toilet stalls, store them temporarily, clean reinstall them.

- Install partition in front of the sinks.

- Removal and disposal of the long partition wall. Replacing of the entrance door.

- Re-install/Modification of fire protection technology in accordance to the fire protection regulation if necessary.

***Female***

- Remove and dispose: sanitary ware, floor/wall tiles, ceiling, cabling & water/sewer line, keep floor drains, fire department need to be informed of disconnecting/covering of fire protection equipment if necessary.

- Prepare substructure of floor/wall/ceiling, prepare new plumbing/electrical connections.

- Provide and place tiles, entire floor and wall's.

- Provide and install gypsum board / ceiling tiles, white, to include LED panel, sensor control.

- Provide and install sanitary ware & wall finishes, room include 2x sinks, 2x faucets, 2x wall-mounted mirrors whit light ,1x metal sink with faucet and water hose-connector.3x toilet bowls and 3x concealed flush tanks.

- Re-install/Modification of fire protection technology in accordance to the fire protection regulation if necessary.

- Removing and Reinstalling Radiators for Tile Work

- Removal of the old showers, installation of two walk-in showers with shower enclosures and fixtures. Installation of floor drains

- and connection to the main floor drainage system

- Replacing of the entrance door.

- Perform final cleaning, Site cleaned before delivery to Government. Likewise the supplier ways

- Provide DPW Project Manager & fire department a detailed installation time schedule

- Provide and install Lockers (selected by the customer)

Required Days after Task Order Award (Period of Performance):

» Government «

120 Calendar Days Inventory list: required prior Final Inspection

As Builts Drawings: not required OEM Manuals: required prior Final Inspection

INFO: (Space is provided below for Information and/or additions to the Scope of Work)

- The estimated construction time (on-site) for this Project will be approx. 60 Working days without delivery time.

- All Equipment and Government/private Property has to be removed by the Customer prior construction.

- Contractor must be escorted into building and will be under U.S. supervision during delivery/installation.